(BAT) Reference Document for the Production of Chlor-alkali ...
(BAT) Reference Document for the Production of Chlor-alkali ...
(BAT) Reference Document for the Production of Chlor-alkali ...
Create successful ePaper yourself
Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.
Table 4.6: Comparison <strong>of</strong> reported conversion costs<br />
Based on [UBA (A), 1998] and personal communication with plants and suppliers<br />
{The table was restricted to real conversions. The rows were reordered in alphabetical order <strong>of</strong> country names.}<br />
Source<br />
Company, location, Plant/base<br />
(year <strong>of</strong> conversion)<br />
Donau Chemie in Brückl<br />
(Austria), 1999<br />
Bayer in Dormagen (Germany),<br />
1999<br />
Borregaard in Sarpsborg<br />
(Norway), 1997<br />
Electroquímica de Hernani in<br />
Hernani (Spain), 2002<br />
Ercros in Sabiñanigo (Spain),<br />
2009<br />
Akzo Nobel, Bohus, Sweden<br />
(estimated 1997)<br />
Associated Octel in Ellesmere<br />
Port (United Kingdom), 1992<br />
[Lindley, 1997]<br />
European union, OSPARCOM<br />
impact<br />
[Lindley, 1997]<br />
European union, OSPARCOM<br />
impact<br />
Annual plant<br />
capacity<br />
[tonne Cl2] <strong>Chlor</strong>ine<br />
capacity in kt/yr<br />
60000<br />
Investment costs<br />
in original<br />
currency<br />
ATS 200 M<br />
ATS 160 M<br />
300000 DEM 240 M<br />
40000 NOK 210 M<br />
Investment<br />
costs in EUR<br />
euros<br />
(currency<br />
conversion<br />
date)<br />
14.5 M<br />
(fixed EMU<br />
conversion rate)<br />
11.6 M<br />
(fixed EMU<br />
conversion rate)<br />
122.7 M<br />
(fixed EMU<br />
conversion rate)<br />
26.6 M<br />
(October 1997)<br />
Investment costs in<br />
euros EUR/tonne<br />
annual Cl2 capacity<br />
Comments Remarks [<strong>Reference</strong>]<br />
WORKING DRAFT IN PROGRESS<br />
Chapter 4<br />
TB/EIPPCB/CAK_Draft_1 December 2011 157<br />
242<br />
194<br />
409<br />
665<br />
15 EUR 6.12 M EUR 6.12 M 408<br />
30 EUR 20 M EUR 20 M 667<br />
100000 SEK 250 M<br />
40000 GBP 11.6 M<br />
Calculation <strong>for</strong> 1<br />
tonne <strong>of</strong> <strong>Chlor</strong>ine<br />
Calculation <strong>for</strong> 1<br />
tonne <strong>of</strong> <strong>Chlor</strong>ine<br />
29 M<br />
(October 1997)<br />
14.5 M<br />
(January 1995)<br />
290<br />
362.5<br />
Power supply and cell room building reused; non-conversion costs included<br />
such as downstream modifications and increased capacity <strong>of</strong> HCl and bleach<br />
production; site clean-up not included [ 226, Schindler 2000 ], [ 234, UBA<br />
AT 1998 ].<br />
Pure conversion costs; estimated waste disposal costs included [ 226,<br />
Schindler 2000 ] , [ 234, UBA AT 1998 ].<br />
Total costs including engineering and construction (new equipment:<br />
DEM 170 M); cell room building, brine filtration, H2 and Cl2 gas treatment<br />
facilities and compressors reused; dismantling <strong>of</strong> most Hg-cells not included<br />
[ 230, Schubert 2000 ], [ 231, Chemie Produktion 2000 ].<br />
Rectifiers reused; new cell room; new brine circuit; construction and<br />
building <strong>of</strong> a landfill; non-conversion costs included [ 227, de Flon 1998 ].<br />
Hydrogen treatment and chlorine gas drying, compression, liquefaction and<br />
absorption unit reused; new cell room, new brine circuit, new rectifiers, new<br />
caustic concentration; decontamination included, soil clean-up not included<br />
[ 235, ANE 2010 ].<br />
Cell room, rectifiers, hydrogen treatment and chlorine absorption reused.<br />
New chlorine gas drying, new chlorine compression and liquefaction, new<br />
brine circuit, new caustic concentration; decontamination included, soil<br />
clean-up not included [ 235, ANE 2010 ].<br />
Rectifiers, site clean-up and waste disposal costs not included [ 233, SEPA<br />
1997 ].<br />
"Old" costs (no previous practical experience); includes <strong>the</strong> clean-up and<br />
disposal <strong>of</strong> <strong>the</strong> contaminated parts <strong>of</strong> <strong>the</strong> plant (excluding soil) [ 225, Lott<br />
1995 ].<br />
EURO 560–610 560–610 560-610 worst case assumptions; non-conversion costs included<br />
EURO 360 360 360 “ideal case”: no changes in power supply and buildings