12.07.2015 Views

The Challenge of Low-Carbon Development - World Bank Internet ...

The Challenge of Low-Carbon Development - World Bank Internet ...

The Challenge of Low-Carbon Development - World Bank Internet ...

SHOW MORE
SHOW LESS

You also want an ePaper? Increase the reach of your titles

YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.

Box 2.1<strong>The</strong> Economics <strong>of</strong> Grid-Connected Renewable EnergyA stylized model provides useful insight into what financial and policy levers can boost the economic attractiveness<strong>of</strong> a renewable energy project. <strong>The</strong> economics depend on four factors: unit cost, capacity utilization, tariff, andcarbon credit rate.A developer needs to finance a power plant with a unit cost <strong>of</strong> $1,000–$4,000 per kW. <strong>The</strong> plant will produce a flow<strong>of</strong> electricity. But most renewable energy plants do not operate at full capacity. Wind plants, for instance, may onlyproduce 25–40 percent <strong>of</strong> their theoretical full output. This ratio is the capacity utilization. <strong>The</strong> electricity is soldat a net tariff <strong>of</strong>, say, 5–15 cents per kWh after transmission costs. This renewably generated electricity may alsodisplace fossil-generated electricity, generating a carbon credit rate <strong>of</strong>, say, 0.2–1.2 cents per kWh, depending onthe price <strong>of</strong> carbon and the kind <strong>of</strong> fuel displaced. <strong>The</strong>n (with some simplifying assumptions, such as negligiblecosts <strong>of</strong> operations and maintenance, no peak-period tariffs, and no payments for capacity or penalties forintermittency) the pretax financial rate <strong>of</strong> return to the project isFinancialrate<strong>of</strong>return=(Tariff +<strong>Carbon</strong> Credit Rate)8,760 *Capaci ty Utilization.Unit Cost(To get the ERR, use economic rather than market values for electricity and carbon, and account for local environmentalbenefits.)This shows that if electricity sells for $.06 per kWh, then the following actions would have equivalent impacts onthe rate <strong>of</strong> return:• Adding carbon credits at $10 per ton CO (assuming displacement <strong>of</strong> .6 kilograms per kWh)2• Adding a renewable energy premium <strong>of</strong> $0.006 to the tariff• Boosting capacity utilization from 30 to 33 percent through better siting, better design, or improved maintenance• Reducing construction costs from $1,100 to $1,000 per KW.<strong>The</strong> developer cares about the return on equity, not the overall return, and therefore leverages its equity byborrowing, ideally, 60–80 percent <strong>of</strong> the capital cost. This works as long as the returns are greater than the interestrate on the loan. <strong>The</strong> prospective returns have to be high enough to outweigh the risks. <strong>The</strong>se include the risk thatthe buyer will renege on the promised tariff, which must be sustained over many years to pay back the large initialcapital investment.Meanwhile, the lender wants to make sure that the investment is sufficiently lucrative that the developer canreadily afford the loan repayments. So lenders insist that the project’s revenue be sufficient to easily cover theloan repayments—that is, that the debt service coverage ratio be significantly greater than one. This ratio can beenhanced through longer loan lengths and lower interest rates.Source: IEG.Note: 8,760 is the approximate number <strong>of</strong> hours in a year.lines. <strong>The</strong> WBG has funded a number <strong>of</strong> mapping exercises(appendix B). Most <strong>of</strong> these modestly funded exercises arestill under way, and impact evaluation is not possible.<strong>The</strong> WBG has financed development <strong>of</strong> anumber <strong>of</strong> renewable energy resource mapsthat might assist in siting decisions andthus improve capacity utilization.<strong>The</strong> WBG could also help, through technical assistance, toensure that projects’ design plans for capacity utilizationare realistic. Hydropower, wind, and landfill gas plants haveundershot their planned production levels; in many casesthis is because <strong>of</strong> inadequate assessment <strong>of</strong> resources at thesite. Box 2.2 explains why this has happened for landfill gasprojects and what is being done in response.Operations and maintenance can affect capacity utilization.Unavailability <strong>of</strong> spare parts can put turbines out <strong>of</strong> commission,for instance. Technical assistance for maintenance andmanufacturing could reduce downtime. As a crude measure<strong>of</strong> WBG support in this area, IEG’s review <strong>of</strong> the 2003–08portfolio found that about one-third <strong>of</strong> minihydro and onequarter<strong>of</strong> wind investment components included trainingand capacity building for installation or maintenance.Renewable Energy | 19

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!