DelIvery Order #06<br />
Task 2 Power Plants Combusllon EfficIency<br />
Busmess Trip Report.<br />
Penod: May 26 - 28. 1997<br />
Desllnallon: Burshtyn Thermal Power Plant<br />
Completed by: Alexander Filippov,<br />
Burns and Roe Kiev ResIdent Engineer<br />
May 30,1997<br />
Dunng the period from May 26 through May 28 I Vlslted Burshtyn Thermal<br />
Power Plant. The purposes ofthe tnp were:<br />
1) To sIgn letters of recelVlng for the equipment supplIed by USAID/Burns and<br />
Roe<br />
2) To schedule a start-up VlSlt of ZIRTEK and INSTROMET compames<br />
techrucal representatives.<br />
3) To teach the plant staffhow to operate the supplied energy eqUlpment.<br />
During the meellng with Mr. Bozenenkov. Deputy director on foreIgn relations he<br />
expressed rus sallsfaction by the fact of recelvmg the equipment. But he stressed<br />
that the plant was facIng serious dIfficulties related Wlth the majOr lack offunds<br />
The main reason IS non-payments for electncity. The plant doesn't get paId,<br />
although tills is one ofthe largest power plants in UkraIne and even sells<br />
electnclty abroad. The plant has bIg debt on wages for its workers. Since<br />
November 1996 the employees have been paId from 30 to 40% oftherr monthly<br />
wages.<br />
On Tuesday. May 27. we had a techmcal mee1lng and diSCUSSlOn of chfferent<br />
quesllons related to Installation of oxygen analyzer ZIRTEK. Meeting was<br />
headed by Mr. Mallevsky. Cruef of control eqUlpment de<strong>part</strong>ment, <strong>12</strong> specialISts<br />
<strong>part</strong>icIpated. By the time of my VlSlt the plan only had opened the boxes Wlth the<br />
eqUlpment and hadn't studIed the manuals yet. So the meellng turned to be a<br />
"bram storm" over different techrucal aspects of oxygen analyzer mstallation.<br />
The speCIaliSts determined the boiler and the points ofinstallallon. responsIble<br />
persons and general prelimmary steps ofwork. I explained neceSSIty to fimsh<br />
mstallallon by the end of June. 1997, in order for the ZIRTEK representallve to<br />
complete start-up ofthe analyzer. Mr. Mallevsky and other managers proIIl1sed<br />
to make their best to fimsh mstallahon in hme.<br />
We dIscussed the Issue of gas chromatograph installation Tills queshon was<br />
very difficult. It looked like the plant had dIfferent reasons not to mstall It at the<br />
hme bemg. FIrst. the system of payment for gas has changed smce the deCISIon<br />
of mstallatlon of gas chromatograph (calonmeter) was made. Now the plant pays<br />
for the volume of receIved gas and for Its "average. contract" calones Dunng last<br />
1.5 years they have not regIstered the calones content lower that contracted. only<br />
on the contrary. So they were reluctant to mstall the deVlce wruch can "make"<br />
them to pay addItional money for the gas. The second reason ofbemg reluctant