<strong>Garney</strong> <strong>Construction</strong>785 E WarrenGardner, KS 66030Phone: 816-278-5950Fax: 816-278-5931SUBMITTAL ITEMO. <strong>26</strong> <strong>24</strong> <strong>13</strong>-<strong>001</strong>PACKAGE O: BP4 CEDTITLE:PROJECT:DRAWIG:STATUS:BIC:4c <strong>600V</strong> SwitchboardsWard County Pump Station ProjectR&RCAINREQUIRED START:REQUIRED FIISH:DAYS HELD: 0DAYS ELAPSED: 14DAYS OVERDUE: 0RECEIVED FROMCAIN PMSET TOFNINLRETURED BYFNI NLFORWARDED TOCAIN PMRevisiono.Description / RemarksReceivedSentDrawing<strong>Returned</strong> Forwarded Status Sepias Prints Date HeldElapsed<strong>001</strong> Bid Pkg 4c 600 VoltSwitchboards2/28/2012 2/28/2012 3/9/2012 3/<strong>13</strong>/2012 R&R 0 1 0 14Please address Engineer review comments and resubmit entire package.<strong>Garney</strong> <strong>Construction</strong>Ward County Pump Station Project<strong>Submittal</strong> o. <strong>26</strong> <strong>24</strong> <strong>13</strong>-<strong>001</strong>This submittal has been reviewed and approved with respect tothe contract documents and specification sectionBP4 CEDApproval or acceptance of the submittal does not relieve thevendor of their responsibility to comply with the contractdocuments.Supplier/Sub: CAIDate: ______________ 3-<strong>13</strong>-12 Reviewed by: _________________M. GraceExpedition ®


SUBMITTALShttps://projectdox.freese.com/imarkupwg/form.asp?formid=6415&wfdirect=&debug=&co...Page 1 of 23/<strong>13</strong>/2012Project No:Project:Client:Contractor:CMD11<strong>26</strong>9DCMAR Ward County Transmission System - ElectricalEquipmentColorado River Municipal Water District<strong>Garney</strong>Shop Drawing #002URGENT Bid Package 4c 600 Volt SwitchboardsWORKFLOW COMPLETED 3/9/2012 11:29 AMSUBMITTAL INFORMATIONSUBMITTALTYPE:SUBMITTAL #: CONTRACTOR REF #: SPEC SECTION: PLAN SHEET: SUBMITTAL STATUS:ShopDrawing002<strong>26</strong> <strong>24</strong> <strong>13</strong>-<strong>001</strong><strong>26</strong> <strong>24</strong> <strong>13</strong>Not Approved, Revise andResubmitSUBMITTALDESCRIPTION:URGENT Bid Package 4c 600 Volt SwitchboardsUPLOAD SUPPORTING DOCUMENTS<strong>26</strong> <strong>24</strong> <strong>13</strong> <strong>600V</strong> <strong>SWBDS</strong>.pdf 2/28/2012 7:38 PM Marcus GraceCONTRACTOR CERTIFICATIONCONTRACTOR COMMENTS:Urgent <strong>Submittal</strong> - <strong>Garney</strong> and FNI will review concurrentlyHOW WILL THE COPIES BE SUBMITTED:ElectronicNUMBER OF COPIES SUBMITTED: 1This shop drawing has been reviewed by the Contractor and certified to be in strict conformance with the Contract Documents as modified by addenda, field orders, andchange orders. Deviations can only be approved by field order or change order. Approval is only for conformance with the design concept of the project and compliancewith the intent of the information given in the Contract Documents. Contractor is responsible for dimensions to be confirmed and correlated at the job site; for informationthat pertains solely to the fabrication processes or to techniques of construction; and for the work of all trades.SUBMITTED BY: Marcus GraceDATE: 2/28/2012 7:41 PMREVIEWER COMMENTSREVIEWER NAME: REVIEWER EMAIL: COMPANY / ORGANIZATION DATESENT:Jeff Hensleyjnh@freese.com4055 International Plaza3/1/2012DATECOMPLETED:3/7/2012REVIEWERCOMMENTS:Per Rebecca Sandoval's comments.REVIEWER NAME: REVIEWER EMAIL: COMPANY / ORGANIZATION DATESENT:RebeccaSandovalrs@freese.comFreese and Nichols, Inc3/1/2012DATECOMPLETED:3/7/2012REVIEWERCOMMENTS:3/7/12Not Approved. Provide Additional Information. Revise and Resubmit. Provide a writtenresponse to each comment on a separate sheet of paper.See attached for complete comments by R.Sandoval.Refer to Jeff Hensley for additional comments.UPLOAD SUPPORTING REVIEW DOCUMENTSCMD SD-02 Switchboard Comments RSandoval 03.07.12.pdfRemove 3/7/2012 4:45 PM Rebecca Sandoval


SUBMITTALShttps://projectdox.freese.com/imarkupwg/form.asp?formid=6415&wfdirect=&debug=&co...Page 2 of 23/<strong>13</strong>/2012DISPLAY ROUTING SLIPCurrent Workflow Step: DCS Admin: Debby Greer Workflow Initiator: Marcus Grace(Click on the Names above to Email User)FNI Forms v1.04


Rebecca SandovalFreese and Nichols, Inc.CMD11<strong>26</strong>9- Contact C4 – Electrical EquipmentSD-002 – <strong>600V</strong> Switchboards3/07/20121. Not Approved. Provide Additional Information. Revise and Resubmit. Provide a written response to each comment on aseparate sheet of paper.2. The warranty shall be in accordance with section <strong>26</strong> <strong>24</strong> <strong>13</strong>-11, 3.06. Currently the submittal does not include anyinformation on the warranty.The following comments refer to “TPSSWBD”:3. Provide all the information listed in section <strong>26</strong> <strong>24</strong> <strong>13</strong>-2, 1.03.A.2. This shall include but not be limited to the following:a) Provide shop drawing information for miscellaneous electrical equipment as indicated in paragraph 1.03.A.2.k. Thisshall include but not be limited to providing shop drawing information for the Surge Protection Device (SPD). SPDshall be in accordance with section 22 <strong>24</strong> <strong>13</strong>-8, 2.02.b) Clearly indicate on the front view elevation drawing the maximum mounting height of power meter as indicated insections 22 <strong>24</strong> <strong>13</strong>-2, 1.03.A.2.l and 22 <strong>24</strong> <strong>13</strong>-6, 2.01.I. As indicated in section <strong>26</strong> <strong>24</strong> <strong>13</strong>-6, 2.01.I the power meterdisplay shall be mounted no higher than 5’-6” AFF which shall include the height of the 4” housekeeping pad.4. As discussed in the pre-submittal meeting, show the vertical distance between the lugs and the bottom/top of equipment.5. Size breaker associated with SPD as required as indicated on the FNI 480V One-Line Diagram.6. Nameplates shall be black with white letters as indicated in section <strong>26</strong> <strong>24</strong> <strong>13</strong>-8, 2.01.S. Currently the submitted bill ofmaterials indicates this but the submitted general notes drawing indicates white with black letters.7. Revise the schedule drawing to indicate the project specific load descriptions indicated on the FNI 480V One-Line Diagram.a) For example change “EUH” to read as “EUH-TPS-1”.8. Provide and show fuses on the secondary side of the 2PTs that are connected to the Power Meter. Currently this isindicated on the submitted one-line drawing but not on the CPT/PM elementary drawing.9. Provide and show 4CTs connected to the Power Meter. Currently the submitted drawings only indicate three are beingprovided.10. Provide and show that the power meter will be a SquareD model PM870. Currently this is indicated on the submitted onelinedrawing but the submitted CPT/PM elementary drawing indicates a PM820 power meter is being provided.11. As indicated in section <strong>26</strong> <strong>24</strong> <strong>13</strong>-7, 2.01.N.2.a.(vii) the power meter shall include ethernet connections. Currently thesubmittal does not indicate that the option for the Ethernet communications card is being provided.12. Where are the LJ frame circuit breaker, PowerPact PJ circuit breaker, and Masterpact NW 2000A & 3000A circuit breakersbeing provided at this site? As indicated in section <strong>26</strong> <strong>24</strong> <strong>13</strong>-2, 1.03.A the submittal shall be organized by specific pumpstation site therefore remove any cut sheets for items that are not being provided at this pump station site.The following comments refer to “OPSSWBD”:<strong>13</strong>. Provide all the information listed in section <strong>26</strong> <strong>24</strong> <strong>13</strong>-2, 1.03.A.2. This shall include but not be limited to the following:a) Provide shop drawing information for miscellaneous electrical equipment as indicated in paragraph 1.03.A.2.k. Thisshall include but not be limited to providing shop drawing information for the Surge Protection Device (SPD). SPDshall be in accordance with section 22 <strong>24</strong> <strong>13</strong>-8, 2.02.14. As discussed in the pre-submittal meeting, show the vertical distance between the lugs and the bottom/top of equipment.15. Size breaker associated with SPD as required as indicated on the FNI 480V One-Line Diagram.16. Nameplates shall be black with white letters as indicated in section <strong>26</strong> <strong>24</strong> <strong>13</strong>-8, 2.01.S. Currently the submitted bill ofmaterials indicates this but the submitted general notes drawing indicates white with black letters.17. Revise the schedule drawing to indicate the project specific load descriptions indicated on the FNI 480V One-LineDiagram.a) For example change “P-1” to read as “OPS P-1 MBFV” and “Pump” to read as “Pump OPS P-1”.18. Provide and show fuses on the secondary side of the 2PTs that are connected to the Power Meter. Currently this isindicated on the submitted one-line drawing but not on the CPT/PM elementary drawing.<strong>Submittal</strong> Review Comments Page 1 of 2


Rebecca SandovalFreese and Nichols, Inc.CMD11<strong>26</strong>9- Contact C4 – Electrical EquipmentSD-002 – <strong>600V</strong> Switchboards(continued)19. Provide and show 4CTs connected to the Power Meter. Currently the submitted drawings only indicate three are beingprovided.20. Provide and show that the power meter will be a SquareD model PM870. Currently this is indicated on the submitted onelinedrawing but the submitted CPT/PM elementary drawing indicates a PM820 power meter is being provided.21. As indicated in section <strong>26</strong> <strong>24</strong> <strong>13</strong>-7, 2.01.N.2.a.(vii) the power meter shall include ethernet connections. Currently thesubmittal does not indicate that the option for the Ethernet communications card is being provided.22. Where are the LJ frame circuit breaker, Masterpact NW 2000A circuit breakers, and MJ circuit breakers being provided atthis site? As indicated in section <strong>26</strong> <strong>24</strong> <strong>13</strong>-2, 1.03.A the submittal shall be organized by specific pump station site thereforeremove any cut sheets for items that are not being provided at this pump station site.23. Provide more detailed data sheet on the PowerPact PJ circuit breaker similar to what was provided for the other breakers.Currently the submittal only includes a couple pages from a catalog/brochure.The following comments refer to “WPSSWBD”:<strong>24</strong>. Reference FNI sheet E-10, WPS 480V One-Line Diagram: The load description “WPS-YP4-BFV1” shall actually read as“WPS-YP4-BFV2”.25. Remove the vertical neutral bus from the sections with the 1000A/3P breakers to the Pump Starters. Currently the“WPSSWBD” one-line shows that it is being provided but it is not shown being provided at “OPSSWBD”. Since the neutral isnot being used on the vertical sections feeding the pump starters it can be removed to maintain consistency between sites.<strong>26</strong>. Provide all the information listed in section <strong>26</strong> <strong>24</strong> <strong>13</strong>-2, 1.03.A.2. This shall include but not be limited to the following:a) Provide shop drawing information for miscellaneous electrical equipment as indicated in paragraph 1.03.A.2.k. Thisshall include but not be limited to providing shop drawing information for the Surge Protection Device (SPD). SPDshall be in accordance with section 22 <strong>24</strong> <strong>13</strong>-8, 2.02.27. As discussed in the pre-submittal meeting, show the vertical distance between the lugs and the bottom/top of equipment.28. Size breaker associated with SPD as required as indicated on the FNI 480V One-Line Diagram.29. Nameplates shall be black with white letters as indicated in section <strong>26</strong> <strong>24</strong> <strong>13</strong>-8, 2.01.S. Currently the submitted bill ofmaterials indicates this but the submitted general notes drawing indicates white with black letters.30. Revise the schedule drawing to indicate the project specific load descriptions indicated on the FNI 480V One-LineDiagram.a) For example change “Pump” to read as “Pump WPS P-1” and “P-1” to read as “WPS P-1 MBFV” and “YP1” to readas “WPS-YP1-MBFV”.b) Note that there is no valve with “YP6” in its description as currently indicated in the submitted schedule.31. Provide and show fuses on the secondary side of the 2PTs that are connected to the Power Meter. Currently this isindicated on the submitted one-line drawing but not on the CPT/PM elementary drawing.32. Provide and show 4CTs connected to the Power Meter. Currently the submitted drawings only indicate three are beingprovided.33. Provide and show that the power meter will be a SquareD model PM870. Currently this is indicated on the submitted onelinedrawing but the submitted CPT/PM elementary drawing indicates a PM820 power meter is being provided.34. As indicated in section <strong>26</strong> <strong>24</strong> <strong>13</strong>-7, 2.01.N.2.a.(vii) the power meter shall include ethernet connections. Currently thesubmittal does not indicate that the option for the Ethernet communications card is being provided.35. Where are the Masterpact NW 3000A circuit breaker and MJ circuit breaker being provided at this site? As indicated insection <strong>26</strong> <strong>24</strong> <strong>13</strong>-2, 1.03.A the submittal shall be organized by specific pump station site therefore remove any cut sheets foritems that are not being provided at this pump station site.<strong>Submittal</strong> Review Comments Page 2 of 2


<strong>Garney</strong> <strong>Construction</strong>785 E WarrenGardner, KS 66030Phone: 816-278-5950Fax: 816-278-5931SUBMITTAL ITEMNO. <strong>26</strong> <strong>24</strong> <strong>13</strong>-<strong>001</strong>PACKAGE NO: BP4 CEDTITLE:PROJECT:DRAWING:STATUS:BIC:4c <strong>600V</strong> SwitchboardsWard County Pump Station ProjectOPNFNIREQUIRED START:REQUIRED FINISH:DAYS HELD: 0DAYS ELAPSED: 0DAYS OVERDUE: 0RECEIVED FROMCAIN PMSENT TOFNINLRETURNED BYFNI NLFORWARDED TOCAIN PMRevisionNo.Description / RemarksReceivedSentDrawing<strong>Returned</strong> Forwarded Status Sepias Prints Date HeldElapsed<strong>001</strong> Bid Pkg 4c 600 VoltSwitchboards2/28/2012 2/28/2012 OPN 0 1 0 0Urgent <strong>Submittal</strong> - <strong>Garney</strong> and FNI will review concurrently<strong>Garney</strong> <strong>Construction</strong>Ward County Pump Station Project<strong>Submittal</strong> No. <strong>26</strong> <strong>24</strong> <strong>13</strong>-<strong>001</strong>This submittal has been reviewed and approved with respect tothe contract documents and specification sectionBP4 CEDApproval or acceptance of the submittal does not relieve thevendor of their responsibility to comply with the contractdocuments.Supplier/Sub:CAINDate: ______________ Reviewed by: _________________2-28-12Expedition ®


600 V SWBDTransmission Pump Station


600 V SWBDOdessa Pump Station


600 V SWBDWell Field Pump Station