Contents<br />
EXECUTIVE SUMMARY ........................................................................................................................11<br />
1.0 INTRODUCTION .........................................................................................................................13<br />
2.0 KEY FINDINGS............................................................................................................................15<br />
3.0 FACILITY DESCRIPTION ..........................................................................................................17<br />
3.1 <strong>CTA</strong> Acoustics Corbin Facility .....................................................................................................17<br />
3.2 Surrounding Community ...............................................................................................................17<br />
3.3 History of the Plant ........................................................................................................................17<br />
3.4 Plant Construction <strong>and</strong> Layout.......................................................................................................18<br />
3.4.1 Plant Construction.............................................................................................................18<br />
3.4.2 Plant Layout......................................................................................................................19<br />
4.0 PROCESS DESCRIPTION ...........................................................................................................23<br />
4.1 Line 405 .........................................................................................................................................23<br />
4.1.1 Raw Materials <strong>and</strong> Feeders...............................................................................................23<br />
4.1.2 Mat-former <strong>and</strong> Baghouse ................................................................................................25<br />
4.1.3 Curing Oven......................................................................................................................26<br />
4.1.4 Molding Department.........................................................................................................28<br />
4.2 Production Line Operation <strong>and</strong> Cleaning.......................................................................................28<br />
4.3 Periodic Line Maintenance ............................................................................................................29<br />
4.4 Plant Shutdowns ............................................................................................................................29<br />
5.0 INCIDENT DESCRIPTION..........................................................................................................31<br />
5.1 Pre-Incident Events........................................................................................................................31<br />
5.1.1 Ventilation Study ..............................................................................................................31<br />