12.07.2015 Views

Council Minutes - Town of Cambridge

Council Minutes - Town of Cambridge

Council Minutes - Town of Cambridge

SHOW MORE
SHOW LESS
  • No tags were found...

Create successful ePaper yourself

Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.

COUNCIL MINUTESTUESDAY 26 JUNE 2012project. A portion <strong>of</strong> these funds are effectively loaned to the projects, providing a return back tothe ELA. A number <strong>of</strong> other projects have also been discussed in the financial planningframework, which is yet to be confirmed by <strong>Council</strong>. Typically, these projects provide new orrenewed community infrastructure.Critical to <strong>Council</strong>'s decision making is its community engagement, strategic communityplanning and financial planning activities, all currently underway and expected to be completedby the end <strong>of</strong> the year. This will help inform <strong>Council</strong> on what the community values and theunderground power survey will be an important input to the community planning.Project DetailsAs detailed above, the indicative cost <strong>of</strong> $11,300 per lot has been prepared based on workundertaken already by Western Power and contains a margin <strong>of</strong> error based on assumptions forthe actual number <strong>of</strong> connections and high load density lots.It is recommended that these figures be used for any survey <strong>of</strong> property owners and if thedecision was made to continue with the project, Western Power would be able to develop afurther design and cost estimate which would have improved accuracy but moreover realisticstaging and timetable plans. The costs to the <strong>Town</strong> to undertake this design work are notinconsiderable and may be in the order <strong>of</strong> 2% <strong>of</strong> the capital cost (ie $ 950,000). Western Powerhave been requested to provide an estimate for this work.Once a decision is made to proceed with the project, the following matters would need to beidentified and resolved:• Survey <strong>of</strong> all lots connected to overhead power, in terms <strong>of</strong> electrical load• Design <strong>of</strong> new underground system, including distribution system, to reticulate power toeach connected residence / property / facility as well as street lighting and other needs• Negotiations with Western Power regarding their internal cost recovery mechanism• Negotiations with Western Power and the State Government to recognise the benefits <strong>of</strong>the project for Western Power• Advise property owners who are not ratepayers (such as Hospitals etc) regarding costrecovery• Development and finalisation <strong>of</strong> cost recovery model recognising the various issuesWorks would be undertaken in stages. At this point in time it is reasonable to assume thatachievement <strong>of</strong> full underground power will take ~6 years from commencement <strong>of</strong> work.As evidenced by earlier stages undertaken in the <strong>Town</strong>, the physical impacts upon verges areusually well managed by the Contractors and supervising staff. It is noted however that theseworks will disturb verges as a necessary part <strong>of</strong> the project.An indicative program assuming all activities meet the project schedule has been developed asfollows:Dec 2012July 2013September 2013February 2014June 2014 to Dec 2019Survey completed and <strong>Council</strong> decision to initiate the projectWestern Power complete design to allow finalisation <strong>of</strong> cost modelCompletion <strong>of</strong> negotiations with Western Power regarding costsharingFinalisation <strong>of</strong> contracts with Western PowerWorks ProgramH:\CEO\GOV\COUNCIL MINUTES\12 MINUTES\JUNE 2012\C CR.DOCX 179

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!