DISTRICT PROFILE - KOHISTAN<br />
quantum of work and capacity of the district to execute the reconstruction plan.<br />
According to the phasing, Rs.26.4648 million funds will be applied in the first year while<br />
Rs.22.872 million of total estimated cost will be undertaken during the second year.<br />
Reconstruction Plan- Governance Sector<br />
<strong>Kohistan</strong><br />
No.ofBuildings Area in sq. ft. Reconstruc<br />
tion Cost<br />
Consultancy<br />
/ Equipment<br />
Cost 20%<br />
Total<br />
13 (5 No.<br />
Reconstruction<br />
& 8 Nos. Repair) 20980 41.114 8.2228 49.3368<br />
80% 20% 100.00%<br />
Source: Governance Strategy, 2006<br />
Table 21<br />
Year-Wise Financial Plan of Governance Sector<br />
<strong>Kohistan</strong><br />
2006-2007 Total<br />
49.3368 49.3368<br />
100% 100%<br />
Source: Governance Strategy, 2006<br />
Some minor damages occur under Tehsil Municipal Administration jurisdiction in Tehsil<br />
Dassu and Tehsil Palas.<br />
Table 22<br />
Extent of Damages to Tehsil Administrations<br />
Buildings Dsitrict <strong>Kohistan</strong><br />
Name of TMAs No. of Schemes<br />
Dassu 25<br />
Palas 01<br />
Total 26<br />
Source: Internal Sources of DRU, <strong>Kohistan</strong><br />
Table 23<br />
Tehsil Municipal Administration<br />
Reconstruction Plan<br />
TMAs 2006-2007 Total Cost ( m)<br />
Dassu 25 7.421<br />
Palas 01 10.00<br />
Total 26 17.421<br />
Source: Internal Sources of DRU, <strong>Kohistan</strong><br />