A1(T) Elkesley Junction Improvements - Highways Agency

A1(T) Elkesley Junction Improvements - Highways Agency A1(T) Elkesley Junction Improvements - Highways Agency

assets.highways.gov.uk
from assets.highways.gov.uk More from this publisher
12.07.2015 Views

VibrationSubjective observations were undertaken during the noise monitoring survey, whichindicated that there were no major sources of vibration in the vicinity of the proposedscheme. Therefore, neither baseline vibration monitoring nor a detailed assessmentof vibration would be required as the potential for vibration impact is deemed to beinsignificant.9.5 Potential ImpactsConstruction PhaseAt present, detailed information regarding construction phasing, timescales andprocesses on which to base a thorough assessment are not available. However, inorder to provide an indication of the potential impacts of this phase, qualitativeassessment of key construction activities typically associated with highwayconstruction works has been undertaken. Typically, the main stages of highwaysconstruction are as follows:• Top soil strip;• Bulk cuts;• Bulk fills;• Ground improvement layer; and• Laying of surface.Construction activities associated with developments of this type have the potential toresult in significant noise impacts dependent upon the proximity of existing sensitiveproperties, the need for significant earth moving and the use of ‘heavy’ plant andmachinery. The greatest impacts generally occur during the initial site establishmentstage when the ground is being prepared/excavated and the main infrastructure isbeing installed. Once this is complete, it is considered that general constructionactivities associated with the proposed scheme should give rise to lower noiseemissions.Increased noise may also result on the local road network due to an increasedvolume of HGV's travelling to and from the site during the construction programme(e.g. for import/export of raw materials, clean fill and waste). The potential effects ofthese sources on local receptors will be most significant in the vicinity of specificworks sites, which may change as development phases proceed.Given that exact details regarding construction techniques and types of plant likely tobe used are not available at present, it is difficult to predict accurately the potentialimpacts of construction noise on local receptors. Nevertheless, it is considereduseful to present potential worst-case noise levels from a selection of typicalconstruction plant, which may be used in a development such as this, and tocalculate noise levels back to different distances, which may reflect noise levels atlocal receptors. The noise levels calculated at distance from each item of plant donot take into account attenuation due to screening and have been based upon hardreflective ground between source and receiver as a worst-case scenario. The figures80

presented are also based upon a 100% ‘on’ time, which is unlikely to occur inpractice.Table 9.8 below presents details for plant which could reasonably be used during thedevelopment programme, with corresponding worst-case noise levels taken from BS5228.Table 9.8 – Potential Noise Levels of Construction PlantPlant Sound power Sound Pressure Level (dB LAeq)Level (dBLWA) 10m20m50m100m200m300mExcavators 118 90 84 76 70 64 60Dumper trucks 110 82 76 68 62 56 52Dozers 118 90 84 76 70 64 60Delivery lorries 105 77 71 63 57 51 47Concretedelivery lorry109 81 75 67 61 55 51Vibrating rollers 106 78 72 64 58 52 48Road roller (5km/h)101 73* 67* 59* 53* 47* 43**Drive by maximum sound pressure level, LpA (max), at speed in km/h shown in bracketsIt is considered that the potentially worst affected properties due to construction noisewould be those located directly adjacent to the new highway alignment, with lesserimpacts at those properties located further away and adjacent to the existing roadnetwork.Impacts to specific identified receptors during the construction phase are expected tobe relatively short-term in duration, although the exact duration over which impactsmight arise is not yet known.It is recommended that a range of good site practices, including ‘Best PracticableMeans’ (BS5228:1997), be adopted in order to mitigate against construction phasenoise and vibration impacts at local receptors. This will be undertaken in the form ofa Construction Environmental Management Plan (CEMP) which should includeprovision for a Temporary Traffic Management (TTM) plan. Examples of suchmeasures and techniques include:81

presented are also based upon a 100% ‘on’ time, which is unlikely to occur inpractice.Table 9.8 below presents details for plant which could reasonably be used during thedevelopment programme, with corresponding worst-case noise levels taken from BS5228.Table 9.8 – Potential Noise Levels of Construction PlantPlant Sound power Sound Pressure Level (dB LAeq)Level (dBLWA) 10m20m50m100m200m300mExcavators 118 90 84 76 70 64 60Dumper trucks 110 82 76 68 62 56 52Dozers 118 90 84 76 70 64 60Delivery lorries 105 77 71 63 57 51 47Concretedelivery lorry109 81 75 67 61 55 51Vibrating rollers 106 78 72 64 58 52 48Road roller (5km/h)101 73* 67* 59* 53* 47* 43**Drive by maximum sound pressure level, LpA (max), at speed in km/h shown in bracketsIt is considered that the potentially worst affected properties due to construction noisewould be those located directly adjacent to the new highway alignment, with lesserimpacts at those properties located further away and adjacent to the existing roadnetwork.Impacts to specific identified receptors during the construction phase are expected tobe relatively short-term in duration, although the exact duration over which impactsmight arise is not yet known.It is recommended that a range of good site practices, including ‘Best PracticableMeans’ (BS5228:1997), be adopted in order to mitigate against construction phasenoise and vibration impacts at local receptors. This will be undertaken in the form ofa Construction Environmental Management Plan (CEMP) which should includeprovision for a Temporary Traffic Management (TTM) plan. Examples of suchmeasures and techniques include:81

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!