adjacent Pine Street; eliminates SEM works; allows tunneling to be performed by TBM for the entire tunnel<br />

alignment which has both schedule <strong>and</strong> cost advantages; ensures safety <strong>and</strong> security in the PSST; minimizes<br />

interference with existing or ongoing transit operations to reduce risks from both safety <strong>and</strong> contractual points <strong>of</strong><br />

view; reduces schedule risk by performing preparatory works at PSST prior to the arrival <strong>of</strong> the TBMs; <strong>and</strong> gives<br />

some additional flexibility for making connections to the existing structure for waterpro<strong>of</strong>ing, as well mechanical,<br />

electrical, ventilation, <strong>and</strong> systems components.<br />

Finally, the lessons learned from the PSST connection have been directly put to use at the north end <strong>of</strong> the U-Link<br />

project where UWS ties in with the future running tunnels expansion to the North. Future running tunnels coming<br />

into the station will be provided with a TBM retrieval shaft built into the permanent works <strong>of</strong> the station, greatly<br />

reducing the impact <strong>of</strong> the future expansion on the operations <strong>of</strong> the University Link light rail.<br />