Evaluation of Aardvark Mk IV Flail - gichd
Evaluation of Aardvark Mk IV Flail - gichd Evaluation of Aardvark Mk IV Flail - gichd
Record of changes iv Issue Date Detail of Changes A 5/9/2000 Draft 1.0 28/10/2000 Initial Issue 1.1 6/11/2000 Minor Amendments 1.2 26/02/2001 Additional Ammendments DERA/LWS/LSAA/TRD000603/1.2
Abstract Aardvark Clearmine Ltd have upgraded their Aardvark flail unit, a system that has an already proven track record for detonating mines and clearing mine affected land. DERA undertook testing and evaluation of the system on behalf of DFID (the Department for International Development). The machine offered for trialing was the MK IV Aardvark Flail, which performed well throughout the trial completing all the tests adequately. Overall, the objectives of the trial, testing the improved power and performance, were achieved by demonstrating the concept of using a flail to clear mines and dense foliage from various terrain. As with most mechanical clearance processes the application of this equipment has to be in the context of the mine threat, type of terrain, climatic and environmental conditions and of the overall demining operation. DERA/LWS/LSAA/TRD000603/1.2 v
- Page 1 and 2: Evaluation of Aardvark Mk IV Flail
- Page 3: Authorisation Prepared by Mr C A Le
- Page 7 and 8: List of contents Authorisation iii
- Page 9 and 10: List of Tables Table 4-1; Improveme
- Page 11 and 12: Figure 6-45; Aardvark just passed R
- Page 13 and 14: 1 Introduction 1.1 Contractual Matt
- Page 15 and 16: Rear Front Figure 3-1; Aardvark Mar
- Page 17 and 18: 4.1 Additional Alterations: 4.1.1 T
- Page 19 and 20: 6 Test Procedures and Results 6.1 G
- Page 21 and 22: Figure 6-2; Measuring the height of
- Page 23 and 24: Figure 6-3; Using load cells to wei
- Page 25 and 26: Figure 6-4; Measuring the Approach
- Page 27 and 28: Figure 6-6; Turning Circle DERA/LWS
- Page 29 and 30: Figure 6-7; Aardvark climbing Birch
- Page 31 and 32: Figure 6-9; Speed = 67m/hr, Depth =
- Page 33 and 34: Figure 6-13; After flailing at 300m
- Page 35 and 36: Figure 6-17; Measuring Level used D
- Page 37 and 38: Figure 6-18; Aardvark entering the
- Page 39 and 40: Figure 6-20; Foliage and terrain en
- Page 41 and 42: This page is intentionally blank DE
- Page 43 and 44: Figure 6-24; Test run before cleara
- Page 45 and 46: This page is intentionally blank DE
- Page 47 and 48: Destroyed Mine Case Figure 6-28; La
- Page 49 and 50: GIAT buried in spoil Figure 6-32; P
- Page 51 and 52: Destroyed Mine Case Figure 6-34; La
- Page 53 and 54: This page is intentionally blank DE
Abstract<br />
<strong>Aardvark</strong> Clearmine Ltd have upgraded their <strong>Aardvark</strong> flail unit, a system that<br />
has an already proven track record for detonating mines and clearing mine<br />
affected land.<br />
DERA undertook testing and evaluation <strong>of</strong> the system on behalf <strong>of</strong> DFID (the<br />
Department for International Development). The machine <strong>of</strong>fered for trialing was<br />
the MK <strong>IV</strong> <strong>Aardvark</strong> <strong>Flail</strong>, which performed well throughout the trial completing all<br />
the tests adequately.<br />
Overall, the objectives <strong>of</strong> the trial, testing the improved power and performance,<br />
were achieved by demonstrating the concept <strong>of</strong> using a flail to clear mines and<br />
dense foliage from various terrain. As with most mechanical clearance processes<br />
the application <strong>of</strong> this equipment has to be in the context <strong>of</strong> the mine threat, type<br />
<strong>of</strong> terrain, climatic and environmental conditions and <strong>of</strong> the overall demining<br />
operation.<br />
DERA/LWS/LSAA/TRD000603/1.2 v