2012-2013 Budget - City of Saginaw MI
2012-2013 Budget - City of Saginaw MI 2012-2013 Budget - City of Saginaw MI
CITY OF SAGINAWCAPITAL IMPROVEMENT PLAN(please note that only those items that were budgeted or has request for multiple years are reflected in the report)ManagerRequest ApprovedFuture YearsDept. Project Funding FY 13 FY 13 FY 14 FY 15 FY 16 FY 17BOAT LAUNCH7546 Lee Street Boat Launch Repairs BL 0 0 45,000 0 0 0If deferred: Scheduled for 2014 Priority 1TOTAL PROJECT COST 45,000Analysis and Explanation:Upgrade boating access to the Saginaw River for the public to include handicap access. Redesign the parking lot to prevent flooding and to repair three (3) boatdocks.Operational ImpactNeeded to keep boat launch operational and in good condition to continue to provide access for recreational activities to the community.TOTAL BOAT LAUNCH45,000SEWER OPERATIONS AND MAINTENANCE4830 Replace Rotork Valve Actuators SF 20,000 20,000 20,000 20,000 20,000 20,000If deferred: Priority 1 1TOTAL PROJECT COST 120,000Analysis and Explanation:Replacement of 2 Rotork valve actuators used throughout the plant. There are 14 Rotork actuators used in the plant that are 40+ years old. This is a systematicreplacement program of the outdated not repairable actuators.Operational ImpactThis project involves replacement of Rotork valve actuators on an annual basis to maintain scheduled replacement plan.356
CITY OF SAGINAWCAPITAL IMPROVEMENT PLAN(please note that only those items that were budgeted or has request for multiple years are reflected in the report)ManagerRequest ApprovedFuture YearsDept. Project Funding FY 13 FY 13 FY 14 FY 15 FY 16 FY 174840 Replace/repair roofs at Retention TreatmentBasins and PlantSF 50,000 50,000 25,000 25,000 25,000 25,000If deferred: Priority 1 1Analysis and Explanation:Replace not repairable roofs at RTBs and plant - repair others if possible.TOTAL PROJECT COST 150,000Operational ImpactThe roofing systems at the remote treatment basins are being repaired as needed to prevent damage to equipment from leaks.4840 Replace Sodium Hypochlorite Feed Pumps atRTBsSF 25,000 25,000 25,000 25,000 25,000 25,000If deferred: Priority 1 1TOTAL PROJECT COST 125,000Analysis and Explanation:Sodium Hypochlorite feed pumps are used to feed chlorine solution at the RTBs. The existing pumps have outlived their service life and need to be replaced.Costs of repairs exceeds cost of replacement. Plans are to replace pumps at one RTB each year.Operational ImpactChlorination of sewage prior to discharge from the remote treatment basins is required and replacement will assure continued regulatory compliance.4840 Final Settling Tank Substructure Replacement SF 125,000 125,000 125,000 125,000 0 0If deferred: Priority 1 1TOTAL PROJECT COST 375,000Analysis and Explanation:The steel substructure collector mechanisms in the final settling tanks are corroding and deteriorating and must be replaced. Repairs are no longer possible onthese 40 year old structures. Failure of the collector mechanism will render the tank unusable.Operational ImpactThe project will enhance reliability of the final settling tank.357
- Page 341 and 342: REVENUE BUDGET SUMMARYWORKERS COMPE
- Page 343 and 344: EXPENDITURE ANALYSIS DETAIL2012/201
- Page 345 and 346: UNFUNDED LIABILITIES FUND (674)RESO
- Page 347 and 348: The above graph reflects numerical
- Page 349 and 350: REVENUE BUDGET SUMMARYFOREST LAWN C
- Page 351 and 352: OAKWOOD CEMETERY (712)RESOURCE ALLO
- Page 353 and 354: EXPENDITURE BUDGET SUMMARYOakwood C
- Page 355 and 356: POLICE AND FIRE PENSION FUND (732)R
- Page 357 and 358: The above graph reflects numerical
- Page 359 and 360: EXPENDITURE ANALYSIS DETAIL2012/201
- Page 361 and 362: 20022003200420052006200720082009201
- Page 363 and 364: CAPITAL IMPROVEMENT PLAN
- Page 365 and 366: for review and approval. If City Co
- Page 367 and 368: intersection of Tittabawassee and C
- Page 369 and 370: CITY OF SAGINAWCIP PROJECTS FOR FY
- Page 371 and 372: CITY OF SAGINAWCAPITAL IMPROVEMENT
- Page 373 and 374: CITY OF SAGINAWCAPITAL IMPROVEMENT
- Page 375 and 376: CITY OF SAGINAWCAPITAL IMPROVEMENT
- Page 377 and 378: CITY OF SAGINAWCAPITAL IMPROVEMENT
- Page 379 and 380: CITY OF SAGINAWCAPITAL IMPROVEMENT
- Page 381 and 382: CITY OF SAGINAWCAPITAL IMPROVEMENT
- Page 383 and 384: CITY OF SAGINAWCAPITAL IMPROVEMENT
- Page 385 and 386: CITY OF SAGINAWCAPITAL IMPROVEMENT
- Page 387 and 388: CITY OF SAGINAWCAPITAL IMPROVEMENT
- Page 389 and 390: CITY OF SAGINAWCAPITAL IMPROVEMENT
- Page 391: CITY OF SAGINAWCAPITAL IMPROVEMENT
- Page 395 and 396: CITY OF SAGINAWCAPITAL IMPROVEMENT
- Page 397 and 398: CITY OF SAGINAWCAPITAL IMPROVEMENT
- Page 399 and 400: CITY OF SAGINAWCAPITAL IMPROVEMENT
- Page 401 and 402: CITY OF SAGINAWCAPITAL IMPROVEMENT
- Page 403 and 404: CITY OF SAGINAWCAPITAL IMPROVEMENT
- Page 405 and 406: CITY OF SAGINAWCAPITAL IMPROVEMENT
- Page 407 and 408: CITY OF SAGINAWCAPITAL IMPROVEMENT
- Page 409 and 410: CITY OF SAGINAWCAPITAL IMPROVEMENT
- Page 411 and 412: CITY OF SAGINAWCAPITAL IMPROVEMENT
- Page 413 and 414: CITY OF SAGINAWCAPITAL IMPROVEMENT
- Page 415 and 416: CITY OF SAGINAWCAPITAL IMPROVEMENT
- Page 417 and 418: CITY OF SAGINAWCAPITAL IMPROVEMENT
- Page 419 and 420: CITY OF SAGINAWCAPITAL IMPROVEMENT
- Page 421 and 422: Performance Management PlanIntroduc
- Page 423 and 424: City AttorneyAndre Borrello, City A
- Page 425 and 426: Community Public Safety - Fire Phil
- Page 427 and 428: Community Public Safety - PoliceBri
- Page 429 and 430: Community Policing - (summary of se
- Page 431 and 432: Inspections - (summary of services)
- Page 433 and 434: The key performance indicator to
- Page 435 and 436: Workers Compensation - (summary of
- Page 437 and 438: Controller’s Office - (summary of
- Page 439 and 440: Department of Public ServicesPhilli
- Page 441 and 442: Explanation of variances:In FY 2012
CITY OF SAGINAWCAPITAL IMPROVEMENT PLAN(please note that only those items that were budgeted or has request for multiple years are reflected in the report)ManagerRequest ApprovedFuture YearsDept. Project Funding FY 13 FY 13 FY 14 FY 15 FY 16 FY 17BOAT LAUNCH7546 Lee Street Boat Launch Repairs BL 0 0 45,000 0 0 0If deferred: Scheduled for 2014 Priority 1TOTAL PROJECT COST 45,000Analysis and Explanation:Upgrade boating access to the <strong>Saginaw</strong> River for the public to include handicap access. Redesign the parking lot to prevent flooding and to repair three (3) boatdocks.Operational ImpactNeeded to keep boat launch operational and in good condition to continue to provide access for recreational activities to the community.TOTAL BOAT LAUNCH45,000SEWER OPERATIONS AND MAINTENANCE4830 Replace Rotork Valve Actuators SF 20,000 20,000 20,000 20,000 20,000 20,000If deferred: Priority 1 1TOTAL PROJECT COST 120,000Analysis and Explanation:Replacement <strong>of</strong> 2 Rotork valve actuators used throughout the plant. There are 14 Rotork actuators used in the plant that are 40+ years old. This is a systematicreplacement program <strong>of</strong> the outdated not repairable actuators.Operational ImpactThis project involves replacement <strong>of</strong> Rotork valve actuators on an annual basis to maintain scheduled replacement plan.356