direct testimony of the capital expenditures, reliability, and - nyseg
direct testimony of the capital expenditures, reliability, and - nyseg direct testimony of the capital expenditures, reliability, and - nyseg
Case 09-E-____; Case 09-G-____ (NYSEG)DIRECT TESTIMONY OF THE CAPITAL EXPENDITURES,RELIABILITY, AND OPERATIONS PANEL123456789101112131415161718192021severe weather related outages due to high winds far exceeded the 2000-2007yearly average numbers of days with severe weather due to high winds reportedacross New York State as calculated by the National Oceanic and AtmosphericAdministration (NOAA). Inflationary effects have increased the cost of labor,vehicles, and materials over time. Finally, as NYSEG continuously improves itsstorm restoration efforts in response to the Commission's requirements, there is acorresponding increase in costs.Q. Can you describe more fully the recommendations by Staff and the impact ofthose recommendations on storm costs?A. The Company continues to implement Staff recommendations to improve stormresponse. These recommendations have included increased priority and staffingfor downed wires, more formalized damage assessment, and more proactiveacquisition and deployment of additional crews. These initiatives should, overtime, improve the quality of storm response. They will also contribute to theincreased cost of storm response.Rural Electric CooperativesQ. What steps did NYSEG take in cooperation with the Cooperatives to address theMerger Conditions as set forth in Appendix 2, Item 3 of the Abbreviated MergerOrders (as affirmed in the Long Merger Order) in Case 07-M-0906?A. On October 7, 2008, NYSEG established a task force to investigate the ruralcooperative issues (the "Task Force").63
Case 09-E-____; Case 09-G-____ (NYSEG)DIRECT TESTIMONY OF THE CAPITAL EXPENDITURES,RELIABILITY, AND OPERATIONS PANEL123456789101112131415161718192021Q. Did NYSEG conduct a transmission study, to be completed no later than 90 daysafter the closing of the Iberdrola acquisition of Energy East, to determine the ageand capacity of all facilities providing service to the substations owned andcontrolled by the Cooperatives and the Village of Sherburne?A. Yes. The Transmission Study was completed on December 8, 2008.Q. Was a meeting held by NYSEG, within 30 days after completion of thetransmission study?A. Yes. A conference call meeting was held on January 7, 2009. Task Forcemembers and Staff members were in attendance.Q. Did the Task Force jointly establish communications protocols no later than 90days after the closing of the Iberdrola acquisition of Energy East?A. The Task Force jointly established communications protocols. NYSEGimplemented these protocols on November 17, 2008.Q. Were capital improvements that could be made to enhance system reliability withrespect to the systems used to serve the Cooperatives and the Village ofSherburne identified by the Task Force?A. The Task Force identified several capital projects to enhance NYSEG facilitysystem reliability serving the Cooperatives. After having been reviewed by theTask Force, these projects are now being included for consideration in this rateproceeding. One example of such a project is the rebuilding 5.36 miles of 46 kVline between NYSEG South New Berlin and New Berlin substation.64
- Page 13 and 14: Case 09-E-____; Case 09-G-____ (NYS
- Page 15 and 16: Case 09-E-____; Case 09-G-____ (NYS
- Page 17 and 18: Case 09-E-____; Case 09-G-____ (NYS
- Page 19 and 20: Case 09-E-____; Case 09-G-____ (NYS
- Page 21 and 22: Case 09-E-____; Case 09-G-____ (NYS
- Page 23 and 24: Case 09-E-____; Case 09-G-____ (NYS
- Page 25 and 26: Case 09-E-____; Case 09-G-____ (NYS
- Page 27 and 28: Case 09-E-____; Case 09-G-____ (NYS
- Page 29 and 30: Case 09-E-____; Case 09-G-____ (NYS
- Page 31 and 32: Case 09-E-____; Case 09-G-____ (NYS
- Page 33 and 34: Case 09-E-____; Case 09-G-____ (NYS
- Page 35 and 36: Case 09-E-____; Case 09-G-____ (NYS
- Page 37 and 38: Case 09-E-____; Case 09-G-____ (NYS
- Page 39 and 40: Case 09-E-____; Case 09-G-____ (NYS
- Page 41 and 42: Case 09-E-____; Case 09-G-____ (NYS
- Page 43 and 44: Case 09-E-____; Case 09-G-____ (NYS
- Page 45 and 46: Case 09-E-____; Case 09-G-____ (NYS
- Page 47 and 48: Case 09-E-____; Case 09-G-____ (NYS
- Page 49 and 50: Case 09-E-____; Case 09-G-____ (NYS
- Page 51 and 52: Case 09-E-____; Case 09-G-____ (NYS
- Page 53 and 54: Case 09-E-____; Case 09-G-____ (NYS
- Page 55 and 56: Case 09-E-____; Case 09-G-____ (NYS
- Page 57 and 58: Case 09-E-____; Case 09-G-____ (NYS
- Page 59 and 60: Case 09-E-____; Case 09-G-____ (NYS
- Page 61 and 62: Case 09-E-____; Case 09-G-____ (NYS
- Page 63: Case 09-E-____; Case 09-G-____ (NYS
- Page 67 and 68: Case 09-E-____; Case 09-G-____ (NYS
- Page 69 and 70: Case 09-E-____; Case 09-G-____ (NYS
- Page 71 and 72: Case 09-E-____; Case 09-G-____ (NYS
- Page 73 and 74: Case 09-E-____; Case 09-G-____ (NYS
- Page 75 and 76: Case 09-E-____; Case 09-G-____ (NYS
- Page 77 and 78: Case 09-E-____; Case 09-G-____ (NYS
- Page 79 and 80: Case 09-E-____; Case 09-G-____ (NYS
- Page 81 and 82: Case 09-E-____; Case 09-G-____ (NYS
- Page 83 and 84: Case 09-E-____; Case 09-G-____ (NYS
- Page 85 and 86: Case 09-E-____; Case 09-G-____ (NYS
- Page 87 and 88: Case 09-E-____; Case 09-G-____ (NYS
- Page 89 and 90: Case 09-E-____; Case 09-G-____ (NYS
- Page 91 and 92: Case 09-E-____; Case 09-G-____ (NYS
- Page 93 and 94: Case 09-E-____; Case 09-G-____ (NYS
Case 09-E-____; Case 09-G-____ (NYSEG)DIRECT TESTIMONY OF THE CAPITAL EXPENDITURES,RELIABILITY, AND OPERATIONS PANEL123456789101112131415161718192021Q. Did NYSEG conduct a transmission study, to be completed no later than 90 daysafter <strong>the</strong> closing <strong>of</strong> <strong>the</strong> Iberdrola acquisition <strong>of</strong> Energy East, to determine <strong>the</strong> age<strong>and</strong> capacity <strong>of</strong> all facilities providing service to <strong>the</strong> substations owned <strong>and</strong>controlled by <strong>the</strong> Cooperatives <strong>and</strong> <strong>the</strong> Village <strong>of</strong> Sherburne?A. Yes. The Transmission Study was completed on December 8, 2008.Q. Was a meeting held by NYSEG, within 30 days after completion <strong>of</strong> <strong>the</strong>transmission study?A. Yes. A conference call meeting was held on January 7, 2009. Task Forcemembers <strong>and</strong> Staff members were in attendance.Q. Did <strong>the</strong> Task Force jointly establish communications protocols no later than 90days after <strong>the</strong> closing <strong>of</strong> <strong>the</strong> Iberdrola acquisition <strong>of</strong> Energy East?A. The Task Force jointly established communications protocols. NYSEGimplemented <strong>the</strong>se protocols on November 17, 2008.Q. Were <strong>capital</strong> improvements that could be made to enhance system <strong>reliability</strong> withrespect to <strong>the</strong> systems used to serve <strong>the</strong> Cooperatives <strong>and</strong> <strong>the</strong> Village <strong>of</strong>Sherburne identified by <strong>the</strong> Task Force?A. The Task Force identified several <strong>capital</strong> projects to enhance NYSEG facilitysystem <strong>reliability</strong> serving <strong>the</strong> Cooperatives. After having been reviewed by <strong>the</strong>Task Force, <strong>the</strong>se projects are now being included for consideration in this rateproceeding. One example <strong>of</strong> such a project is <strong>the</strong> rebuilding 5.36 miles <strong>of</strong> 46 kVline between NYSEG South New Berlin <strong>and</strong> New Berlin substation.64