Hartsfield-Jackson Atlanta International Airport Runway 8R/26L ...
Hartsfield-Jackson Atlanta International Airport Runway 8R/26L ... Hartsfield-Jackson Atlanta International Airport Runway 8R/26L ...
Estimating Considerations � BBatch h plant l site i � Cement and Flyash Storage � Material Availability � Handling of Cement and Flyash � Concrete Temperature �� Overall Resources � People � Equipment
BATCH PLANT AREA Large Erie Plant Small Erie Plant
- Page 1 and 2: Hartsfield-Jackson Atlanta Internat
- Page 3 and 4: • 5 Runway System ATL Airfield Ov
- Page 5 and 6: Project Schedule � Project Planni
- Page 7 and 8: Runway 8R/26L Rehabilitation - Mode
- Page 9 and 10: Modeling - Construction Option 1 Ph
- Page 11 and 12: Modeling - Construction Option 2
- Page 13 and 14: Design Lessons � Haul Road parall
- Page 15: Procurement Lessons � PPre-Qualif
- Page 19 and 20: Small Erie Plant Fun Fact - Over 10
- Page 21 and 22: CEMENT TRAILERS - 15 EA Fun Fact -
- Page 23 and 24: CHILLERS - 5 Each The chillers were
- Page 25 and 26: Paving Equipment Resources � 2 GG
- Page 27 and 28: Pre-construction Planning Lessons
- Page 29 and 30: What-if Plans • Anticipate variab
- Page 31 and 32: Pre-construction Site Investigation
- Page 33 and 34: Test Strip - Low Slump Concrete
- Page 35 and 36: Test Strip - Slip Paving
- Page 37 and 38: Test Strip - Electrical
- Page 39 and 40: TEST STRIP - Finished Product Fun F
- Page 41 and 42: Slab Dumpsite - 14 AC
- Page 43 and 44: Fun Facts �� The slabs removed
- Page 45 and 46: SUBGRADE PREPARATION - 67,800 SY Ov
- Page 47 and 48: ASPHALT PAVING - 70,300 TONS Fun Fa
- Page 49 and 50: The Job Progress g
- Page 51 and 52: Day 14
- Page 53 and 54: Day 39
- Page 55 and 56: Opening Day - Day 59 1/2
- Page 57 and 58: Keys to Success � Complete Team E
- Page 59: THANK YOU! QQuestions? ti ?
BATCH PLANT AREA<br />
Large Erie Plant<br />
Small Erie Plant