eserves the right to seek indulgence of CONTRACTOR tomaintain the agreed Time Schedule of Completion.In such an event the CONTRACTOR shall be obliged for workingby CONTRACTOR's personnel for additional time beyondstipulated working hours as also Sundays and Holidays andachieve the completion date/interim targets.46 Payment if the contract isterminated:46.1 If the CONTRACT shall be terminated as per Tender pursuant toClause no. 29 of GCC, the CONTRACTOR shall be paid by theEMPLOYER in so far as such amounts or items shall not havealready been covered by payments of amounts made to theCONTRACTOR for the WORK executed and accepted byENGINEER-IN-CHARGE prior to the date of termination at therates and prices provided for in the CONTRACT and in additionto the following:a) The amount payable in respect of anypreliminary items, so far as the Work or servicecomprised therein has been carried out or performedand an appropriate portion as certified byENGINEER-IN- CHARGE of any such items or servicecomprised in which has been partially carried out orperformed.b) Any other expenses which the CONTRACTORhas expended for performing the WORK under theCONTRACT subject to being duly recommended byENGINEER-IN-CHARGE and approved by EMPLOYERfor payment, based on documentary evidence of hishaving incurred such expenses.46.2 The CONTRACTOR will be further required to transfer the titleand provide the following in the manner and as directed by theEMPLOYER.a) Any and all completed works.b) Such partially completed WORK includingdrawings, informations and CONTRACT rights as theCONTRACTOR has specially performed, produced oracquired for the performance of the CONTRACTOR.47 No waiver of rights: 47.1 Neither the inspection by the EMPLOYER or any of their officials,employees, or agents nor any order by the EMPLOYER forpayment of money or any payment for or acceptance of thewhole or any part of the Work by the EMPLOYER nor anyextension of time, nor any possession taken by EMPLOYERshall operate as a waiver of any provision of the CONTRACT, orof any power herein reserved to the EMPLOYER, or any right todamages herein provided, nor shall any waiver of any breach inthe CONTRACT be held to be a waiver of any other subsequentbreach.48 Certificate not to affectright of employer and48.1 No interim payment certificate(s) issued by the Engineer-in-Charge of the EMPLOYER, nor any sum paid on account by the
liability of contractor:EMPLOYER, nor any extension of time for execution of the workgranted by EMPLOYER shall affect or prejudice the rights of theEmployer against the CONTRACTOR or relieve theCONTRACTOR of his obligations for the due performance of theCONTRACT, or be interpreted as approval of the WORK done orof the equipment supplied and no certificate shall create liabilityfor the EMPLOYER to pay for alterations, amendments,variations or additional works not ordered, in writing, byEMPLOYER or discharge the liability of the CONTRACTOR forthe payment of damages whether due, ascertained, or certified ornot or any sum against the payment of which he is bound toindemnify the EMPLOYER.49 Language and measures: 49.1 All documents pertaining to the CONTRACT includingSpecifications, Schedules, Notices, Correspondence, operatingand maintenance Instructions, DRAWINGS, or any other writingshall be written in English language. The Metric System ofmeasurement shall be used in the CONTRACT unless otherwisespecified.50 Transfer of title: 50.1 The title of Ownership of supplies furnished by theCONTRACTOR shall not pass on to the EMPLOYER for allSupplies till the same are finally accepted by the EMPLOYERafter the successful completion of PERFORMANCE TEST andGUARANTEE TEST and issue of FINAL CERTIFICATE.50.2 However, the EMPLOYER shall have the lien on all such worksperformed as soon as any advance or progressive payment ismade by the EMPLOYER to the CONTRACTOR and theCONTRACTOR shall not subject these works for use other thanthose intended under this CONTRACT.51 Release of information: 51.1 The CONTRACTOR shall not communicate or use in advertising,publicity, sales releases or in any other medium, photographs, orother reproduction of the Work under this CONTRACT ordescription of the site dimensions, quantity , quality or otherinformation, concerning the Work unless prior written permissionhas been obtained from the EMPLOYER.52 Brand names: 52.1 The specific reference in the SPECIFICATIONS and documentsto any material by trade name, make or catalogue number shallbe construed as establishing standard or quality andperformance and not as limited competition. However,TENDERER may offer other similar equipments provided itmeets the specified standard design and performancerequirements.53 Completion of contract: 53.1 Unless otherwise terminated under the provisions of any otherrelevant clause, this CONTRACT shall be deemed to have beencompleted at the expiration of the PERIOD OF LIABILITY asprovided for under the CONTRACT.54 Spares: 54.1 The CONTRACTOR shall furnish to the EMPLOYER all sparesrequired for COMMISSIONING of the plants, recommendatoryand/or mandatory spares, which are required essential by themanufacturer/supplier. The same shall be delivered at SITE,3(Three) months before COMMISSIONING.Also the CONTRACTOR should furnish the manufacturing
- Page 1 and 2:
GAIL (India) LimitedTENDER DOCUMENT
- Page 3 and 4:
TABLE OF CONTENTFORVOLUME-I OF IINa
- Page 5 and 6:
\\Rajesh\RAJESH\Cavery\Tender\Const
- Page 7 and 8:
SECTION - IINVITATION FOR BIDS (IFB
- Page 9 and 10:
shall be payable by the bidder at t
- Page 11 and 12:
1.0 BRIEF PROJECT DETAILSBIDDER’S
- Page 13 and 14:
APPENDIX - ACUT-OUT SLIPS (4 NOS. )
- Page 15 and 16:
CUT-OUT SLIP - 2PART - I(UNPRICED B
- Page 17 and 18:
CUT-OUT SLIP - 4PART - III(BID SECU
- Page 19 and 20:
ACKNOWLEDGEMENT CUM CONSENT LETTERT
- Page 21 and 22:
\\Rajesh\RAJESH\Cavery\Tender\Const
- Page 23 and 24:
MEMORANDUM(a) General Description o
- Page 25 and 26:
\\Rajesh\RAJESH\Cavery\Tender\Const
- Page 27 and 28:
INSTRUCTIONS TO BIDDERSNotes on the
- Page 29 and 30:
F. Award of Contract36. Award37. Em
- Page 31 and 32:
minimum 8” NB, ANSI rating of 300
- Page 33 and 34:
• Annexure-I : Bid Evaluation Cri
- Page 35 and 36:
Part-A: Techno-commercial un-priced
- Page 37 and 38:
Statutory variations in excise duty
- Page 39 and 40:
16.9 For Indian Bidders : Indian Go
- Page 41 and 42:
iv)Permanent Income Tax number of A
- Page 43 and 44:
26.2 Priced Bid Opening26.2.1 GAIL/
- Page 45 and 46:
33.2 The domestic value addition sh
- Page 47 and 48:
the bidding documents. The Contract
- Page 49 and 50:
CONTENTSSl.No.Description1) Annexur
- Page 51 and 52:
EVALUATION /COMPARISON OF BIDS1.0 T
- Page 53 and 54:
LIST OF FORMATS{Annexure - II TO In
- Page 55 and 56:
F-1BIDDER’S GENERAL INFORMATIONTo
- Page 57 and 58:
F-2BID FORMToM/s GAIL (India) Limit
- Page 59 and 60:
F-3AFINANCIAL DETAILEACH BIDDER MUS
- Page 61 and 62:
Sheet 2 of 2INSTRUCTIONS FOR FURNIS
- Page 63 and 64:
F-5LETTER OF AUTHORITYPROFORMA FOR
- Page 65 and 66:
F-7CERTIFICATEGAIL India Limited,De
- Page 67 and 68:
F-9PRESENT COMMITMENTS OF THE BIDDE
- Page 69 and 70:
Sheet 2 of 24. The guarantee herein
- Page 71 and 72: F-12CONSTRUCTION SCHEDULE WITH BAR
- Page 73 and 74: F-14CONFIRMATION REGARDING SCHEDULE
- Page 75 and 76: COMMERCIAL QUESTIONNAIRE{Annexure -
- Page 77 and 78: Sl.MECON’s QueryNo.8. Confirm tha
- Page 79 and 80: CHECK LIST{Annexure - IV to Instruc
- Page 81 and 82: (A.3) CHECK LISTThis check list dul
- Page 83 and 84: (B.12) Confirmation regarding accep
- Page 85 and 86: (E)CONFIRM THE FOLLOWING REGARDING
- Page 87 and 88: GENERAL CONDITIONS OF CONTRACTFORPR
- Page 89 and 90: SECTION-IV (GENERAL OBLIGATIONS)21.
- Page 91 and 92: equipment, materials, labour etc.iv
- Page 93 and 94: General Conditions of ContractSecti
- Page 95 and 96: 1.1.21 "SITE" shall mean the lands
- Page 97 and 98: deducted from the running account b
- Page 99 and 100: allocated to them on the project si
- Page 101 and 102: taken as correct.c) When it is not
- Page 103 and 104: tenders received without assigning
- Page 105 and 106: 17 Award of Contract: 17.1 The Acce
- Page 107 and 108: herein and CODES referred to. Where
- Page 109 and 110: the award and the forfeiture of bid
- Page 111 and 112: The decision of the ENGINEER-IN-CHA
- Page 113 and 114: or any other person or persons, or
- Page 115 and 116: een given to him by any person.35 C
- Page 117 and 118: such sub-letting or Subcontracting
- Page 119 and 120: the CONTRACTOR before starting-up t
- Page 121: y CONTRACTOR pursuant to the provis
- Page 125 and 126: orne by the CONTRACTOR and the EMPL
- Page 127 and 128: above shall, however, not apply for
- Page 129 and 130: 63 Setting out works: 63.1 The ENGI
- Page 131 and 132: of WORK at his own cost. The materi
- Page 133 and 134: EMPLOYER's property and will be dis
- Page 135 and 136: CONTRACTOR shall be liable to pay c
- Page 137 and 138: ) As soon as reasonably practicable
- Page 139 and 140: CONTRACTOR to perform any acts, mat
- Page 141 and 142: v) SCHEDULE OF RATES TO COVER TAXES
- Page 143 and 144: CONTRACT, or any part thereof, in t
- Page 145 and 146: labour and staff colonies are clear
- Page 147 and 148: and duties (E.D. and S.T.) beyond t
- Page 149 and 150: CONTRACTOR shall require the SUB-CO
- Page 151 and 152: EMPLOYER or of a third party during
- Page 153 and 154: CONTRACTOR shall also be liable for
- Page 155 and 156: 107.2 FOR THE SETTLEMENT OF DISPUTE
- Page 157 and 158: platform of such scaffolding or sta
- Page 159 and 160: 2) Suitable facemasks should be sup
- Page 161 and 162: 119 Precautions against fire: 119.1
- Page 163 and 164: PROFORMA OF INDEMNITY BOND FOR SUPP
- Page 165 and 166: PROFORMA FOR CONTRACT AGREEMENTLOA
- Page 167: elong to the EMPLOYER and the CONTR