Processes for Biological NitrogenRemoval: Post-anoxicPost-anoxic denitrification can be carried out in a two-sludge processusing an external C source (typically methanol)An SRT of 5 days is normally used. Effluent N < 3 mgN/LThe anoxic tank is followed by a short aeration time of 10-20 min torelease the N 2bubbles entrapped in the MLVSSHigh operation costs!!!The process is designed based on methanol denitrification kinetics52