Procurement Lessons<br />

� Design Bid Build<br />

� Pre-Qualify Paving Contractors based on experience, financial<br />

strength (5 Qualified)<br />

� Liquidated Damages – based on Planning model delays<br />

� Nightly <strong>Runway</strong> Opening Delay - $500/ minute<br />

� Nightly Taxiway Opening Delay - $100/ minute<br />

� Phase 1 (Mobilization)- $ $75,000 /day. Termination if 10 days late<br />

� Phase 2 (Paving and Lighting) - $225,000/day<br />

� Miscellaneous Modification budget established at 2.5% ($2 million)<br />

� Addressed weather delays in contract, during pre-bid and again<br />

after award<br />

� Extended Bid process<br />

�� Requested a detailed schedule and construction method with Bid<br />

� Increased invoicing cycle from once a month to weekly invoicing<br />

� 50% of mobilization paid on first invoice