SCHEMATIC CONSTRUCTION PROCESS5 6Reinforcement bars are laid into the U-shaped blocks. Stirrups are placed every 20 cm. The length of thesestirrups depends on the height of the slab to be builtand has to be designed by the structural engineer.7 8(CONTINUED)The U-shaped blocks are filled with concrete, min. The upper reinforcement parts for the slab are placedquality C25.in position.FROM TECHNICAL MANUALS VOL I AND II SCHEMATIC CONSTRUCTION PROCESS11Addis AbabaCity Government