01.12.2012 Views

Slab Track 'NBU System' - Naumburger Bauunion GmbH & Co. KG

Slab Track 'NBU System' - Naumburger Bauunion GmbH & Co. KG

Slab Track 'NBU System' - Naumburger Bauunion GmbH & Co. KG

SHOW MORE
SHOW LESS

You also want an ePaper? Increase the reach of your titles

YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.

A company of<br />

ThyssenKrupp<br />

Services<br />

<strong>Slab</strong> <strong>Track</strong> ‘NBU System’<br />

<strong>Co</strong>ncept, Execution and<br />

<strong>Co</strong>nstruction Site Report<br />

ThyssenKrupp GfT Gleistechnik<br />

THE WAY OF RAIL


<strong>Slab</strong> <strong>Track</strong> ‘NBU System’ –<br />

Further Development of a Proven <strong>Track</strong> <strong>Co</strong>ncept.<br />

<strong>Co</strong>ntinuous production of concrete support slab<br />

International endeavours to innovate the timetested<br />

concept of stable positioned slab tracks as<br />

an alternative to traditional ballasted tracks are<br />

numerous. A particularly economic example of<br />

these efforts is represented by the <strong>Slab</strong> <strong>Track</strong><br />

System <strong>Naumburger</strong> <strong>Bauunion</strong>/NBU that was<br />

approved by the Federal Railway Authority of<br />

Germany (EBA) for field tests in 2004. Within this<br />

concept all sleeper elements were wiped out in<br />

favour of a wholly monolithic construction type.<br />

The construction is made by using the technology<br />

of slipform pavers and applying the fastening<br />

system Krupp ECF/Elastic Clip Fastener.<br />

The conceptual starting point for this type of<br />

construction was the search for a long lasting<br />

solution of material compound by the use of highly<br />

efficient slip-form pavers throughout the whole<br />

fabrication. Due to the optimal design set-up of<br />

the construction Type NBU a manual fabrication<br />

of the slab track can be performed under tight<br />

spatial conditions on the construction site as well.<br />

A broad range of system applications for tunnels,<br />

bridges and trough structures can be covered by<br />

the multiple designs of the <strong>Slab</strong> <strong>Track</strong> NBU<br />

System. The necessary precision, accuracy and<br />

stability are the result of well tested principles of<br />

track and road paving. Transitional areas towards<br />

the ballast track are built by special system design<br />

features.<br />

2<br />

Tunnels without<br />

super-elevation<br />

Viaducts/bridges<br />

with super-elevation<br />

rail runway ± 0.00<br />

rail UIC 60<br />

rail fastening<br />

ballast<br />

concrete support<br />

layer<br />

hydraulically bonded layer<br />

frost protection layer<br />

soll<br />

1.43 5<br />

longitucianl<br />

groove melting joint<br />

asphalt-top layer<br />

Production<br />

segment<br />

„Longitudinal<br />

groove profile“<br />

<strong>Slab</strong> <strong>Track</strong><br />

NBU System<br />

System Layout:<br />

General Section View<br />

with Fastening System<br />

Krupp ECF


Innovation and Efficiency<br />

on Testing Ground.<br />

In the frame of a Field Test Agreement concluded<br />

with DB Netz AG the construction of the <strong>Slab</strong> <strong>Track</strong><br />

NBU System was executed within the range of<br />

the section 2600 <strong>Co</strong>logne – Aachen – Federal<br />

border in early summer 2008. The length of this<br />

special section NBU System is approximately<br />

100 meters. In addition a transition area composed<br />

of 5 m Rheda 2000 and 45 m roadbed with<br />

ballast gluing was built at both ends. Thus the<br />

total construction section comprises a length of<br />

approx. 200 m.<br />

The regular production standard of the concrete<br />

base course is allotted by a slipform paver with<br />

special equipment. Due to the cramped spatial<br />

circumstances in place – the central sheeting<br />

extending into the working field, an enlarged<br />

clearance gauge and a very short transition to the<br />

Rheda elements – a manual casting by concrete<br />

pump got necessary and technologically advantageous.<br />

A high-quality design was assured and<br />

fully verified throughout the entire fabrication.<br />

The overall fitting of the Hydraulically Bonded<br />

Layer (HBL), reinforcement /earthing, the<br />

<strong>Co</strong>ncrete Support Layer (CSL) and the rigging of<br />

the mounting rail as well as the grouting of the<br />

longitudinal channels were affected in an optimal<br />

way. The key steps of the construction scheme<br />

are described and documented by the following<br />

record.<br />

Legend<br />

THE WAY OF RAIL<br />

New construction<br />

Stocks<br />

Cable line<br />

Excavation drainage<br />

Passage<br />

Shaft<br />

Trench<br />

Internal earth FF<br />

Flat bar 50 x 4 cross connection with earth<br />

bridge in accordance with 3 EBS 15.03.19<br />

(details see drawing A-4.01)<br />

Location of OL mast (check on site)<br />

Fit cross connection with earth bridge on<br />

each OL mast<br />

Position Map and<br />

Particularities of the<br />

Test <strong>Track</strong><br />

3


Record of Major <strong>Co</strong>nstruction Steps.<br />

In view of the construction process<br />

one distinguishes mainly between:<br />

the set-up until the upper edge of the<br />

HBL and subsequently the fitting of the<br />

CSL including the complete track laying.<br />

The following record focuses on the<br />

chronological comments and display<br />

of the run of major construction steps<br />

in phase two.<br />

4<br />

1<br />

Fitting of the HBL occurred in two layers of 0.15 m thickness<br />

each and setting out of the track axis and the positioning of the<br />

formwork for the CSL.


2<br />

3<br />

<strong>Co</strong>mpletion of formwork including fitting and compaction of the C 30/37 LP<br />

concrete by a hose pump.<br />

4 5<br />

Chamfers production of dummy joints with a depth of at least 120 mm,<br />

finishing treatment of the concrete according to DIN 1045 by moistening<br />

and airproofed barriers.<br />

At a distance of 0.2 m the laying of the transverse<br />

reinforcement as well as longitudinal reinforcement<br />

with 4 earthing irons were made; in order to<br />

guarantee a safe and stable interconnection in the<br />

transition area 4 x 4 exhaust dowels were<br />

cemented.<br />

Placement of set-up rails via rail winches and<br />

discrete support point Krupp ECF at a distance<br />

of 0.65 m, exact vertical and longitudinal<br />

adjustment and fixation by special tools.<br />

6<br />

7<br />

8<br />

THE WAY OF RAIL<br />

Final inspection of the railway track before the filling<br />

of the longitudinal channels by high end grout.<br />

9<br />

During the grouting work the permanent control over<br />

the consistency by verification of the spreading<br />

gauge and test specimen was carried out.<br />

5


Record of Major <strong>Co</strong>nstruction Steps.<br />

6<br />

10<br />

11 12<br />

Gluing of the ground ballast by two-components<br />

polyurethane mixture and placement of support rails<br />

in the transition area, documentation of the torque by<br />

a twin headed screw machine.<br />

Bracing of anchors with the<br />

necessary torque, altitude<br />

correction at individual support<br />

points by inserting equalisation<br />

plates.


Efficiency and Design Advantages of the<br />

<strong>Slab</strong> <strong>Track</strong> ‘NBU System’.<br />

Talks with professional users, applied planning and execution of<br />

the real construction gave evidence of multiple advantages and<br />

application schemes of the NBU System that are resulting from the<br />

specific design principles and engineering particularities, mainly the<br />

sleeper-less construction layout<br />

Advantages and particular areas of application<br />

High potential of industrial<br />

execution and running by<br />

proved and well tested<br />

construction and paving<br />

technology known for its<br />

high productivity.<br />

Special advantages in view<br />

of track construction in<br />

special climatic areas as<br />

desert zones – where a high<br />

potential of silt up exists – due<br />

to low surface and blocking<br />

resistance in case of adequate<br />

and elevated track<br />

design.<br />

Abolition of joint transition<br />

areas between prefabricated<br />

parts and the “in situ”<br />

concrete construction that<br />

ensures optimal LCC-values,<br />

low maintenance routine and<br />

long life of the system.<br />

Independence of prefabricated<br />

elements and extended<br />

transportation logistics by<br />

complete local construction<br />

in situ and easy feeding of<br />

ready mix concrete by mobile<br />

plants following the progress<br />

and advancement of the<br />

construction site.<br />

Advantages in logistics and<br />

local safety by obstacle-free<br />

move on the CSL during its<br />

construction as well as in<br />

case of emergencies and<br />

damage repairs due to a<br />

plain and sleeper-less<br />

surface.<br />

Manufacture of concrete support slab with longitudinal grooves<br />

THE WAY OF RAIL<br />

High efficiency of the construction<br />

cycle by the use of<br />

conventional and easy-tomobilize<br />

road paving and track<br />

laying technology through all<br />

fabrication steps without<br />

depending extensively on<br />

special tools and machinery.<br />

7


Solid <strong>Slab</strong> <strong>Track</strong> <strong>GmbH</strong><br />

A Joint Venture of<br />

<strong>Naumburger</strong> <strong>Bauunion</strong> and ThyssenKrupp GfT Gleistechnik<br />

ThyssenKrupp<br />

GfT Gleistechnik<br />

TK<br />

ThyssenKrupp GfT Gleistechnik <strong>GmbH</strong><br />

Altendorfer Straße 120<br />

D-45143 Essen<br />

Phone: +49 2 01 1 88-37 12<br />

Fax: +49 2 01 1 88-37 75<br />

e-mail: gleistechnik@thyssenkrupp.com<br />

www.tkgftgleistechnik.de<br />

<strong>Naumburger</strong> <strong>Bauunion</strong> <strong>GmbH</strong> & <strong>Co</strong><br />

Gewerbegebiet Süd<br />

D-06618 Görschen<br />

Phone: +49 3 44 45 70-101<br />

Fax: +49 3 44 45 70-200<br />

e-mail: info@naumburger-bauunion.de<br />

www.naumburger-bauunion.de<br />

THE WAY OF RAIL<br />

Subject to change without notice · TK GfT Gleistechnik · GB · 09/2008

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!