11.07.2015 Views

Specifications - FAACO - Federal Aviation Administration Contract ...

Specifications - FAACO - Federal Aviation Administration Contract ...

Specifications - FAACO - Federal Aviation Administration Contract ...

SHOW MORE
SHOW LESS

You also want an ePaper? Increase the reach of your titles

YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.

VESDA FIRE ALARM SYSTEM UPGRADE PROJECT NOVEMBER, 2010NEW YORK AIR ROUTE TRAFFIC CONTROL CENTER (ZNY) (REVISED AUGUST, 2011)RONKONKOMA, NEW YORKVESDA FIRE ALARM SYSTEMUPGRADE PROJECT(JCN 805563)NEW YORK AIR ROUTE TRAFFICCONTROL CENTER (ZNY)RONKONKOMA, NEW YORKSPECIFICATIONSNOVEMBER 2010(REVISED AUGUST 22, 2011)Prepared by:<strong>Federal</strong> <strong>Aviation</strong> <strong>Administration</strong>ATO Tech Ops Engineering ServicesNew York Enroute Engineering Center, AJW-E12AProject Engineer - Walter C. LauPage 1 of 190


VESDA FIRE ALARM SYSTEM UPGRADE PROJECT NOVEMBER, 2010NEW YORK AIR ROUTE TRAFFIC CONTROL CENTER (ZNY) (REVISED AUGUST, 2011)RONKONKOMA, NEW YORKSECTIONTITLEDIVISION 6 - WOOD AND PLASTICS(NOT USED)07270 FIRESTOPPINGDIVISION 7 - THERMAL AND MOISTURE PROTECTIONDIVISION 8 - DOORS AND WINDOWS(NOT USED)DIVISION 9 – FINISHES(NOT USED)DIVISION 10 – SPECIALTIES(NOT USED)DIVISION 11 – EQUIPMENT(NOT USED)DIVISION 12 – FURNISHINGS(NOT USED)DIVISION 13 – SPECIAL CONSTRUCTION13850 LASER AIR SAMPLING SMOKE DETECTION SYSTEM (THIS SECTIONREVISED AUGUST 22, 2011)13851 FIRE ALARM AND DETECTION SYSTEMS (THIS SECTION ADDEDAUGUST 22, 2011)DIVISION 15 – MECHANICAL(NOT USED)DIVISION 16 - ELECTRICAL16050 BASIC ELECTRICAL MATERIALS AND METHODSPage 3 of 190


VESDA FIRE ALARM SYSTEM UPGRADE PROJECT NOVEMBER, 2010NEW YORK AIR ROUTE TRAFFIC CONTROL CENTER (ZNY) (REVISED AUGUST, 2011)RONKONKOMA, NEW YORK16100 RACEWAYS, BOXES AND CABINETS16120 WIRES AND CABLESSECTIONTITLE16190 SUPPORTING DEVICES16195 ELECTRICAL IDENTIFICATION16452 GROUNDING* * * * *Page 4 of 190


VESDA FIRE ALARM SYSTEM UPGRADE PROJECT NOVEMBER, 2010NEW YORK AIR ROUTE TRAFFIC CONTROL CENTER (ZNY) (REVISED AUGUST, 2011)RONKONKOMA, NEW YORK1-1 SUMMARY OF WORK1-1.1 General.-1-1.1.1 Scope of work.- These specifications, together with the referenced specifications,standards, and drawings specified in the <strong>Contract</strong> Documents, cover the requirements for allwork associated with the construction of the Vesda Fire Alarm System Upgrade Project at theNew York Air Route Traffic Control Center (ZNY ARTCC) located in Ronkonkoma, New York.Following is a general description of the work:ZNY – VESDA FIRE ALARM SYSTEM UPGRADE PROJECTJCN 805563SCOPE OF WORKTHERE ARE FOUR BASIC BUILDING AREAS OF WORK:THIS SECTIONDELETED ANDREVISED1) DYSIM & CONTROL WING BASEMENT2) OPERATIONS WING BASEMENT3) CONTROL WING FIRST FLOOR4) CONTROL WING ATTIC1) DYSIM & CONTROL WING BASEMENT:A) DYSIM AREA BASEMENT:• CONTRACTOR TO REMOVE 1-DETECTOR, 1-CONTROLLER, 1-POWERSUPPLY, 1-BATTERY CABINET.• FURNISH AND INSTALL:1) ONE VESDA LASER SCANNER SMOKE DETECTOR, MODEL VLS-314WITH INTEGRAL DISPLAY, PROGRAMMER, AND SUFFICIENT ON BOARDRELAYS.2) ONE VESDA POWER SUPPLY, VESDA MODEL VPS-100US-120, WITH 2VESDA MODEL VBT-012 BATTERIES.3) ESTABLISH ONE ADDITIONAL FIRE ALARM AIR SAMPLING PIPINGZONE.4) ALL NECESSARY ACCESSORIES AND HARDWARE.Page 5 of 190


VESDA FIRE ALARM SYSTEM UPGRADE PROJECT NOVEMBER, 2010NEW YORK AIR ROUTE TRAFFIC CONTROL CENTER (ZNY) (REVISED AUGUST, 2011)RONKONKOMA, NEW YORKTHIS SECTIONDELETED ANDREVISED5) ALL NECESSARY MODIFICATIONS TO EXISTING PIPING, FIRE ALARMTERMINAL CABINET, FIRE ALARM CONTROL PANEL, FIRE ALARM ANDPOWER WIRING, FACP PROGRAMMING, ETC,.B) CONTROL WING BASEMENT:• CONTRACTOR TO REMOVE 2-DETECTORS. CONTRACTOR MAY REUSE TWOEXISTING BACKBOXES, IF NEEDED.• FURNISH AND INSTALL:1) TWO VESDA LASER SCANNER SMOKE DETECTORS, VESDA MODELVLS-304, EACH WITH INTEGRAL DISPLAY.2) TWO REMOTE TERMINATION AND RELAY PROCESSOR CARDS,VESDA PART # VRT-501.3) ESTABLISH THREE ADDITIONAL FIRE ALARM AIR SAMPLING PIPINGZONES IN EACH NEW DETECTOR.4) ALL NECESSARY ACCESSORIES AND HARDWARE.5) ALL NECESSARY MODIFICATIONS TO EXISTING PIPING, FIRE ALARMTERMINAL CABINET, FIRE ALARM CONTROL PANEL, FIRE ALARM ANDPOWER WIRING, FACP PROGRAMMING, ETC,.6) TIE-IN OF THE TWO NEW VESDA LASER SCANNER SMOKEDETECTORS, VESDA MODEL VLS-304 TO THE NEW VESDA LASERSCANNER SMOKE DETECTOR, MODEL VLS-314 LOCATED IN THEOPERATIONS WING BASEMENT.7) TIE IN OF DETECTOR ELECTRICAL POWER TO NEW POWER SUPPLYAND BACKUP BATTERIES LOCATED IN OPERATIONS WING BASEMENT.2) OPERATIONS WING BASEMENT:• CONTRACTOR TO REMOVE 2-DETECTORS, 1-CONTROLLER, 1-POWERSUPPLY, 1-BATTERY CABINET. CONTRACTOR MAY REUSE EXISTINGBACKBOXES IF NEEDED.• FURNISH AND INSTALL:1) ONE VESDA LASER SCANNER SMOKE DETECTOR, MODEL VLS-314,WITH INTEGRAL DISPLAY AND PROGRAMMER.Page 6 of 190


VESDA FIRE ALARM SYSTEM UPGRADE PROJECT NOVEMBER, 2010NEW YORK AIR ROUTE TRAFFIC CONTROL CENTER (ZNY) (REVISED AUGUST, 2011)RONKONKOMA, NEW YORK2) ONE VESDA LASER SCANNER SMOKE DETECTOR, MODEL VLS-304,WITH INTEGRAL DISPLAY.3) ) TWO REMOTE TERMINATION AND RELAY PROCESSOR CARDS,VESDA PART # VRT-501.4) ONE VESDA POWER SUPPLY, VESDA MODEL VPS-300US-120, WITH SIXVESDA BACKUP BATTERIES, VESDA PART # VBT-012.5) ONE VESDA POWER SUPPLY, VESDA MODEL VPS-100-120, WITH TWOVESDA BACKUP BATTERIES, VESDA PART # VBT-012.6) ESTABLISH THREE ADDITIONAL FIRE ALARM AIR SAMPLING PIPINGZONES AT EACH DETECTOR.7) ALL NECESSARY ACCESSORIES AND HARDWARE.THIS SECTIONDELETED ANDREVISED8) ALL NECESSARY MODIFICATIONS TO EXISTING PIPING, FIRE ALARMTERMINAL CABINET, FIRE ALARM CONTROL PANEL, FIRE ALARM ANDPOWER WIRING, FACP PROGRAMMING, ETC..3) CONTROL WING FIRST FLOOR:• MODIFY EXISTING UNDERFLOOR AIR SAMPLING PIPING AS SHOWN ONDRAWINGS, ESTABLISHING TWO ADDITIONAL FIRE ALARM AIR SAMPLINGPIPING ZONES.4) CONTROL WING ATTIC FLOOR:• CONTRACTOR TO REMOVE 4-DETECTORS, 1-CONTROLLER, 1-POWERSUPPLY, 1-BATTERY CABINET. CONTRACTOR MAY REUSE EXISTINGBACKBOXES IF NEEDED.• FURNISH AND INSTALL:1) ONE VESDA LASER SCANNER SMOKE DETECTOR, MODEL VLS-314,WITH INTEGRAL DISPLAY AND PROGRAMMER.2) THREE VESDA LASER SCANNER SMOKE DETECTORS, MODEL VLS-304,WITH INTEGRAL DISPLAY.Page 7 of 190


VESDA FIRE ALARM SYSTEM UPGRADE PROJECT NOVEMBER, 2010NEW YORK AIR ROUTE TRAFFIC CONTROL CENTER (ZNY) (REVISED AUGUST, 2011)RONKONKOMA, NEW YORK3) ONE VESDA POWER SUPPLY, VESDA MODEL VPS-300US-120, WITH SIXVESDA BACKUP BATTERIES, VESDA PART # VBT-012.4) ONE VESDA POWER SUPPLY, VESDA MODEL VPS-100US-120, WITHTWO VESDA BACKUP BATTERIES, VESDA PART # VBT-012.5) ESTABLISH 1 ADDITIONAL FIRE ALARM AIR SAMPLING PIPING ZONESAT 1 0F 4 DETECTORS.6) ESTABLISH 2 ADDITIONAL FIRE ALARM AIR SAMPLING PIPING ZONESAT 1 0F 4 DETECTORS.7) ESTABLISH TWO ADDITIONAL FIRE ALARM AIR SAMPLING PIPINGZONES AT 2 0F 4 DETECTORS.8) ALL NECESSARY ACCESSORIES AND HARDWARE.THIS SECTIONDELETED ANDREVISED9) ALL NECESSARY MODIFICATIONS TO EXISTING PIPING, FIRE ALARMTERMINAL CABINET, FIRE ALARM CONTROL PANEL, FIRE ALARM ANDPOWER WIRING, FACP PROGRAMMING, ETC..NOTE:1. IF CONTRACTOR ENCOUNTERS ANY HAZARDUOUS, OR CONTROLLEDWASTE, HE SHALL DISPOSE OF THE MATERIAL IN ACCORDANCE WITH ALLFAA STANDARDS AND ORDERS, ALL NATIONAL STANDARDS AND ALLSTATE AND LOCAL REQUIREMENTS.2. ALL AIR SAMPLING PIPING SHOWN ON DRAWINGS IS EXISTING. LOCATIONSARE DIAGRAMMATIC ONLY. CONTRACTOR TO FIELD VERIFY LOCATION OFALL AIR SAMPLING PIPING AND RECORD CONFIGURATION AND LOCATIONON PROJECT DRAWINGS.3. CONTRACTOR TO VERIFY AND CONFIRM IN WRITING TO THE COTR THATTHE EXISTING AIR SAMPLING PIPING IS FREE OF ANY OBSTRUCTIONS ANDIS CONTINUOUS THROUGHOUT. IF ANY OBSTRUCTIONS AREENCOUNTERED CONTRACTOR IS TO REMOVE THOSE OBSTRUCTIONS.4. CONTRACTOR TO VERIFY THAT THE REPLACEMENT VESDA DETECTORMODEL VLS314 IS FULLY COMPATIBLE WITH EXISTING FIRE ALARMPage 8 of 190


VESDA FIRE ALARM SYSTEM UPGRADE PROJECT NOVEMBER, 2010NEW YORK AIR ROUTE TRAFFIC CONTROL CENTER (ZNY) (REVISED AUGUST, 2011)RONKONKOMA, NEW YORKTHIS SECTIONDELETED ANDSYSTEM AND EXISTING AIR SAMPLING PIPING AND THAT THERE IS NOEXISITNG CONDITION THAT WOULD PREVENT THE NEW EQUIPMENT ANDINSTALLATION FROM MEETING, OR EXCEEDING, MANUFACTURER’S REVISEDRECOMMENDED CRITERIA AND THE PROJECT’S OBJECTIVES.CONTRACTOR TO SUBMIT VERIFICATION IN WRITING TO COTR FORAPPROVAL.5. WHEN COMPLETED THERE WILL BE A TOTAL OF 29 FIRE ALARM AIRSAMPLING PIPING ZONES ANUNCIATING AT THE FACILITY’S FIRE ALARMCONTROL PANEL. EACH FIRE ALARM AIR SAMPLING PIPING ZONE WILLHAVE FOUR SMOKE THRESHOLD ALARM LEVELS.6. CONTRACTOR SHALL PROVIDE IN DEPTH, MANUFACTURER APPROVEDTRAINING, ON SITE, FOR UP TO FOUR FAA EMPLOYEES ON EACH OF THREESHIFTS. TRAINING SHALL INCLUDE REPROGRAMMING OF VESDACONTOLLERS, PREVENTIVE MAINTENANCE, TROUBLESHOOTING, ANDCLEANING OF AIR SAMPLING PIPING, IN ADDITION TO THE FACTORYAUTHORIZED END USER TRAINING.7. AT 4, 8, AND 12 MONTHS AFTER ACCEPTANCE OF SYSTEM, CONTRACTORSHALL RETURN TO FACILITY AND RE-VERIFY ALL SYSTEM CHECKSDELINEATED IN THE SPECIFICATION. CONTRACTOR WILL DOCUMENT INWRITING THE RESULTS OF THE SYSTEM CHECKS RE-VERIFICATION, ANDSUBMIT TO THE FACILITY. IF ANY PARAMETERS ARE OUT OF RANGE, OR IFTHE FACILITY DEEMS IT NECESSARY, CONTRACTOR WILL REPROGRAMSYSTEM AS NEEDED, OR REQUIRED.8. CONTRACTOR SHALL REPLACE ALL POWER WIRING FROM NEAREST HOMERUN JUNCTION BOX TO NEW EQUIPMENT AND DEVICES. CONTRACTORSHALL ALSO REPLACE ALL FIRE ALARM WIRING FROM EXISTING FIREALARM LOOP TO NEW EQUIPMENT AND DEVICES. CONTRACTOR SHALLALSO REPLACE ALL WIRING BETWEEN ALL COMPONENTS OF THE VESDAFIRE ALARM SYSTEM.Page 9 of 190


VESDA FIRE ALARM SYSTEM UPGRADE PROJECT NOVEMBER, 2010NEW YORK AIR ROUTE TRAFFIC CONTROL CENTER (ZNY) (REVISED AUGUST, 2011)RONKONKOMA, NEW YORKSCOPE OF WORK(REVISED AUGUST 22, 2011)THERE ARE FOUR BASIC BUILDING AREAS OF WORK:1) BASEMENT DYSIM AREA, ADJACENT TO CONTROL WING BASEMENT AREA.2) CONTROL WING BASEMENT.3) OPERATIONS WING BASEMENT.4) CONTROL WING ATTIC.1) BASEMENT DYSIM AREA, ADJACENT TO CONTROL WING BASEMENT AREA• CONTRACTOR TO REMOVE 1-DETECTOR, 1-CONTROLLER, 1-POWERSUPPLY, 1-BATTERY CABINET.• FURNISH AND INSTALL:1) ONE VESDA LASER PLUS SMOKE DETECTOR, MODEL VLP-012, WITHINTEGRAL DISPLAY MODULE, LCD PROGRAMMER, FIRE AND OK LEDS(FOK) AND SUFFICIENT ON BOARD RELAYS.2) ONE VESDA POWER SUPPLY, VESDA MODEL VPS-100US-120, WITH 2VESDA MODEL VBT-012 BATTERIES.3) ALL NECESSARY ACCESSORIES AND HARDWARE.4) ALL NECESSARY MODIFICATIONS TO EXISTING PIPING, FIRE ALARMTERMINAL CABINET, FIRE ALARM CONTROL PANEL, FIRE ALARM ANDPOWER WIRING, FACP PROGRAMMING, ETC,.2) CONTROL WING BASEMENT:• CONTRACTOR TO REMOVE 2-DETECTORS. CONTRACTOR MAY REUSE TWOEXISTING BACKBOXES, IF NEEDED.• FURNISH AND INSTALL:1) TWO VESDA LASER PLUS SMOKE DETECTOR, MODEL VLP-012, WITHINTEGRAL DISPLAY MODULE, LCD PROGRAMMER, FIRE AND OK LEDS(FOK) AND SUFFICIENT ON BOARD RELAYS.Page 10 of 190


VESDA FIRE ALARM SYSTEM UPGRADE PROJECT NOVEMBER, 2010NEW YORK AIR ROUTE TRAFFIC CONTROL CENTER (ZNY) (REVISED AUGUST, 2011)RONKONKOMA, NEW YORK2) ALL NECESSARY ACCESSORIES AND HARDWARE.3) ALL NECESSARY MODIFICATIONS TO EXISTING PIPING, FIRE ALARMTERMINAL CABINET, FIRE ALARM CONTROL PANEL, FIRE ALARM ANDPOWER WIRING, FACP PROGRAMMING, ETC,.4) TIE IN OF DETECTOR ELECTRICAL POWER TO NEW POWER SUPPLYAND BACKUP BATTERIES LOCATED IN OPERATIONS WING BASEMENT.3) OPERATIONS WING BASEMENT:• CONTRACTOR TO REMOVE 2-DETECTORS, 1-CONTROLLER, 1-POWERSUPPLY, 1-BATTERY CABINET. CONTRACTOR MAY REUSE EXISTINGBACKBOXES IF NEEDED.• FURNISH AND INSTALL:1) TWO VESDA LASER PLUS SMOKE DETECTOR, MODEL VLP-012, WITHINTEGRAL DISPLAY MODULE, LCD PROGRAMMER, FIRE AND OK LEDS(FOK) AND SUFFICIENT ON BOARD RELAYS.2) ONE VESDA POWER SUPPLY, VESDA MODEL VPS-300US-120, WITH SIXVESDA BACKUP BATTERIES, VESDA PART # VBT-012.3) ONE VESDA POWER SUPPLY, VESDA MODEL VPS-100-120, WITH TWOVESDA BACKUP BATTERIES, VESDA PART # VBT-012.4) ALL NECESSARY ACCESSORIES AND HARDWARE.5) ALL NECESSARY MODIFICATIONS TO EXISTING PIPING, FIRE ALARMTERMINAL CABINET, FIRE ALARM CONTROL PANEL, FIRE ALARM ANDPOWER WIRING, FACP PROGRAMMING, ETC.4) CONTROL WING ATTIC:• CONTRACTOR TO REMOVE 4-DETECTORS, 1-CONTROLLER, 1-POWERSUPPLY, 1-BATTERY CABINET. CONTRACTOR MAY REUSE EXISTINGBACKBOXES IF NEEDED.Page 11 of 190


VESDA FIRE ALARM SYSTEM UPGRADE PROJECT NOVEMBER, 2010NEW YORK AIR ROUTE TRAFFIC CONTROL CENTER (ZNY) (REVISED AUGUST, 2011)RONKONKOMA, NEW YORK• FURNISH AND INSTALL:1) FOUR VESDA LASER PLUS SMOKE DETECTOR, MODEL VLP-012, WITHINTEGRAL DISPLAY MODULE, LCD PROGRAMMER, FIRE AND OK LEDS(FOK) AND SUFFICIENT ON BOARD RELAYS.2) ONE VESDA POWER SUPPLY, VESDA MODEL VPS-300US-120, WITH SIXVESDA BACKUP BATTERIES, VESDA PART # VBT-012.3) ONE VESDA POWER SUPPLY, VESDA MODEL VPS-100US-120, WITHTWO VESDA BACKUP BATTERIES, VESDA PART # VBT-012.4) ALL NECESSARY ACCESSORIES AND HARDWARE.5) ALL NECESSARY MODIFICATIONS TO EXISTING PIPING, FIRE ALARMTERMINAL CABINET, FIRE ALARM CONTROL PANEL, FIRE ALARM ANDPOWER WIRING, FACP PROGRAMMING, ETC.NOTES:1. THE INTENT OF THIS PROJECT IS TO MAINTAIN THE EXISTING PIPINGNETWORK AS INSTALLED AND CONNECT TO THE NEW VESDA VLP SMOKEDETECTOR UNITS, PROVIDED THE MAXIMUM AIR SAMPLE TRANSPORT TIMEFROM THE MOST REMOTE AIR SAMPLING PORT TO THE DETECTOR DOES NOTEXCEED 120 SECONDS, IN ACCORDANCE WITH NFPA 72. INDIVIDUAL ZONINGOF THE SAMPLING PIPING IS NOT REQUIRED.2. ALL AIR SAMPLING PIPING SHOWN ON DRAWINGS IS EXISTING. LOCATIONSARE DIAGRAMMATIC ONLY. CONTRACTOR TO FIELD VERIFY LOCATION OFALL AIR SAMPLING PIPING AND RECORD CONFIGURATION AND LOCATIONON PROJECT DRAWINGS.3. CONTRACTOR TO VERIFY, AND CONFIRM IN WRITING, TO THE COTR THATTHE EXISTING AIR SAMPLING PIPING IS FREE OF ANY OBSTRUCTIONS ANDIS CONTINUOUS THROUGHOUT. IF ANY OBSTRUCTIONS AREENCOUNTERED CONTRACTOR IS TO REMOVE THOSE OBSTRUCTIONS.4. CONTRACTOR TO VERIFY THAT THE REPLACEMENT VESDA DETECTORMODEL VLP-012 IS FULLY COMPATIBLE WITH THE EXISTING FIRE ALARMPage 12 of 190


VESDA FIRE ALARM SYSTEM UPGRADE PROJECT NOVEMBER, 2010NEW YORK AIR ROUTE TRAFFIC CONTROL CENTER (ZNY) (REVISED AUGUST, 2011)RONKONKOMA, NEW YORKSYSTEM AND THE EXISTING AIR SAMPLING PIPING, AND THAT THERE IS NOEXISITNG CONDITION THAT WOULD PREVENT THE NEW EQUIPMENT ANDINSTALLATION FROM MEETING, OR EXCEEDING, MANUFACTURER’SRECOMMENDED CRITERIA AND THE PROJECT’S OBJECTIVES.CONTRACTOR TO SUBMIT THE VERIFICATION OF THE PRECEDING INWRITING TO COTR FOR APPROVAL.5. CONTRACTOR SHALL PERFORM ALL TESTING OF NEW AND EXISTINGSYSTEMS AS REQUIRED BY NFPA 72 – NATIONAL FIRE ALARM ANDSIGNALING CODE.6. WHEN COMPLETED THERE WILL BE A TOTAL OF 9 FIRE ALARM AIRSAMPLING PIPING ZONES ANUNCIATING AT THE FACILITY’S FIRE ALARMCONTROL PANEL.7. OUTPUT TO THE MAIN FIRE ALARM CONTROL PANEL WILL BE PROVIDEDTHROUGH 4 ADDRESSABLE MONITOR POINTS PER EACH VLP SMOKEDETECTOR. THE FOLLOWING OUTPUTS FROM EACH VLP SMOKE DETECTORUNIT SHALL BE MONITORED WITH ADDRESSABLE MONITOR MODULES:a. FIRE 1 (ALARM) – RELAY 6 – ALARM CONDITION TO THE FACP.b. ACTION – RELAY 5 – SUPERVISORY CONDITION TO THE FACP.c. ALERT – RELAY 4 – SUPERVISORY CONDITION TO THE FACP.d. FAULT (TROUBLE) – RELAYS 2 AND 3 – THESE TWO RELAYS MAYMONITORED BY THE SAME ADDRESSABLE MODULE – TROUBLECONDITION TO THE FACP.8. OFF-NORMAL CONDITIONS WILL LATCH AT EACH VLP PANEL TO PREVENTTHE CONDITION FROM BEING TRANSMITTED REPEATEDLY TO THE FIREALARM CONTROL PANEL.9. ALARM THRESHOLDS FOR THE ALERT, ACTION AND FIRE CONDITONS WILLBE SET AS FOLOWS:a. ALERT – 0.02% SUPERVISORY CONDITION TO THE FACP.b. ACTION – 0.03% SUPERVISORY CONDITION TO THE FACP.Page 13 of 190


VESDA FIRE ALARM SYSTEM UPGRADE PROJECT NOVEMBER, 2010NEW YORK AIR ROUTE TRAFFIC CONTROL CENTER (ZNY) (REVISED AUGUST, 2011)RONKONKOMA, NEW YORKc. FIRE – 1.0% OBS/FT MINIMUM OBSCURATION – ALARM CONDITION TOTHE FACP, IN THOSE AREAS THAT DO NOT HAVE EXISTING SPOT SMOKEDETECTORS.d. IN AREAS THAT HAVE EXISTING SPOT SMOKE DETECTORS, THE VESDAVLP SENSITIVITY WILL BE SET TO THE SAME OBSCURATION LEVEL AS THEEXISTING SPOT TYPE SMOKE DETECTORS.10. CONTRACTOR SHALL PROVIDE IN DEPTH, MANUFACTURER APPROVEDTRAINING, ON SITE, FOR UP TO FOUR FAA EMPLOYEES ON EACH OF THREESHIFTS. TRAINING SHALL INCLUDE REPROGRAMMING OF VESDACONTOLLERS, PREVENTIVE MAINTENANCE, TROUBLESHOOTING, ANDCLEANING OF AIR SAMPLING PIPING, IN ADDITION TO THE FACTORYAUTHORIZED END USER TRAINING.11. AT 4, 8, AND 12 MONTHS AFTER ACCEPTANCE OF SYSTEM, CONTRACTORSHALL RETURN TO FACILITY AND RE-VERIFY ALL SYSTEM CHECKSDELINEATED IN THE SPECIFICATION. CONTRACTOR WILL DOCUMENT INWRITING THE RESULTS OF THE SYSTEM CHECKS RE-VERIFICATION, ANDSUBMIT TO THE FACILITY. IF ANY PARAMETERS ARE OUT OF RANGE, OR IFTHE FACILITY DEEMS IT NECESSARY, CONTRACTOR WILL REPROGRAMSYSTEM AS NEEDED, OR REQUIRED.12. CONTRACTOR SHALL REPLACE ALL POWER WIRING FROM NEAREST HOMERUN JUNCTION BOX TO NEW EQUIPMENT AND DEVICES. CONTRACTORSHALL ALSO REPLACE ALL FIRE ALARM WIRING FROM EXISTING FIREALARM LOOPS TO THE NEW EQUIPMENT AND DEVICES. CONTRACTORSHALL ALSO REPLACE ALL WIRING BETWEEN ALL COMPONENTS OF THEVESDA FIRE ALARM SYSTEM.13. CONTRACTOR SHALL ALSO MODIFY, AND OR ADD, CONDUIT AND WIRINGTO MEET THE REQUIREMNTS OF THE SPECIFICATIONS, AS REQUIRED.14. IF CONTRACTOR ENCOUNTERS ANY HAZARDUOUS, OR CONTROLLEDWASTE, HE SHALL DISPOSE OF THE MATERIAL IN ACCORDANCE WITH ALLFAA STANDARDS AND ORDERS, ALL NATIONAL STANDARDS AND ALLSTATE AND LOCAL REQUIREMENTS.15. ALL NEW CONDUIT AND OUTLET BOXES SHALL BE PAINTED RED ANDLABELED IN ACCORDANCE WITH NFPA 72.Page 14 of 190


VESDA FIRE ALARM SYSTEM UPGRADE PROJECT NOVEMBER, 2010NEW YORK AIR ROUTE TRAFFIC CONTROL CENTER (ZNY) (REVISED AUGUST, 2011)RONKONKOMA, NEW YORK<strong>Contract</strong> duration for completion of all work shall be 180 calendar days, excluding FAAholiday moratorium periods specified in Division 1-5.1-1.1.2 Intent of specifications.-(a)(b)This specification identifies all labor and equipment to perform the work required toconstruct the facility. All work performed and all materials and equipment used shall beapproved by the <strong>Contract</strong>ing Officer (CO). This shall include but not be limited toconstruction testing, inspection, scheduling, reporting, and submittals.Titles.- Titles to division and sections of the specifications and notes and titles on drawingsreferring to subcontractors, division of work by trade, or type of work, are introducedmerely for convenience in reading the specifications and drawings and do not imply anyseparate contractual arrangements of work assignments. Such separations into titleddivisions and sections shall not operate to make the Government an arbiter to establishsubcontract limits between the contractor and subcontractors, or between the subcontractorsthemselves.1-1.1.3 <strong>Contract</strong> documents.-(a)The construction of this facility shall be in accordance with the lines and grades shown onthe drawings. The contractor shall not use dimensions scaled from drawings. Alldimensions shown on the drawings shall be verified by the contractor by actualmeasurements in the field. Any discrepancies between the drawings and specifications andthe existing conditions shall be referred to the CO for adjustment before any work affectedis performed.1-1.1.4 Precedence of contract documents.-(a)In the event of a difference between the following contract provisions, the order ofprecedence to determine which provision shall govern is:1. <strong>Contract</strong> Clauses and Provisions2. Project <strong>Specifications</strong>3. Project Drawings as listed in Part III - Section J(b)Any discrepancies between the contract provisions, the specifications and the contractdrawings shall be referred to the CO for a written determination in accordance withPage 15 of 190


VESDA FIRE ALARM SYSTEM UPGRADE PROJECT NOVEMBER, 2010NEW YORK AIR ROUTE TRAFFIC CONTROL CENTER (ZNY) (REVISED AUGUST, 2011)RONKONKOMA, NEW YORK<strong>Contract</strong> Clause entitled SPECIFICATION AND DRAWINGS FOR CONSTRUCTION.Refer to Part II, Section I.1-1.1.5 <strong>Contract</strong>ing Officer. - The term "<strong>Contract</strong>ing Officer" (CO) as used herein denotes theperson designated to act on behalf of the Government in the performance of this contract. Wherereference is made to "<strong>Federal</strong> <strong>Aviation</strong> <strong>Administration</strong>" (FAA), "Resident Engineer" (RE),"<strong>Contract</strong>ing Officer's Representative" (COR), or the like, this shall mean the <strong>Contract</strong>ing Officeror his/her authorized representative.1-1.1.6 <strong>Contract</strong>or Superintendence.- In accordance with <strong>Contract</strong> Clause entitledSUPERINTENDENCE BY THE CONTRACTOR, the <strong>Contract</strong>or shall at all times duringperformance of this contract and until the work is completed and accepted, directly superintendthe work or assign and have on site a competent superintendent with the authority to act for the<strong>Contract</strong>or.END OF SECTIONPage 16 of 190


VESDA FIRE ALARM SYSTEM UPGRADE PROJECT NOVEMBER, 2010NEW YORK AIR ROUTE TRAFFIC CONTROL CENTER (ZNY) (REVISED AUGUST, 2011)RONKONKOMA, NEW YORK1-2 SITE ACCESS, CONSTRUCTION LIMITS, USE OF FACILITIES AND WORK HOURS1-2.1 General.-1-2.1.1 Existing facility operations.- The ARTCC is a 24 hour, 7 day per week operatingfacility. The <strong>Contract</strong>or shall perform all work in a manner which does not conflict with oradversely affect the air traffic operational environment or functions of the ARTCC. In the eventof any actual or potential conflict, air traffic control activities shall have priority over all<strong>Contract</strong>or activities. The <strong>Contract</strong>or shall plan for and provide services in such a manner and atsuch times that will not disrupt facility operations, and shall conform to those proceduresconsidered essential by the FAA for ensuring air traffic safety.1-2.1.2 Construction limits and access.-(a)(b)(c)(d)(e)(f)The contractor shall confine operations, activities, storage of materials and employeeparking within the designated area, as indicated on the drawings. Additional space thecontractor deems necessary shall be obtained off site, at no additional cost to theGovernment.Access for the contractor, sub-contractors, employees, deliveries, etc., will be inapproximate locations as indicated on the construction staging plan. And as directed by theCOR.Access to the construction site shall be kept unobstructed. If temporary access obstructionis unavoidable, the contractor shall advise the Resident Engineer (RE) immediately.Temporary roadways and/or other access may be authorized only by the facility, via the RE.Vehicles transporting materials shall not be loaded beyond the capacity prescribed by<strong>Federal</strong>, State or Local law.Obstruction of existing roadways, driveways, etc., to the ARTCC is strictly prohibited.Access to the loading dock and ramp shall be maintained.(g) Damage caused by the contractor's activities to existing paving, lawns, curbs, sidewalks,interior/exterior of the building shall be repaired. All costs of repairs shall be paid by thecontractor. After notice to proceed and prior to the commencement of construction, thecontractor and RE shall conduct joint inspections of the existing areas affected by theconstruction. Existing damage/defects shall be noted and will be used as the basis fordetermination of damages caused by the contractor's operations.1-2.1.3 <strong>Contract</strong>or's use of premises.-(a)<strong>Contract</strong>or shall assume full responsibility for the protection and safekeeping of productsstored on the site.Page 17 of 190


VESDA FIRE ALARM SYSTEM UPGRADE PROJECT NOVEMBER, 2010NEW YORK AIR ROUTE TRAFFIC CONTROL CENTER (ZNY) (REVISED AUGUST, 2011)RONKONKOMA, NEW YORK(b)(c)(d)The contractor and his subcontractors shall maintain the job site in a neat and orderlycondition - This includes the daily removal of rubbish, waste and tools, equipment andmaterials not required for the work in progress.Concessionaires shall not be allowed on the grounds of the facility.Use of the cafeteria is permitted providing the privilege is coordinated with the COR inorder not to conflict with FAA personnel lunch shifts.1-2.1.4 Government use and access to premises.-(a)(b)The Government reserves the right to enter the premises during the term of the contract forperiodic work inspections and for maintenance of existing equipment. The <strong>Contract</strong>or shallallow the CO and RE complete access to all portions of the work.See Part II, Section I, <strong>Contract</strong> Clause entitled OTHER CONTRACTS, for work by othercontractors.1-2.1.5 Work hours.- (REVISED AUGUST 2011)Work shall be performed as follows :DYSIM AREA BASEMENT – 4:00 P.M. TO 12:00 A.M.OPERATIONS AND CONTROL WING BASEMENT – 12:00 A.M. TO 5:30 A.M.(Revised August 2011)CONTROL ROOM – 12:00 A.M. TO 5:30 A.M.CONTROL ROOM ATTIC – 7:00 A.M. TO 4:00 P.M.ADMINISTRATION SPACES – 4:00 P.M. TO 12:00 A.M.EQUIPMENT ROOMS – 12:00 A.M. TO 5:30 A.M.(Revised August 2011)CRITICAL TIE-INS - 12:00 A.M. TO 5:30 A.M.ALL FIRE ALARM TIE-INS – 12:00 A.M. TO 5:30 A.M.Except for the following:Page 18 of 190


VESDA FIRE ALARM SYSTEM UPGRADE PROJECT NOVEMBER, 2010NEW YORK AIR ROUTE TRAFFIC CONTROL CENTER (ZNY) (REVISED AUGUST, 2011)RONKONKOMA, NEW YORKa) Shutdowns and cutovers of environmental, utility and electrical systems impacting thefacility operations shall be accomplished between the hours of 12 a.m. and 5:30 a.m. Allpreparatory work shall be completed prior to shutdown/cutover to minimize downtime.Shutdown and cutovers shall be scheduled and coordinated with the RE a minimum of 10working days in advance of the shutdown/cutover.(b)No work shall be scheduled or take place during the week of and the weekend precedingand following the Thanksgiving, Christmas and New Years Holidays. Only emergencywork to restore critical services to the facility will be considered and a moratorium waivermust be submitted and approved. The moratorium period will not be counted against thecontract construction duration for the project.1-2.1.6 Notification of planned overtime work.- In the event the contractor intends to workovertime, nights, weekends or holidays, he shall notify the RE, who will coordinate with the COfor approval, at least 24 hours in advance of his commencement of the overtime work and 48hours prior to night, weekend or holiday work.1-2.1.7 Security requirements.-A. Refer to <strong>Contract</strong> Clauses, attachments and guidelines provided by the <strong>Contract</strong>ing Officerat the Preconstruction Meeting.END OF SECTIONPage 19 of 190


VESDA FIRE ALARM SYSTEM UPGRADE PROJECT NOVEMBER, 2010NEW YORK AIR ROUTE TRAFFIC CONTROL CENTER (ZNY) (REVISED AUGUST, 2011)RONKONKOMA, NEW YORK1-3 CONTRACTOR QUALITY CONTROL, SAFETY, COORDINATION, PERMITS,TESTING1-3.1 General. - The <strong>Contract</strong>or is responsible for quality control and shall establish and maintainan effective quality control system in compliance with the <strong>Contract</strong> Clause entitled "Inspection ofConstruction." The quality control system shall consist of plans, procedures, and organizationnecessary to produce an end product which complies with the contract requirements. The systemshall cover all construction operations, both on-site and off-site, and shall be keyed to theproposed construction sequence.1-3.2 Quality Control Plan.-1-3.2.1 General.- The <strong>Contract</strong>or shall furnish for review by the Government, not later than30 days after receipt of notice to proceed, the <strong>Contract</strong>or Quality Control (CQC) Plan proposed toimplement the requirements of the <strong>Contract</strong> Clause entitled "Inspection of Construction." Theplan shall identify personnel, procedures, control, instructions, test, records, and forms to beused. The <strong>Contract</strong>or shall provide an interim plan for the first 30 days of operation WITHIN 14DAYS AFTER AWARD OF CONTRACT. Construction will be permitted to begin only afteracceptance of the CQC Plan or acceptance of an interim plan applicable to the particular featureof work to be started. Work outside of the features of work included in an accepted interim planwill not be permitted to begin until acceptance of a CQC Plan or another interim plan containingthe additional features of work to be started.1-3.2.2 Content of the CQC Plan.- The CQC plan shall include, as a minimum, the following tocover all construction operations, both on-site and off-site, including work by subcontractors,fabricators, suppliers and purchasing agents:(a)(b)(c)A description of the quality control organization, including a chart showing lines ofauthority and acknowledgment that the CQC staff shall implement the three phase controlsystem for all aspects of the work specified. The staff shall include a CQC system managerwho shall report to the project manager or someone higher in the <strong>Contract</strong>or's organization.Project manager in this context shall mean the individual with responsibility for the overallmanagement of the project including quality and production.The name, qualifications (in resume format), duties, responsibilities, and authorities of eachperson assigned a QC function.A copy of the letter to the CQC System Manager signed by an authorized official of thefirm which describes the responsibilities and delegates sufficient authorities to adequatelyperform the functions of the CQC System Manager including authority to stop work whichis not in compliance with the contract. The CQC System Manager shall issue letters ofdirection to all other various quality control representatives outlining duties, authorities andresponsibilities. Copies of these letters will also be furnished to the Government.Page 20 of 190


VESDA FIRE ALARM SYSTEM UPGRADE PROJECT NOVEMBER, 2010NEW YORK AIR ROUTE TRAFFIC CONTROL CENTER (ZNY) (REVISED AUGUST, 2011)RONKONKOMA, NEW YORK(d)(e)(f)(g)(h)(i)Procedures for scheduling, reviewing, certifying, and managing submittals, including thoseof subcontractors, off-site fabricators, suppliers and purchasing agents. These proceduresshall be in accordance with Section 1-7 SUBMITTALS.Control, verification and acceptance testing procedures for each specific test to include thetest name, specification paragraph requiring test, feature of work to be tested, testfrequency, and person or laboratory responsible for each test.Procedures for tracking preparatory, initial, and follow-up control phases and control,verification, and acceptance tests including documentation.Procedures for tracking construction deficiencies from identification through acceptablecorrective action. These procedures will establish verification that identified deficiencieshave been corrected.Reporting procedures, including proposed reporting formats.A list of the definable features of work. A definable feature of work is a task which isseparate and distinct from other tasks and has separate control requirements. It could beidentified by different trades or disciplines, or it could be work by the same trade in adifferent environment. Although each section of the specifications may generally beconsidered as a definable feature of work, there are frequently more than one definablefeature under a particular section. This list will be reviewed for concurrence during thecoordination meeting.1-3.2.3 Acceptance of Plan.- Acceptance of the <strong>Contract</strong>or's CQC plan is required prior to thestart of construction. Acceptance is conditional and will be predicated on satisfactoryperformance during the construction. The Government reserves the right to require the<strong>Contract</strong>or to make changes in his CQC plan and operations including removal of personnel, asnecessary, to obtain the quality specified.1-3.2.4 Notification of Changes.- After acceptance of the QC plan, the <strong>Contract</strong>or shall notifythe <strong>Contract</strong>ing Officer in writing a minimum of seven calendar days prior to any proposedchange. Proposed changes are subject to acceptance by the <strong>Contract</strong>ing Officer.1-3.3 Coordination Meeting.- After the Preconstruction Conference, before start of construction,and prior to acceptance by the Government of the Quality Control Plan, the <strong>Contract</strong>or shall meetwith the <strong>Contract</strong>ing Officer or Authorized Representative and discuss the <strong>Contract</strong>or's qualitycontrol system. During the meeting, a mutual understanding of the system details shall bedeveloped, including the forms for recording the CQC operations, control activities, testing,administration of the system for both on-site and off-site work, and the interrelationship of<strong>Contract</strong>or's Management and control with the Government's Quality Assurance. Minutes of themeeting will be prepared by the <strong>Contract</strong>or and signed by both the <strong>Contract</strong>or and the<strong>Contract</strong>ing Officer. The minutes shall become a part of the contract file. There may beoccasions when subsequent conferences will be called by either party to reconfirm mutualPage 21 of 190


VESDA FIRE ALARM SYSTEM UPGRADE PROJECT NOVEMBER, 2010NEW YORK AIR ROUTE TRAFFIC CONTROL CENTER (ZNY) (REVISED AUGUST, 2011)RONKONKOMA, NEW YORKunderstandings and/or address deficiencies in the CQC system or procedures which may requirecorrective action by the <strong>Contract</strong>or.1-3.4 Quality Control Organization.-1-3.4.1 General.- The quality control system manager and surveillance personnel shall be fullyqualified by experience and background to perform their assigned responsibilities.1-3.4.2 System Manager.- The <strong>Contract</strong>or shall identify an individual, within his organization atthe site of the work as <strong>Contract</strong>or Quality Control System Manager, who shall be responsible foroverall management and have the authority to act in all <strong>Contract</strong>or's Quality Control (CQC)matters for the <strong>Contract</strong>or; for this project it is allowed to have the project superintendent actas the CQC System Manager. The designated System Manager shall have a minimum of 5years experience in supervision or inspection of building construction projects of complexity,magnitude, and type of work similar to the project or prior approval of the <strong>Contract</strong>ing Officer.The System Manager's performance shall be acceptable to the <strong>Contract</strong>ing Officer, andacceptability will be based principally on timeliness, accuracy, and completeness of the CQC'sassessment of the condition of the elements of contract work. <strong>Contract</strong> work will not bepermitted to be performed without an acceptable incumbent CQC System Manager onsite unlessspecifically authorized by the <strong>Contract</strong>ing Officer.1-3.5 Quality Control Meetings.- The <strong>Contract</strong>or's Project Manager shall meet with the<strong>Contract</strong>ing Officer or the <strong>Contract</strong>ing Officer's Authorized Representative at regular intervals,weekly or monthly as considered necessary by the <strong>Contract</strong>ing Officer, to assess the effectivenessof the Quality Control system. Special meetings may be called at any time when desired by the<strong>Contract</strong>ing Officer. Reports will be reviewed to determine their effectiveness in the overallQuality Control system. Particular emphasis will be placed on discussion of methods toeliminate the recurrence of problem areas.1-3.6 Submittals.- Procedures for processing shop drawings, samples, certificates, and othersubmittals shall be developed and submitted for approval as part of the <strong>Contract</strong>or's QualityControl Plan. The procedures shall include the establishment of responsibilities to assure at eachlevel adequate review and approval; timely delivery, including verification procedures; andproper storage.1-3.6.1 Certification.- The <strong>Contract</strong>or is responsible for, and the Quality Control manager shallcertify that, the submittals comply with contract requirements. Submittals shall be as specified inSection 1-7 SUBMITTALS.1-3.6.2 Government Approved Submittals.- Submittals requiring Government approval will beidentified as having received <strong>Contract</strong>or approval by being so stamped and dated. Delays in theapproval process shall not be the basis for consideration of a time extension when such delay isthe result of the <strong>Contract</strong>or's failure to make proper submittal or make corrections in accordancewith the specifications or the <strong>Contract</strong>ing Officer's comments or is the result of a resubmittalwhich is required because of an unsatisfactory original submittal. Approval action will notPage 22 of 190


VESDA FIRE ALARM SYSTEM UPGRADE PROJECT NOVEMBER, 2010NEW YORK AIR ROUTE TRAFFIC CONTROL CENTER (ZNY) (REVISED AUGUST, 2011)RONKONKOMA, NEW YORKrelieve the <strong>Contract</strong>or of his responsibility for compliance with the contract but will indicate onlythat the general method of construction and detailing is satisfactory.1-3.6.3 Deviations.- All proposed deviations from contract requirements shall be submitted inwriting for approval.1-3.7 Control.- <strong>Contract</strong>or Quality Control is the means by which the <strong>Contract</strong>or ensures that theconstruction, to include that of subcontractors and suppliers, complies with the requirements ofthe contract. The controls shall be adequate to cover all construction operations, including bothon-site and off-site fabrication, and will be keyed to the proposed construction sequence. Thecontrols shall include at least three phases of control to be conducted by the CQC systemmanager for all definable features of work, as follows:1-3.7.1 Preparatory Phase.- This phase shall be performed prior to beginning work on eachdefinable feature of work and shall include:(a)(b)(c)(d)(e)(f)(g)(h)(i)A review of each paragraph of applicable specifications.A review of the contract plans.A check to assure that all materials and/or equipment have been tested, submitted, andapproved.A check to assure that provisions have been made to provide required control inspectionand testing.Examination of the work area to assure that all required preliminary work has beencompleted and is in compliance with the contract.A physical examination of required materials, equipment, and sample work to assure thatthey are on hand, conform to approved shop drawing or submitted data, and are properlystored.Complete the FAA Pre-Construction and Maintenance Project Safety and HealthChecklist (N3900.57) to assure safety and risk analysis requirements are met. Workwith the Resident Engineer to identify potential life safety and work related risks tothe air traffic control system for inclusion in the Project Risk Mangement Plan. TheRisk Management Plan is maintained by the FAA and shall be reviewed beforestarting any phase of work as applicable.Discussion of procedures for constructing the work including repetitive deficiencies.Document construction tolerances and workmanship standards for that phase of work.A check to ensure that the portion of the plan for the work to be performed has beenaccepted by the <strong>Contract</strong>ing Officer.Page 23 of 190


VESDA FIRE ALARM SYSTEM UPGRADE PROJECT NOVEMBER, 2010NEW YORK AIR ROUTE TRAFFIC CONTROL CENTER (ZNY) (REVISED AUGUST, 2011)RONKONKOMA, NEW YORK(j)The Government shall be notified at least 48 hours in advance of beginning any of therequired action of the preparatory phase. This phase shall include a meeting conducted bythe CQC system manager and attended by the superintendent, other CQC personnel (asapplicable), and the foreman responsible for the definable feature. The results of thepreparatory phase actions shall be documented by separate minutes prepared by the CQCsystem manager and attached to the daily QC report. The <strong>Contract</strong>or shall instructapplicable workers as to the acceptable level of workmanship required in order to meetcontract specifications.1-3.7.2 Initial Phase.- This phase shall be accomplished at the beginning of a definable feature ofwork. The following shall be accomplished:(a)(b)(c)(d)(e)(f)(g)A check of preliminary work to ensure that it is in compliance with contract requirements.Review minutes of the preparatory meeting.Verification of full contract compliance. Verify required control inspection and testing.Establish level of workmanship and verify that it meets minimum acceptable workmanshipstandards. Compare with sample panels is appropriate.Resolve all differences.Check safety to include compliance with and upgrading of the safety plan and activityhazard analysis. Review the activity analysis with each worker.The Government shall be notified at least 48 hours in advance of beginning the initialphase. Separate minutes of this phase shall be prepared by the CQC system manager andattached to the daily QC report. Exact location of initial phase shall be indicated for futurereference and comparison with follow-up phases.The initial phase should be repeated for each new crew to work on-site, or any timeacceptable specified quality standards are not being met.1-3.7.3 Follow-up Phase.- Daily checks shall be performed to assure continuing compliance withcontract requirements, including control testing, until completion of the particular feature ofwork. The checks shall be made a matter of record in the CQC documentation. Final follow-upchecks shall be conducted and all deficiencies corrected prior to the start of additional features ofwork which may be affected by the deficient work. The <strong>Contract</strong>or shall not build upon orconceal non-conforming work.1-3.7.4 Additional Preparatory and Initial Phases.- Additional preparatory and initial phases maybe conducted on the same definable features of work as determined by the Government if thequality of on-going work is unacceptable; or if there are changes in the applicable QC staff or inPage 24 of 190


VESDA FIRE ALARM SYSTEM UPGRADE PROJECT NOVEMBER, 2010NEW YORK AIR ROUTE TRAFFIC CONTROL CENTER (ZNY) (REVISED AUGUST, 2011)RONKONKOMA, NEW YORKthe on-site production supervision or work crew; or if work on a definable feature is resumedafter a substantial period of inactivity, or if other problems develop.1-3.8 <strong>Contract</strong>or Request For Information (RFI).- In accordance with <strong>Contract</strong> Clause"SPECIFICATIONS AND DRAWINGS", in case of discrepancy either in the figures, in thedrawings, or in the specifications, the matter shall be promptly submitted to the RE, who shallpromptly respond in writing. Submit a written request to RE and allow at least 3 working daysfor Government response. Include the date of the request, the date response is needed, adescription of the problem, identification of work on hold, impact of delay in Governmentresponse, scope changes deemed necessary and recommended solutions, and any otherinformation pertinent. The Government reserves the right to charge the contractor foradministrative costs associated with responding to an RFI, which does not involve discrepanciesin the specifications and drawings.1-3.9 Tests.-1-3.9.1 Testing Procedure.- The <strong>Contract</strong>or shall perform tests specified or required to verifythat control measures are adequate to provide a product which conforms to contractrequirements. Testing includes operation and/or acceptance tests when specified. The<strong>Contract</strong>or shall procure the services of an approved testing laboratory or establish an approvedtesting laboratory at the project site. A list of tests to be performed shall be furnished as a part ofthe CQC plan. The list shall give the test name, frequency, specification paragraph containingthe test requirements, the personnel and laboratory responsible for each type of test, and anestimate of the number of tests required. The <strong>Contract</strong>or shall perform the following activitiesand record and provide the following data:(a)(b)(c)(d)(e)Verify that testing procedures comply with contract requirements.Verify that facilities and testing equipment are available and comply with testing standards.Check test instrument calibration data against certified standards.Verify that recording forms and test identification control number system, including all ofthe test documentation requirements, have been prepared.Results of all tests taken, both passing and failing tests, will be recorded on the QualityControl report for the date taken. Specification paragraph reference, location where testswere taken, and the sequential control number identifying the test will be given. Actual testreports may be submitted later, if approved by the <strong>Contract</strong>ing Officer, with a reference tothe test number and date taken. An information copy of tests performed by an off-site orcommercial test facility will be provided directly to the <strong>Contract</strong>ing Officer. Failure tosubmit timely test reports, as stated, may result in nonpayment for related work performedand disapproval of the test facility for this contract.Page 25 of 190


VESDA FIRE ALARM SYSTEM UPGRADE PROJECT NOVEMBER, 2010NEW YORK AIR ROUTE TRAFFIC CONTROL CENTER (ZNY) (REVISED AUGUST, 2011)RONKONKOMA, NEW YORK1-3.10 Completion Inspection.- At the completion of all work or any increment thereofestablished by a completion time stated in the Special Clause entitled "Commencement,Prosecution, and Completion of Work," or stated elsewhere in the specifications, the CQCsystem manager shall conduct an inspection of the work and develop a "punch list" of itemswhich do not conform to the approved plans and specifications. Such a list of deficiencies shallbe included in the CQC documentation, as required by paragraph DOCUMENTATION below,and shall include the estimated date by which the deficiencies will be corrected. The CQCsystem manager or staff shall make a second inspection to ascertain that all deficiencies havebeen corrected and so notify the Government. These inspections and any deficiency correctionsrequired by this paragraph will be accomplished within the time stated for completion of theentire work or any particular increment thereof if the project is divided into increments byseparate completion dates.1-3.11 Documentation.- The <strong>Contract</strong>or shall maintain current records of quality controloperations, activities, and tests performed, including the work of subcontractors and suppliers.These records shall be on an acceptable form and shall include factual evidence that requiredquality control activities and/or tests have been performed, including but not limited to thefollowing:(a)(b)(c)(d)(e)(f)(g)(h)(i)(j)<strong>Contract</strong>or/subcontractor and their area of responsibility.Operating plant/equipment with hours worked, idle, or down for repair.Work performed today, giving location, description, and by whom. When NetworkAnalysis (NAS) is used, identify each phase of work performed each day by NAS activitynumber.Test and/or control activities performed with results and references to specifications/planrequirements. The control phase should be identified (Preparatory, Initial, Follow-up). Listdeficiencies noted along with corrective action.Material received with statement as to its acceptability and storage.Identify submittals reviewed, with contract reference, by whom, and action taken.Off-site surveillance activities, including actions taken.Job safety evaluations stating what was checked, results, and instructions or correctiveactions.List instructions given/received and conflicts in plans and/or specifications.<strong>Contract</strong>or's verification statement.Page 26 of 190


VESDA FIRE ALARM SYSTEM UPGRADE PROJECT NOVEMBER, 2010NEW YORK AIR ROUTE TRAFFIC CONTROL CENTER (ZNY) (REVISED AUGUST, 2011)RONKONKOMA, NEW YORK(k)These records shall indicate a description of trades working on the project; the number ofpersonnel working; weather conditions encountered; and any delays encountered. Theserecords shall cover both conforming and deficient features and shall include a statementthat equipment and materials incorporated in the work and workmanship comply with thecontract. The original and one copy of these records in report form shall be furnished to theGovernment daily within 24 hours after the date(s) covered by the report, except thatreports need not be submitted for days on which no work is performed. As a minimum, onereport shall be prepared and submitted for every seven days of no work and on the last dayof a no work period. All calendar days shall be accounted for throughout the life of thecontract. The first report following a day of no work shall be for that day only. Reportsshall be signed and dated by the CQC system manager. The report from the CQC systemmanager shall include copies of test reports and copies of reports prepared by allsubordinate quality control personnel.1-3.12 Sample Forms.- Sample <strong>Contract</strong>or Quality Control Report forms are enclosed at the endof this section.1-3.13 Notification of Noncompliance.- The <strong>Contract</strong>ing Officer will notify the <strong>Contract</strong>or ofany detected noncompliance with the foregoing requirements. The <strong>Contract</strong>or shall, after receiptof such notice, immediately take corrective action. Such notice, when delivered to the <strong>Contract</strong>orat the site of the work, shall be deemed sufficient for the purpose of notification. If the<strong>Contract</strong>or fails or refuses to comply promptly, the <strong>Contract</strong>ing Officer may issue an orderstopping all or part of the work until satisfactory corrective action has been taken. No part of thetime lost due to such stop orders shall be made the subject of claim for extension of time or forexcess costs or damages by the <strong>Contract</strong>or.1-3.14 Coordination, Local Permits and Testing.-1-3.14.1 Project Coordination.-(a)(b)It shall be the duty of the <strong>Contract</strong>or to prepare a detailed schedule of work and work layoutto resolve conflicts and to assure coordination of the work by different trades.It shall be the duty of the <strong>Contract</strong>or to resolve all coordination conflicts that arise amonghis subcontractors. If, in the opinion of the RE, a potential or actual conflict exists, the REwill notify the CO, who shall instruct the contractor to take immediate steps to coordinatethe work and resolve any conflicts.1-3.14.2 Local Permits.& National Electrical Code-(a)The <strong>Contract</strong>or shall make application, pay fees, etc., to obtain local building permits andinspection as required.Page 27 of 190


VESDA FIRE ALARM SYSTEM UPGRADE PROJECT NOVEMBER, 2010NEW YORK AIR ROUTE TRAFFIC CONTROL CENTER (ZNY) (REVISED AUGUST, 2011)RONKONKOMA, NEW YORK(b)(c)This project is designed in accordance with the International Building Code, the UniformPlumbing Code, and the National Electric Code. The <strong>Contract</strong>or shall perform all work incompliance with the latest edition of these codes.The requirements of the specification and drawings applicable to this contract areintended to be in conformity with the National Electrical Code, National Safety Code,State and Local electrical codes and all pertinent FAA orders. The contractor shall reviewthese documents prior to starting work. If they are found to be in conflict, the moststringent requirement shall be provided by the contractor. In determining whether anadjustment in contract price or time may be involved, it shall be understood that the<strong>Contract</strong>or’s bid price has been based on performing the work in conformity with themost stringent requirement.1-3.14.3 Testing.- The <strong>Contract</strong>or shall arrange and pay for the services of Independent TestingLaboratories/Engineers to perform specified services and testing as required. (sample of typical<strong>Contract</strong>or's daily report)1-3.15 Safety Requirements.-1-3.15.1 <strong>Contract</strong>or Safety Plan.- The <strong>Contract</strong>or shall develop and submit a required Safety Planand other safety documents showing how the work shall be accomplished in accordance withOSHA 29 CFR 1910 and OSHA 29 CFR 1926. The Safety Plan, and other safety documents,shall be submitted to the Site Representative for review and approval. The Safety Plan shall besubmitted with in 10 days of the Notice-to-proceed. No construction will be authorized until theSafety Plan has been approved.END OF SECTIONPage 28 of 190


VESDA FIRE ALARM SYSTEM UPGRADE PROJECT NOVEMBER, 2010NEW YORK AIR ROUTE TRAFFIC CONTROL CENTER (ZNY) (REVISED AUGUST, 2011)RONKONKOMA, NEW YORKDAILY CONSTRUCTION QUALITY CONTROL REPORT<strong>Contract</strong> Number: ______________________ Date: __________ Rpt No.____________<strong>Contract</strong> Title: ______________________________ Location: ____________________Weather: Clear __ P.Cloudy __ Cloudy __ Rainfall __ (__% of workday)Temperature during workday: High ____ degrees F. Low ___ degrees F.1. WORK PERFORMED BY CONTRACTOR/SUBCONTRACTOR(S):<strong>Contract</strong>or Name No. of Workers Crafts/Hours Work performed______________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________2. EQUIPMENT DATA:Type, Size, Etc. Owned/Rented Hours Used Hours Standby__________________________________________________________________________________________________________________________________________________________________________________________________________________________________________3. QUALITY CONTROL INSPECTIONS AND RESULTS: (Include a description ofpreparatory, initial, and/or follow up inspections or meetings; check of subcontractors work andmaterials delivered to the site compared to submittals and/or specifications; comments on theproper storage of materials; include comments on corrective actions to be taken):________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________Page 29 of 190


VESDA FIRE ALARM SYSTEM UPGRADE PROJECT NOVEMBER, 2010NEW YORK AIR ROUTE TRAFFIC CONTROL CENTER (ZNY) (REVISED AUGUST, 2011)RONKONKOMA, NEW YORK4. QUALITY CONTROL TESTING AND RESULTS (comment on tests and attach testreports):__________________________________________________________________________________________________________________________________________________________________________________________________________________________________________5. DAILY SAFETY INSPECTIONS (Include comments on new hazards to be added to theHazard Analysis and corrective action of any safety issues):__________________________________________________________________________________________________________________________________________________________________________________________________________________________________________6. REMARKS (Include conversations with or instructions from the Government representatives;delays of any kind that are impacting the job; conflicts in the contract documents; comments onchange orders; environmental considerations; etc.):__________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________CONTRACTOR'S VERIFICATION: The above report is complete and correct. All material,equipment used, and work performed during this reporting period are in compliance with thecontract documents except as noted above.___________________________________CONTRACTOR QC REPRESENTATIVEPage 30 of 190


VESDA FIRE ALARM SYSTEM UPGRADE PROJECT NOVEMBER, 2010NEW YORK AIR ROUTE TRAFFIC CONTROL CENTER (ZNY) (REVISED AUGUST, 2011)RONKONKOMA, NEW YORKTEST REPORTSTRUCTURE OR BUILDINGCONTRACT NO.DESCRIPTION OF ITEM, SYSTEM, OR PART OF SYSTEM TESTED:______________________________________________________________________________________________________________________________________________________________________________DESCRIPTION OF TEST:___________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________NAME AND TITLE OF PERSON IN CHARGE OF PERFORMING TESTS FORCONTRACTOR:NAMETITLESIGNATUREI HEREBY CERTIFY THAT THE ABOVE DESCRIBED ITEM, SYSTEM, OR PART OFSYSTEM HAS BEEN TESTED AS INDICATED ABOVE AND FOUND TO BE ENTIRELYSATISFACTORY AS REQUIRED IN THE CONTRACT SPECIFICATIONS.SIGNATURE OF CONTRACTOR QUALITY CONTROL INSPECTOR_DATEREMARKS:_____________________________________________________________________Page 31 of 190


VESDA FIRE ALARM SYSTEM UPGRADE PROJECT NOVEMBER, 2010NEW YORK AIR ROUTE TRAFFIC CONTROL CENTER (ZNY) (REVISED AUGUST, 2011)RONKONKOMA, NEW YORKDAILY CONSTRUCTION QUALITY CONTROL REPORT<strong>Contract</strong> No.: ____________________________Date: Report No. _Description and Location of Work:___________________________________________________WEATHER: (Clear) (P. Cloudy); Temperature: _____________ Min. ___________ Max;(Snow) (Rainfall) _____________ Inches<strong>Contract</strong>or/Subcontractor Activity:<strong>Contract</strong>or/TimeWork in Progress Subcontractor Craft Workeda.____________________________________________________________________________b.____________________________________________________________________________c.____________________________________________________________________________d.____________________________________________________________________________e.____________________________________________________________________________f.____________________________________________________________________________Equipment Data: (Indicate items of construction equipment, other than hand tools, at the job siteand whether or not used.)<strong>Contract</strong>or/TimeEquipment Subcontractor Craft Used _a.___________________________________________________________________________b.____________________________________________________________________________c.____________________________________________________________________________d.____________________________________________________________________________Page 32 of 190


VESDA FIRE ALARM SYSTEM UPGRADE PROJECT NOVEMBER, 2010NEW YORK AIR ROUTE TRAFFIC CONTROL CENTER (ZNY) (REVISED AUGUST, 2011)RONKONKOMA, NEW YORKThree Phase Inspection Program:1. Preparatory Inspection: Include status of transmittals, Quality Control meetings, testsrequired, materials delivered, materials compliance with submittals and standards, materialstorage, conflict in drawings or specifications, environmental conflicts, instructions fromGovernment.Job Safety: (Analyze hazards. Plan safety program. Schedule safety meetings.)2. Initial Inspection: Include new feature of work started, number of personnel in trades andhours worked, result of inspection, compliance of work with plans and specifications, results oftests, instructions from Government.Job Safety: (Insure compliance with Safety Program and Analysis. Observe safetymeetings and reporting.)3. Follow up Inspections: Include work inspected, result of inspection, compliance with plansand specifications, results of tests, delays to work, defects, and rejection of work, proposedremedial action, corrective action taken, instructions from Government.Job Safety: (Note any deficiencies and corrections.)Page 33 of 190


VESDA FIRE ALARM SYSTEM UPGRADE PROJECT NOVEMBER, 2010NEW YORK AIR ROUTE TRAFFIC CONTROL CENTER (ZNY) (REVISED AUGUST, 2011)RONKONKOMA, NEW YORKCONTRACTOR'S VERIFICATION: The above report is complete and correct and all materialand equipment used and work performed during this reporting period are in compliance with thecontract plans and specifications except as noted above.______________________________________________CONTRACTOR QUALITY CONTROL INSPECTORPage 34 of 190


VESDA FIRE ALARM SYSTEM UPGRADE PROJECT NOVEMBER, 2010NEW YORK AIR ROUTE TRAFFIC CONTROL CENTER (ZNY) (REVISED AUGUST, 2011)RONKONKOMA, NEW YORK1-4 CUTTING AND PATCHING1-4.1 General.-1-4.1.1 Requirements included.- <strong>Contract</strong>or shall be responsible for all cutting, fitting andpatching, required to complete the work or to:(a)(b)(c)(d)(e)Make the parts fit together properly.Remove and replace defective work.Remove and replace work not conforming to requirementsRemove samples of installed work as specified for testing.Provide penetrations of surfaces for installation of piping, air ductwork, and electricalconduit.1-4.1.2 Submittals.-(a)Submit a written Request for Information (RFI) to the RE a minimum of 5 days in advanceof executing any cutting or alteration which may affect:1. Work of the Government or any separate contractor.2. Structural integrity of any element of the Project.3. Integrity of weather-exposed or moisture- resistant elements or systems.4. Efficiency, operational life, maintenance or safety of operational elements.5. Visual qualities of sight-exposed elements.(b)Request shall include:1. Identification of the Project.2. Description of affected work.3. The necessity for cutting, alteration, or excavation.4. Effect on work of Government or other work, or on structural or weatherproof integrityof the affected element.5. Description of proposed work:a) Scope of cutting, patching, alteration, or excavation.b) Trades who will execute the work.c) Products proposed to be used.d) Extent of refinishing to be done.6. Alternatives to cutting and patching.7. Cost proposal, when applicable8. Written concurrence of any separate contractor whose work will be affected.(c)Should conditions of work or the schedule indicate a change of products from originalinstallation, contractor shall submit request for substitution as specified in Section 1-9,"Materials and Equipment."Page 35 of 190


VESDA FIRE ALARM SYSTEM UPGRADE PROJECT NOVEMBER, 2010NEW YORK AIR ROUTE TRAFFIC CONTROL CENTER (ZNY) (REVISED AUGUST, 2011)RONKONKOMA, NEW YORK(d)Submit written notice to the RE designating the date and time the work will be uncovered.1-4.2 Products.-1-4.2.1 Materials.- Comply with specifications and standards for each specific productinvolved.1-4.3 Execution.-1-4.3.1 Inspection.-(a)(b)(c)Inspect existing conditions of project, including elements subject to damage or tomovement during cutting and patching.After uncovering work, inspect conditions affecting installation of products, or performanceof work.Report unsatisfactory or questionable conditions to the RE in writing; do not proceed withwork until the RE has provided further instructions.1-4.3.2 Preparation.-(a)(b)(c)Provide adequate temporary support as necessary to assure structural value or integrity ofaffected portion of work.Provide devices and methods to protect other portions of project from damage.Provide protection from elements for that portion of the project which may be exposed bycutting and patching work.1-4.3.3 Performance.-(a)(b)(c)(d)(e)Execute cutting and demolition by methods which will prevent damage to other work, andwill provide proper surfaces to receive installation of repairs.Execute fitting and adjustment of products to provide a finished installation to comply withspecified products, functions, tolerance and finishes.Restore work which has been cut or removed; install new products to provide completework in accordance with requirements of <strong>Contract</strong> Documents.Fit work airtight to pipes, sleeves, ducts, conduit and other penetrations through surfaces.Refinish entire surfaces as necessary to provide an even finish to match adjacent finishes:Page 36 of 190


VESDA FIRE ALARM SYSTEM UPGRADE PROJECT NOVEMBER, 2010NEW YORK AIR ROUTE TRAFFIC CONTROL CENTER (ZNY) (REVISED AUGUST, 2011)RONKONKOMA, NEW YORK1. For continuous surfaces, refinish entire unit to the nearest natural break line.2. For an assembly, refinish entire unit.END OF SECTIONPage 37 of 190


VESDA FIRE ALARM SYSTEM UPGRADE PROJECT NOVEMBER, 2010NEW YORK AIR ROUTE TRAFFIC CONTROL CENTER (ZNY) (REVISED AUGUST, 2011)RONKONKOMA, NEW YORK1-5 SCHEDULE CONSTRAINTS1-5.1. Critical Time Constraints.- <strong>Contract</strong> duration for completion of all work shall be 180calendar days from notice to proceed, excluding the FAA holiday moratorium days.FAA Holiday Moratorium: No work shall be scheduled or take place during the week ofand the weekend preceding and following the Thanksgiving, Christmas and New YearsHolidays as well as other days as indicated in Part I – Section H Special <strong>Contract</strong>Requirements. Only emergency work to restore critical services to the facility will beconsidered and a moratorium waiver must be submitted and approved. The moratoriumperiod will not be counted against the contract construction duration for the project.1-5.3 Critical Activities.- The constraints identified in this specification section shall beincluded as activities on the <strong>Contract</strong>or prepared construction schedule.END OF SECTIONPage 38 of 190


VESDA FIRE ALARM SYSTEM UPGRADE PROJECT NOVEMBER, 2010NEW YORK AIR ROUTE TRAFFIC CONTROL CENTER (ZNY) (REVISED AUGUST, 2011)RONKONKOMA, NEW YORK1-6 CONTRACTOR PREPARED CONSTRUCTION SCHEDULE1-6.1 Construction Schedule.- The progress chart to be prepared by the <strong>Contract</strong>or pursuant tothe <strong>Contract</strong> Clause entitled "SCHEDULE FOR CONSTRUCTION CONTRACTS" shall consistof a Gantt or bar chart as described below. The scheduling of construction is the responsibility ofthe <strong>Contract</strong>or and contractor management personnel shall actively participate in development ofthe schedule so that intended sequences and procedures are clearly understood1-6.2 Activity number and duration.- Provide a chart with a minimum of 50 activities indicatingall major activities and associated durations, including major submittals, material deliverydurations and installation, unless otherwise approved by the <strong>Contract</strong>ing Officer (CO). Thenumber of activities shall be subject to CO approval. In calculating activity duration, normalinclement weather, holidays and other non-working days shall be considered. Activities whichare planned to be performed by use of overtime or multi-shifts to be worked including Saturdays,Sundays, and holidays, shall be identified and must be coordinated in accordance with therequirements in specification section 1-2, Site Access, Construction Limits, Use of Facilities andWork Hours.1-6.3 Two-week "Look Ahead" schedule.- A weekly construction coordination meeting shall beheld between the <strong>Contract</strong>or and the Resident Engineer. Schedules shall be submitted weekly,just prior to the weekly construction site meetings. Only activities scheduled to be occurringduring the forecasted two week time periods are to be shown. The two week time periods aredetermined by starting day being the day of the weekly construction site meeting. Early and LateStart and Finish dates, and subcontractors involved are data to be included in the schedule.END OF SECTIONPage 39 of 190


VESDA FIRE ALARM SYSTEM UPGRADE PROJECT NOVEMBER, 2010NEW YORK AIR ROUTE TRAFFIC CONTROL CENTER (ZNY) (REVISED AUGUST, 2011)RONKONKOMA, NEW YORK1-7 FIRE LIFE SAFETY REQUIREMENTSPROCEDURE FOR FIRE/LIFE SAFETY OUTAGES & INTERIM SAFETYMEASURES FOR FULL OR PARTIAL FIRE/LIFE SAFETY SYSTEM ANDFEATURE OUTAGESImplementation of interim measures is required for a nonfunctional or partiallyoperating fire/life safety (F/LS) systems in FAA owned, operated or occupiedfacilities.The following Procedure for Fire/Life Safety Outages, includes steps mandated bythe <strong>Federal</strong> <strong>Aviation</strong> <strong>Administration</strong> and nationally recognized F/LS codes andstandards. This procedure and the appropriate interim measures should beimplemented as soon as fire/life safety systems are out of service. Where the fire/lifesafety system outage is planned due to construction and maintenance, execution ofthe procedures identified should be planned and initiated prior to the outage.INCLUDED F/LS FEATURES AND SYSTEMSF/LS features and systems are those facility components provided to protect thebuilding occupants, facility, NAS operational continuity, and ultimately the missionof the FAA from the hazards of fire and explosion. A partial listing of F/LS systemsand features, addressed by this procedure are provided below:Fire Alarm & DetectionFire SprinklersFire Standpipes & ValvesFire Suppression ReleasingFire Pumps & ControllersFire ExtinguishersElevator RecallAir Handling Unit ShutdownEmergency Security InterfacesSmoke ManagementFire & Smoke BarriersFire & Smoke Opening ProtectionFire & Smoke DampersFire & Smoke DoorsFirestopping & Joint ProtectionProtected & Unobstructed EgressEmergency LightingEgress MarkingPage 40 of 190


VESDA FIRE ALARM SYSTEM UPGRADE PROJECT NOVEMBER, 2010NEW YORK AIR ROUTE TRAFFIC CONTROL CENTER (ZNY) (REVISED AUGUST, 2011)RONKONKOMA, NEW YORKEmergency Power SuppliesSTAKEHOLDERS IN F/LS OUTAGESAll impacted stakeholders should be notified of outages and be included in theimplementation of planned F/LS system and feature outages. Potential stakeholdersmay include facility management and occupants, safety management team, firedepartment, resident engineer, contractors, and the central fire alarm monitoringstation.Initial communications for unplanned outages should be accomplished as soon aspossible and include documentation by memorandum, email, letter or signagepostings within the facility, in accordance with FAA policy.INTERIM MEASURES (PARTIAL LIST)1. Inform all facility occupants of the outage or partially functional F/LS feature anddiscuss its effect on daily and emergency operations. The facility Emergency ActionPlan should be reviewed to identify necessary modifications. The informationshould highlight the purpose and importance of the F/LS feature, the impact oneveryday operations, and the increased responsibility of all personnel.2. Evaluate the level of risk posed by the non-functioning or partially functioningfeature and the hazards present in the facility. Identify any areas that may have aspecific risk and may require a fire watch in order to provide appropriate protectionto the occupants. Appoint a “fire warden” to oversee implementation and evaluatethe effectiveness of the interim procedures. The local safety manager should beconsulted for long term, broad reaching or high impact outages. Additionally, FAAsafety professionals should be consulted when the proper interim measures areunclear.3. Conduct daily inspections to ensure the means of egress is not obstructed orcompromised. Confirm the egress is free of combustibles or storage of any kind.4. Ensure all doors opening into the stairs are checked to ensure door hardware isfunctioning properly. This includes a visual inspection of all doors to ensure theconstruction has not been compromised and checking all door hardware includinglatching hardware and self-closing devices to verify proper operation. Magnetic doorholders should be disconnected and not be returned to use until the fire alarm systemis functioning normally.5. Ensure that fire and smoke doors in the facility are not propped open for any reason.Page 41 of 190


VESDA FIRE ALARM SYSTEM UPGRADE PROJECT NOVEMBER, 2010NEW YORK AIR ROUTE TRAFFIC CONTROL CENTER (ZNY) (REVISED AUGUST, 2011)RONKONKOMA, NEW YORK6. Institute the necessary risk reduction actions, which may include the following:a. Enhancing occupant evacuation procedures by requiringimmediate evacuation upon alarmb. Updating building occupants on the proper use of fire extinguishersc. Providing additional fire extinguishersd. Strictly enforcing all working contractors’ site safety planse. Implementing a requirement for daily construction activitybriefings by the resident engineerf. Strictly enforcing "hot work", (e.g., welding, cutting, etc.)safety approvals or banning all hot work during F/LSoutagesg. Maintaining the storage of construction combustibles orflammable and combustible liquids outside of the facilityh. Strictly enforcing the daily clean up of constructionmaterials and excess dust7. Conduct biweekly testing and inspections of:a. Exit signageb. Exits for improper storage or obstructionsc. Exit stairs including treads, landings, and handrailsd. Exit illuminatione. Emergency lightingf. Housekeeping and fire prevention measures are in effect8. Post signage throughout the facility to indicate interim measures are in effect.9. Confirm, through testing and inspection, the proper operation of all F/LS features,systems and components remaining operational during the outage.10. In cases where the fire detection & alarm system is compromised, implementprocedures for notifying facility occupants in the event of an emergency (e.g., radio,public address, etc.) and ensure personnel are aware of the procedures in effect andclear of their responsibilities.11. In cases where the F/LS systems interface with building controls is compromised,provide a temporary manual switch in the control areas (cab or control room), whichactivate the stair pressurization system, elevator recall or other special facilityfeatures. If the facility (specifically an ATCT) has a vented vestibule system, ensurelouvers are in the open position while the fire alarm system is not functioning.12. Ensure trouble signals at the main fire alarm control panel and the control areaannunciator panels remain functional. Trouble signals at either panel should not bePage 42 of 190


VESDA FIRE ALARM SYSTEM UPGRADE PROJECT NOVEMBER, 2010NEW YORK AIR ROUTE TRAFFIC CONTROL CENTER (ZNY) (REVISED AUGUST, 2011)RONKONKOMA, NEW YORKby-passed. All trouble signals should be cleared only upon the system’s return tonormal operations.13. Inform all personnel upon restoring the F/LS feature to full operation and reinstatethe normal occupant emergency procedures.For additional information, contact the local safety officer, Regional Occupational Safetyand Health Manager, or the facility manager.END OF SECTIONPage 43 of 190


VESDA FIRE ALARM SYSTEM UPGRADE PROJECT NOVEMBER, 2010NEW YORK AIR ROUTE TRAFFIC CONTROL CENTER (ZNY) (REVISED AUGUST, 2011)RONKONKOMA, NEW YORK1-8 TEMPORARY FACILITIES1-8.1 General.-1-8.1.1 Requirement Included.-(a)(b)Furnish, install and maintain temporary facilities required for construction; remove oncompletion of the work.Facilities include, sanitary, water, electricity, lighting, heating, ventilation, telephone,construction aids, barriers, project sign, parking and site access.1-8.1.2 Related Requirements.-(a) Section 1-2: Site Access, Construction limits, Use of Facilities and WorkHours.(b)Section 1-10: Protection of Work1-8.2 Products.-1-8.2.1 Temporary Sanitary Facilities.-(a)(b)The contractor shall provide and maintain adequate temporary toilet accommodations forthose persons employed on the project site outside the construction area. Theaccommodations shall be sanitary, chemical-type toilet facilities.Permanent sanitary facilities within the construction area may be used by constructionpersonnel.1-8.2.2 Temporary Water.-(a)(b)The contractor shall provide temporary service and hose bibbs for drinking andconstruction use.The existing building water system may be used for construction purposes at no cost to thecontractor. Obtain location connections from the Resident Engineer. Extend system asnecessary to comply with temporary water requirements.1-8.2.3 Temporary Electrical Power.-(a)Reasonable amounts of electrical power will be furnished at no cost. <strong>Contract</strong>or will haveto supply breakers perform all work required to access power. Connections to the existingfacility electrical system at any other point is prohibited.Page 44 of 190


VESDA FIRE ALARM SYSTEM UPGRADE PROJECT NOVEMBER, 2010NEW YORK AIR ROUTE TRAFFIC CONTROL CENTER (ZNY) (REVISED AUGUST, 2011)RONKONKOMA, NEW YORK(b)(c)The contractor shall provide a fused disconnect switch at the point of connection.The contractor shall provide all supply lines for lights and power, extension outlets, andextension cords, trailers, receptacles, bulbs, fuses and other equipment required for safetyand for proper execution of the work, and for inspection purposes. ALL ELECTRICALWORK THAT CONNECTS TO THE FACILITY ELECTRICAL SYSTEM SHALL BECOORDINATED THROUGH THE RESIDENT ENGINEER. The only personnelauthorized to access energized electrical panels are the FAA Environmental Support Unitpersonnel. Failure to adhere to these requirements may result in removal from the jobsite.1-8.2.4 Temporary Lighting.- Provide temporary artificial lighting in enclosed areas and for allareas when natural light does not meet minimum requirements for:(a)(b)(c)Construction Areas: Uniform illumination of 20 foot-candles.Security.Temporary offices, storage, shop and other construction buildings.1-8.2.5 Not Used1-8.2.6 Temporary Ventilation.- Furnish, install and maintain temporary ventilating as requiredto prevent hazardous accumulations of dusts, fumes, mists, vapors, or gases in areas occupiedduring construction.(a)(b)(c)Provide local exhaust ventilation to prevent harmful dispersal of hazardous substances intoatmosphere of occupied areas.Provide local exhaust ventilation with capacity to produce negative pressure and enclosethe immediate work area with dust partitions to protect adjacent equipment.Dispose of exhaust materials in a manner which will not result in harmful exposure topersons.1-8.2.7 Temporary Telephone.-(a)(b)The <strong>Contract</strong>or shall furnish, install and maintain temporary telephone service forconstruction needs throughout construction period.The <strong>Contract</strong>or shall arrange with local telephone service company, provide direct lineservice for use of personnel and employees:1. One direct line instrument in contractor's field office.2. Other instruments at contractor's option, or as required by regulations.Page 45 of 190


VESDA FIRE ALARM SYSTEM UPGRADE PROJECT NOVEMBER, 2010NEW YORK AIR ROUTE TRAFFIC CONTROL CENTER (ZNY) (REVISED AUGUST, 2011)RONKONKOMA, NEW YORK(c)(d)The <strong>Contract</strong>or shall pay cost for installation, maintenance and removal of temporaryservices, and restoration of existing or permanent facilities used.The <strong>Contract</strong>or shall pay service company charges for local telephone service, and for tollcharges. Cell phones may be used with in the construction area.1-8.2.8 Construction Aids.-(a)(b)Furnish, install and maintain required construction aids. Remove on completion of work.Provide construction aids and equipment required by personnel and to facilitate executionof the work; trench boxes, scaffolds, staging, ladders, stairs, ramps, runways, platforms,railings, hoists, cranes, chutes and other such facilities and equipment.1-8.2.9 Barriers.-(a)(b)(c)Furnish, install and maintain suitable barriers as required to prevent public entry, and toprotect the work, existing facilities, trees and plants from construction operations; removewhen no longer needed, or at completion of work.Materials of contractor's option, as appropriate to serve required purpose.Where any removal, drilling or cutting of walls or other surfaces in areas of existingfacilities operations occurs, the contractor shall install temporary partitions prior todemolition to prevent entrance of dust or other matter into the working areas. Wherenormal activities are to be carried on inside the building adjacent to the partition, thepartition shall be thermally insulated and acoustically treated to prevent entry oftemperature extremes and construction noise.1-8.2.10 Not Used1-8.2.11 Not Used1-8.2.12 Temporary Parking and Access.-(a)Provide and maintain, all weather, vehicular access to site and within site to provideuninterrupted access:1. To temporary construction facilities, storage and work areas.2. For use by persons and equipment involved in construction project.3. For use by emergency vehicles.(b)Provide and maintain, all weather temporary parking facilities for use by constructionpersonnel.Page 46 of 190


VESDA FIRE ALARM SYSTEM UPGRADE PROJECT NOVEMBER, 2010NEW YORK AIR ROUTE TRAFFIC CONTROL CENTER (ZNY) (REVISED AUGUST, 2011)RONKONKOMA, NEW YORK(c)Locate roads, drives, walks and parking facilities to provide uninterrupted access toconstruction offices, mobilization, work, storage areas, and other areas required forexecution of the contract.1. <strong>Contract</strong>or and the contractor's personnel shall utilize the parking areas designatedon the drawing.(d)Provide access for emergency vehicles.1. Maintain driveways a minimum of 15 feet wide between and around combustiblematerials in storage and mobilization areas.(e)(f)(g)Maintain traffic areas free as possible of excavated materials, construction equipment,products, snow, ice and debris.Keep fire hydrants and water control valves free from obstruction and accessible for use.Maintain roads, walks and parking areas in sound, clean condition.1. Repair or replace any portions damaged during progress of construction work.(h)Completely remove temporary materials and construction when construction needs can bemet by use of permanent installation.1. Remove and dispose of compacted materials to depths required by variousconditions to be met in completed work.(i)Restore areas to original or to specified conditions at completion of work.1-8.3 Execution.-1-8.3.1 Utility Costs.-(a)Consumption costs of the temporary power service and temporary water service furnishedto the contractor will be paid by the Government. Extension from the point of connection,including equipment, operation and attendance shall be paid for by the contractor.1-8.3.2 Maintenance.-(a)All costs in connection with the maintenance of all temporary facilities shall be paid by thecontractor.1-8.3.3 Compliance.- All work covered in this section shall comply with provisions of otherapplicable divisions and all applicable local requirementsPage 47 of 190


VESDA FIRE ALARM SYSTEM UPGRADE PROJECT NOVEMBER, 2010NEW YORK AIR ROUTE TRAFFIC CONTROL CENTER (ZNY) (REVISED AUGUST, 2011)RONKONKOMA, NEW YORK1-8.3.4 Operation of Permanent Equipment.- Use of permanent equipment by the contractor isstrictly prohibited without written approval of the FAA prior to use.1-8.3.5 Removal of Temporary Facilities.- The contractor shall promptly remove all temporaryfacilities from premises at end of work. If the contractor fails to do so within a reasonable timeafter notification, the FAA will have the items removed at the contractor's expense.END OF SECTIONPage 48 of 190


VESDA FIRE ALARM SYSTEM UPGRADE PROJECT NOVEMBER, 2010NEW YORK AIR ROUTE TRAFFIC CONTROL CENTER (ZNY) (REVISED AUGUST, 2011)RONKONKOMA, NEW YORK1-9 MATERIALS AND EQUIPMENT1-9.1 General.-1-9.1.1 Requirements Included.-(a)Material and equipment incorporated into the work:1. Conform to applicable specifications and standards.2. Comply with size, make, type and quality specified, or as specifically approved inwriting by the CO.3. Manufactured and Fabricated Products:a) Design, fabricate and assemble in accordance with the best engineering and shoppractices.b) Manufacture like parts of duplicate units to standard sizes and gages, to beinterchangeable.c) Two or more items of the same kind shall be identical, by the same manufacturer.d) Products shall be suitable for service conditions.e) Equipment capacities, sizes and dimensions shown or specified hall be adhered tounless variations are specifically approved in writing.4. Do not use material or equipment for any purpose other than for which it isdesigned or is specified.(b)Furnish and install products specified, under options and conditions for substitution statedin this section.1-9.1.2 Related Requirements.-(a) Part I, Section E, F, G.(b)Section 1-7: Submittals1-9.1.3 Manufacturer's Instructions.-(a)When <strong>Contract</strong> Documents requires that installation of work shall comply withmanufacturer's printed instructions, obtain and distribute copies of such instructions toparties involved in the installation, including two copies to the RE.1. Maintain one set of complete instructions at the job site during installation and untilcompletion.(b)Handle, install, connect, clean, condition and adjust products in strict accordance with suchinstructions and in conformity with specified requirements.Page 49 of 190


VESDA FIRE ALARM SYSTEM UPGRADE PROJECT NOVEMBER, 2010NEW YORK AIR ROUTE TRAFFIC CONTROL CENTER (ZNY) (REVISED AUGUST, 2011)RONKONKOMA, NEW YORK1. Should job conditions or specified requirements conflict with manufacturer'sinstructions, consult with the RE for further instructions.2. Do not proceed with work without clear instructions.(c)Perform work in accordance with manufacturer's instructions. Do not omit any preparatorystep or installation procedure unless specifically modified or exempted by <strong>Contract</strong>Documents.1-9.1.4 Transportation and Handling.-(a)Arrange deliveries of products in accordance with construction schedules, coordinate toavoid conflict with work and conditions at the site. All deliveries shall be coordinated inadvance with the Resident Engineer and the Security personnel at the main entrance.The contractor shall have a point of contact identified and available to receive theshipment. Failure to adhere to these requirements may result in the shipment beingturned away at the Main Entrance by the Security personnel. Any additional costs ortime as a result of failure to adhere to these requirements shall be the responsibility ofthe <strong>Contract</strong>or.1. Deliver products in undamaged condition, in manufacturer’s original containers orpacking, with identifying labels intact and legible.2. Immediately on delivery, inspect shipments to assure compliance with requirementsof <strong>Contract</strong> Documents and approved submittals, and that products are properlyprotected and undamaged.(b)Provide equipment and personnel to handle products by methods to prevent soiling ordamage to products or packing.1-9.1.5 Storage.-(a)Store products in accord with manufacturer's instructions, with seals and labels intact andlegible.1. Store products subject to damage by the elements in weathertight enclosures.2. Maintain temperature and humidity within the ranges required by manufacturer'sinstructions.(b)Exterior Storage.1. Store fabricated products above the ground, on blocking or skids, prevent soiling orstaining. Cover products which are subject to deterioration with impervious sheetcoverings, provide adequate ventilation to avoid condensation.2. Store loose granular materials in a well-drained area on solid surfaces to preventmixing with foreign matter.Page 50 of 190


VESDA FIRE ALARM SYSTEM UPGRADE PROJECT NOVEMBER, 2010NEW YORK AIR ROUTE TRAFFIC CONTROL CENTER (ZNY) (REVISED AUGUST, 2011)RONKONKOMA, NEW YORK(c)Arrange storage in a manner to provide easy access for inspection. Make periodicinspections of stored products to assure that products are maintained under specifiedconditions, and free from damage or deterioration.1-9.1.6 Substitutions.-(a)Submit separate request for each substitution, support each request with:1. Complete data substantiating compliance of proposed substitution with requirementsstated in <strong>Contract</strong> Documents:a) Product identification, including manufacturer's name and address.b) Manufacturer's literature; identify:1) Product description.2) Reference standards.3) Performance and test data.c) Samples, as applicable.d) Name and address of similar projects on which product has been used, and date ofeach installation.2. Itemized comparison of the proposed substitution with product specified. Listsignificant variations.3. Data relating to changes in construction schedule.4. Any effect of substitution on separate contracts.5. List of changes required in other work or products.6. Accurate cost data comparing proposed substitution with product specified include:a) Amount of any net change to <strong>Contract</strong> Sum.7. Designation of required license fees or royalties.8. Designation of availability of maintenance services, sources of replacement materials.(b)Substitutions will not be considered for acceptance when:1. They are indicated or implied on shop drawings or product data submittals without aformal request from contractor.2. They are requested directly by a subcontractor or supplier.3. Acceptance will require substantial revision of <strong>Contract</strong> Documents.(c)(d)Substitute products shall not be ordered or installed without written acceptance of the CO.CO will determine acceptability of proposed substitutions.Page 51 of 190


VESDA FIRE ALARM SYSTEM UPGRADE PROJECT NOVEMBER, 2010NEW YORK AIR ROUTE TRAFFIC CONTROL CENTER (ZNY) (REVISED AUGUST, 2011)RONKONKOMA, NEW YORK(e)In making formal request for substitution contractor represents that:1. He has investigated proposed product and has determined that it is equal to orsuperior in all respects to that specified.2. He will provide same warranties or bonds for substitutions as for product specified.3. He will coordinate installation of accepted substitution into work to be complete in allrespects.4. He waives claims for additional costs caused by substitution which may subsequentlybecome apparent.5. Cost data is complete and includes related costs under his contract.1-9.2 Products.- Not UsedEND OF SECTIONPage 52 of 190


VESDA FIRE ALARM SYSTEM UPGRADE PROJECT NOVEMBER, 2010NEW YORK AIR ROUTE TRAFFIC CONTROL CENTER (ZNY) (REVISED AUGUST, 2011)RONKONKOMA, NEW YORK1-10 PROTECTION OF WORK1-10.1 General.-1-10.1.1 Requirements Included.-(a)(b)It shall be the contractor's responsibility to provide protection of work from weather,physical damage, improper use, and other adverse natural conditions.It shall be the responsibility of the contractor to replace any damaged work includingfinishes, material, and equipment.1-10.1.2 Related Requirements.-(a)(b)(c)(d)Part I - Section I, <strong>Contract</strong> Clause entitled PROTECTION OF EXISTING VEGETATION,STRUCTURES, EQUIPMENT, UTILITIES, AND IMPROVEMENTS.The Respective Section of the Specification covering items of work.Section 1-9: Materials and EquipmentSection 1-11: Cleaning1-10.1.3 Protection During Installation.-(a)(b)(c)Provide dust protection for existing FAA electronic equipment in work site.Provide protection of temporary openings in the building to protect the contents and enablework to progress.Provide protection of base materials to receive finishes or other work from weather andphysical damage.1-10.1.4 Protection After Installation.-(a)(b)(c)Provide protection of installed products to prevent damage from subsequent operations.Remove when no longer needed, prior to completion of work.Control traffic to prevent damage to equipment and surfaces.Provide coverings to protect finished surfaces from damage.1. Cover projections, walls, corners, and jambs, sills and soffits of openings, in areasused for traffic and for passage of products in subsequent work.2. Protect finished floors and stairs from dirt and damage.Page 53 of 190


VESDA FIRE ALARM SYSTEM UPGRADE PROJECT NOVEMBER, 2010NEW YORK AIR ROUTE TRAFFIC CONTROL CENTER (ZNY) (REVISED AUGUST, 2011)RONKONKOMA, NEW YORKa) In areas subject to foot traffic, secure heavy paper, sheet goods, or other materialsin placeb) For movement of heavy products, lay planking or similar materials in place.c) For storage of products, lay tight wood sheeting in place.d) Cover walls and floors of elevator cars, and surfaces of elevator car doors used byconstruction personnel.(d)Lawns and Landscaping.1. Prohibit traffic of any kind across planted lawn and landscaped areas not in thedesignated construction area. Any lawn or landscaping damaged by the contractorshall be repaired or replaced at their expense.1-10.2 Products.- Not Used1-10.3 Execution.- Not UsedEND OF SECTIONPage 54 of 190


VESDA FIRE ALARM SYSTEM UPGRADE PROJECT NOVEMBER, 2010NEW YORK AIR ROUTE TRAFFIC CONTROL CENTER (ZNY) (REVISED AUGUST, 2011)RONKONKOMA, NEW YORK1-11 CLEANING1-11.1 General.-1-11.1.1 Requirements Included.-(a)(b)(c)Execute cleaning during the progress of work.Execute cleaning for final inspection.Execute cleaning at completion of the work.1-11.1.2 Related Requirements.-(a)(b)Section 1-9: Material and EquipmentSection 1-12: Final Inspection and Acceptance of Work1-11.1.3 Disposal Requirements.-(a)Conduct cleaning and disposal operations to comply with codes, ordinances, regulations,and anti-pollution laws.1-11.2 Products.-1-11.2.1 Materials.-(a)(b)(c)(d)Use only those cleaning materials which will not create hazards to health or property andwhich will not damage surfaces.Use only those cleaning materials and methods recommended by manufacturers of thesurface material to be cleaned.Use cleaning materials only on surfaces recommended by cleaning material manufacturer.Provide and maintain cleaning equipment such as wet/dry vacuum cleaners, brooms, dustpans, mops, and mop buckets throughout construction period for immediate cleanup ofspills.1-11.3 Execution.-1-11.3.1 During Construction.-Page 55 of 190


VESDA FIRE ALARM SYSTEM UPGRADE PROJECT NOVEMBER, 2010NEW YORK AIR ROUTE TRAFFIC CONTROL CENTER (ZNY) (REVISED AUGUST, 2011)RONKONKOMA, NEW YORK(a)(b)(c)(d)Execute daily cleaning to keep the work, the site and adjacent properties free fromaccumulations of waste materials, rubbish and windblown debris, resulting fromconstruction operations.Provide on-site containers for the collection of waste materials, debris and rubbish. TheFAA on-site waste containers are not to be used by the <strong>Contract</strong>or.Remove waste materials, debris and rubbish from the site periodically and dispose of atlegal areas away from the site.Clean up after each work shift in the ARTCC operating areas.1-11.3.2 Dust Control.-(a)(b)(c)Maintain construction areas in dust-free conditions to prevent contamination of existingequipment.Clean interior spaces prior to the start of finish painting and continue cleaning on anas-needed basis until painting is finished.Schedule operations so that dust and other contaminants resulting from cleaning processwill not fall on wet or newly-coated surfaces.1-11.3.3 Final Cleaning.-(a)(b)(c)(d)Employ skilled workmen for final cleaning.Remove grease, mastic, adhesive, dust, dirt, stains, fingerprints, labels, and other foreignmaterials from visible interior and exterior surfaces.Polish glossy surfaces to a clear shine.Ventilating system:1. Clean permanent filters and replace disposable filters if units were not operatedduring construction.2. Do not operate blowers and coils without filters during construction.(e)(f)(g)Broom clean exterior paved surfaces; rake clean other surfaces of the grounds.Prior to final completion, or owner occupancy, contractor shall conduct an inspection ofsight-exposed interior and exterior surfaces, and all work areas to verify that the entire workis clean.Wax and polish tile floors.Page 56 of 190


VESDA FIRE ALARM SYSTEM UPGRADE PROJECT NOVEMBER, 2010NEW YORK AIR ROUTE TRAFFIC CONTROL CENTER (ZNY) (REVISED AUGUST, 2011)RONKONKOMA, NEW YORK1-11.3.4 Debris Control.-(a)(b)Maintain all areas under contractor's control free of extraneous debris.Initiate and maintain a specific program to prevent accumulation of debris at constructionsite, storage and parking areas, or along access roads and haul routes.1. Provide containers for deposit of debris.2. Prohibit overloading of trucks to prevent spillage on access and haul routes.a) Provide periodic inspection of traffic areas to enforce requirements.(c)Schedule periodic collections and disposal of debris.1. Provide additional collection and disposal of debris whenever the periodic schedule isinadequate to prevent accumulation.END OF SECTIONPage 57 of 190


VESDA FIRE ALARM SYSTEM UPGRADE PROJECT NOVEMBER, 2010NEW YORK AIR ROUTE TRAFFIC CONTROL CENTER (ZNY) (REVISED AUGUST, 2011)RONKONKOMA, NEW YORK1-12 FINAL INSPECTION AND ACCEPTANCE OF WORK1-12.1 General.- This section covers final inspection and acceptance of work at contractcompletion.1-12.1.1 Certificate of Completion.- When the <strong>Contract</strong>or considers the work is complete, heshall submit written certification that:(a)(b)(c)(d)(e)(f)<strong>Contract</strong> Documents have been reviewed.Work has been inspected for compliance with contract.Equipment and Systems have been tested in the presence of the RE and appropriate facilitypersonnel and are operational.Required operational, and maintenance data and parts list have been submitted andapproved.Required instruction of maintenance personnel has been accomplished.Work is completed, premises cleaned and ready for inspection.1-12.1.2 Final Inspection.- The RE will coordinate with the CO and facility personnel toschedule the final inspection upon approval and endorsement of the <strong>Contract</strong>or's CompletionCertification.1-12.1.3 Punch List.- The RE will furnish the contractor with a list of discrepancies in the work,material and equipment noted during the final inspection.1-12.1.4 Acceptance Of Work.- The <strong>Contract</strong>or shall correct discrepancies noted during thefinal inspection, clean the premises and notify the RE that the work is ready for acceptance.Before final payment, the contractor shall secure from the ARTCC Airway Facilities Manager,and submit to the <strong>Contract</strong>ing Officer, a written release stating that the clean-up and restorationof all work areas and the return of all temporary security badges has been accomplished to hissatisfaction.1-12.1.5 Guarentee Of Work.-The contractor shall submit to the <strong>Contract</strong>ing Officer’s Technical Rep, prior to thefinal inspection, all equipment and material manufacturer’s guarantees/warranteesas specified in the subsequent technical “Description/<strong>Specifications</strong>.” In addition, aguarantee document covering all parts and labor provided under this contract forone (1) year from the date of final acceptance shall be provided by the generalcontractor to the <strong>Contract</strong>ing Officer prior to final acceptance. During the warranteeperiod the contractor shall take corrective action in response to emergency callswithin two (2) hours.END OF SECTIONPage 58 of 190


VESDA FIRE ALARM SYSTEM UPGRADE PROJECT NOVEMBER, 2010NEW YORK AIR ROUTE TRAFFIC CONTROL CENTER (ZNY) (REVISED AUGUST, 2011)RONKONKOMA, NEW YORK1-13 AS-BUILT FIELD DATA1-13.1 General.- The <strong>Contract</strong>or shall keep at the construction site two complete sets of fullsized prints of the contract drawings. During construction, these prints shall be reproduced toshow all deviations in actual construction from the contract drawings. The color red shall beused to indicate all additions and green to indicate all deletions. The drawings shall show thefollowing information but not be limited thereto:(a)(b)(c)(d)(e)The locations and description of any utility lines and other installations of any kind ordescription known to exist within the construction area. The location includes dimensionsto permanent features.The locations and dimensions of any changes within the building or structure, and theaccurate location and dimension of all underground utilities and facilities.Changes in details of design or additional information obtained from working drawingsspecified to be prepared and/or furnished by the contractor including, but not limited to,fabrication erection, installation, and placing details, pipe sizes, insulation material,dimensions of equipment foundations, etc.All changes or modifications from the original design and from the final inspection.Where contract drawings or specification allow options, only the option actually used in theconstruction shall be shown on the as-built drawings. The option not used shall be deleted.1-13.2 Updating Field Data.- These deviations shall be shown in the same general detail utilizedin the contract drawings. Marking of the prints shall be pursued continuously duringconstruction to keep them up to date. In addition, the <strong>Contract</strong>or shall maintain full size markedupdrawings, survey notes, sketches, nameplate data, pricing information, description, and serialnumbers of all installed equipment. This information shall be maintained in a current conditionat all times until the completion of the work. The resulting field-marked prints and data shall bereferred to and marked as "As-Built Field Data,” and shall be used for no other purpose. Theyshall be made available for inspection by the RE whenever requested during construction andshall be jointly inspected for accuracy and completeness by the RE and responsible representativeof the <strong>Contract</strong>or prior to submission of each monthly pay estimate. Failure to keep the As-BuiltField Data (including Equipment-in-Place list) current shall be sufficient justification to withholda retained percentage from the monthly pay estimate.1-13.3 Submittal of the As-Built Field Data.- Three sets of color marked As-Built Field Datashall be submitted to the <strong>Contract</strong>ing Officer for review and approval a minimum of 20 calendardays prior to the date of final inspection. If review of the preliminary as-built field drawingsreveals errors and/or omissions, the drawings will be returned to the <strong>Contract</strong>or for corrections.The <strong>Contract</strong>or shall make all corrections and include any deviations in actual construction whichmay have occurred since submission of preliminary as-built field drawings and return thePage 59 of 190


VESDA FIRE ALARM SYSTEM UPGRADE PROJECT NOVEMBER, 2010NEW YORK AIR ROUTE TRAFFIC CONTROL CENTER (ZNY) (REVISED AUGUST, 2011)RONKONKOMA, NEW YORKdrawings to the <strong>Contract</strong>ing Officer or the <strong>Contract</strong>ing Officer Representative within 10 calendardays of receipt.END OF SECTIONPage 60 of 190


VESDA FIRE ALARM SYSTEM UPGRADE PROJECT NOVEMBER, 2010NEW YORK AIR ROUTE TRAFFIC CONTROL CENTER (ZNY) (REVISED AUGUST, 2011)RONKONKOMA, NEW YORK1-14 ADDITIONAL GENERAL REQUIREMENTSSubcontract DataWorking HoursThe <strong>Contract</strong>ing Officer shall be notified promptly of any changes ofsubcontractors. The <strong>Contract</strong>ing Officer will be furnished a true copy of allwritten first-tier subcontracts and any amendments or modifications thereto withinthirty (30) days after entering into such subcontract agreement. The <strong>Contract</strong>ingOfficer will be furnished a true copy of all written settlement agreements reachedwith first tier subcontractors within ten (10) days after consummation of suchsettlement agreements.Any work to be performed by the contractor during other than normal 7:30 a.m. to4:00 p.m. weekday hours, or normal local union work hours, including workspecified herein to be performed at night, must be coordinated with the<strong>Contract</strong>ing Officer’s Technical Representative at least forty-eight (48) hours inadvance of commencing said work.1. Demolition and construction noise must beminimized. Concrete sawing, core drilling, concrete demolition, and anchordrilling shall be allowed only at pre-arranged times approved by the<strong>Contract</strong>ing Officer’s technical Representative. If this work causes noiseproblems it may have to be scheduled between midnight to five a.m.2. Each bidder will be expected to reviewthe drawings and specifications in order to determine the amount of workwhich must be accomplished during other than normal working hours. It willbe the bidders’ responsibility to adequately reflect this item in the bidestimate.Existing Facility OperationsThe ARTCC is a twenty-four (24) hour, seven (7) day per week operationalfacility. It will be necessary to coordinate all construction activity so as not tointerfere with the functions of the ARTCC. Work shall be scheduled and plannedby the contractor, and coordinated with the <strong>Contract</strong>ing Officer’s TechnicalRepresentative, so that normal facility operations may continue with a minimumof disruption or interference.Page 61 of 190


VESDA FIRE ALARM SYSTEM UPGRADE PROJECT NOVEMBER, 2010NEW YORK AIR ROUTE TRAFFIC CONTROL CENTER (ZNY) (REVISED AUGUST, 2011)RONKONKOMA, NEW YORKSpecialty SubcontractorsAccess to the facility by FAA personnel and visitors shall be kept open andunobstructed at all times. If any interference with the existing facility operation oraccess seems to be unavoidable, the contractor shall advise the COR before suchinterference develops. He shall then proceed as directed by the COR. If theobstruction or interference could have been foreseen by the contractor, all steps tocorrect the interference or obstruction shall be performed at no additional cost tothe Government. This will not relieve the contractor of his responsibility for anyother damages due to his neglect or lack of foresight. Loss of momentum, or workstoppage, due to activities of FAA Air Route Traffic Control operations, shall notbe considered as sufficient cause for subsequent allowance to, or claim by, thecontractor.Prior to bidding, the contractor should examine the premises and satisfy himselfas to the existing conditions under which he will be obligated to perform the workincluded in this contract.The contractor shall, without additional expense to the Government, employspecialty contractors where required by the specifications. When a "Specialty<strong>Contract</strong>or" is specified as a requirement, it shall mean a subcontractor ofestablished reputation who is regularly engaged and specializes in manufacturingand/or installing the items required by the contract, who selects and combines thematerials involved, whether at the site, or in the factory, or both, and whomaintains and makes available for such purpose a regular force of workers whoare skilled in such work. They shall be licensed by the manufacturer as installers,or work under direct supervision of the manufacturer.Daily Labor Status ReportLocal requirementsThe contractor shall, at the close of each working day, submit EA Form 4474-2 tothe <strong>Contract</strong>ing Officer’s Technical Representative with an accurate account ofthe work force employed on the project that day. The report shall include the workforce of all subcontractors, the number of each type of craftsman, and the totaltime each craftsman worked. A copy of Form 4474-2 will be provided by theCOTR.The <strong>Contract</strong>or shall adhere to all local codes and regulations of the FAA whileperforming his/her duties in any area of the Miami Air Route Traffic ControlCenter (ARTCC).Letter of ReleasePage 62 of 190


VESDA FIRE ALARM SYSTEM UPGRADE PROJECT NOVEMBER, 2010NEW YORK AIR ROUTE TRAFFIC CONTROL CENTER (ZNY) (REVISED AUGUST, 2011)RONKONKOMA, NEW YORKAfter completion of all contract work, the <strong>Contract</strong>or shall obtain a letter from theAirway Facility Chief indicating that all disturbed areas were left in satisfactorycondition. A copy of the letter shall be furnished to the <strong>Contract</strong>ing Officer.Materials Furnished by <strong>Contract</strong>orAll contractor-furnished materials shall be new and shall be approved by the<strong>Contract</strong>ing Officer’s Technical Rep. In cases where the contractor intends to usematerials "as equal" to those specified, he shall submit to the <strong>Contract</strong>ingOfficer’s Technical Rep all pertinent details (drawings, specifications, samples,etc.) of these materials within ten (10) days after the contract award. In addition,contractor shall submit all information and materials as identified in thespecification. The contractor shall be responsible for all additional materials andwork required by such substitutions.MeetingsJob site meetings shall be held every week at the job site. Date and time shall beestablished at the Pre-Construction meeting. It will be mandatory that the contractoror project manager and superintendent attend as well as the subcontractors or theirrepresentatives. Minutes of the meeting shall be prepared by the <strong>Contract</strong>or anddistributed to all participants within twenty-four (24) hours.Page 63 of 190


VESDA FIRE ALARM SYSTEM UPGRADE PROJECT NOVEMBER, 2010NEW YORK AIR ROUTE TRAFFIC CONTROL CENTER (ZNY) (REVISED AUGUST, 2011)RONKONKOMA, NEW YORKPART 1 - GENERAL1.1 SUMMARYSECTION 01300 – SUBMITTAL PROCEDURESA. This Section includes administrative and procedural requirements for submittalsrequired for performance of the Work, including the following:1. <strong>Contract</strong>or's construction schedule.2. Submittal schedule.3. Daily construction reports.4. Shop Drawings.5. Product Data, including Material Safety Data Sheets (MSDS).6. Samples.7. Quality assurance submittals.8. Certificates.9. Warranty Information.10. Operation and Maintenance Manuals.B. Administrative Submittals: Refer to other Sections of the <strong>Contract</strong> Documents forrequirements for administrative submittals. Such submittals include, but are not limitedto, the following:1. Permits.2. Applications for Payment.3. Performance and payment bonds.4. Insurance certificates.5. List of subcontractors.1.2 DEFINITIONSA. Coordination Drawings show the relationship and integration of different constructionelements that require careful coordination during fabrication or installation to fit in thespace provided or to function as intended.B. Field samples are full-size physical examples erected on-site to illustrate finishes,coatings, or finish materials. Field samples are used to establish the standard by whichthe Work will be judged.Page 64 of 190


VESDA FIRE ALARM SYSTEM UPGRADE PROJECT NOVEMBER, 2010NEW YORK AIR ROUTE TRAFFIC CONTROL CENTER (ZNY) (REVISED AUGUST, 2011)RONKONKOMA, NEW YORKC. Mockups are full-size assemblies for review of construction, coordination, testing, oroperation; they are not Samples.D. CONTRACTING OFFICER or COR: <strong>Contract</strong>ing Officer’s Technical Representative.E. RE: Resident Engineer.F. Critical Path Method (CPM): A method of planning and scheduling a constructionproject where activities are arranged based on activity relationships along the criticalpath of the project. (See G below.)G. Network Logic Diagram: A graphic diagram of a network schedule, showing theactivities and activity relationships.H. Activity: A discrete part of a project which can be identified for planning, scheduling,monitoring, and controlling the construction project. Activities included in aconstruction schedule consume time and resources.1. Critical activities are on the critical path.2. Predecessor activity is an activity that must be completed before a given activitycan begin.I. Event: The starting or ending point of an activity.J. Milestone: A key or critical point in time for reference or measurement.K. Float: The measure of leeway (time) in activity performance. Total float is the measureof leeway in starting or completing an activity without adversely affecting the plannedproject completion date.1.3 SUBMITTAL PROCEDURESA. Coordination: Coordinate preparation and processing of submittals with performanceof construction activities. Transmit each submittal sufficiently in advance ofperformance of related construction activities to avoid delay.1. Coordinate each submittal with fabrication, purchasing, testing, delivery, othersubmittals, and related activities that require sequential activity.Page 65 of 190


VESDA FIRE ALARM SYSTEM UPGRADE PROJECT NOVEMBER, 2010NEW YORK AIR ROUTE TRAFFIC CONTROL CENTER (ZNY) (REVISED AUGUST, 2011)RONKONKOMA, NEW YORK2. Coordinate transmittal of different types of submittals for related elements of theWork so processing will not be delayed by the need to review submittalsconcurrently for coordination.a. The CONTRACTING OFFICER reserves the right to withhold action on asubmittal requiring coordination with other submittals until all relatedsubmittals are received.3. Processing: To avoid the need to delay installation as a result of the time requiredto process submittals, allow sufficient time for submittal review, including timefor resubmittals.a. Allow 20 working days for initial review. Allow additional time if theCONTRACTING OFFICER must delay processing to permit coordinationwith subsequent submittals.b. If an intermediate submittal is necessary, process the same as the initialsubmittal.c. Allow 20 working days for reprocessing each submittal.d. No extension of <strong>Contract</strong> Time shall be authorized because of failure totransmit submittals to the CONTRACTING OFFICER sufficiently in advanceof the Work to permit processing.e. All submittals on the <strong>Contract</strong>or’s critical path or for project materialidentified as long lead time times (delivery time greater than six weeks) aredue 45 calendar days after contract award.f. Any submittal that has to be re-submitted more than two (2) times forreview, due to omissions, errors or failure to comply with the specificationsby the contractor, shall subject the prime contractor to a fee of sixty dollars($60.00) per hour for further review by the FAA or its representatives. Suchre-submittal shall not entitle the contractor to an extension of contract time.B. Submittal Preparation: Place a permanent label or title block on each submittal foridentification. Indicate the name of the <strong>Contract</strong>or that prepared each submittal on thelabel or title block.1. Provide a space approximately 4 by 5 inches on the label or beside the title blockon Shop Drawings to record the <strong>Contract</strong>or's review and approval markings andthe action taken.2. Include the following information on the label for processing and recording actiontaken.Page 66 of 190


VESDA FIRE ALARM SYSTEM UPGRADE PROJECT NOVEMBER, 2010NEW YORK AIR ROUTE TRAFFIC CONTROL CENTER (ZNY) (REVISED AUGUST, 2011)RONKONKOMA, NEW YORKa. Submittal number, numbered sequentially.b. Project name.c. Date.d. Name and address of the Design Architect/Engineer.e. Name and address of the <strong>Contract</strong>or.f. Name and address of the subcontractor.g. Name and address of the supplier.h. Name of the manufacturer.i. Number and title of appropriate Specification Section.j. Drawing number and detail references, as appropriate.3. Submittals that do not have <strong>Contract</strong>or’s approval stamp will be returned withoutprocessing. Affix the approval stamp to each submittal stating that is has beenreviewed and includes any necessary corrections and the material contained hereinis in compliance with the Construction Documents.C. Submittal Transmittal: Package each submittal appropriately for transmittal andhandling. Transmit each submittal from the <strong>Contract</strong>or to the CONTRACTINGOFFICER using a transmittal form. The CONTRACTING OFFICER will not acceptsubmittals received from sources other than the <strong>Contract</strong>or.1. On the transmittal, record relevant information and requests for data. On theform, or separate sheet, record deviations from <strong>Contract</strong> Document requirements,including variations and limitations. Include <strong>Contract</strong>or's certification thatinformation complies with <strong>Contract</strong> Document requirements.2. Transmittal form: Use form furnished by CONTRACTING OFFICER.1.4 CONSTRUCTION SCHEDULEA. General:1. Project Schedule Purpose:a. Assure adequate planning, scheduling and reporting during execution of theWork by the <strong>Contract</strong>or.b. When more than one Prime contractor is working at the site, assure coordinationof the Work by the <strong>Contract</strong>or and various subcontractors and suppliers.c. Assist the <strong>Contract</strong>or and CONTRACTING OFFICER in monitoring theprogress of the Work and evaluate proposed changes to the <strong>Contract</strong> and theprogress schedule.d. Assist the CONTRACTING OFFICER and <strong>Contract</strong>or in the preparation andevaluation of the <strong>Contract</strong>or’s monthly progress payments.Page 67 of 190


VESDA FIRE ALARM SYSTEM UPGRADE PROJECT NOVEMBER, 2010NEW YORK AIR ROUTE TRAFFIC CONTROL CENTER (ZNY) (REVISED AUGUST, 2011)RONKONKOMA, NEW YORKB. Responsibility for Completion:1. The <strong>Contract</strong>or shall furnish sufficient forces, offices, facilities and equipment, andshall work such hours including night shift and overtime operations as required toensure the prosecution of the Work in accordance with the current monthly ProjectSchedule Updates.2. Failure of the <strong>Contract</strong>or to comply with requirements of this paragraph shall be abasis for determination by the CONTRACTING OFFICER that the <strong>Contract</strong>or isnot prosecuting the Work.C. Two-Week “Look Ahead” Schedule: This schedule format may be of the <strong>Contract</strong>or’schoosing, either bar chart or CPM form. Only activities scheduled to be occurringduring the forecasting two-week time periods shall be shown. Schedules shall besubmitted weekly, just prior to the weekly construction site meetings. The two-weektime periods are determined by starting day being the day of the weekly constructionsite meeting. Early and Late Start and Finish dates, and list of subcontractors involvedshall be included in the schedule.D. Progress Meeting: A bi-monthly meeting shall be conducted on site to be attended bythe <strong>Contract</strong>or’s project manager and appropriate <strong>Contract</strong>ing Officer’s representative.During this meeting the <strong>Contract</strong>or will describe, on an activity by activity basis, allproposed revisions and adjustments to the schedule required to reflect the current statusof the project. Activity progress, proposed revisions and adjustments are subject to theRE’s review and approval. The following shall be addressed:1. The actual start and actual finish dates for activities in progress or completed asappropriate.2. The estimated remaining duration for each activity in progress. Progresscalculations must be based on remaining duration for each activity and be in anapproved calculation mode.E. <strong>Contract</strong> Completion Date Extension: In the event the <strong>Contract</strong>or requests an extensionof the <strong>Contract</strong> completion date for other contractual reason, he shall furnish suchjustification as the <strong>Contract</strong>ing Officer may deem necessary for a determination of the<strong>Contract</strong>or’s right to an extension of time under the provisions of the <strong>Contract</strong>. In suchevent the schedule revisions must clearly display that the <strong>Contract</strong>or has used in full theavailable float time for the work involved with the request. Actual delays that are foundto be caused by the <strong>Contract</strong>or’s own actions or lack of action, and which result in theextension of the projected contract completion date shall not be a cause for extension ofthe <strong>Contract</strong> completion date. The <strong>Contract</strong>ing Officer may find cause to extend thecontract completion date under the <strong>Contract</strong> in the absence of a request by the<strong>Contract</strong>or when, in the <strong>Contract</strong>ing Officer’s judgment, it is equitable.Page 68 of 190


VESDA FIRE ALARM SYSTEM UPGRADE PROJECT NOVEMBER, 2010NEW YORK AIR ROUTE TRAFFIC CONTROL CENTER (ZNY) (REVISED AUGUST, 2011)RONKONKOMA, NEW YORKF. Float Time: Float available in the schedule at any time shall not be considered as forexclusive use by either the <strong>Contract</strong>or or the FAA. Extensions of time for performanceof work required under <strong>Contract</strong>, Clauses entitled, “CHANGES,” “DIFFERING SITECONDITIONS,” “DEFAULT (FIXED PRICE CONSTRUCTION),” or“SUSPENSION OF WORK” will be granted only to the extent that equitable timeadjustments for affected activities exceed the total float along their paths.1.5 SUBMITTAL SCHEDULEA. After development and acceptance of the <strong>Contract</strong>or's Construction Schedule, prepare acomplete schedule of submittals. Submit the schedule within 10 calendar days of thedate required for submittal of the <strong>Contract</strong>or's Construction Schedule.1. Coordinate Submittal Schedule with the <strong>Contract</strong>or's Construction Schedule.2. Prepare the schedule in chronological order. Provide the following information:a. Scheduled date for the first submittal.b. Related Section number.c. Submittal category (Shop Drawings, Product Data, or Samples).d. Name of the subcontractor.e. Description of the part of the Work covered.f. Scheduled date for resubmittal.g. Scheduled date for the <strong>Contract</strong>ing Officer's final release or approval.B. Distribution: Following response to the initial submittal, print and distribute copies tothe CONTRACTING OFFICER, subcontractors, and other parties required to complywith submittal dates indicated. Post copies in the Project meeting room and field office.1. When revisions are made, distribute to the same parties and post in the samelocations. Delete parties from distribution when they have completed theirassigned portion of the Work and are no longer involved in construction activities.C. Schedule Updating: Revise the schedule after each meeting or activity where revisionshave been recognized or made. Issue the updated schedule concurrently with the reportof each meeting.1.6 CONSTRUCTION SCHEDULESA. Construction Phasing Plan: Provide schedule including constraints and workrestrictions indicated in the <strong>Contract</strong> Documents and as follows and show howthe sequence of the Work is affected.1. Phasing: Arrange list of activities on schedule by phase.2. Work under More Than One <strong>Contract</strong>: Include a separate activity for eachcontract.3. FAA-Furnished Products: Include a separate activity for each product. Deliverydates indicated stipulate the earliest possible delivery date.4. Show the effect of the following items on the schedule:a. Coordination with existing construction.Page 69 of 190


VESDA FIRE ALARM SYSTEM UPGRADE PROJECT NOVEMBER, 2010NEW YORK AIR ROUTE TRAFFIC CONTROL CENTER (ZNY) (REVISED AUGUST, 2011)RONKONKOMA, NEW YORKb. Limitations of continued occupancies.c. Uninterruptible services.d. Partial occupancy before Substantial Completion.e. Use of premises restrictions.f. Environmental control.g. Other information as required by CONTRACTING OFFICER.B. Proposed dust-control measures.C. Proposed noise-control measures.D. Welding and Torch Cutting Plan. Prior to any welding or torch cutting activity, submit aWelding and Torch Cutting Plan for approval by the CONTRACTING OFFICER.Identify the work where welding and cutting will be performed, locations of the work,types of welding and cutting being proposed, schedule for proposed welding and cuttingactivities and plan for protecting the facility and its occupants, operations andequipment during the welding and cutting activities.1. Building electrical power may not be used for arc welding.2. Building components, including structural or miscellaneous steel, may not be usedas grounding return for welding activities.3. Provide ventilation and exhaust to the outside during welding and cuttingactivities to keep zone clear. Do not weld or cut unless ventilation and exhausthas been deemed acceptable by the CONTRACTING OFFICER or ResidentEngineer.4. Provide non-flammable shields to protect persons and properties.5. Keep cylinders upright and chained or secured to support.6. Remove flammable materials from welding and cutting areas prior to beginningwelding and cutting activities. Keep fire extinguishers in the welding and cuttingareas.7. Follow AWS “Specification and Safety Practice Codes” as published by theAmerican Welding Society (AWS) and OSHA Safety Requirements.1.7 DAILY CONSTRUCTION REPORTSRefer to Division 1-3, Quality Control1.8 SHOP DRAWINGSA. Submit newly prepared information drawn accurately to scale. Highlight, encircle, orotherwise indicate deviations from the <strong>Contract</strong> Documents. Do not reproduce <strong>Contract</strong>Documents or copy standard information as the basis of Shop Drawings. Standardinformation prepared without specific reference to the Project is not a Shop Drawing.B. Shop Drawings include fabrication and installation Drawings, setting diagrams,schedules, patterns, templates and similar Drawings. Include the followinginformation:Page 70 of 190


VESDA FIRE ALARM SYSTEM UPGRADE PROJECT NOVEMBER, 2010NEW YORK AIR ROUTE TRAFFIC CONTROL CENTER (ZNY) (REVISED AUGUST, 2011)RONKONKOMA, NEW YORK1. Dimensions.2. Identification of products and materials included by sheet and detail number.3. Compliance with specified standards.4. Notation of coordination requirements.5. Notation of dimensions established by field measurement.6. Sheet Size: Except for templates, patterns and similar full-size Drawings, submitShop Drawings on sheets at least 8-1/2 by 11 inches but no larger than 36 by 48inches.7. Initial Submittal: Submit one correctable, translucent, reproducible print and sixblue- or black-line prints for the CONTRACTING OFFICER's review. TheCONTRACTING OFFICER will return the reproducible print and two nonreproducibleprints.8. Final Submittal: If final submittal is required, submit one correctable, translucent,reproducible print and 6 blue- or black-line prints and 2 additional prints whererequired for maintenance manuals, plus the number of prints needed by theCONTRACTING OFFICER for distribution.a. One of the prints returned shall be marked up and maintained as a "RecordDocument."9. Do not use Shop Drawings without an appropriate final stamp indicating actiontaken.1.9 PRODUCT DATAA. Collect Product Data into a single submittal for each element of construction or system.Product Data includes printed information, such as manufacturer's installationinstructions, catalog cuts, standard color charts, roughing-in diagrams and templates,standard wiring diagrams, and performance curves.1. Mark each copy to show applicable choices and options. Where printed ProductData includes information on several products that are not required, mark copiesto indicate the applicable information. Include the following information:a. Manufacturer's printed recommendations.b. Compliance with trade association standards.c. Compliance with recognized testing agency standards.d. Application of testing agency labels and seals.e. Notation of dimensions verified by field measurement.f. Notation of coordination requirements.2. Do not submit Product Data until compliance with requirements of the <strong>Contract</strong>Documents has been confirmed.3. Preliminary Submittal: Submit a preliminary single reproducible copy of ProductData where selection of options is required.4. Submittals: Submit 6 copies of each required submittal; submit 8 copies whererequired for maintenance manuals. The CONTRACTING OFFICER will retaintwo, and will return the others marked with action taken and corrections ormodifications required.a. Unless noncompliance with <strong>Contract</strong> Document provisions is observed, thesubmittal may serve as the final submittal.Page 71 of 190


VESDA FIRE ALARM SYSTEM UPGRADE PROJECT NOVEMBER, 2010NEW YORK AIR ROUTE TRAFFIC CONTROL CENTER (ZNY) (REVISED AUGUST, 2011)RONKONKOMA, NEW YORK1.10 SAMPLES5. Distribution: Furnish copies of final submittal to installers, subcontractors,suppliers, manufacturers, fabricators, and others required for performance ofconstruction activities. Show distribution on transmittal forms.a. Do not proceed with installation until a copy of Product Data is in theInstaller's possession.b. Do not permit use of unmarked copies of Product Data in connection withconstruction.A. Submit full-size, fully fabricated Samples cured and finished as specified and physicallyidentical with the material or product proposed. Samples include partial sections ofmanufactured or fabricated components, cuts or containers of materials, color rangesets, and swatches showing color, texture, and pattern.1. Mount or display Samples in the manner to facilitate review of qualities indicated.Prepare Samples to match the CONTRACTING OFFICER's sample. Include thefollowing:a. Specification Section number and reference.b. Generic description of the Sample.c. Sample source.d. Product name or name of the manufacturer.e. Compliance with recognized standards.f. Availability and delivery time.g. Associated submittal, if applicable.2. Submit Samples for review of size, kind, color, pattern, and texture. SubmitSamples for a final check of these characteristics with other elements and acomparison of these characteristics between the final submittal and the actualcomponent as delivered and installed.a. Where variation in color, pattern, texture, or other characteristic is inherent inthe material or product represented, submit at least 3 multiple units that showapproximate limits of the variations.b. Refer to other Specification Sections for requirements for Samples thatillustrate workmanship, fabrication techniques, and details of assembly,connections, operation, and similar construction characteristics.c. Refer to other Sections for Samples to be returned to the <strong>Contract</strong>or forincorporation in the Work. Such Samples must be undamaged at time of use.On the transmittal, indicate special requests regarding disposition of Samplesubmittals.d. Samples not incorporated into the Work, or otherwise designated as the FAA'sproperty, are the property of the <strong>Contract</strong>or and shall be removed from the siteafter acceptance of that work, and prior to Substantial Completion.3. Preliminary Submittals: Submit a full set of choices where Samples are submittedfor selection of color, pattern, texture, or similar characteristics from a range ofstandard choices.Page 72 of 190


VESDA FIRE ALARM SYSTEM UPGRADE PROJECT NOVEMBER, 2010NEW YORK AIR ROUTE TRAFFIC CONTROL CENTER (ZNY) (REVISED AUGUST, 2011)RONKONKOMA, NEW YORKa. The CONTRACTING OFFICER shall review and return preliminarysubmittals with the CONTRACTING OFFICER's notation, indicatingselection and other action.4. Submittals: Except for Samples illustrating assembly details, workmanship,fabrication techniques, connections, operation, and similar characteristics, submit3 sets. The CONTRACTING OFFICER shall return one set marked with theaction taken.5. Maintain sets of Samples, as returned, at the Project Site, for quality comparisonsthroughout the course of construction.a. Unless noncompliance with <strong>Contract</strong> Document provisions is observed, thesubmittal may serve as the final submittal.b. Sample sets may be used to obtain final acceptance of the constructionassociated with each set.B. Distribution of Samples: Prepare and distribute additional sets to subcontractors,manufacturers, fabricators, suppliers, installers, and others as required for performanceof the Work. Show distribution on transmittal forms.1. Field samples are full-size examples erected on-site to illustrate finishes, coatings,or finish materials and to establish the Project standard.a. Comply with submittal requirements to the fullest extent possible. Processtransmittal forms to provide a record of activity.1.11 QUALITY ASSURANCE SUBMITTALSA. Submit quality-control submittals, including design data, certifications, manufacturer'sinstructions, manufacturer's field reports, and other quality-control submittals asrequired under other Sections of the <strong>Specifications</strong>.B. Certifications: Where other Sections of the <strong>Specifications</strong> require certification that aproduct, material, or installation complies with specified requirements, submit anotarized certification from the manufacturer certifying compliance with specifiedrequirements.1. Signature: Certification shall be signed by an officer of the manufacturer or otherindividual authorized to sign documents on behalf of the company.C. Inspection and Test Reports: Requirements for submittal of inspection and test reportsfrom independent testing agencies are specified in individual sections of these<strong>Specifications</strong> and each written report shall include the following:1. Date issued2. Project title and number3. Testing laboratory name, address, and telephone number4. Name and signature of laboratory inspector5. Data and time of sampling or inspection6. Record of temperature and weather conditions7. Date of test8. Identification of product and specifications9. Location of sample or test in the project10. Type of inspection or testPage 73 of 190


VESDA FIRE ALARM SYSTEM UPGRADE PROJECT NOVEMBER, 2010NEW YORK AIR ROUTE TRAFFIC CONTROL CENTER (ZNY) (REVISED AUGUST, 2011)RONKONKOMA, NEW YORK11. Results of tests and compliance with <strong>Contract</strong> Documents12. Interpretation of test results, when requested by CONTRACTINGOFFICER1.12 OPERATIONS/MAINTENANCE (O&M) INSTRUCTIONS AND PARTS LISTA. Prior to final inspection of acceptance, review contents of O&M manual with theFAA’s designated operating and maintenance personnel over a period of not more thanfive working days, instructing them in operation, adjustments and maintenance ofproducts, equipment, and systems. Maintain equipment and pay all costs of operation,demonstration, tests, and instruction until acceptance by the FAA.B. Refer to Section 01782, “Operation and Maintenance Manual Data” for requirementsfor submitting data for manuals.1.13 CONTRACTING OFFICER'S ACTIONA. Except for submittals for the record or information, where action and return is required,the CONTRACTING OFFICER shall review each submittal, mark to indicate actiontaken, and return promptly.1. Compliance with specified characteristics is the <strong>Contract</strong>or's responsibility.B. Action Stamp: The CONTRACTING OFFICER shall stamp each submittal with auniform, action stamp. The CONTRACTING OFFICER shall mark the stampappropriately to indicate the action taken, as follows:1. Final Unrestricted Release: When the CONTRACTING OFFICER marks asubmittal "Approved," the Work covered by the submittal may proceed providedit complies with requirements of the <strong>Contract</strong> Documents. Final payment dependson that compliance.2. Final-But-Restricted Release: When the CONTRACTING OFFICER marks asubmittal "Approved as Noted," the Work covered by the submittal may proceedprovided it complies with notations or corrections on the submittal andrequirements of the <strong>Contract</strong> Documents. Final payment depends on thatcompliance.3. Returned for Resubmittal: When the CONTRACTING OFFICER marks asubmittal "Not Approved, Revise and Resubmit," do not proceed with Workcovered by the submittal, including purchasing, fabrication, delivery, or otheractivity. Revise or prepare a new submittal according to the notations; resubmitwithout delay. Repeat if necessary to obtain different action mark.a. Do not use, or allow others to use, submittals marked "Not Approved, Reviseand Resubmit" at the Project Site or elsewhere where Work is in progress.4. Other Action: Where a submittal is for information or record purposes or specialprocessing or other activity, the CONTRACTING OFFICER will return thesubmittal marked "Action Not Required."C. Unsolicited Submittals: The CONTRACTING OFFICER may return unsolicitedsubmittals to the sender without action.Page 74 of 190


VESDA FIRE ALARM SYSTEM UPGRADE PROJECT NOVEMBER, 2010NEW YORK AIR ROUTE TRAFFIC CONTROL CENTER (ZNY) (REVISED AUGUST, 2011)RONKONKOMA, NEW YORKPART 2 - PRODUCTS (NOT APPLICABLE)PART 3 - EXECUTION3.1 SUBMITTAL SCHEDULEA. General: <strong>Contract</strong>or shall submit to the CONTRACTING OFFICER in duplicate, aschedule listing all items that will be furnished for review and approval. The scheduleshall include but not necessarily be limited to shop drawings and manufacturer’sliterature, test procedures, test results, certificates of compliance, material samples, andspecial guarantees. The schedule shall indicate the type of item, <strong>Contract</strong> requirementreference, the <strong>Contract</strong>or’s scheduled date for submitting the above items, identificationof the first schedule activity and projected needs for approval answers to supportprocurement or installation. In preparing the schedule, allow 20 days for review,approval, and possible resubmittal. Scheduling shall be coordinated with the approvedconstruction progress chart. The <strong>Contract</strong>or shall revise and/or update the schedule asdirected. Revised schedule shall be made available to CONTRACTING OFFICER formonitoring.END OF SECTIONPage 75 of 190


VESDA FIRE ALARM SYSTEM UPGRADE PROJECT NOVEMBER, 2010NEW YORK AIR ROUTE TRAFFIC CONTROL CENTER (ZNY) (REVISED AUGUST, 2011)RONKONKOMA, NEW YORKSECTION 01782 - OPERATIONS AND MAINTENANCE MANUAL DATAPART 1 - GENERAL1.1 SUMMARYA. This Section includes requirements for Operation and Maintenance (O&M) manuals forhard copy and electronic/record documents, including the following:1. Prepare and submit operation and maintenance manuals for building operatingsystems and equipment.2. Project record document submittal.3. Provide O&M data to the Government for use in updating Air Route Traffic ControlCenters (ARTCC) O&M documents.a) Prior to any demolition, the <strong>Contract</strong>or shall obtain from the <strong>Contract</strong>ingOfficer’s Representative (COTR) a copy of the electronic O&M equipmentinventory for the specific part of the facility being constructed/renovated underthis contract. The <strong>Contract</strong>or shall annotate on the inventory list anyequipment removed or taken out of service as a result ofconstruction/renovation and return it to the COTR upon completion ofdemolition.b) An inventory of each component and piece of equipment requiring operationsand maintenance documentation identified in the specification and contractdrawings shall be documented and provided to the COTR in worksheet format.Use Attachment 1 to this section to identify systems and sub-systems.Attachment 2 is the format that shall be used to document O&M equipmentinventory information. COTR will provide guidance on how to completeworksheets.B. Related references for submitting information for operation and maintenance manuals:1. Appropriate Sections of Divisions 13 and 16 specify special operation andmaintenance data requirements for specific pieces of equipment or buildingoperating systems.1.2 QUALITY ASSURANCEA. Maintenance Manual Preparation: In preparation of maintenance manuals, usecompetent/certified personnel thoroughly trained and experienced in operation andmaintenance of equipment or systems involved.1. Provide O & M manuals prepared in accordance with this Section.Page 76 of 190


VESDA FIRE ALARM SYSTEM UPGRADE PROJECT NOVEMBER, 2010NEW YORK AIR ROUTE TRAFFIC CONTROL CENTER (ZNY) (REVISED AUGUST, 2011)RONKONKOMA, NEW YORK2. Where specifications require written instructions, use personnel skilled in technicalwriting where necessary for communication of essential data.3. Where specifications require drawings or diagrams, use personnel skilled inpreparing drawings clearly in an understandable format.1.3 SUBMITTAL SCHEDULEA. Submittal Schedule: Unless otherwise noted, comply with the following schedule forsubmitting operation and maintenance manuals:1. Draft O&M Documentation for Individual Items. Sixty days after approval of eachtechnical submittal, submit 2 draft sets of O&M documentation for the approveditem to the COTR for review. All O&M submittals shall be manufacturer’s originalpublications. Photocopies will not be accepted. Manuals shall be organized bysystem, as described in Paragraph “O&M Manual Sections By Building System” ofthis Section. The COTR will return 1 copy of the draft with comments within 30days of receipt.2. Inventory Information. Submit 2 paper copies and one electronic version in MSExcel format 60 days before substantial completion.3. Final O&M Documentation. Make corrections or modifications to comply with theCOTR’s comments. Submit three sets of the final O&M documentation to theCOTR within 15 days of receipt of the COTR’s comments.B. Form of Submittal: Prepare operation and maintenance manuals in the form of aninstructional manual for use by the Government's operating personnel. Organize intosets in sizes as indicated. Organize O&M information by system as described inSchedule at end of Part 3 of this Section.1. Binders: For each manual, provide heavy-duty, commercial-quality, 3-ring, vinylcovered,loose-leaf binders, maximum of 3 inches thick, sized to receive 8-1/2-by-11- inch paper. Provide a clear plastic sleeve on the spine and front cover to holdlabels describing contents. Provide 3-hole punched, heavy-duty sheet protectors tohold folded oversized documents. Do not fill binders to more than 1/2 capacity.a. Where multiple binders are necessary to accommodate data, correlate datain each binder into related groupings according to the Project Manual tableof contents. Cross-reference other binders where necessary to provideessential information for proper operation or maintenance of the piece ofequipment or system.b. Identify each binder on front and spine, with the printed title "OPERATIONAND MAINTENANCE MANUAL," Project title or name, and subjectmatter covered. Indicate volume number for multiple volume sets ofmanuals.Page 77 of 190


VESDA FIRE ALARM SYSTEM UPGRADE PROJECT NOVEMBER, 2010NEW YORK AIR ROUTE TRAFFIC CONTROL CENTER (ZNY) (REVISED AUGUST, 2011)RONKONKOMA, NEW YORK2. Dividers: Provide heavy paper dividers with clear celluloid-covered tabs for eachseparate Section. Mark each tab to indicate contents. Provide a description of theProduct and major parts of equipment included in the Section on each divider.3. Text Material: Provide the manufacturer's standard printed material. Ifmanufacturer's standard printed material is not available, provide speciallyprepared data, computer generated, on 8-1/2-by-11 inch, 20-lb/sq. ft. white bondpaper.4. Drawings: Provide reinforced, punched binder tabs on drawings and bind withtext. Where oversize drawings are necessary, fold drawings to the same size astext pages, and inserted in a 3-hole-punched, heavy-duty plastic sheet protector.C. Submit 2 copies of each manual, in final form, on equipment and systems to the COTRfor distribution. Include information for each unit of equipment, each operating system,and each electric and electronic system.D. Payment Processing: No payment will be made for materials delivered on site for whichDraft O&M Documentation for Individual Items has not been approved.1.4 MANUAL CONTENTA. Include information required by the individual Specification Sections in the form ofData Packages. Data packages shall be developed for each building component, pieceof equipment and system based on level of complexity and as specified in the individualSpecification Sections. Data packages shall be provided in accordance with Schedule atend of Part 3 of this Section. Applicability of data packages is as follows:1. Data Package 1: General building materials and components such as sealants, lightfixtures, door hardware, etc.2. Data Package 2: Simple operating components such as valves, hatches, louvers,plumbing fixtures3. Data Package 3: Minor equipment such as small pumps and fans4. Data Package 4: Major and complex equipment such as AHU's, package AC units,large pumps and motors, elevators, control systems, alarm systems, etc.B. Data Package information shall be provided as follows:1. Data Package 1:a. Manufacturer’s product information.b. Supplier information.c. Warranty information.d. MSDS, when appropriate.2. Data Package 2:Page 78 of 190


VESDA FIRE ALARM SYSTEM UPGRADE PROJECT NOVEMBER, 2010NEW YORK AIR ROUTE TRAFFIC CONTROL CENTER (ZNY) (REVISED AUGUST, 2011)RONKONKOMA, NEW YORKa. Manufacturer’s product informationb. Supplier informationc. Warranty informationd. Safety precautionse. Maintenance and repair proceduresf. Replacement parts identification & installation3. Data Package 3:a. Manufacturer’s product informationb. Supplier informationc. Warranty informationd. Safety precautionse. Maintenance and repair proceduresf. Replacement parts identification & installationg. Normal operating instructionsh. Lubrication datai. Preventive maintenance plan/schedulej. Alignment, adjusting and checking informationk. Removal and replacement instructionsl. Parts identificationm. Wiring diagrams4. Data Package 4: Data Package 3 information plus:a. Equipment or System Description including:1) Equipment or System Function2) Operating characteristics3) Safety precautions4) Environmental and limiting conditions5) Performance curves6) Engineering data and tests7) Complete nomenclature and number of replacement parts8) Supplier and vendor informationb. Manufacturer's Information including:1) Assembly drawings and diagrams required for maintenance2) List of items recommended to be stocked as spare parts3) Wiring and control diagramsc. Maintenance Procedures detailing essential maintenance procedures including:Page 79 of 190


VESDA FIRE ALARM SYSTEM UPGRADE PROJECT NOVEMBER, 2010NEW YORK AIR ROUTE TRAFFIC CONTROL CENTER (ZNY) (REVISED AUGUST, 2011)RONKONKOMA, NEW YORK1) Printed operation and maintenance instructions2) Routine operations3) Troubleshooting guide & diagnostic techniques4) Disassembly, repair and reassemble5) Alignment, adjusting and checking6) Lubrication data7) Consumable information such as belts and filters8) Testing equipment & special tool informationd. Operating Procedures including:1) Start up and shut down procedures2) Equipment or system break-in3) Routine and normal operating instructions4) Regulation and control procedures5) Emergency procedures6) Summer and winter operating instructions7) Required sequences for electric or electronic systems8) Special operating instructions9) Operator service requirementsC. Software: Specified program listings, interface control documents, source code listing,and copies of the operating programs on media appropriate to use as backup for thesystem software. Include instructions for loading the operating software onto thesystem.D. Additional requirements:1. For each system, general system or equipment description. Include size, weight,power consumption, power requirements, and outline drawings.2. Copies of applicable Shop Drawings, Product Data, Drawings, and Schematics forthe equipment systems.3. Theory of Operation: Description of technical operating characteristics of thesystem and individual equipment using standard phraseology; descriptions ofinterface requirements including operating protocols; equipment displays andscreens; make reference to installation drawings, schematics and equipmentdisplays as required for technical understanding.E. Identification Legends:1. Piping and equipment: Provide a computer-generated legend to correspond withidentification devices installed on piping and equipment. List the identifyingdevice, its’location, a brief description of the devices function, and the I.D. number.Page 80 of 190


VESDA FIRE ALARM SYSTEM UPGRADE PROJECT NOVEMBER, 2010NEW YORK AIR ROUTE TRAFFIC CONTROL CENTER (ZNY) (REVISED AUGUST, 2011)RONKONKOMA, NEW YORK2. Panel boards and switchboards: Provide a computer-generated legend for eachpanel board and switchboard installed in the project. This information shall be aduplicate of the legend placed in the panel board.3. Valve Tags and Schedule: Provide a computer-generated schedule of all valvetags. Include valve type, manufacturer, equipment location and size for all newlyinstalled valves.F. Organize the manual into separate Sections, by system as described in Paragraph “O&MManual Sections By Building System” of this Article, for each system or piece ofrelated equipment.1. Title Page: Provide a title page in a transparent, plastic envelope as the first sheetof each manual. Provide the following information:a. Subject matter covered by the manualb. Name and address of the Projectc. Date of submittald. Name, address, and telephone number of the <strong>Contract</strong>ore. Name and address of the Architectg. Cross-reference to related systems in other operation and maintenance manuals.h. Name, address and telephone number of all Sub-<strong>Contract</strong>ors.2. Table of Contents: After the title page, include a computer-generated table ofcontents for each volume, arranged systematically according to the Project Manualformat. Include a list of each product incorporated, identified by product nameand other appropriate identifying symbol and indexed to the content of thevolume. Each Data Package shall be tabbed and separately listed in the Table ofContents. Where multiple volumes are required to accommodate data, provide acomprehensive table of contents for all volumes in each volume of the set.3. General Information: Provide a general information Section immediatelyfollowing table of contents, listing each product included in the manual, identifiedby product name. Under each product, list the name, address, and telephonenumber of the Sub-<strong>Contract</strong>or or installer and the maintenance <strong>Contract</strong>or whereapplicable. Clearly delineate the extent of responsibility of each of these entities.Include a local source for replacement parts and equipment.4. Product Data: Where the manuals include manufacturer's standard printed data,include only sheets that are pertinent to the part or product installed. Mark eachsheet to identify each part or product included in the installation. Where theProject includes more than one item in a tabular format, identify each item, usingappropriate references from the <strong>Contract</strong> Documents. Identify data that isapplicable to the installation, and delete references to information that is notapplicable.5. Written Text: Prepare written text to provide necessary information wheremanufacturer's standard printed data are not available, and the information isnecessary for proper operation and maintenance of equipment or systems. PreparePage 81 of 190


VESDA FIRE ALARM SYSTEM UPGRADE PROJECT NOVEMBER, 2010NEW YORK AIR ROUTE TRAFFIC CONTROL CENTER (ZNY) (REVISED AUGUST, 2011)RONKONKOMA, NEW YORKwritten text where it is necessary to provide additional information or tosupplement data included in the manual. Organize text in a consistent formatunder separate headings for different procedures. Where necessary, provide alogical sequence of instruction for each operation or maintenance procedure.5. Drawings: Provide specially prepared drawings where necessary to supplementmanufacturer's printed data to illustrate the relationship of component parts ofequipment or systems or to provide control or flow diagrams. Coordinate thesedrawings with information contained in project record drawings to ensure correctillustration of the completed installation.6. Warranties, Bonds, and Service <strong>Contract</strong>s: Provide a copy of each warranty, bond,or service contract tabbed in a separate binder. Provide written data outliningprocedures to follow in the event of product failure. List circumstances andconditions that would affect the validity of a warranty or bond.PART 2 – PRODUCTS (NOT USED)PART 3 – EXECUTION (NOT USED)END OF SECTIONPage 82 of 190


VESDA FIRE ALARM SYSTEM UPGRADE PROJECT NOVEMBER, 2010NEW YORK AIR ROUTE TRAFFIC CONTROL CENTER (ZNY) (REVISED AUGUST, 2011)RONKONKOMA, NEW YORKAttachment 2: Format for O&M Inventory InformationEquipmentIdentificationDescriptionAttachment 2: Format for O&M Inventory InformationRoom Manufacturer Vendor Model SerialNumberSystemI.D.Sub-SystemI.D.NotesPage 83 of 190


VESDA FIRE ALARM SYSTEM UPGRADE PROJECT NOVEMBER, 2010NEW YORK AIR ROUTE TRAFFIC CONTROL CENTER (ZNY) (REVISED AUGUST, 2011)RONKONKOMA, NEW YORKPage 84 of 190


VESDA FIRE ALARM SYSTEM UPGRADE PROJECT NOVEMBER, 2010NEW YORK AIR ROUTE TRAFFIC CONTROL CENTER (ZNY) (REVISED AUGUST, 2011)RONKONKOMA, NEW YORKSECTION 01820 - DEMONSTRATION AND TRAININGPART 1GENERAL1.1 SUMMARYB. This Section includes administrative and procedural requirements forinstructing FAA's personnel, including the following:1. Demonstration of operation of systems, subsystems, and equipment.2. Training in operation and maintenance of systems, subsystems, andequipment.3. Written documentation of training and FAA personnel comprehension.1.2 SUBMITTALSA. Instruction Program: Within 90 days of <strong>Contract</strong> Acceptance Inspection(CAI), submit three copies of instructional program outlines fordemonstration and training, including a schedule of proposed dates,times, length of instruction time, instructors' names and instructors’qualifications for each training module. Include learning objective andoutline for each training module. Instruction program shall be basedupon and utilize the approved operation and maintenance manual data.1. At completion of training, submit one complete training manual for FAA'suse.B. Attendance Record: For each training module, submit list of participantsand length of instruction time.C. Evaluations: For each participant and for each training module, submitresults and documentation of performance-based test, and studentevaluations of training.1.3 QUALITY ASSURANCEA. Facilitator Qualifications: A firm or individual experienced in training oreducating maintenance personnel in a training program similar in contentand extent to that indicated for this Project, and whose work has resultedin training or education with a record of successful learning performance.Page 85 of 190


VESDA FIRE ALARM SYSTEM UPGRADE PROJECT NOVEMBER, 2010NEW YORK AIR ROUTE TRAFFIC CONTROL CENTER (ZNY) (REVISED AUGUST, 2011)RONKONKOMA, NEW YORKB. Instructor Qualifications: A factory-authorized service representativeexperienced in operation and maintenance procedures and training.C. Pre-instruction Conference: Conduct conference at Project site. Reviewmethods and procedures related to demonstration and training including,but not limited to, the following:1. Inspect and discuss locations and other facilities required for instructionincluding classroom training and field training.2. Review and finalize instruction schedule and verify availability ofeducational materials, instructors' personnel, audiovisual equipment, andfacilities needed to avoid delays.3. Review required content of instruction.4. For instruction that must occur outside, review weather and forecastedweather conditions and procedures to follow if conditions are unfavorable.1.4 COORDINATIONA. Coordinate instruction schedule with FAA operations. Adjust scheduleas required to minimize disrupting FAA operations.B. Coordinate instructors, including providing notification of dates, times,length of instruction time, and course content.C. Coordinate content of training modules with content of approvedoperation, and maintenance manuals. Do not submit instruction programuntil operation and maintenance data has been reviewed and approved.PART 2 - PRODUCTS2.1 INSTRUCTION PROGRAMA. Program Structure: Develop a comprehensive instruction program.Include individual training modules for each system and equipment notpart of a system, as required by technical Specification Sections and theSchedule of Training in Part 3 of this Section. In addition <strong>Contract</strong>orshall include requirements of the General Fire Alarm Note #15. ondrawing # ZNY-805563-F001.B. Training Modules: Develop a learning objective and teaching outline foreach module. Include a description of specific skills and knowledge thatPage 86 of 190


VESDA FIRE ALARM SYSTEM UPGRADE PROJECT NOVEMBER, 2010NEW YORK AIR ROUTE TRAFFIC CONTROL CENTER (ZNY) (REVISED AUGUST, 2011)RONKONKOMA, NEW YORKparticipant is expected to master. For each module, include instructionfor the following as applicable:1. Basis of System Design, Operational Requirements, and Criteria: Includethe following:a. System, subsystem, and equipment descriptions.b. Performance and design criteria if <strong>Contract</strong>or is delegated designresponsibility.c. Operating standards.d. Regulatory requirements.e. Equipment function.f. Operating characteristics.g. Limiting conditions.h. Performance curves.2. Documentation: Review the following items in detail:a. Operations manuals.b. Maintenance manuals.c. Project Record Documents.d. Identification systems.e. Warranties and bonds.f. Maintenance service agreements and similar continuingcommitments.3. Emergencies: Include the following:a. Instructions on meaning of warnings, trouble indications, and errormessages.b. Instructions on stopping.c. Shutdown instructions for each type of emergency.d. Operating instructions for conditions outside of normal operatinglimits.e. Sequences for electric or electronic systems.f. Special operating instructions and procedures.4. Operations: Include the following:a. Startup procedures.b. Equipment or system break-in procedures.c. Routine and normal operating instructions.d. Regulation and control procedures.e. Control sequences.f. Safety procedures, including lockout/tag out requirements.Page 87 of 190


VESDA FIRE ALARM SYSTEM UPGRADE PROJECT NOVEMBER, 2010NEW YORK AIR ROUTE TRAFFIC CONTROL CENTER (ZNY) (REVISED AUGUST, 2011)RONKONKOMA, NEW YORKg. Instructions on stopping.h. Normal shutdown and re-start instructions.i. Operating procedures for system, subsystem, or equipment failure.j. Seasonal and weekend operating instructions.k. Required sequences for electric or electronic systems.l. Special operating instructions and procedures.5. Adjustments: Include the following:a. Alignments.b. Checking adjustments.c. Noise and vibration adjustments.d. Economy and efficiency adjustments.6. Troubleshooting: Include the following:a. Diagnostic instructions.b. Test and inspection procedures.7. Maintenance: Include the following:a. Inspection procedures.b. Types of cleaning agents to be used and methods of cleaning.c. List of cleaning agents and methods of cleaning detrimental toproduct.d. Procedures for routine cleaninge. Procedures for preventive/predictive maintenance.f. Procedures for routine maintenance.g. Instruction on use of special tools.8. Repairs: Include the following:a. Diagnosis instructions.b. Repair instructions.c. Disassembly; component removal, repair, and replacement; andreassembly instructions.d. Instructions for identifying parts and components.e. Review of spare parts needed for operation and maintenance.C. Training Duration: Duration of training and demonstration is addressedunder Part 3 – Execution. Training and demonstration duration forspecific items within a training module may be adjusted with FAAapproval to meet the overall goals of the training module.Page 88 of 190


VESDA FIRE ALARM SYSTEM UPGRADE PROJECT NOVEMBER, 2010NEW YORK AIR ROUTE TRAFFIC CONTROL CENTER (ZNY) (REVISED AUGUST, 2011)RONKONKOMA, NEW YORKPART 3 - EXECUTION3.1 PREPARATIONA. Assemble educational materials necessary for instruction, includingdocumentation and training module. Assemble training modules into acombined training manual.B. Set up instructional equipment at instruction location.3.2 INSTRUCTIONA. Qualified Facilitator shall prepare instruction program and trainingmodules, to coordinate instructors, and coordinate between <strong>Contract</strong>orand FAA for number of participants, instruction times, dates andlocation.B. Qualified Instructors shall instruct FAA's personnel to adjust, operate,and maintain equipment and systems.1. The COTR will furnish names and positions of participants.C. Scheduling: Provide instruction at mutually agreed on times. Forequipment that requires seasonal operation, provide instruction onactions necessary to prepare for and execute seasonal change over.1. Schedule training through the COTR with at least 30 days' advance notice.D. Evaluation: At conclusion of each training module, assess and documenttraining.1. Assess and document each participant’s mastery of module by use of anoral performance-based test.2. Obtain each participant’s evaluation of the training via a pre-printedsurvey form approved by the COTR.Page 89 of 190


VESDA FIRE ALARM SYSTEM UPGRADE PROJECT NOVEMBER, 2010NEW YORK AIR ROUTE TRAFFIC CONTROL CENTER (ZNY) (REVISED AUGUST, 2011)RONKONKOMA, NEW YORKE. Cleanup: Collect used and leftover educational materials. Removeinstructional equipment. Restore systems and equipment to conditionexisting before initial training use.F. Record of Training. Provide a record of training. Record shall includelist of attendees, student evaluation of training, evaluation of studentcomprehension at the end of training and recommendations for follow-ontraining.3.3 SCHEDULE OF TRAININGSPECIFICATION SECTIONNO. TITLE13850 Air Sampling SmokeDetection SystemHOURSTRAININGThree 2-hoursessionsNOTESProvide training for 3 shifts. Includeproject tour to show location of eachdetector and power supply.END OF SECTIONPage 90 of 190


VESDA FIRE ALARM SYSTEM UPGRADE PROJECT NOVEMBER, 2010NEW YORK AIR ROUTE TRAFFIC CONTROL CENTER (ZNY) (REVISED AUGUST, 2011)RONKONKOMA, NEW YORKSECTION 07270 - FIRESTOPPINGPART 1 - GENERAL1.1 SUMMARYA. This Section includes through-penetration firestop systems forpenetrations through the following fire-resistance-rated assemblies,including both empty openings and openings containing penetratingitems:1. Floors.2. Roofs.3. Walls and partitions.4. Smoke barriers.1.2 PERFORMANCE REQUIREMENTSA. General: For the following constructions, provide through-penetrationfirestop systems that are produced and installed to resist spread of fireaccording to requirements indicated, resist passage of smoke and othergases, and maintain original fire-resistance rating of assembly penetrated.1. Fire-resistance-rated load-bearing walls, including partitions, with fireprotection-ratedopenings.2. Fire-resistance-rated non-load-bearing walls, including partitions, withfire-protection-rated openings.3. Fire-resistance-rated floor assemblies.4. Fire-resistance-rated roof assemblies.B. F-Rated Systems: Provide through-penetration firestop systems with F-ratings indicated, as determined per ASTM E 814, but not less than thatequaling or exceeding fire-resistance rating of constructions penetrated.C. T-Rated Systems: For the following conditions, provide throughpenetrationfirestop systems with T-ratings indicated, as well as F-ratings, as determined per ASTM E 814, where systems protectpenetrating items exposed to potential contact with adjacent materials inoccupiable floor areas:1. Penetrations located outside wall cavities.Page 91 of 190


VESDA FIRE ALARM SYSTEM UPGRADE PROJECT NOVEMBER, 2010NEW YORK AIR ROUTE TRAFFIC CONTROL CENTER (ZNY) (REVISED AUGUST, 2011)RONKONKOMA, NEW YORK2. Penetrations located outside fire-resistive shaft enclosures.3. Penetrations located in construction containing fire-protection-ratedopenings.4. Penetrating items larger than 4-inch- diameter nominal pipe or 16 sq. in. inoverall cross-sectional area.D. For through-penetration firestop systems exposed to view, traffic,moisture, and physical damage, provide products that after curing do notdeteriorate when exposed to these conditions both during and afterconstruction.1. For piping penetrations for plumbing and wet-pipe sprinkler systems,provide moisture-resistant through-penetration firestop systems.2. For floor penetrations with annular spaces exceeding 4 inches in width andexposed to possible loading and traffic, provide firestop systems capableof supporting floor loads involved either by installing floor plates or byother means.3. For penetrations involving insulated piping, provide through-penetrationfirestop systems not requiring removal of insulation.E. For through-penetration firestop systems exposed to view, provideproducts with flame-spread ratings of less than 25 and smoke-developedratings of less than 450, as determined per ASTM E 84.1.3 SUBMITTALSA. Product Data: For each type of through-penetration firestop systemproduct indicated.B. Shop Drawings: For each through-penetration firestop system, showeach kind of construction condition penetrated, relationships to adjoiningconstruction, and kind of penetrating item. Include firestop designdesignation of testing and inspecting agency acceptable to authoritieshaving jurisdiction that evidences compliance with requirements for eachcondition indicated.1. Submit documentation, including illustrations, from a qualified testing andinspecting agency that is applicable to each through-penetration firestopsystem configuration for construction and penetrating items.2. Where Project conditions require modification of qualified testing andinspecting agency's illustration to suit a particular through-penetrationfirestop condition, submit illustration, with modifications marked,approved by through-penetration firestop system manufacturer's fireprotectionengineer.Page 92 of 190


VESDA FIRE ALARM SYSTEM UPGRADE PROJECT NOVEMBER, 2010NEW YORK AIR ROUTE TRAFFIC CONTROL CENTER (ZNY) (REVISED AUGUST, 2011)RONKONKOMA, NEW YORKC. Qualification Data: For firms and persons specified in "QualityAssurance" Article to demonstrate their capabilities and experience.Include lists of completed projects with project names and addresses,names and addresses of architects and owners, and other informationspecified.D. Product Certificates: Signed by manufacturers of through-penetrationfirestop system products certifying that products furnished comply withrequirements.E. Product Test Reports: From a qualified testing agency indicatingthrough-penetration firestop system complies with requirements, basedon comprehensive testing of current products.1.4 QUALITY ASSURANCEA. Installer Qualifications: An experienced installer who has completedthrough-penetration firestop systems similar in material, design, andextent to that indicated for this Project and whose work has resulted inconstruction with a record of successful in-service performance.B. Installer Qualifications: An experienced installer who is qualified byhaving the necessary experience, staff, and training to installmanufacturer's products per specified requirements. A manufacturer'swillingness to sell its through-penetration firestop system products to<strong>Contract</strong>or or to an installer engaged by <strong>Contract</strong>or does not in itselfconfer qualification on buyer.C. Source Limitations: Obtain through-penetration firestop systems, foreach kind of penetration and construction condition indicated, from asingle manufacturer.D. Fire-Test-Response Characteristics: Provide through-penetration firestopsystems that comply with the following requirements and those specifiedin "Performance Requirements" Article:1. Firestopping tests are performed by a qualified testing and inspectingagency. A qualified testing and inspecting agency is UL, or anotheragency performing testing and follow-up inspection services for firestopsystems acceptable to authorities having jurisdiction.2. Through-penetration firestop systems are identical to those tested perASTM E 814. Provide rated systems complying with the followingrequirements:.Page 93 of 190


VESDA FIRE ALARM SYSTEM UPGRADE PROJECT NOVEMBER, 2010NEW YORK AIR ROUTE TRAFFIC CONTROL CENTER (ZNY) (REVISED AUGUST, 2011)RONKONKOMA, NEW YORKa. Through-penetration firestop system products bear classificationmarking of qualified testing and inspecting agency.b. Through-penetration firestop systems correspond to those indicatedby reference to through-penetration firestop system designationslisted by the following:1) UL in "Fire Resistance Directory."E. Pre-installation Conference: Conduct conference at Project site tocomply with requirements in Division 1 Section "Project Meetings."1.5 DELIVERY, STORAGE, AND HANDLINGA. Deliver through-penetration firestop system products to Project site inoriginal, unopened containers or packages with intact and legiblemanufacturers' labels identifying product and manufacturer; date ofmanufacture; lot number; shelf life, if applicable; qualified testing andinspecting agency's classification marking applicable to Project; curingtime; and mixing instructions for multicomponent materials.B. Store and handle materials for through-penetration firestop systems toprevent their deterioration or damage due to moisture, temperaturechanges, contaminants, or other causes.1.6 PROJECT CONDITIONSA. Environmental Limitations: Do not install through-penetration firestopsystems when ambient or substrate temperatures are outside limitspermitted by through-penetration firestop system manufacturers or whensubstrates are wet due to rain, frost, condensation, or other causes.B. Ventilate through-penetration firestop systems per manufacturer's writteninstructions by natural means or, where this is inadequate, forced-aircirculation.1.7 COORDINATIONA. Coordinate construction of openings and penetrating items to ensure thatthrough-penetration firestop systems are installed according to specifiedrequirements.Page 94 of 190


VESDA FIRE ALARM SYSTEM UPGRADE PROJECT NOVEMBER, 2010NEW YORK AIR ROUTE TRAFFIC CONTROL CENTER (ZNY) (REVISED AUGUST, 2011)RONKONKOMA, NEW YORKB. Coordinate sizing of sleeves, openings, core-drilled holes, or cutopenings to accommodate through-penetration firestop systems.C. Notify Owner's inspecting agency at least seven days in advance ofthrough-penetration firestop system installations; confirm dates and timeson days preceding each series of installations.D. Do not cover up through-penetration firestop system installations thatwill become concealed behind other construction until Owner'sinspecting agency and building inspector, if required by authoritieshaving jurisdiction, have examined each installation.PART 2 - PRODUCTS2.1 MANUFACTURERSA. Manufacturers: Subject to compliance with requirements, provideproducts by one of the following:1. Hilti Construction Chemicals, Inc.2. Isolatek International.3. Nelson Firestop Products.4. 3M Fire Protection Products.5. Tremco.2.2 FIRESTOPPING, GENERALA. Compatibility: Provide through-penetration firestop systems that arecompatible with one another, with the substrates forming openings, andwith the items, if any, penetrating through-penetration firestop systems,under conditions of service and application, as demonstrated by throughpenetrationfirestop system manufacturer based on testing and fieldexperience.B. Accessories: Provide components for each through-penetration firestopsystem that are needed to install fill materials and to comply with"Performance Requirements" Article. Use only components specified bythrough-penetration firestop system manufacturer and approved by thequalified testing and inspecting agency for firestop systems indicated.Accessories include, but are not limited to, the following items:1. Permanent forming/damming/backing materials, including the following:Page 95 of 190


VESDA FIRE ALARM SYSTEM UPGRADE PROJECT NOVEMBER, 2010NEW YORK AIR ROUTE TRAFFIC CONTROL CENTER (ZNY) (REVISED AUGUST, 2011)RONKONKOMA, NEW YORKa. Slag-/rock-wool-fiber insulation.b. Sealants used in combination with other forming/damming/backingmaterials to prevent leakage of fill materials in liquid state.c. Fire-rated form board.d. Fillers for sealants.2. Temporary forming materials.3. Substrate primers.4. Collars.5. Steel sleeves.2.3 FILL MATERIALSA. General: Provide through-penetration firestop systems containing thetypes of fill materials indicated in the Through-Penetration FirestopSystem Schedule at the end of Part 3 by reference to the types ofmaterials described in this Article. Fill materials are those referred to indirectories of the referenced testing and inspecting agencies as fill, void,or cavity materials.B. Cast-in-Place Firestop Devices: Factory-assembled devices for use incast-in-place concrete floors and consisting of an outer metallic sleevelined with an intumescent strip, a radial extended flange attached to oneend of the sleeve for fastening to concrete formwork, and a neoprenegasket.C. Latex Sealants: Single-component latex formulations that after cure donot re-emulsify during exposure to moisture.D. Firestop Devices: Factory-assembled collars formed from galvanizedsteel and lined with intumescent material sized to fit specific diameter ofpenetrant.E. Intumescent Composite Sheets: Rigid panels consisting of aluminumfoil-facedelastomeric sheet bonded to galvanized steel sheet.F. Intumescent Putties: Nonhardening dielectric, water-resistant puttiescontaining no solvents, inorganic fibers, or silicone compounds.G. Intumescent Wrap Strips: Single-component intumescent elastomericsheets with aluminum foil on one side.H. Mortars: Prepackaged, dry mixes consisting of a blend of inorganicbinders, hydraulic cement, fillers, and lightweight aggregate formulatedPage 96 of 190


VESDA FIRE ALARM SYSTEM UPGRADE PROJECT NOVEMBER, 2010NEW YORK AIR ROUTE TRAFFIC CONTROL CENTER (ZNY) (REVISED AUGUST, 2011)RONKONKOMA, NEW YORKfor mixing with water at Project site to form a nonshrinking,homogeneous mortar.I. Pillows/Bags: Reusable, heat-expanding pillows/bags consisting ofglass-fiber cloth cases filled with a combination of mineral-fiber, waterinsolubleexpansion agents and fire-retardant additives.J. Silicone Foams: Multicomponent, silicone-based liquid elastomers that,when mixed, expand and cure in place to produce a flexible,nonshrinking foam.K. Silicone Sealants: Moisture-curing, single-component, silicone-based,neutral-curing elastomeric sealants of grade indicated below:1. Grade: Pourable (self-leveling) formulation for openings in floors andother horizontal surfaces and nonsag formulation for openings in verticaland other surfaces requiring a nonslumping, gunnable sealant, unlessindicated firestop system limits use to nonsag grade for both openingconditions.2. Grade for Horizontal Surfaces: Pourable (self-leveling) formulation foropenings in floors and other horizontal surfaces.3. Grade for Vertical Surfaces: Nonsag formulation for openings in verticaland other surfaces.2.4 MIXINGA. For those products requiring mixing before application, comply withthrough-penetration firestop system manufacturer's written instructionsfor accurate proportioning of materials, water (if required), type ofmixing equipment, selection of mixer speeds, mixing containers, mixingtime, and other items or procedures needed to produce products ofuniform quality with optimum performance characteristics for applicationindicated.PART 3 - EXECUTION3.1 EXAMINATIONA. Examine substrates and conditions, with Installer present, for compliancewith requirements for opening configurations, penetrating items,substrates, and other conditions affecting performance.Page 97 of 190


VESDA FIRE ALARM SYSTEM UPGRADE PROJECT NOVEMBER, 2010NEW YORK AIR ROUTE TRAFFIC CONTROL CENTER (ZNY) (REVISED AUGUST, 2011)RONKONKOMA, NEW YORKB. Proceed with installation only after unsatisfactory conditions have beencorrected.3.2 PREPARATIONA. Surface Cleaning: Clean out openings immediately before installingthrough-penetration firestop systems to comply with writtenrecommendations of firestop system manufacturer and the followingrequirements:1. Remove from surfaces of opening substrates and from penetrating itemsforeign materials that could interfere with adhesion of through-penetrationfirestop systems.2. Clean opening substrates and penetrating items to produce clean, soundsurfaces capable of developing optimum bond with through-penetrationfirestop systems. Remove loose particles remaining from cleaningoperation.3. Remove laitance and form-release agents from concrete.B. Priming: Prime substrates where recommended in writing by throughpenetrationfirestop system manufacturer using that manufacturer'srecommended products and methods. Confine primers to areas of bond;do not allow spillage and migration onto exposed surfaces.C. Masking Tape: Use masking tape to prevent through-penetration firestopsystems from contacting adjoining surfaces that will remain exposed oncompletion of Work and that would otherwise be permanently stained ordamaged by such contact or by cleaning methods used to remove smearsfrom firestop system materials. Remove tape as soon as possible withoutdisturbing firestop system's seal with substrates.3.3 THROUGH-PENETRATION FIRESTOP SYSTEM INSTALLATIONA. General: Install through-penetration firestop systems to comply with"Performance Requirements" Article and firestop system manufacturer'swritten installation instructions and published drawings for products andapplications indicated.B. Install forming/damming/backing materials and other accessories of typesrequired to support fill materials during their application and in theposition needed to produce cross-sectional shapes and depths required toachieve fire ratings indicated.Page 98 of 190


VESDA FIRE ALARM SYSTEM UPGRADE PROJECT NOVEMBER, 2010NEW YORK AIR ROUTE TRAFFIC CONTROL CENTER (ZNY) (REVISED AUGUST, 2011)RONKONKOMA, NEW YORK1. After installing fill materials, remove combustible forming materials andother accessories not indicated as permanent components of firestopsystems.C. Install fill materials for firestop systems by proven techniques to producethe following results:1. Fill voids and cavities formed by openings, forming materials, accessories,and penetrating items as required to achieve fire-resistance ratingsindicated.2. Apply materials so they contact and adhere to substrates formed byopenings and penetrating items.3. For fill materials that will remain exposed after completing Work, finish toproduce smooth, uniform surfaces that are flush with adjoining finishes.3.4 FIELD QUALITY CONTROLA. Inspecting Agency: Owner will engage a qualified independentinspecting agency to inspect through-penetration firestop systems and toprepare test reports.1. Inspecting agency will state in each report whether inspected throughpenetrationfirestop systems comply with or deviate from requirements.B. Proceed with enclosing through-penetration firestop systems with otherconstruction only after inspection reports are issued.C. Where deficiencies are found, repair or replace through-penetrationfirestop systems so they comply with requirements.3.5 IDENTIFICATIONA. Identify through-penetration firestop systems with pressure-sensitive,self-adhesive, preprinted vinyl labels. Attach labels permanently tosurfaces of penetrated construction on both sides of each firestop systeminstallation where labels will be visible to anyone seeking to removepenetrating items or firestop systems. Include the following informationon labels:1. The words: "Warning--Through-Penetration Firestop System--Do NotDisturb. Notify Building Management of Any Damage."2. <strong>Contract</strong>or's name, address, and phone number.3. Through-penetration firestop system designation of applicable testing andinspecting agency.Page 99 of 190


VESDA FIRE ALARM SYSTEM UPGRADE PROJECT NOVEMBER, 2010NEW YORK AIR ROUTE TRAFFIC CONTROL CENTER (ZNY) (REVISED AUGUST, 2011)RONKONKOMA, NEW YORK4. Date of installation.5. Through-penetration firestop system manufacturer's name.6. Installer's name.3.6 CLEANING AND PROTECTIONA. Clean off excess fill materials adjacent to openings as Work progressesby methods and with cleaning materials that are approved in writing bythrough-penetration firestop system manufacturers and that do notdamage materials in which openings occur.B. Provide final protection and maintain conditions during and afterinstallation that ensure through-penetration firestop systems are withoutdamage or deterioration at time of Substantial Completion. If, despitesuch protection, damage or deterioration occurs, cut out and removedamaged or deteriorated through-penetration firestop systemsimmediately and install new materials to produce through-penetrationfirestop systems complying with specified requirements.END OF SECTION 07270Page 100 of 190


VESDA FIRE ALARM SYSTEM UPGRADE PROJECT NOVEMBER, 2010NEW YORK AIR ROUTE TRAFFIC CONTROL CENTER (ZNY) (REVISED AUGUST, 2011)RONKONKOMA, NEW YORKSECTION 13850 – LASER AIR SAMPLING SMOKE DETECTION SYSTEM(This Section Revised August 22, 2011)PART 1 - GENERAL1.1 SCOPEA. This document provides specification details for the Smoke Detectors,and system components for upgrading the existing air sampling pipingsystems, as specified in the contract drawings, that are located at the NewYork Air Route Traffic Control Center in Ronkonkoma, New York.1.2 GENERALA. The existing VESDA smoke detectors and power supplies shall beremoved and disposed off in accordance with all FAA Standards andOrders, and all <strong>Federal</strong>, State, and Local Rules and Regulations.Documentation shall be submitted as per all Governing bodies and FAArequirements.B. The system shall consist of highly sensitive LASER-based SmokeDetectors with aspirators connected to networks of sampling pipes.C. Each of 9 VESDA model VLP-012 smoke detector units shall beprovided with: Display Module, LCD Programmer, Fire and OK LEDS(FOK) and sufficient on board relays, integral to each detector.1.3 APPROVALSA. The Very Early Smoke Detection System must be of a type submitted to,tested, approved, and/or listed by:1. FM (Factory Mutual), US2. UL (Underwriters Laboratories Inc), US3. ULC (Underwriters Laboratories Canada), Canada1.4 CODES, STANDARDS OR REGULATIONSA. The entire installation shall be installed to comply with one or more ofthe following codes or standards:Page 101 of 190


VESDA FIRE ALARM SYSTEM UPGRADE PROJECT NOVEMBER, 2010NEW YORK AIR ROUTE TRAFFIC CONTROL CENTER (ZNY) (REVISED AUGUST, 2011)RONKONKOMA, NEW YORK1. NFPA Standards, US, in particular NFPA 72 – National Fire Alarm andSignaling Code2. NEC Standards, US3. Local codes and standards4. Year 2000 compliancy standards including, LPS2000, GTE PA96014T1.5 SYSTEM DESCRIPTIONA. Design Requirements1. Shall consist of a highly sensitive LASER-based smoke detector, aspirator,and filter.2. The System shall:a. Be modular, with each detector monitored by a Display featuringLEDs and a sounder. The system shall be configured by aProgrammer that is integral to the system.b. Allow programming of:1) Four smoke threshold alarm levels per sector.2) Time delays.3) Faults including airflow, detector, power, filter and network aswell as an indication of the urgency of the fault.4) Sufficient onboard and or remote configurable relay outputsfor remote indication of alarm and fault conditions, with fullinterfacing to the existing Fire Alarm Control Panel3. The <strong>Contract</strong>or shall verify that the existing air sampling pipe network,that transports air to the detection system, is fully adequate and iscompatible with the new smoke detectors. <strong>Contract</strong>or will supportcompatibility by calculations from a computer-based design modelingtool, or a demonstrated equivalent method, and submit for approval.4. Equipment will include a high level interface with the building fire alarmsystem.5. Performance Requirementsa. Shall be tested and approved to cover up to 20,000 sq. ft.b. Shall be approved to provide very early smoke detection and providefour output levels corresponding to Alert, Action, Fire 1 and Faultper pipe (sector). These levels shall be programmable and able to beset at sensitivities ranging from 0.0015–6% obsc/ft. For complianceto UL approval range is 0.0015-4% obsc/ft.c. Shall report any fault on the unit by using configurable fault outputrelays or via VSM.Page 102 of 190


VESDA FIRE ALARM SYSTEM UPGRADE PROJECT NOVEMBER, 2010NEW YORK AIR ROUTE TRAFFIC CONTROL CENTER (ZNY) (REVISED AUGUST, 2011)RONKONKOMA, NEW YORKd. Shall be self monitoring for filter contamination.e. Shall incorporate a flow sensor in each sector pipe and providestaged airflow faults.1.6 SUBMITTALSA. Product data, site drawings, system designs, and or redesigns, shall besubmitted and shall include pipe layout, operational calculations andperformance criteria, and shall be signed by a licensed Professional FireProtection Engineer or certified NICET Level IV Fire Alarm Designer.B. A copy of the manufacturer’s installation, operation and maintenancemanuals shall be supplied upon completion of the installation.C. System commissioning data shall be supplied within 30 days ofcompletion of the installation.1.7 QUALITY ASSURANCEA. Qualifications1. Manufacturera. The manufacturer shall have a minimum of 15 years productionexperience in the manufacturer and design of high sensitivity AirSampling-type smoke detection systems.b. The manufacturer shall be certified as meeting ISO 9002 formanufacturing.2. Technology: Both Light Scattering and Particle Counting shall be utilizedin this device as follows:a. The Laser Detection Chamber shall be of the mass Light Scatteringtype and capable of detecting a wide range of smoke particle types ofvarying size. A particle counting method shall be employed for thepurposes of:1) Preventing large particles from affecting the true smokereading.2) Monitoring contamination of the filter (dust & dirt etc.) toautomatically notify when maintenance is required.Note: The Particle Counting Circuitry shall not be used for thepurpose of smoke density measurement.Page 103 of 190


VESDA FIRE ALARM SYSTEM UPGRADE PROJECT NOVEMBER, 2010NEW YORK AIR ROUTE TRAFFIC CONTROL CENTER (ZNY) (REVISED AUGUST, 2011)RONKONKOMA, NEW YORKb. The Laser Detection Chamber shall incorporate a separate secondaryclean air feed from the filter; providing clean air barriers acrosscritical detector optics to eliminate internal detector contamination.c. The detector shall not use adaptive algorithms to adjust thesensitivity from that set during commissioning. A learning tool shallbe provided to ensure the best selection of appropriate alarmthresholds during the commissioning process.3. Equipment Supplier: The equipment supplier shall be authorized andtrained by the manufacturer to calculate/design, install, test and maintainthe air sampling system and shall be able to produce a certificate statingsuch on request.PART 2 - PRODUCTS2.1 MANUFACTURERA. Air Sampling Smoke Detection System: Acceptable Manufacturer:XtralisPrivate Bag 215495 Blackburn RoadMount Waverley VIC 3149AustraliaTelephone: +61 3 9211 7200Fax: +61 3 9211 7201USTelephone: +1 781 740 2223Fax: +1 781 740 4433Toll Free (in the US) 800 229 4434Website: www.xtralis.com2.2 MANUFACTURED UNIT(S)A. VESDA LaserPLUS Air Sampling smoke detection system - PartNumber VLP-012, with Display Module, LCD Programmer, Fire and OKLEDS (FOK)Page 104 of 190


VESDA FIRE ALARM SYSTEM UPGRADE PROJECT NOVEMBER, 2010NEW YORK AIR ROUTE TRAFFIC CONTROL CENTER (ZNY) (REVISED AUGUST, 2011)RONKONKOMA, NEW YORK2.3 DETECTOR ASSEMBLYA. The Detector, Filter, Aspirator and Relay Outputs shall be housed in amounting box and shall be arranged in such a way that air is drawn fromthe fire risk and a sample passed through the Dual Stage Filter andDetector by the Aspirator.B. The Detector shall be LASER-based type and shall have an obscurationsensitivity range of 0.0015%/ft – 6% obsc/ft.C. The Detector shall have four independent field programmable smokealarm thresholds across its sensitivity range with adjustable time delaysfor each threshold between 0-60 seconds.D. The Detector shall also incorporate facilities to transmit the followingfaults• Detector• Air flow• Filter• System• Zone• Network• Power• Urgent and Minor faults. Minor faults shall be considered asservicing or maintenance signals. Urgent faults indicate the unit maynot be able to detect smoke.E. The detector shall have four in-line sample pipe inlets and must containa flow sensor for each pipe inlet. Both Minor and Urgent flow faultscan be reported.F. The filter must be a two-stage disposable filter cartridge. The first stageshall be capable of filtering particles in excess of 20 microns from theair sample. The second stage shall be ultra- fine, removing more than99% of contaminant particles of 0.3microns or larger, to provide a cleanair barrier around the detector’s optics to prevent contamination andincrease service life.G. The aspirator shall be a purpose-designed rotary vane air pump. It shallbe capable of allowing for multiple sampling pipe runs up to 600 ft. intotal, (4 pipe runs per detector) with a transport time of less than 120seconds or as appropriate codes dictate.H. The Assembly must contain relays for alarm and fault conditions. Therelays shall be software programmable to the required functions. Therelays must be rated at 2 AMP at 30 VDC. Remote relays shall beoffered as an option and either configured to replicate those on thedetector or programmed differently.Page 105 of 190


VESDA FIRE ALARM SYSTEM UPGRADE PROJECT NOVEMBER, 2010NEW YORK AIR ROUTE TRAFFIC CONTROL CENTER (ZNY) (REVISED AUGUST, 2011)RONKONKOMA, NEW YORKI. The Assembly shall be able to be surface mounted to a wall or recessedin the wall cavity (the unit may be inverted in either option).J. The assembly shall have built-in event and smoke logging. It shall storesmoke levels, alarm conditions, operator actions and faults. The dateand time of each event shall be recorded. Each detector (zone) shall becapable of storing up to 18,000 events and does not require the presenceof a display in order to do so.2.4 DISPLAYSA. Each Detector will contain an integral Display Module.B. Each Display shall provide the following features at a minimum:• A 20 segment bargraph display.• Four independent high intensity alarm indicators, Alert, Action,Fire 1 and Fault, corresponding to the four alarm thresholds of thedetector.• Alarm threshold indicators for Alert, Action and Fire 1.• Detector fault and airflow fault indicators.• Faults originating in the particular VLP zone (Zone Fault) shall bedistinguished from those produced by the overall smoke detectionsystem and from those resulting from network wiring errors(Network Fault). LED indicators shall be provided for each faultcategory.• Minor and urgent fault LED indicators.• Four buttons supporting the following features:a) Mode/Test - Scrolls through the information on the Display’sdigital display: Sensitivity (Fire 1 Threshold setting), currentsmoke level and VLP Zone number. When pressed and heldinitiates a lamp test on the individual display module.b) Silence - Silences all devices on the systemc) Reset - Unlatches all latched alarm conditions on the assignedVLP zone.d) Isolate - Isolates the individual VLP zone (inhibits Alarm andFault relays and initiates Isolate relay).Page 106 of 190


VESDA FIRE ALARM SYSTEM UPGRADE PROJECT NOVEMBER, 2010NEW YORK AIR ROUTE TRAFFIC CONTROL CENTER (ZNY) (REVISED AUGUST, 2011)RONKONKOMA, NEW YORK2.5 PROGRAMMERSA. A Programmer Module will be located integrally within the detector.Alternatively, programming may be performed using a Windows ®application running on a PC connected through a High LevelInterfacing unit (PC-Link HLI).B. Each Programmer shall support the following features at a minimum:1. Programming of any device on the system.2. Viewing of the status of any device in the system.3. Adjustment of the alarm thresholds of a nominated detector.4. Setting of Day/night, weekend and holiday sensitivity thresholdsettings.5. Initiation of AutoLearn, to automatically configure the detector’salarm threshold settings to suit the current environment.6. Multi-level password control.7. Programmable latching or non-latching relay operation.8. Programmable energized or de-energized relays.9. Programmable high and low flow settings for airflow supervision.10. Programmable aspirator speed control.11. Programmable maintenance intervals.12. Facilities for referencing with time dilution compensation.13. Testing of relays assigned to a specific zone to aid commissioning.2.6 DEVICE NETWORKING REQUIREMENTSA. The devices in the smoke detection system shall be capable of communicatingwith each other via twisted pair RS485 cable. The network shall be able tosupport up to 250 devices (detectors, displays and programmers), of which atleast 100 detectors can be supported.B. The network shall be capable of being configured in a fault tolerant loop for bothshort circuit and open circuit. Any communication faults shall be reportedunambiguously and shall be clearly attributable to an individual device or wirelink in the fault messages.C. PC based configuration tools shall be available to configure and managethe network of detectors.Page 107 of 190


VESDA FIRE ALARM SYSTEM UPGRADE PROJECT NOVEMBER, 2010NEW YORK AIR ROUTE TRAFFIC CONTROL CENTER (ZNY) (REVISED AUGUST, 2011)RONKONKOMA, NEW YORK2.7 DIGITAL COMMUNICATION PORTADigital communication port shall comply with EIA RS485 Protocol.2.8 APPLICATIONA. Detection Alarm Levels: Output to the main building fire Alarm ControlPanel (FACP) shall be provided through 4 addressable monitor points perVESDA Model VLP-012 Smoke Detector Unit. Monitor the followingoutputs from each VLP-012 unit with addressable monitor modules, asfollows:1. Fire 1 (Alarm) – Relay 6 – Alarm condition to Fire Alarm Control Panel.2. Action - Relay 5 – Supervisory condition to Fire Alarm Control Panel.3. Alert – Relay 4 – Supervisory condition to Fire Alarm Control Panel.4. Fault (Trouble) – Relays 2 and 3 – These two relays may be monitored bythe same addressable module – Trouble condition to the Fire AlarmControl Panel.B. Off-normal conditions should latch at the VLP-012 panel to prevent thecondition from being transmitted repeatedly to the Fire Alarm ControlPanel.C. Alarm thresholds for the Alert, Action, and Fire conditions shall be set asfollows:1. Alert - 0.02% obs/ft – Supervisory condition to Fire Alarm Control Panel.2. Action - 0.03% obs/ft - Supervisory condition to Fire Alarm ControlPanel.3. Fire - 1.0% Obs/ft minimumobscuration – Alarm to Fire Alarm ControlPanel.NOTE:In those protected areas where spot detectors are also installed under theraised floor, the VESDA VLP-012 Smoke Detector Fire Alarm Threshold,shall be set to the same obscuration level as the spot detectors.The setting for Fire 1 shall always appear as 100% on the bar graph scale.D. Each Sector shall have its alarm thresholds set by a Sector Factor. TheSector Factor range shall be between 0.5 and 2.0 (where 2.0 doubles thenormal alarm threshold settings).Page 108 of 190


VESDA FIRE ALARM SYSTEM UPGRADE PROJECT NOVEMBER, 2010NEW YORK AIR ROUTE TRAFFIC CONTROL CENTER (ZNY) (REVISED AUGUST, 2011)RONKONKOMA, NEW YORKE. Initial (factory default) Delay settings:1. Scan Delay: 10 seconds2. Fault Alarm: 5 secondsF. Fault Alarms1. The Detector Fault relay shall be connected to the appropriate alarm zoneon the Fire Alarm Control Panel in such a way that a Detector Fault wouldregister a fault condition on the FACP. The Minor Fault and Isolate relaysshall also be connected to the appropriate control system.G. Power Supply and Batteries1. The system shall be powered from a regulated supply of nominally 24VDC. The battery charger and battery shall comply with the relevantCodes, Standards and Regulations. 24 hours standby battery back up isrequired followed by 30 minutes in an alarm condition.2. Local Power Supply Standards that may apply:a. UL 1481 Listed (provided the power supply and standby batterieshave been appropriately sized/rated to accommodate the system’spower requirements).b. US Telecommunication Central Office Power Supply: The systemshall operate on negative 48 VDC (provided continuously from thetelephone central office power source) converted to 24VDC.2.9 EXISTING AIR SAMPLING PIPEA. The <strong>Contract</strong>or shall verify that the existing air sampling pipe network,that transports air to the detection system, is fully adequate and iscompatible with the new smoke detectors. <strong>Contract</strong>or will supportcompatibility by calculations from a computer-based design modeling tool,or a demonstrated equivalent method, and submit for approval.PART 3 - INSTALLATION3.1 QUALIFICATIONSPage 109 of 190


VESDA FIRE ALARM SYSTEM UPGRADE PROJECT NOVEMBER, 2010NEW YORK AIR ROUTE TRAFFIC CONTROL CENTER (ZNY) (REVISED AUGUST, 2011)RONKONKOMA, NEW YORKA. Installer Qualifications: Engage a factory-authorized Installer to performwork of this Section. Installer shall have a minimum of 5 years experiencein design, installation, and testing of fire detection and alarm systems.Submit resume listing installer’s qualifications including manufacturer’scertification as an approved system installer and a list of recentlycompleted projects demonstrating 5 years of system installation experienceand provide proof of available telephone communications on a 24 hour,seven day a week basis. Be able to provide replacement parts on anemergency basis, and have experienced service personnel available foremergency service.B. Start-up personnel qualifications: Submit resume listing start-up personnelqualifications including manufacturer’s certification as an approvedsystem technician and a list of recently completed projects demonstrating 5years of system start-up experience.3.2 THE DETECTION SYSTEMA. The <strong>Contract</strong>or shall install the system in accordance with themanufacturer's System Design Manual.3.3 EXISTING AIR SAMPLING PIPE NETWORKA. <strong>Contract</strong>or shall verify that there will be full and complete compatibilitybetween the new VESDA Laser Scanner Smoke Detectors and theexisting Air Sampling Piping Network. <strong>Contract</strong>or will verify that thereis no existing condition that would prevent the new equipment, andinstallation, from meeting, or exceeding Manufacturer’s recommendedcriteria and the Project’s objectives. <strong>Contract</strong>or shall submit verification,in writing to the COTR for approval, at the time of equipment submittals.3.4 COMMISSIONING TESTSA. The Fire Alarm System, VESDA System, and all pertinent hardware andsoftware, shall be tested in accordance with all requirements of NFPA 72– National Fire Alarm and Signaling Code.B. The <strong>Contract</strong>or shall allow for the manufacturer’s representative to attendcommissioning of the entire installation in the presence of the ownerand/or its representative.Page 110 of 190


VESDA FIRE ALARM SYSTEM UPGRADE PROJECT NOVEMBER, 2010NEW YORK AIR ROUTE TRAFFIC CONTROL CENTER (ZNY) (REVISED AUGUST, 2011)RONKONKOMA, NEW YORKC. All necessary instrumentation, equipment, materials and labor shall beprovided by the <strong>Contract</strong>or.D. The <strong>Contract</strong>or shall record all tests and system calibrations and a copyof these results shall be retained on site in the System Log Book.3.5 SYSTEM CHECKSA. Visually check all pipes to ensure that all joints, fittings, bends, samplingpoints, etc., comply with the Specification.B. Check the system to ensure the following features are operational andprogrammed in accordance with the specification.1. Alarm threshold levels (for both day and night settings),2. Pipes in use,3. Detector address,4. Display address,5. Clock and date,6. Time delays,7. Air flow fault thresholds,8. Display buttons operable (Mode, Silence, Reset, Isolate),9. Referencing10. Units set to U.S./S.I.C. Check to ensure that all ancillary warning devices operate as specified.D. Check interconnection with Fire Alarm Control Panel to ensure correctoperation.3.6 TESTSA. The Fire Alarm System, VESDA System, and all pertinent hardware andsoftware, shall be tested in accordance with all requirements of NFPA 72– National Fire Alarm and Signaling Code.B. Introduce Smoke into the Detector Assembly to provide a basicfunctional test.C. Introduce smoke to the least favorable Sampling Point in each SamplingPipe. Transport time is not to exceed the local codes.D. If more than two bar graph divisions illuminate under normal conditions(no smoke test), review event log for two (2) weeks from date ofPage 111 of 190


VESDA FIRE ALARM SYSTEM UPGRADE PROJECT NOVEMBER, 2010NEW YORK AIR ROUTE TRAFFIC CONTROL CENTER (ZNY) (REVISED AUGUST, 2011)RONKONKOMA, NEW YORKcommissioning and make appropriate adjustments to the alarm and delaythresholds.E. Activate the appropriate Fire Alarm zones and advise all concerned thatthe system is fully operational. Fill out the log book and commissioningreport accordingly.F. At 4, 8, and 12, months after acceptance of system, <strong>Contract</strong>or shallreturn to the Facility and reverify all system checks, that are enumeratedin the specification. <strong>Contract</strong>or will then document the results, in writing,to the Facility. If any parameters are out of range, or if the Facility deemsit necessary, the <strong>Contract</strong>or will reprogram the system as needed, orrequired, at no additional cost to the FAA.3.7 SPARE PARTSA. Provide sufficient renewable spare parts, including all filters, to allow for 2 yearsnormal maintenance.B. <strong>Contract</strong>or shall furnish to the FAA the name, address, and telephone number ofthe nearest supplier of parts and filters.3.8 WARRANTYA .Include a service and parts guarantee of the system for a minimum period of oneyear and provide any services and equipment incidental to the properperformance of the system under warranty at no additional cost to theGovernment.End of SectionPage 112 of 190


VESDA FIRE ALARM SYSTEM UPGRADE PROJECT NOVEMBER, 2010NEW YORK AIR ROUTE TRAFFIC CONTROL CENTER (ZNY) (REVISED AUGUST, 2011)RONKONKOMA, NEW YORKSECTION 13851 – FIRE ALARM AND DETECTION SYSTEMS(This Section Added August 22, 2011)PART 1 - GENERAL1.1 SUMMARYA. This specification section provides the requirements for interfacing theexisting VESDA Smoke Detection system to the existing analogaddressable fire alarm system. Completion of the work will not changethe system operation, except to integrate the new circuits and devices intothe existing system. All new equipment shall be installed andprogrammed to operate in accordance with Section 1.5. The Fire Alarmsystem shall be designed, installed, and tested in accordance with NFPA72, International Building Code, and this specification.B. Work includes the following:1. (SEE Specification Section 13850 - LASER AIR SAMPLING SMOKEDETECTION SYSTEM AND DIVISION 1 – GENERALREQUIREMENTS, SUMMARY OF WORK, PARAGRAPH 1-1.1.1 –SCOPE OF WORK.)C. It is not the intent of this project to modify any of the existing equipmentor programming except as needed to complete this project. If anyexisting condition is different than as indicated in these specificationsbring the matter to the attention of the COTR for resolution.D. Related Sections1. Section 07270 - FIRESTOPPING2. Section 13850 – LASER AIR SAMPLING SMOKE DETECTIONSYSTEM1.2 AIR TRAFFIC CONTROL EQUIPMENT RESTRICTIONSA. Job conditions: Do not permit interference with the air traffic controlfunction at the Center. Schedule and plan work to permit normal facilityoperations to continue with a minimum of disruption. Access to thefacility shall be kept unobstructed at all times. If interference with thePage 113 of 190


VESDA FIRE ALARM SYSTEM UPGRADE PROJECT NOVEMBER, 2010NEW YORK AIR ROUTE TRAFFIC CONTROL CENTER (ZNY) (REVISED AUGUST, 2011)RONKONKOMA, NEW YORKexisting facility operations seems to be unavoidable, advise the COTR 10days prior to such interference. Proceed as directed by the COTR.B. Equipment Shutdown: Each ARTCC maintains air traffic controlcontinuously without shutdown. Various techniques are employed toachieve maximum system availability. Mechanical and electrical systemsin direct support of air traffic operation and environmental systems haveredundant configurations. Shutdown of equipment shall be scheduledwith the COTR at least 10 days prior to the contractor's need. Thereliability of mechanical and electrical systems is compromised whenredundant equipment is not available. Every effort willbe made by the Government to allow work to be accomplished during the<strong>Contract</strong>or's normal working hours; however, the COTR may require that certainequipment be shut down during off normal hours and be restored to serviceimmediately after this period. Government personnel shall accomplishshutdown of equipment.C. Interruptions of the existing addressable fire alarm system shall berequested in writing to the COTR at least five (5) days prior to the<strong>Contract</strong>or’s needs. The fire alarm systems, or portions thereof, shallonly be taken out of service during off-normal hours, for intervals of nomore than four (4) hours out of every eight (8) hours. The COTR shallbe contacted if these criteria cannot be met, so that alternate protectioncan be provided.1.3 REFERENCE STANDARDSA. The current issues of the following documents, in effect on the date ofthe invitation for bid, form a part of this specification and are applicableto the extent specified herein. NFPA Appendices shall be consideredmandatory for the purposes of this specification. In referenced NFPApublications, the advisory provisions shall be mandatory, as though theword "shall" had been substituted for "should" wherever it appears.B. International Code Council1. International Building Code.C. Americans with Disabilities Act (ADA)1. Accessibility Guidelines for Buildings and Facilities.Page 114 of 190


VESDA FIRE ALARM SYSTEM UPGRADE PROJECT NOVEMBER, 2010NEW YORK AIR ROUTE TRAFFIC CONTROL CENTER (ZNY) (REVISED AUGUST, 2011)RONKONKOMA, NEW YORKD. Factory Mutual (FM)1. Factory Mutual Approval Guide.E. National Fire Protection Association (NFPA)1. 70: National Electrical Code.2. 72: National Fire Alarm Code.3. 101: Safety to Life from Fire in Buildings and Structures.F. Occupational Safety and Health <strong>Administration</strong> (OSHA)1. 1910.7 Nationally Recognized Testing Laboratories (NRTL).G. Underwriters Laboratories (UL)1. 864: Control Units for Fire Protective Signaling Systems.2. 1481: Power Supplies for Fire Protective Signaling Systems.H. Electronic Industries Association (EIA)1. TIA-422: Electrical Characteristics of Balanced Voltage Digital InterfaceCircuits.1.4 CONFLICTING REQUIREMENTSA. In the case of a conflict within this specification, applicable codes, andother supplemental specifications, the <strong>Contract</strong>or shall submit the matterin writing to the <strong>Contract</strong>ing Officer’s Technical Representative (COTR)who will provide written clarification. Alert the COTR to anydiscrepancies found.1.5 EXISTING SYSTEM DESCRIPTIONA. General: A system with addressable detectors, addressable manual pullstations, addressable interface devices, and addressable control devices.Operation of manual pull stations, smoke detectors, air sampling smokedetection system alarm, or sprinkler system water flow will activatealarms. Duct smoke detectors are configured as supervisory.Page 115 of 190


VESDA FIRE ALARM SYSTEM UPGRADE PROJECT NOVEMBER, 2010NEW YORK AIR ROUTE TRAFFIC CONTROL CENTER (ZNY) (REVISED AUGUST, 2011)RONKONKOMA, NEW YORK1. The system is a complete and fully operational fire detection and alarmsystem.2. System includes but is not limited to the Fire Alarm Control Panel (FACP)interface boards, FACP power supplies, FACP batteries, area smokedetectors, duct smoke detectors, manual pull stations, addressableinterface and control devices, air sampling smoke detection system,sprinkler system supervision, audible and visual alarms, wiring, conduits,signs, and appurtenances.3. The system is configured with both Stage I and Stage II alarm notificationappliances. Stage I notification alarm appliances consist of ceilingmounted red strobes in the DSR Control Room. Stage II clear strobes andchimes are installed in the DSR Control Room. The Stage II audible NACis automatically silenced after 60 seconds and can be silenced at any timemanually.4. Alarm verification is enabled for analog smoke detectors connected to theFACP.5. The existing Fire Alarm Control Panel serves other areas of this building.The fire alarm system must remain in service during all phases ofconstruction.B. Major components:1. Smoke detectors;2. Duct smoke detectors;3. Manual fire alarm (pull) stations;4. Addressable interface devices;5. Addressable control devices;6. Interconnecting wiring;7. Conduit; and accessories.C. Circuit supervision:1. Class A style 6 wiring for signaling line circuits;2. Class B style B initiating device circuits where the addressable interfacedevice is located within three feet and in the same room as the equipmentbeing monitored, otherwise Class A style D; and3. Class A style Z wiring for notification appliance circuits per NFPA 72.D. System alarm detection: When a confirmed fire condition is detected byone or more fire alarm initiating device (pull station, smoke detector, airsampling system alarm or sprinkler water flow) in any part of the facility,including the Control Room, the following occurs immediately:Page 116 of 190


VESDA FIRE ALARM SYSTEM UPGRADE PROJECT NOVEMBER, 2010NEW YORK AIR ROUTE TRAFFIC CONTROL CENTER (ZNY) (REVISED AUGUST, 2011)RONKONKOMA, NEW YORK1. System alarm LED lights on the FACP.2. Sounding of the local alarm-sounding device in the FACP.3. Activation of the audible and visual alarm appliances in the ARTCC(except in the Control Room) and the Power Service Building for generalevacuation. (Duct smoke detector does not activate the general evacuationsignal.)4. Activation of the Stage I visual alarm appliances in the Control Room.(Duct smoke detector does not activate the Stage I visual alarmappliances.)5. Transmit a fire alarm signal to a UL Listed Central Station.6. FACP, remote annunciators and the front-end personal computer indicatesthe pertinent information associated with the alarm on the Liquid CrystalDisplay (LCD).7. Record is made of the status change in system memory.E. Control Room Stage II alarm activation: When any First Floor ControlWing alarm initiating device is activated subsequent to the activation ofthe system alarm or a First Floor Control Wing manual pull station isactivated independently, the following occurs immediately:1. System alarm LED lights on the FACP.2. Sounding of the local alarm-sounding device in the FACP.3. Activation of the Stage II audible (the chime shall automatically silenceafter 60 seconds) and visual alarm appliances in the Control Room.Audible and visual alarm appliances in the remainder of the ARTCC andthe Power Service Building remain activated.4. De-activation of the Stage I visual alarm appliances in the Control Room.5. Fire alarm signal is transmitted to a UL Listed Central Station.6. FACP, remote annunciators and the front-end personal computer indicatesthe pertinent information associated with the alarm on the Liquid CrystalDisplay (LCD).7. Record is made of the status change in system memory.F. System trouble detection: When a trouble condition is indicated by amalfunction of an initiating device circuit, signaling line circuit, ornotification appliance circuit, the following functions occur immediately:1. System trouble LED lights on the FACP.2. Sounding of the local trouble-sounding device in the FACP.3. Trouble alarm signal is transmitted to a UL Listed Central Station.4. FACP, remote anunciators and the front-end personal computer indicatesthe pertinent information associated with the alarm on the LCD.Page 117 of 190


VESDA FIRE ALARM SYSTEM UPGRADE PROJECT NOVEMBER, 2010NEW YORK AIR ROUTE TRAFFIC CONTROL CENTER (ZNY) (REVISED AUGUST, 2011)RONKONKOMA, NEW YORK5. Record is made of the status change in system memory.G. Supervisory Signals: When an off normal condition is indicated by awater valve tamper switch, sprinkler panel trouble, air sampling smokedetector trouble signal, activation of a duct smoke detector, air samplingsystem pre-alarm, analog addressable smoke detector alarm verificationpre-alarm signal, or other off normal condition, the following functionsoccur immediately:1. System supervisory LED lights on the FACP.2. Sounding of the local supervisory sounding device in the FACP.3. Supervisory alarm signal is transmitted to a UL Listed Central Station.4. FACP, remote annunciators and the front-end personal computer indicatesthe pertinent information associated with the alarm on the LCD.5. Record is made of the status change in system memory.H. Firecycle III System Monitoring: The fire alarm system monitors thefollowing signals from each Viking Firecycle III system:1. Alarm signal (from ZRM terminals 13 and 15)2. Trouble signal (from TB 3)3. Supervisory Low Air signal (from ZRM terminals 4 and 6)4. Main Control Valve Tamper Supervisory signal (directly from tamperswitch)5. Test Control Valve Tamper Supervisory signal (directly from tamperswitch)6. Alarm Pressure Switch alarm signal (directly from pressure switch)1.6 NEW CIRCUITS AND DEVICESA. Comply with NFPA 72 to maintain circuit classifications.B. Add new devices to existing signaling line circuits. When adding newdevices, the existing circuit shall be interrupted between two existingdevices. The circuit shall be re-routed from one existing device to eachsuccessive new device, and then to the other (next) existing device. Allsignaling line circuit routing shall meet NFPA requirements for a Class Acircuit.Page 118 of 190


VESDA FIRE ALARM SYSTEM UPGRADE PROJECT NOVEMBER, 2010NEW YORK AIR ROUTE TRAFFIC CONTROL CENTER (ZNY) (REVISED AUGUST, 2011)RONKONKOMA, NEW YORK1.7 SUBMITTALSA. Product Data: Submit product data for each type of system componentspecified including dimensioned plans and elevations showing minimumclearances and installed features and devices. Include list of materialsand Nationally Recognized Testing Laboratory (NRTL)-listing data.Product data shall also include, but not be limited to, manufacturerscatalog cuts, wiring requirements, technical data, and warranty data foreach component or device used in theB. system. Manufacturers literature and technical data shall indicate thetype, size, rating, style, catalog number, product names, photos, andcatalog data for the following, if multiple devices are contained in asingle product data sheet, the submittal shall be annotated to clearlyindicate which products are being proposed:1. Addressable interface devices;2. System components to be placed within existing FACP;3. Conduit, wire and cable; and4. Signs and labels.C. Calculations: Provide calculations required to verify compliance withNFPA 72 and this Specification Section for all new and affected existingcircuits:1. Conduit fill calculationsD. Shop Drawings: Drawings shall be signed and sealed by a licensedProfessional Fire Protection Engineer or certified NICET Level IV FireAlarm Designer. Drawings shall indicate locations, installation detailsand sequence of operation of devices and equipment associated with thesystem and existing circuits. Floor plans showing equipment locations,conduit sizes and runs, wire counts and sizes, and other details shall beprovided. All drawings shall clearly indicate new work versus existingconditions. Wiring diagrams shall include diagrams for equipment andfor the system with terminals and interconnections identified. Makediagrams specific to this Project and distinguish between field andfactory wiring. Clearly identify interface requirements between the firealarm system and Section 13850, “Laser Air Sampling Smoke DetectionSystem.”Page 119 of 190


VESDA FIRE ALARM SYSTEM UPGRADE PROJECT NOVEMBER, 2010NEW YORK AIR ROUTE TRAFFIC CONTROL CENTER (ZNY) (REVISED AUGUST, 2011)RONKONKOMA, NEW YORKE. Installer Qualifications: Submit resume listing installer’s qualificationsincluding manufacturer’s certification as an approved system installerand a list of recently completed projects demonstrating 5 years of systeminstallation experience.F. Startup Personnel Qualifications: Submit resume listing startuppersonnel qualifications including manufacturer’s certification as anapproved system technician and a list of recently completed projectsdemonstrating 5 years of system startup experience.G. As-Built Drawings: Upon completion of system update existing as-builtdrawings showing actual installation conditions. If adequate existing asbuiltdrawings do not exist, notify COTR. Show locations andidentification addresses of addressable interface devices, flow switchesand tamper switches installed or wired as part of this work. Also showconduit routing details, including new conduit to existing FACP.H. Test Plan: A test plan that describes the methods to be used for systemtesting shall be submitted. Include a step-by-step description of the tests,and indicate type and location of test apparatus to be employed.Demonstrate that the operation and installation requirements specifiedhave been met. Test all new devices installed according to NFPA 72requirements. Additionally, there are existing initiating devices andnotification appliances connected to theI. FACP, which serve other areas of the facility. Test at least 10% ofexisting initiating devices and all existing notification devices. ExistingFACP contains approximately 800 addressable devices and 80notification appliances.J. Record of Field Tests of System: Submit a record of field tests fordevices tested. Record shall include device location, type, address, andother relevant data as well as date of test and signature of startuppersonnel performing tests.K. Inspection documents are specified in Part 3 of this Section.1.8 QUALITY ASSURANCEA. Installer Qualifications: Engage a factory-authorized Installer to performwork of this Section. Installer shall have a minimum of 5 yearsexperience in design, installation, and testing of fire detection and alarmPage 120 of 190


VESDA FIRE ALARM SYSTEM UPGRADE PROJECT NOVEMBER, 2010NEW YORK AIR ROUTE TRAFFIC CONTROL CENTER (ZNY) (REVISED AUGUST, 2011)RONKONKOMA, NEW YORKsystems. Submit a list of systems of similar nature and scope,successfully completed within the last two years and provide proof ofavailable telephone communications on a 24 hour, seven day a weekbasis. Be able to provide replacement parts on an emergency basis, andhave experienced service personnel available for emergency service.B. Single-Source Responsibility: Obtain fire alarm components from asingle source that assumes responsibility for compatibility of systemcomponents.C. Comply with NFPA 70 and 72.D. Listing and Labeling: Provide fire alarm systems and componentsspecified in this Section that are listed and labeled and maintain theoverall listing for the entire fire detection and alarm system.1. The Terms "Listed" and "Labeled": As defined in the National ElectricalCode, Article 100.2. Listing and Labeling Agency Qualifications: A "Nationally RecognizedTesting Laboratory" (NRTL) as defined in OSHA Regulation 1910.7.1.9 DELIVERY, STORAGE, AND HANDLINGA. Store equipment and materials inside and protected from weather.1.10 SEQUENCING AND SCHEDULINGA. Existing Addressable Fire Alarm Equipment: The existing addressablefire alarm system protects other areas of the ARTCC. Existing circuitsare routed through the work areas; all existing circuits shall bemaintained unless noted otherwise. The FACP shall remain operationalat all times.B. Equipment Installation: After installation of new equipment, label alldevices “Not in Service” until tested and accepted by the COTR.Page 121 of 190


VESDA FIRE ALARM SYSTEM UPGRADE PROJECT NOVEMBER, 2010NEW YORK AIR ROUTE TRAFFIC CONTROL CENTER (ZNY) (REVISED AUGUST, 2011)RONKONKOMA, NEW YORKPART 2 - PRODUCTS2.1 GENERALA. Provide new system components designed and fabricated by onemanufacturer with the following characteristics:1. Equipment and materials: Design and fabricate in accordance with thelatest edition of NFPA 13, 70, 72, and 101.2. Provide standard products of the manufacturer's latest design that aresuitable to perform the functions intended. The name of the manufacturerand the serial number shall appear on major components. Equipment,material, devices, and accessories shall be NRTL listed and labeled fortheir intended use.3. Manufacturers of NRTL listed or approved addressable fire detectionsystems shall have an established record of working installations and shallbe capable of providing documentation showing experience withaddressable systems.4. Compatible with existing site FACP maintaining NRTL listing or approval(such as UL 864) of the overall system.2.2 MANUFACTURERSA. Acceptable manufacturers: Manufacturers of equipment compatible withthe existing addressable fire alarm system. Initiating devices, controldevices, and interface devices provided under this contract shall be of themanufacturer's latest design and match existing facility equipment.1. Existing fire alarm equipment: Simplex2.3 ADDRESSABLE DEVICESA. General: Provide the following new detection and alarm circuit devicesas needed, designed to interface with existing FACP for central alarmcapability, and suitable for use in a Class A electrically supervised 24VDC circuit.B. Addressable interface device: To monitor and supervise a device, andprovide an input signal with a unique address to the existing FACPidentifying the status of the device. Distinguish the following inputsignal conditions: normal (open contact), short circuit (closed contact),and open circuit (field wire break). Provide one addressable interfacePage 122 of 190


VESDA FIRE ALARM SYSTEM UPGRADE PROJECT NOVEMBER, 2010NEW YORK AIR ROUTE TRAFFIC CONTROL CENTER (ZNY) (REVISED AUGUST, 2011)RONKONKOMA, NEW YORKdevice for each function to be monitored. Each monitored device shallhave a unique address in the FACP software.2.4 FIRE ALARM CONTROL PANELA. FACP Components: Provide as needed to meet requirements of thisspecification. Maintain UL 864 listing of entire FACP.1. Interface Boards: Provide additional interface boards, chassis, powersupplies and appurtenances necessary to meet requirements of thisspecification and to provide a fully functional fire alarm system.2.5 CABLE AND WIRINGA. Bell wire, intercom, or telephone wire is not acceptable. Comply withNEC Article 760 requirements and manufacturer’s recommendations.B. For initiating device circuits, provide type FPL cable with red PVC jacketand 18 to 12 AWG, solid, twisted conductors. Match existing wiring.C. For signaling line circuits, provide type FPL cable with red PVC jacket,aluminum-polyester shield and 18 to 12 AWG, solid, twisted conductors.Match existing wiring.2.6 FUNCTIONAL DESCRIPTION OF SYSTEMA. Software: Existing to remain.B. System Functions and Operating Features: Existing to remain asdescribed below:1. Priority of Signals: Accomplish automatic response functions by the firstalarm initiated. The highest priority is an alarm signal. Supervisory andtrouble signals have second- and third-level priority respectively. Higherprioritysignals take precedence over signals of lower priority, even thoughthe lower-priority condition occurred first. Annunciate alarm signalsregardless of priority or order received.2. Non-Interfering: Circuit wiring shall be configured for non-interferingoperation. A signal on one circuit shall not prevent the receipt of signalsPage 123 of 190


VESDA FIRE ALARM SYSTEM UPGRADE PROJECT NOVEMBER, 2010NEW YORK AIR ROUTE TRAFFIC CONTROL CENTER (ZNY) (REVISED AUGUST, 2011)RONKONKOMA, NEW YORKfrom any other circuit. Circuits shall be manually resettable from the FACPafter the initiating device or devices are restored to normal.3. Silencing at the FACP: Switches provide capability for acknowledgment ofalarm, supervisory, trouble, and other specified signals at the FACP, andcapability to silence the local audible signal and light a light-emitting diode(LED). Subsequent alarms cause the audible signal to sound again untilsilenced by switch operation. Restoring alarm, supervisory, and troubleconditions to normal extinguishes the associated LED and causes the audiblesignal to sound again until restoration is acknowledged by switch operation.4. Loss of Primary Power Sounds a Trouble Signal at the FACP: The FACPindicates when the fire alarm system is operating on an alternate powersupply.5. FACP Alphanumeric Display: Displays plain-English-language descriptionsand addresses of initiating devices, alarms, trouble signals, supervisorysignals, monitoring actions, system and component status, and systemcommands.6. Remote Detector Sensitivity Adjustment: Manipulation of controls at theFACP allows the selection of specific addressable smoke detectors foradjustment, display of their current status and sensitivity settings, andcontrol of changes in those settings. The same controls can be used toprogram repetitive, scheduled, automated changes in sensitivity of specificdetectors. Sensitivity adjustments and sensitivity adjustment schedulechanges are recorded by the system printer.7. Independent System Monitoring: Supervise each Automatic On/OffSprinkler system for both normal operation and trouble.8. Circuit Supervision: Indicate circuit faults by a trouble signal at the FACP.Provide a distinctive indicating audible tone and LED-indicating light. Themaximum permissible elapsed time between the occurrence of the troublecondition and its indication at the FACP is 200 seconds.9. See specification Section 13850 – Laser Air Sampling Smoke DetectionSystem for new and additional System Functions and Operating Features.TOPART 3 - EXECUTION3.1 INSTALLATION, GENERALA. Install system according to NFPA standards referenced in Parts 1 and 2of this Section and manufacturer’s recommendations.B. New system devices and appliances shall be wired to the FACP.Connection to the FACP shall provide the sequence of operation requiredby this specification. The addressable fire detection and alarm system inPage 124 of 190


VESDA FIRE ALARM SYSTEM UPGRADE PROJECT NOVEMBER, 2010NEW YORK AIR ROUTE TRAFFIC CONTROL CENTER (ZNY) (REVISED AUGUST, 2011)RONKONKOMA, NEW YORKthe existing building shall remain in service at all times duringconstruction.C. Circuit conductors entering or leaving the FACP shall be connected toscrew type terminals with each terminal marked for identification.D. When adding devices to an existing signaling line circuit, the existingcircuit shall be interrupted between two existing devices. The circuitshall be re-routed from one existing device, to each successive newdevice, and then to the other (next) existing device. All signaling linecircuit routing shall meet the NFPA requirements for a “Class A” circuit.3.2 EQUIPMENT INSTALLATIONA. Install all equipment as per Manufacturer’s recommendations and allpertinent Codes and FAA Regulations.3.3 WIRING INSTALLATIONA. Wiring Method: Conceal raceway except in unfinished spaces and asindicated. Do not splice wire except where required to connect to adevice. Where lengths of wire must be joined together to complete along run, join them at a terminal strip mounted in a hinged or screw coverjunction box. Do not transpose or change colors.1. Install cable and wire in appropriately sized raceway, but not less than 3/4inch diameter.2. Install cable of the type indicated for the use, and install in accordancewith NEC Article 760.3. Leave eight-inch wire tails at each device box.4. Loop the cable for initiating device circuits from the addressable interfacedevice to the initiating device, then back to addressable interface device.5. Loop the cable for signaling line circuits from the FACP to the firstaddressable initiating device, then on to each successive addressabledevice, and then back to the FACP. Connect to earth ground only at theFACP. Do not route intelligent detector wiring adjacent to, or in the sameconduit with 120/240 VAC power wiring or other high current circuits.6. Provide a minimum of two inches of separation between cable and openconductors, light, power, or class one circuits. Do not place cable inoutlet boxes or raceways containing non-fire alarm conductors.7. Install all wiring in EMT.Page 125 of 190


VESDA FIRE ALARM SYSTEM UPGRADE PROJECT NOVEMBER, 2010NEW YORK AIR ROUTE TRAFFIC CONTROL CENTER (ZNY) (REVISED AUGUST, 2011)RONKONKOMA, NEW YORKB. Wiring within Enclosures: Install conductors parallel with or at rightangles to the sides and back of the enclosure. Bundle, lace, and train theconductors to terminal points. Connect conductors that are terminated,spliced, or interrupted in any enclosure associated with the fireC. Alarm system to terminal blocks. Mark each terminal according to thesystem's wiring diagrams. Make connections with approved crimp-onterminal spade lugs, pressure-type terminal blocks, or plug connectors.D. Cable Connections: Use numbered terminal strips in junction, pull oroutlet boxes, cabinets, or equipment enclosures where circuit connectionsare made. Wire nuts are not permitted.E. Color Coding: Color-code fire alarm conductors differently from thenormal building power wiring. Paint fire alarm system conduit, junctionboxes and covers red.F. UL listed through-penetration firestop systems: Provide at fire alarmconduit penetrations through fire rated floors and walls in accordancewith requirements of Section 07840, “Through-Penetration FirestopSystems”.3.4 IDENTIFICATIONA. Identify system components, raceway, wiring, cabling, and terminals.B. All Fire Alarm and thermal detector circuit conduits: In maintenanceareas, and above dropped ceilings, conduit shall be painted red. Infinished, office and administration areas, conduit shall be painted with a1” wide red stripe band every 5 feet. In all areas: Junction boxes, andtheir covers and condulet fittings, and their covers, shall be painted red.3.5 GROUNDINGA. Ground cable shields and equipment according to system manufacturer'sinstructions to eliminate shock hazard and to minimize, to the greatestextent possible, ground loops, common mode returns, noise pickup, crosstalk, and other impairments.Page 126 of 190


VESDA FIRE ALARM SYSTEM UPGRADE PROJECT NOVEMBER, 2010NEW YORK AIR ROUTE TRAFFIC CONTROL CENTER (ZNY) (REVISED AUGUST, 2011)RONKONKOMA, NEW YORK3.6 FIELD QUALITY CONTROLA. General: Demonstrate that the entire Fire Alarm and Control systemfunctions as designed and specified. Test circuits under automatic alarmconditions, manual alarm conditions, and equipment shutdown inaccordance with NFPA 72. There are approximately 800 existing alarminitiating devices and approximately 80 notification appliances in otherareas of the facility. Test at least 10 percent of the existing initiatingdevices and all notification appliances in accordance with NFPA 72. Ifthe software is changed or a modification is performed that affects thesystem operation a 100% test shall be performed. Tests shall bewitnessed by the COTR.B. Manufacturers Field Service: Provide services of factory-authorizedstartup personnel to supervise the field assembly and connection ofcomponents and the pretesting, testing, and adjustment of the system.C. Pretesting: After the installation is complete, have factory trainedpersonnel inspect the system in accordance with the manufacturersrecommended procedures, include testing the wiring for properconnection, continuity and resistance to ground. After installation, align,adjust, and balance the system and perform complete pretesting.Determine, through pretesting, the conformance of the system to therequirements of the Drawings and <strong>Specifications</strong>. Correct deficienciesobserved in pretesting. Replace malfunctioning or damaged items withnew ones and retest until satisfactory performance and conditions areachieved. Prepare forms for systematic recording of acceptance testresults.D. Report of Pretesting: After pretesting is complete, provide a lettercertifying the installation is complete and fully operable, including thenames and titles of the witnesses to the preliminary tests.E. Final Test Notice: Provide a 10-day minimum notice in writing when thesystem is ready for final acceptance testing.F. Operations Test: Test the complete system. Functions including systemand equipment interlocks shall be operational at least 10 days prior to thefinal acceptance test. Verify the system and equipment interlocks, i.e.,audible and visual alarms and equipment shutdowns, function at testtime. Test each circuit for trouble by inducing a trouble condition to thesystem.G. Minimum System Tests: Test the system according to the proceduresoutlined in NFPA 72. Minimum required tests are as follows:Page 127 of 190


VESDA FIRE ALARM SYSTEM UPGRADE PROJECT NOVEMBER, 2010NEW YORK AIR ROUTE TRAFFIC CONTROL CENTER (ZNY) (REVISED AUGUST, 2011)RONKONKOMA, NEW YORK1. Verify the absence of unwanted voltages between new circuit conductorsand ground.2. Verify that the control unit is in the normal condition as detailed in themanufacturers operation and maintenance manual.3. Test initiating and indicating circuits for proper signal transmission underopen circuit conditions. One connection each should be opened at not lessthan 10 percent of the initiating and indicating devices. Observe propersignal transmission according to class of wiring used.4. Test each new initiating device for alarm operation and proper response atthe control unit.5. Test the system for specified functions according to the approvedoperation and maintenance manual. Systematically initiate specifiedfunctional performance items at each station, including making allpossible alarm and monitoring initiations and using all communicationsoptions. For each item, observe related performance at all devicesrequired to be affected by the item under all system sequences. Observeindicating lights, displays, signal tones, and annunciator indications.6. Coordinate fire alarm test with sprinkler system installation and testing.H. Retesting: correct deficiencies indicated by tests and completely retestwork affected by such deficiencies. Verify by the system test that thetotal system meets the <strong>Specifications</strong> and complies with applicablestandards.I. Report of Tests and Inspections: Provide a written record of inspections,tests, and detailed test results in the form of a test log. Submit log uponthe satisfactory completion of tests.J. Tag equipment, stations, and other components at which tests have beensatisfactorily completed.3.7 CLEANING AND ADJUSTINGA. Cleaning: Remove paint splatters and other spots, dirt, and debris.Touch up scratches and marred finish to match original finish. Cleanunit internally using methods and materials recommended bymanufacturer.3.8 WARRANTYA. Include a service and parts guarantee of the new system components for aperiod of three years and provide any services and equipment incidentalto the proper performance of the system under warranty at no additionalPage 128 of 190


VESDA FIRE ALARM SYSTEM UPGRADE PROJECT NOVEMBER, 2010NEW YORK AIR ROUTE TRAFFIC CONTROL CENTER (ZNY) (REVISED AUGUST, 2011)RONKONKOMA, NEW YORKcost to the Government. <strong>Contract</strong>or shall be available on a 24-hour, 7-day a week basis during the warranty period. Response to the warrantyrequest shall be within four hours of the initial contact.B. END OF SECTION 13851Page 129 of 190


VESDA FIRE ALARM SYSTEM UPGRADE PROJECT NOVEMBER, 2010NEW YORK AIR ROUTE TRAFFIC CONTROL CENTER (ZNY) (REVISED AUGUST, 2011)RONKONKOMA, NEW YORKSECTION 16050 - BASIC ELECTRICAL MATERIALS AND METHODSPART 1 - GENERAL1.1 SUMMARYA. General:1. Materials and equipment must comply with all requirements of the contractdocuments. Materials furnished by the contractor must be new, the standardproducts of manufacturers regularly engaged in the production of suchmaterials, and of the manufacturer’s latest designs that comply with thespecification requirements. Wherever standards have been established byUnderwriters’ Laboratories, Inc., the material must bear the UL label.B. This Section includes the following electrical materials and methods:1. Supporting devices for electrical components.2. Electrical demolition.3. Cutting and patching for electrical construction.4. Touchup painting.C. Applicable provisions of this Project include the following:1. Removal of existing electrical, telephone, and data equipment in accordancewith demolition drawings and specifications.2. Equipment, wiring devices, and electrical connections required forinstallation of electrical equipment.3. Indoor, normal and emergency lighting system.4. Raceways and wiring for power and controls.5. Grounding systems.6. Division 13850, “Fire Alarm and Detection Systems” contains therequirements that relate to this Section.7. Division 13900, “Fire Suppression Sprinkler System” contains therequirements that relate to this Section.8. Division 15900, “Control Systems – Electronic And Direct Digital Control”contains the requirement that relate to this Section.9. Seismic bracing; Zone 2B.Page 130 of 190


VESDA FIRE ALARM SYSTEM UPGRADE PROJECT NOVEMBER, 2010NEW YORK AIR ROUTE TRAFFIC CONTROL CENTER (ZNY) (REVISED AUGUST, 2011)RONKONKOMA, NEW YORKD. Provide products which conform to and installation that complies with therequirements of Uniform <strong>Federal</strong> Accessibility Standards (UFAS).E. Space requirements: Electrical equipment sizes indicated on the Drawings aregenerally based on specified manufacturer.1. Verify that the equipment proposed will fit in the space indicated on theDrawings. Coordinate building dimensions with architectural and structuraldrawings. Equipment furnished and installed under other Sections of thisspecification must be coordinated with electrical equipment installed underthis Section.2. Maintain clearances required by NEC around electrical equipment.Establish the exact location of electrical equipment based on the actual fieldverified dimensions of equipment furnished.1.2 REFERENCE STANDARDSA. General: Comply with the standards in effect as of the date of the <strong>Contract</strong>Documents as applicable to the extent specified in Division 16. The rules,regulations and reference specifications enumerated in these specifications mustbe considered as minimum requirements. Adherence to other standards mustnot relieve the contractor from furnishing and installing higher grades ofmaterials and workmanship when so required by this specification. Seeparagraph 1.4.C for minimum work experience in the State of New York.Adherence to this specification must not relieve the <strong>Contract</strong>or from furnishingand installing higher grades of materials and workmanship when so required bythe contract Drawings or special contracts provisions. This specification mustgovern when conflicts occur between it and the documents referenced in Article1.1 paragraph A, sub-paragraph 1, of this Section.B. American National Standards Institute (ANSI)1. A13.1: Scheme for the Identification of Piping Systems.C. American Society for Testing and Materials (ASTM)1. A36: Standard Specification for Carbon Structural Steel.2. A53: Standard Specification for Pipe, Steel, Black and Hot-Dipped, Zinc-Coated, Welded and Seamless.Page 131 of 190


VESDA FIRE ALARM SYSTEM UPGRADE PROJECT NOVEMBER, 2010NEW YORK AIR ROUTE TRAFFIC CONTROL CENTER (ZNY) (REVISED AUGUST, 2011)RONKONKOMA, NEW YORKD. <strong>Federal</strong> <strong>Aviation</strong> <strong>Administration</strong> (FAA) Standards1. FAA-C-1217f Electrical Work, Interior.2. FAA-STD-019e Lightning, Grounding, Bonding and ShieldingRequirements for Facilities.E. Institute of Electrical and Electronic Engineers (IEEE)1. 519: Recommended Practices and Requirements for Harmonic Controland Electrical Power Systems.F. National Electrical <strong>Contract</strong>ors Association (NECA)1. Standard of Installation.G. National Electrical Manufacturers Association (NEMA)1. WC5: Thermoplastic-Insulated Wire and Cable for theTransmission and Distribution of Electrical Energy.2. WC7: Cross Linked Thermosetting Polyethylene Insulated Wire andCable for the Transmission and Distribution of Electrical Energy.H. National Fire Protection Association (NFPA)1. 70: 2008 National Electrical Code (NEC).I. Occupational Safety and Health <strong>Administration</strong> (OSHA)1. 29CFR-1910.7: Description and Requirements for a Nationally RecognizedTesting Laboratory (NRTL).J. Underwriters Laboratories (UL)1. 486A: Wire Connectors and Soldering Lugs for Use with CopperConductors.1.3 SUBMITTALSA. Product data for each type of product specified.Page 132 of 190


VESDA FIRE ALARM SYSTEM UPGRADE PROJECT NOVEMBER, 2010NEW YORK AIR ROUTE TRAFFIC CONTROL CENTER (ZNY) (REVISED AUGUST, 2011)RONKONKOMA, NEW YORKB. Shop drawings detailing fabrication, installation, and location of supports,seismic bracing, and anchorage for electrical items.C. Project Record Documents: Maintain at the job site a separate set of white printsof the <strong>Contract</strong> Documents for the purpose of recording the system anddimension changes of those portions of work in which actual construction issignificantly at variance with the <strong>Contract</strong> Documents. The <strong>Contract</strong>or mustrecord changes for both GFE and <strong>Contract</strong>or provided equipment. Uponacceptance of the project, submit documents to the COTR, with verification ofdata accuracy. Mark the Drawings with colored pencil. Prepare the Drawingsas the work progresses. Upon completion of work submit Drawings clearlyindicating the following:1. Locations of devices, conduits, equipment and other pertinent items.2. Schematic and interconnection wiring diagrams of the completed power andcontrol system incorporating the data derived from the equipment shopdrawings. The drawings must be detailed to wire and terminal blocknumbers, conductor color coding, device designations, locations, and reflectidentifications established at the site.D. Samples of color, lettering style, and other graphic representation required foreach identification product for Project.E. Operation and Maintenance Instructions:1. Reference Material: Provide copies of operating and maintenanceinstructions, equipment service manuals, catalog cuts and illustrations asdescribed in Section 01782, “Operation and Maintenance Manual Data.”The material must include equipment model and serial numbers,performance characteristics, and power and utility requirements. Finalacceptance of this equipment is contingent upon submission of requireddocuments to, and approval by, the COTR prior to equipment or facilityturnover.2. Minimum Data Required: Operating and maintenance instructions mustcontain the following minimum data and must comply with submittalrequirements specified in individual Sections of the <strong>Specifications</strong> andSection 01782 “Operation and Maintenance Manual Data.” Training on theoperation and maintenance of special equipment must be conducted by acertified technician from the manufacturer.Page 133 of 190


VESDA FIRE ALARM SYSTEM UPGRADE PROJECT NOVEMBER, 2010NEW YORK AIR ROUTE TRAFFIC CONTROL CENTER (ZNY) (REVISED AUGUST, 2011)RONKONKOMA, NEW YORKa. Operating instructions must include illustrations and explanations forcontrols, initial set points, and startup and shutdown procedures for bothnormal and emergency conditions.b. Maintenance instructions must include periodic inspection andlubrication requirements, and when applicable, equipment performanceverification requirements. Include a list of required tools and equipmentto maintain the system.c. Troubleshooting and fault diagnosis data must list trouble symptoms,instructions necessary to determine cause of trouble and the actionrequired to restore equipment to operating condition.d. Repair instructions must include equipment disassembly, repair,replacement, and reassembly. Checkout or test data must also beprovided. Reprogramming instructions must be provided for equipmenthaving a programmable memory. Repacking instructions must beprovided for sending equipment to the manufacturer or to a repair depotfor repairs.e. A parts list must be furnished that includes part names and part numbersthat are shown on illustrations or tables. The parts list must identify theactual manufacturer of the part; replacement cost, and must also containa notation of identifying products as Commercial grade for commonnon-special design hardware.f. The instructions must contain a list of spare parts recommended by theequipment manufacturer to support the operation of the equipment for aone-year time period. Provide names, addresses, and telephone numbersof all service organizations that supply repair parts for the system orsystems to be furnished.g. The O&M data must include overhaul instructions that are required toreturn the equipment to full operational capability in the event that themachinery stops working properly.h. The O&M data must contain the following:1) Wiring diagrams;2) Electrical schematics;3) Control diagrams;4) Wire terminal assignments;5) Equipment layouts;6) Record Electrical Drawings, modified to record actual conditions andmodifications, including dimensions;7) Approved Shop Drawings; andPage 134 of 190


VESDA FIRE ALARM SYSTEM UPGRADE PROJECT NOVEMBER, 2010NEW YORK AIR ROUTE TRAFFIC CONTROL CENTER (ZNY) (REVISED AUGUST, 2011)RONKONKOMA, NEW YORK8) A list of all subcontractors used on the project with address andphone number.i. After final tests and adjustments have been completed, fully instruct theCOTR and other personnel, as directed by the COTR, in details ofoperation and maintenance of special equipment, including controlsystem, and fire alarm system, as installed. Submit outline of proposedinstruction course, scheduled during a 3 week period, 21 days prior tostart, for approval by the COTR.F. Operating Tests: An interim operating and performance test must be performedfor each major equipment item after installation is complete and before the itemis placed in service. After mechanical systems have been completely installedand balanced, test each system for proper operation. Tests must be conducted inthe presence of the COTR under design conditions to ensure proper sequenceand operation throughout the range of operation. Make adjustments as requiredto ensure proper functioning of the systems. Special tests on individual systemsare specified under individual sections. Tests must be scheduled and approvedin writing by COTR at least 21 calendar days prior to conducting tests.<strong>Contract</strong>or must demonstrate, to the COTR’s satisfaction, proper operation ofcontrol devices by simulating actual operating conditions. Devices tested mustinclude, but not be limited to, flow and pressure controls, temperature controls,and system interlocks and alarms.1.4 QUALITY ASSURANCEA. Comply with NFPA 70 for components and installation.B. Listing and Labeling: Provide products specified in this Section that are listedand labeled.1. The Terms "Listed and Labeled": As defined in the National ElectricalCode, Article 100.2. Listing and Labeling Agency Qualifications: A NRTL as defined in OSHARegulation 1910.7.C. Qualifications: At a minimum the installers must be licensed electricians in theState of New York and have a minimum of five years related work experience.Page 135 of 190


VESDA FIRE ALARM SYSTEM UPGRADE PROJECT NOVEMBER, 2010NEW YORK AIR ROUTE TRAFFIC CONTROL CENTER (ZNY) (REVISED AUGUST, 2011)RONKONKOMA, NEW YORKD. Summary: Submit a summary of the Electrical Test Report and Motor TestReport, noting deviations from requirements listed below:1. Maximum plus or minus five percent variation between nominal systemvoltage and no load voltage and between no load and full load voltage;2. Variation between motor average phase current and measured individualphase currents does not exceed the manufacturer's specified limits; and;3. Maximum plus or minus ten percent variation between average phasecurrent and measured individual phase currents for panelboards.1.5 SEQUENCING AND SCHEDULINGA. Coordinate electrical equipment installation with other building components.B. Arrange for chases, slots, and openings in building structure during progress ofconstruction to allow for electrical installations.C. Coordinate installing required supporting devices and other structuralcomponents as they are constructed.D. Sequence, coordinate, and integrate installing electrical materials and equipmentfor efficient flow of the Work.E. Coordinate connecting electrical service to components furnished under otherSections.F. Coordinate requirements for access panels and doors where electrical itemsrequiring access are covered by finished surfaces.G. Coordinate installing electrical identification after completion of finishingwhere identification is applied to field-finished surfaces.H. Coordinate installing electrical identifying devices and markings prior toinstalling acoustical ceilings and similar finishes that conceal such items.I. Interruption of Power: <strong>Contract</strong>or is advised that this facility includes a fullyoperational Air Traffic Control Center (ARTCC). The electrical power systemis comprised of the types: critical, essential, and building service. Work must beperformed on the three types as indicated on drawings. Unscheduledinterruptions of the electrical service may cause aircraft accidents and loss ofPage 136 of 190


VESDA FIRE ALARM SYSTEM UPGRADE PROJECT NOVEMBER, 2010NEW YORK AIR ROUTE TRAFFIC CONTROL CENTER (ZNY) (REVISED AUGUST, 2011)RONKONKOMA, NEW YORKlife. <strong>Contract</strong>or is advised that failure to establish and maintain proper meansand methods during the Work, resulting in accidents or loss of life, may result incharges of criminal negligence.1. Work requiring a temporary or permanent de-energizing of critical, essential,and building service power systems must be scheduled and approved inwriting by the COTR at least 14 calendar days in advance of performance ofwork.2. Work may not commence until written authorization is received from theCOTR.3. Unscheduled interruptions of power must not be allowed at any time.4. Only Government personnel are authorized to energize or de-energizeequipment, to operate circuit breakers, switches, or fuses in this facility.Only the FAA must authorize the Utility Company to turn on, or turn off, thecommercial power to this facility.PART 2 - PRODUCTS2.1 SUPPORTING DEVICESA. Channel and Angle Supports, Raceways Supports, Sleeves, and Fasteners: Asspecified in section 16190, “ Supporting Devices”.2.2 TOUCH-UP PAINTA. For Equipment: Provided by equipment manufacturer and selected to matchequipment finish.B. For Non-equipment Surfaces: Matching type and color of undamaged, existingadjacent finish.C. For Galvanized Surfaces: Zinc-rich paint recommended by item manufacturer.PART 3 - EXECUTION3.1 EQUIPMENT INSTALLATION REQUIREMENTSA. Where manufacturers recommended installation methods conflict with contractrequirements, difference must be resolved by the COTR.Page 137 of 190


VESDA FIRE ALARM SYSTEM UPGRADE PROJECT NOVEMBER, 2010NEW YORK AIR ROUTE TRAFFIC CONTROL CENTER (ZNY) (REVISED AUGUST, 2011)RONKONKOMA, NEW YORKB. The installation must be accomplished by skilled workers regularly engaged inthis type of work. Where required by local regulation, the workers must beproperly certified and/or licensed.C. Install components and equipment to provide the maximum possible headroomwhere mounting heights or other location criteria are not indicated.D. Install items level, plumb, and parallel and perpendicular to other buildingsystems and components, except where otherwise indicated.E. Install equipment to facilitate service, maintenance, and repair or replacement ofcomponents. Connect for ease of disconnecting, with minimum interferencewith other installations of new and existing equipment.F. Give right of way to raceways and piping systems installed at a required slope.G. Removal and Relocation of the Existing Work: The Drawings indicate theextent of modifications to existing work. Electrical equipment, which is part of,or operates in conjunction with, relocated mechanical equipment must bedisconnected, relocated and reinstalled with mechanical equipment. Equipmentand materials indicated to be relocated will be inspected by COTR prior toremoval. The relocation and reinstallation of mechanical equipment is specifiedin applicable Mechanical Sections of the <strong>Specifications</strong>. The work must beperformed with care in order not to damage the existing equipment andmaterials. Repair or replace, at no cost in time or money to the FAA, equipmentand materials damaged. Notify the COTR prior to removal of equipment andmaterials indicated on the Drawings to be removed and relocated.H. Removal of Polychlorinated Biphenyls (PCB) Contaminated Ballasts: Lightingballasts used in this facility do no contain PCBs. However, if PCBcontaminated ballasts are found from the removal of the lightingfixtures/ballasts, they must be turned over to the FAA. The FAA will disposethese PCB contaminated ballasts.3.2 ELECTRICAL SUPPORTING METHODSA. Damp Locations: Hot-dip galvanized materials or nonmetallic, U-channelsystem components.Page 138 of 190


VESDA FIRE ALARM SYSTEM UPGRADE PROJECT NOVEMBER, 2010NEW YORK AIR ROUTE TRAFFIC CONTROL CENTER (ZNY) (REVISED AUGUST, 2011)RONKONKOMA, NEW YORKB. Dry Locations: Steel materials.C. Conform to manufacturers recommendations for selecting supports.3.3 INSTALLATIONA. The rules, regulations, and reference documents indicated must be considered asminimum requirements and must not relieve the <strong>Contract</strong>or from furnishing andinstalling higher grades of materials and workmanship than are specified orwhen required by the <strong>Contract</strong> Drawings. Equipment must be installed in amanner to provide proper working spaces, access, and space for removal of theequipment as required by the various equipment.B. <strong>Contract</strong> Drawings: Where the Drawings schematically indicate the work,diagrammatically or otherwise, furnish and install equipment, material, andlabor for a complete and proper installation. Ensure that electrical andcommunications Work is coordinated and compatible with Architectural,Mechanical and Structural Work.C. Fire stopping: Apply to cable and raceway penetrations of fire-rated floor andwall assemblies. Perform fire stopping as specified in Section 07840,"Through-Penetration Fire stop Systems" to reestablish the original fireresistancerating of the assembly at the penetration.D. Fastening: Unless otherwise indicated, securely fasten electrical items and theirsupporting hardware to the building structure in accordance with Section 16190,“Supporting Devices”, and with National Electrical Code (NEC) requirements.Install hangers and supports to withstand forces for UBC Seismic Zone 2B.E. Install identification devices where required in accordance with therequirements of Section 16195, “Electrical Identification”. Engrave nameplatesas indicated, to a maximum of 3 lines.F. Wiring Methods:1. General: All wiring must consist of insulated copper conductors installed inmetallic raceways, unless otherwise specified.2. Conductor routing: Panelboards, disconnect switches, etc., must not be usedas raceway for conductor routing other than conductors that originate orterminate in these enclosures. Isolated ground conductors will be allowed totraverse these enclosures.3. Conductor separation: Power conductors must be routed separately from allPage 139 of 190


VESDA FIRE ALARM SYSTEM UPGRADE PROJECT NOVEMBER, 2010NEW YORK AIR ROUTE TRAFFIC CONTROL CENTER (ZNY) (REVISED AUGUST, 2011)RONKONKOMA, NEW YORKother conductor types. Route power conductors and other conductors inseparate raceways, or by a metallic divider between the power conductorsand the other conductors in the same raceway.a. Power cables of less than 600 volts may be installed in the same duct,however, 480/277V power cables must be in separate raceways from208/120V power cables.b. Power cables of less than 600 volts must not be installed in the sameduct with control, telephone, or signal type cables.4. Neutral conductor: Shared/common neutrals must not be permitted, i.e.,each overcurrent device must have its own separate neutral conductor.Neutral conductor sizes must not be less than the respective feeder or phaseconductor sizes.5. Ground conductor: Shared/common grounding conductors must not bepermitted, i.e., each overcurrent device must have its own separate groundconductor.3.4 DEMOLITIONA. Where electrical work to remain is damaged or disturbed in the course of theWork, remove damaged portions and install new products of equal capacity,quality, and functionality.B. Accessible Work Indicated to Be Demolished: Remove exposed electricalinstallation in its entirety.C. Abandoned Work: Remove electrical conductors in their entirety. Cap andpatch surface to match existing finish.D. Removal: Remove demolished material from the Project site.E. Temporary Disconnection: Remove, store, clean, reinstall, reconnect, and makeoperational components indicated for relocation.3.5 CUTTING AND PATCHINGA. Cut, channel, chase, and drill floors, walls, partitions, ceilings, and othersurfaces necessary for electrical installations. Perform cutting by skilledmechanics of the trades involved. Refer to Section 1-4 “Cutting and Patching.”Page 140 of 190


VESDA FIRE ALARM SYSTEM UPGRADE PROJECT NOVEMBER, 2010NEW YORK AIR ROUTE TRAFFIC CONTROL CENTER (ZNY) (REVISED AUGUST, 2011)RONKONKOMA, NEW YORKB. Repair disturbed surfaces to match adjacent undisturbed surfaces.3.6 TOUCH-UP PAINTINGA. Thoroughly clean damaged areas and provide primer, intermediate, and finishcoats to suit the degree of damage at each location.B. Follow paint manufacturer's written instructions for surface preparation and fortiming and application of successive coats.3.7 FIELD TESTINGA. General: Perform the tests specified and other tests necessary to establish theadequacy, quality, safety, completed status, and suitable operation of eachsystem. Repair or replace equipment that does not meet test requirements andretest. Tests must be scheduled and approved in writing by COTR at least 21calendar days prior to conducting tests. Unless otherwise indicated, thecontractor must furnish all test instruments, materials and labor necessary toperform tests designated in Division 16 Sections. All tests must be performed inthe presence of the COTR. All instruments must have been calibrated within aperiod of two years preceding testing. Calibrations must be traceable toapplicable industry recognized standards.B. An interim operating and performance test must be performed for each majorequipment item after installation is complete and before the item is placed inservice. After mechanical systems have been completely installed and balanced,test each system for proper operation. Tests must be conducted in the presenceof the COTR under design conditions to ensure proper sequence and operationthroughout the range of operation. Make adjustments as required to ensureproper functioning of the systems. Special tests on individual systems arespecified under individual sections. Provide 21 days written notice to the COTRfor major tests. <strong>Contract</strong>or must demonstrate, to the COTR’s satisfaction, properoperation of control devices by simulating actual operating conditions.C. After final tests and adjustments have been completed, fully instruct the COTRand other personnel as directed by the COTR in details of operation andPage 141 of 190


VESDA FIRE ALARM SYSTEM UPGRADE PROJECT NOVEMBER, 2010NEW YORK AIR ROUTE TRAFFIC CONTROL CENTER (ZNY) (REVISED AUGUST, 2011)RONKONKOMA, NEW YORKmaintenance of electrical equipment, including control systems and fire alarmsystem as installed.D. Complete the Electrical Test Report included as Attachment No. 1. Provide therequested information for each panelboard and its power supply conductors.Perform insulation resistance tests in compliance with Section 16120, "Wire andCables", on wires including the neutral before connection to source and to loads.E. Complete the Motor Test Report included as Attachment No. 2. Provide therequested information for each motor. Motors must be tested for ground or shortcircuits after installation, but before start up. Windings must test free from shortcircuits and grounds. Minimum insulation resistance for motors, phase to phase andphase to ground, must not be less than 30 megohm measured with a 500 volt DCinsulation resistance tester. Apply the test voltage for at least one minute after thereading has stabilized.F. Complete the Meggar Test Report included as Attachment No. 3. Provide therequested information for each branch circuit conductor. Perform insulationresistance tests in compliance with Section 16120, "Wire and Cables", on wiresincluding the neutral before connection to source and to load.G. Load Balancing: After the <strong>Contract</strong>or Acceptance Inspection (CAI) of electricalsystems, redistribute the loads where there is a greater than a twenty percentdifference between readings in two or more phases, in accordance with Section16470, “Panelboards.”END OF SECTION 16050Page 142 of 190


VESDA FIRE ALARM SYSTEM UPGRADE PROJECT NOVEMBER, 2010NEW YORK AIR ROUTE TRAFFIC CONTROL CENTER (ZNY) (REVISED AUGUST, 2011)RONKONKOMA, NEW YORKATTACHMENT NO. 1Electrical Test ReportProject Name Date Sheet No.___ of ___ProjectNo._____________________Address_____________________________SERVICETRANSFORMER SIZENL SERVICEVOLTAGEFL SERVICEVOLTAGEPANEL OR SWBDSERVED FROMPANEL ORSWITCHBOARDLOCATIONMANUFACTURERTYPEFEEDER OCPROTECTIONFEEDERCONDUCTOR SIZEGROUNDCONDUCTOR SIZEMEASUREDCONDITIONSNO LOAD FEEDERPHASE PHASE PHASEA B C A B C A B CPage 143 of 190


VESDA FIRE ALARM SYSTEM UPGRADE PROJECT NOVEMBER, 2010NEW YORK AIR ROUTE TRAFFIC CONTROL CENTER (ZNY) (REVISED AUGUST, 2011)RONKONKOMA, NEW YORKVOLTAGEOPERATING LOADFEEDER VOLTAGEOPERATING LOADFEEDER CURRENTCONDUCTOR INSULRESISTANCE 0/ ABCONDUCTOR INSULRESISTANCE 0/ BCCONDUCTOR INSULRESISTANCE 0/ CACONDUCTOR INSULRESISTANCE TOGROUNDNEUTRAL INSULRES TO GR W/GRCONN REMOVEDATTACHMENT NO. 2Motor Test ReportProject Name Date Sheet No.___ of ___ProjectNo._____________________Address_____________________________DESTINATIONLOCATIONHORSEPOWERNEMA STARTER SIZESTARTER MFG & CATNUMBERHEATER CAT NUMBERMAXIMUM HEATERPage 144 of 190


VESDA FIRE ALARM SYSTEM UPGRADE PROJECT NOVEMBER, 2010NEW YORK AIR ROUTE TRAFFIC CONTROL CENTER (ZNY) (REVISED AUGUST, 2011)RONKONKOMA, NEW YORKAMPSCONDUCTOR SIZEGROUND COND SIZESERVED FROM PNL ORMCCMEASURED CONDITIONSACTUAL MOTORCURRENTPHASEPHASEA B C A B CNAMEPLATE MOTORCURRENTNO LOAD VOLTAGEFULL LOAD VOLTAGECONDUCTOR INSULRESISTANCE 0/ ABCONDUCTOR INSULRESISTANCE 0/ BCCONDUCTOR INSULRESISTANCE 0/ CACONDUCTOR INSULRESISTANCE TO GROUNDPage 145 of 190


VESDA FIRE ALARM SYSTEM UPGRADE PROJECT NOVEMBER, 2010NEW YORK AIR ROUTE TRAFFIC CONTROL CENTER (ZNY) (REVISED AUGUST, 2011)RONKONKOMA, NEW YORKATTACHMENT NO. 3Meggar Test Report(power/control wire & cable)Project Name _____________________ Date Sheet No. ____ of ____Project No._____________________Address_____________________________NOTE: MEGGAR ALL PHASES, RECORD MINIMUM READING.WIRE OR CABLEPanel No.Ckt. No.Feeder No.WIRETAGGINGVOLT.NO. SIZE FROM TO MEGOHMSSUPERVISOR O.K.Page 146 of 190


VESDA FIRE ALARM SYSTEM UPGRADE PROJECT NOVEMBER, 2010NEW YORK AIR ROUTE TRAFFIC CONTROL CENTER (ZNY) (REVISED AUGUST, 2011)RONKONKOMA, NEW YORKDISTRIBUTION:RE/ENGINEERCONTRACTORCENTRAL RECORDS ____RE/ENG/DATE________________________________________<strong>Contract</strong>or Supervisor/DatePage 147 of 190


VESDA FIRE ALARM SYSTEM UPGRADE PROJECT NOVEMBER, 2010NEW YORK AIR ROUTE TRAFFIC CONTROL CENTER (ZNY) (REVISED AUGUST, 2011)RONKONKOMA, NEW YORKSECTION 16100 - RACEWAYS, BOXES, AND CABINETSPART 1 - GENERAL1.1 SUMMARYA. This Section includes raceways, fittings, boxes, enclosures, and cabinets forelectrical and communication wiring. Devices must be installed per requirements forSeismic Zone 3.B. Raceways include the following:1. Rigid metal conduit (RMC).2. Intermediate metal conduit (IMC).3. Electrical metallic tubing (EMT).4. Flexible metal conduit (FMC).5. Liquid-tight flexible conduit (LFMC).6. Metal wireways.C. Boxes, enclosures, and cabinets include the following:1. Device boxes.2. Outlet boxes.3. Pull and junction boxes.4. Conduit bodies.5. Cable access boxes.6. Cabinets and hinged cover enclosures.7. Control Enclosures.1.2 REFERENCE STANDARDSA. American National Standards Institute (ANSI)1. C80.1: Rigid steel conduit-zinc coated.2. C80.3: Electrical metallic tubing-zinc coated.3. C80.6: Intermediate metal conduit zinc coated.B. <strong>Federal</strong> <strong>Aviation</strong> <strong>Administration</strong> (FAA)1. FAA-C-1217f Electrical Work, Interior.2. FAA-STD-019e Lightning, Grounding, Bonding and ShieldingRequirements for Facilities.C. <strong>Federal</strong> Standards (FS)Page 148 of 190


VESDA FIRE ALARM SYSTEM UPGRADE PROJECT NOVEMBER, 2010NEW YORK AIR ROUTE TRAFFIC CONTROL CENTER (ZNY) (REVISED AUGUST, 2011)RONKONKOMA, NEW YORK1. WC586: Conduit outlet boxes, bodies, and entrance caps.D. National Electrical <strong>Contract</strong>or’s Association (NECA)1. Standard of installation.E. National Electrical Manufacturers Association (NEMA)1. 250: Enclosures for electrical equipment.2. FB 1: Fittings, cast metal boxes and conduit bodies for conduitand cable assemblies.3. OS1: Sheet-steel outlet boxes, device boxes, covers, and boxsupports.F. National Fire Protection Association (NFPA)1. 70: 2008 National Electrical Code (NEC).G. Occupational Safety and Health <strong>Administration</strong> (OSHA)(NRTL).1. 1910.7: Nationally Recognized Testing LaboratoriesH. Underwriters Laboratories (UL)conductors.1. 1: Flexible metal conduit.2. 6: Rigid metal conduit.3. 50: Enclosures for electrical equipment.4. 94V-0: Test for Flammability of Plastic Materials.4. 360: Liquid-tight flexible metal conduit.5. 486A: Wire connectors and soldering lugs for use with copper6. 514A: Metallic outlet boxes.7. 514B: Fittings for conduit and outlet boxes.8. 797: Electrical metallic tubing.9. 870: Wireways, auxiliary gutters and associated fittings.10. 1242: Intermediate metal conduits.I. Uniform Building Code (UBC)1.3 SYSTEM DESCRIPTIONPage 149 of 190


VESDA FIRE ALARM SYSTEM UPGRADE PROJECT NOVEMBER, 2010NEW YORK AIR ROUTE TRAFFIC CONTROL CENTER (ZNY) (REVISED AUGUST, 2011)RONKONKOMA, NEW YORKA. Conduit size is indicated on Drawings. Minimum size conduit must be 3/4inch diameter.1.4 SUBMITTALSA. Product data for all raceway, wireway and fittings, floor boxes, hinged coverenclosures, and cabinets. Provide shop drawings for nonstandard boxes, enclosures, andcabinets. Include layout drawings showing components, wiring, supports, and seismicbracing.1.5 QUALITY ASSURANCEA. Comply with NFPA 70 "National Electrical Code" for components andinstallation.1. Boxes must be sized in accordance with NEC Article 314.B. Listing and Labeling: Provide products specified in this Section that are listed andlabeled.1. The Terms "Listed and Labeled": As defined in the "National Electrical Code,"Article 100.2. Listing and Labeling Agency Qualifications: A NRTL as defined in OSHARegulation 1910.7.C. Comply with NECA "Standard of Installation."D. Coordinate layout and installation of raceway and boxes with other constructionelements to ensure adequate headroom, working clearance, and access.PART 2 - PRODUCTS2.1 GENERALA. Enclosures must conform to NEMA standards.2.2 METAL CONDUIT AND TUBINGA. Rigid Steel Conduit: ANSI C80.1 and UL 6.B. Intermediate Metal Conduit: ANSI C80.6.Page 150 of 190


VESDA FIRE ALARM SYSTEM UPGRADE PROJECT NOVEMBER, 2010NEW YORK AIR ROUTE TRAFFIC CONTROL CENTER (ZNY) (REVISED AUGUST, 2011)RONKONKOMA, NEW YORKC. Electrical Metallic Tubing and Fittings: ANSI C80.3 and UL 797 with steelcompression-type fittings. (Screw type fittings are not acceptable). Use for lighting,building power, fire alarm, environmental and communication circuits in concealed areas,such as: suspended ceilings, furred walls, raised floors, and where these circuits are notsubject to physical damage.D. Flexible Metal Conduit, Zinc Coated steel: UL 1 and FS WW-C-5661. Liquid-tight Flexible Metal Conduit: Flexible metal conduit with PVCjacket: UL 3602. Provide flexible metal conduit in minimum 24 inches or 10 diameterlengths for connection to motors and equipment subject to vibration andmovement.3. Conduit and fittings must be type listed for grounding.E. Fittings: NEMA FB 1 and UL 514B, compatible with conduit and of threadedtype. Set screw fittings are not allowed. Conduit expansion and deflection fittings must bewatertight. Fabricate from material compatible with conduit to be used. Expansion anddeflection fittings must be equipped with bonding jumper cable to provide electricalcontinuity. Lock-nut and bushings inside boxes or enclosures must be grounding type.2.3 OUTLET AND DEVICE BOXESA. Sheet Metal Boxes: NEMA OS 1 and UL 514A.B. Cast Metal Boxes: NEMA FB 1, type FD, cast ferroalloy box with threaded hubs,and with gasketed cover.C. Exposed Outlet Boxes: UL 514A steel, malleable iron or cast iron boxes withthreaded conduit entry for surface mounting in areas having exposed conduit systems.D. Flush Outlet Boxes: UL 514A hot-dip galvanized steel, square or rectangular, 2-1/8 inches deep by four inches square, with extension ring where necessary.E. Boxes for lighting fixtures: Flush mounted or in concealed areas: octagonal, fourinches by 2-1/8 inches deep, galvanized steel, with fixture stud supports and attachmentsto properly support ceiling and bracket type lighting fixtures.F. Boxes must not contain concentric knockouts.2.4 PULL AND JUNCTION BOXESA. Small Sheet Metal Boxes: NEMA OS 1 and UL 514A.Page 151 of 190


VESDA FIRE ALARM SYSTEM UPGRADE PROJECT NOVEMBER, 2010NEW YORK AIR ROUTE TRAFFIC CONTROL CENTER (ZNY) (REVISED AUGUST, 2011)RONKONKOMA, NEW YORK2.5 CABINETS AND ENCLOSURESA. Hinged Cover Enclosures: NEMA 250, steel enclosure with continuous hingecover and flush latch. Finish inside and out with manufacturer's standard enamel.B. Cabinets: NEMA 250, type 1, code gauge galvanized steel box with removableinterior panel and removable front, finished inside and out with manufacturer's standardenamel. Hinged door in front cover with flush latch and concealed hinge. Include metalbarriers to separate wiring of different systems and voltage, and include accessory feetwhere required for freestanding equipment.1. Cabinets must be constructed with interior dimensions not lessthan those indicated on the Drawings.2. Provide 3/4 inch plywood backboard unless otherwise indicated.3. Key latch to match panelboards. All panels must be keyed alike.Provide two keys with each cabinet unless otherwise notified.C. NOT USED.D. Safety: UL 50E. Control Enclosures: NEMA 1CS-6F. Telephone and Signal Cabinets must be constructed in accordance with NECArticle 312 Part II.G. All locks in project must be keyed alike.PART 3 - EXECUTION3.1 EXAMINATIONA. Examine surfaces to receive raceways, boxes, enclosures, and cabinets forcompliance with installation tolerances and other conditions affecting performance of theraceway system. Do not proceed with installation until unsatisfactory conditions havebeen corrected.B. Examine raceways prior to installation. No crushed or deformed raceway must beinstalled.3.2 WIRING METHODSA. Outdoors: N/APage 152 of 190


VESDA FIRE ALARM SYSTEM UPGRADE PROJECT NOVEMBER, 2010NEW YORK AIR ROUTE TRAFFIC CONTROL CENTER (ZNY) (REVISED AUGUST, 2011)RONKONKOMA, NEW YORKC. Conduit Use:1. Install RMC or IMC for all branch circuit panel feeders, distribution panelfeeders, transformer feeders, motor control center feeders, and distribution switchboards.2. Install EMT for communication, lighting, and branch circuits in concealedlocations indoors only.3.3 INSTALLATIONA. Install raceways, boxes, enclosures, and cabinets as indicated, according tomanufacturer's written instructions. Install to withstand forces for the UBC Seismic Zoneindicated in Section 16050, “Basic Electrical Materials and Methods.”B. Minimum size raceway must be 3/4 inch, unless otherwise noted.C. Conceal conduit and EMT, unless otherwise indicated, within finished walls,ceilings, and floors/raised floors.1. Raceways must not be attached to the ceiling suspension system.2. Raceways must not be attached to or supported by roof decks.3. Do not anchor or strap raceways to wall furring channels or to otherraceways.D. Keep raceways at least 6 inches away from parallel runs of insulated flues, steam,or hot water pipes. Do not install raceways near uninsulated high temperature serviceswithout prior approval of the COTR. Install horizontal raceway runs above water andsteam piping.E. Install raceways level and square and at proper elevations. Provide adequateheadroom.1. Install conduit to drain moisture to nearest outlet or pull box.2. Inside radii of bends in conduits must not be less than six times thenominal diameter.3. No run must contain more than two 90 deg bends, or the equivalentbetween conduit terminations.4. Telephone and signal raceway 2 inches and smaller: no run of 3/4 inchmust exceed 50 ft; or 100 ft for 1 inch to 2 inch and a maximum of two 90 deg bends, orthe equivalent. Install pull boxes or junction boxes where necessary to comply with theserequirements.5. Provide conduit bodies, pull and junction boxes required to meet the bendscriteria.Page 153 of 190


VESDA FIRE ALARM SYSTEM UPGRADE PROJECT NOVEMBER, 2010NEW YORK AIR ROUTE TRAFFIC CONTROL CENTER (ZNY) (REVISED AUGUST, 2011)RONKONKOMA, NEW YORK6. Install a pull wire in all empty tubing and conduit systems. Pull wire mustbe No. 14 AWG zinc-coated steel or plastic with a minimum 200 pound tensile strength.Provide ten inches of slack at each end of the pull wire.F. Complete raceway installation before starting conductor installation.G. Support raceways and boxes as specified in Section 16050, "Basic ElectricalMaterials and Methods.”1. Boxes for fixtures on suspended ceilings must be supported independentlyof the ceiling supports.2. Boxes must not be supported from sheet-metal roof decks.H. Use temporary closures to prevent foreign matter from entering raceway.1. Prevent the lodgment of plaster, dirt, or trash in raceways, boxes, fittings,and equipment during construction. Clogged raceways must be entirely freed ofobstructions or replaced. Clean each conduit run before pulling in conductors.I. Make bends and offsets so the inside diameter is not reduced. Unless otherwiseindicated, keep the legs of a bend in the same plane and keep the straight legs of offsetsparallel.1. Telephone and signal conduit that is 1 inch and larger must have aminimum inside radii 12 times the nominal conduit diameter.2. No run must contain more than two 90 deg bends, or theequivalent. Provide pull boxes, junction boxes, and conduit bodies as required to meetthe bends criteria. For critical power conduits, only conduit bodies are allowed.J. Use raceway fittings compatible with raceway and suitable for use and location.For intermediate steel conduit, use threaded rigid steel conduit fittings, except asotherwise indicated.K. Run concealed raceways with a minimum of bends in the shortest practicaldistance considering the type of building construction and obstructions, except asotherwise indicated.L. Floor and Wall Penetrations:1. Penetrations through walls or floors must be sealed to prevent moistureand rodent entry and to deter air transfer.2. Seal penetrations of walls which separate individually temperature orhumidity controlled areas, to prevent air circulation.Page 154 of 190


VESDA FIRE ALARM SYSTEM UPGRADE PROJECT NOVEMBER, 2010NEW YORK AIR ROUTE TRAFFIC CONTROL CENTER (ZNY) (REVISED AUGUST, 2011)RONKONKOMA, NEW YORKM. Install raceways parallel to or at right angles to nearby surfaces or structuralmembers, and follow the surface contours as much as practical.1. Run parallel or banked raceways together, on common supports where practical.2. Make bends in parallel or banked runs from same center line to make bendsconcentric. Use factory elbows only where they can be installed parallel; otherwise,provide field bends for parallel raceways.N. Join raceways with fittings designed and approved for the purpose and makejoints tight.1. Use bonding locknuts and bushings at connections subject to vibration. Usebonding jumpers where joints cannot be made tight.2. Use insulating bushings for all conduits to protect conductors.3. Provide expansion fittings for all raceways passing through the buildingexpansion joints and for conduit runs longer than 300 ft.O. Where knockouts are used, provide double locknuts, one on each side with agrounding bushing or grounding locknut used on the inside (use grounding bushings onconduit 1 inch and larger).P. Raceway Supports: Comply with NFPA 70 and the following requirements:1. Conform to manufacturer’s recommendations for selecting and installingsupports.2. Install individual and multiple raceway hangers and riser clamps to supportraceways. Provide U-bolts, clamps, attachments and other hardware necessary for hangerassembly and for securing hanger rods and conduits.3. Support parallel runs of horizontal raceways together on trapeze- or bracket-typehangers.4. Spare Support Capacity: Size supports for multiple conduits so capacity can beincreased by a 25 percent minimum in the future.5. Support individual horizontal raceways with separate, malleable iron pipe hangersor clamps.6. Hanger Rods: 1/4-inch diameter or larger threaded steel, except as otherwiseindicated.7. Spring Steel Fasteners: Specifically designed for supporting single conduits ortubing. May be used in lieu of malleable iron hangers for 1-1/2 inch and smallerraceways serving lighting and receptacle branch circuits above suspended ceilings and forfastening raceways to channel and slotted angle supports.8. In vertical runs, arrange support so that the load produced by the weight of theraceway and the enclosed conductors is carried entirely by the conduit supports, with noweight load on raceway terminals. Install supports simultaneously with raceway.Page 155 of 190


VESDA FIRE ALARM SYSTEM UPGRADE PROJECT NOVEMBER, 2010NEW YORK AIR ROUTE TRAFFIC CONTROL CENTER (ZNY) (REVISED AUGUST, 2011)RONKONKOMA, NEW YORK9. Strength of each support must be adequate to carry present and future loadmultiplied by a safety factor of at least four. Where this determination results in a safetyallowance of less than 200 lbs., provide additional strength until there is a minimum of200 lbs. safety allowance in the strength of each support.10. Space supports for raceways in accordance with Table 1 of this section. Spacesupports for raceway types not covered by the above in accordance with the NationalElectrical Code (NEC).11. Support exposed and concealed raceway within 1 foot of an unsupported box andaccess fittings. In horizontal runs, support at the box and access fittings may be omittedwhere box or access fittings are independently supported and raceway terminals are notmade with chase nipples or threadless box connectors.(continued on next page)Page 156 of 190


VESDA FIRE ALARM SYSTEM UPGRADE PROJECT NOVEMBER, 2010NEW YORK AIR ROUTE TRAFFIC CONTROL CENTER (ZNY) (REVISED AUGUST, 2011)RONKONKOMA, NEW YORKHORIZONTAL RUNSTABLE 1: SPACING FOR RACEWAY SUPPORTSRacewayNo. of RMC &Size Conductors IMC EMT(Inches) in Run Location (1) (1)3/4 1 or 2 Flat ceiling or wall. 5 53/4 1 or 2 Where it is difficult to provide 7 7supports except at intervalsfixed by the buildingconstruction.3/4 3 or more Any location. 7 71 3 or more Any location.1 & larger 1 or 2 Flat ceiling or wall. 6 61 & larger 1 or 2 Where it is difficult to provide 10 10supports except at intervalsfixed by the building construction.1 & larger 3 or more Any location. 10 103/4 and larger .... Concealed. 10 10VERTICAL RUNSRacewayNo. of RMC &Size Conductors IMC EMT(Inches) in Run Location (1,2) (1)3/4 .... Exposed. 7 71,1-1/4 .... Exposed. 8 81-1/2 and larger .... Exposed. 10 10Up to 2 .... Shaftway. 14 102-1/2 .... Shaftway. 16 103 & larger .... Shaftway. 20 103/4 & larger .... Concealed. 10 10NOTES: (1) Maximum spacing of supports (ft).(2) Maximum spacings for IMC above apply to straight runs only.Otherwise the maximums for EMT apply.ABBREVIATIONS: EMT Electrical metallic tubing.IMC Intermediate metal conduit.RMC Rigid metal conduit.Page 157 of 190


VESDA FIRE ALARM SYSTEM UPGRADE PROJECT NOVEMBER, 2010NEW YORK AIR ROUTE TRAFFIC CONTROL CENTER (ZNY) (REVISED AUGUST, 2011)RONKONKOMA, NEW YORKQ. Miscellaneous Supports: Install metal channel racks for mounting cabinets,panelboards, disconnects, control enclosures, pull boxes, junction boxes, and otherdevices except where components are mounted directly to structural features ofadequate strength.R. In open overhead spaces, cast boxes threaded to raceways need not be separatelysupported, except where used for fixture support; support sheet-metal boxes directly fromthe building structure or by bar hangers. Where bar hangers are used, support the barhanger from the building structure, not on the ceiling cross member.S. Sleeves: Install for cable and raceway penetrations of concrete slabs and walls,except where core-drilled holes are used. Install for cable and raceway penetrations ofmasonry and fire-rated gypsum walls and of all other fire-rated floor and wall assemblies.Install sleeves during erection of concrete and masonry walls.T. Fire stopping: Apply to cable and raceway penetrations of fire-rated floor andwall assemblies. Perform fire stopping as specified in Section 07840, “Through-Penetration Fire stopping Systems” to reestablish the original fire-resistance rating of theassembly at the penetration.U. Fastening: Unless otherwise indicated, fasten electrical items and their supportinghardware securely to the building structure, including but not limited to conduits,raceways, cables, cabinets, panelboards, boxes, disconnect switches, and controlcomponents in accordance with the following:1. Fasten by means of wood screws on wood; toggle bolts on hollow masonry units;concrete inserts or expansion bolts on concrete or solid masonry; and by machine screwsor spring-tension clamps on steel.2. Threaded studs driven by a powder charge must not be used.3. In partitions of light steel construction use sheet-metal screws.4. Drill holes in concrete beams so holes more than 1-1/2 inches deep do not cutmain reinforcing bars.5. Drill holes in concrete so holes more than 3/4 inch deep do not cut mainreinforcing bars.6. Fill and seal holes drilled in concrete and not used.7. Select fasteners so the load applied to any fastener does not exceed 25 percent ofthe proof-test load. Use vibration and shock-resistant fasteners for attachments toconcrete slabs.V. Terminations: Where raceways are terminated with locknuts and bushings, alignthe raceway to enter squarely, and install the locknuts with dished part against the box.Use two locknuts, one inside and one outside the box. In addition a bushing must beinstalled on the interior threaded end of the conduit to protect conductor insulation.Page 158 of 190


VESDA FIRE ALARM SYSTEM UPGRADE PROJECT NOVEMBER, 2010NEW YORK AIR ROUTE TRAFFIC CONTROL CENTER (ZNY) (REVISED AUGUST, 2011)RONKONKOMA, NEW YORKW. Where terminating in threaded hubs, screw the raceway or fitting tight into thehub so the end bears against the wire protection shoulder. Where chase nipples are used,align the raceway so the coupling is square to the box, and tighten the chase nipple so nothreads are exposed.X. Make raceway terminations tight. Use bonding bushings or wedges atconnections subject to vibration. Use bonding jumpers where joints cannot be madetight. Use insulating bushings to protect conductors.Y. Install pull wires in empty raceways. Use No. 14 AWG zinc-coated steel ormonofilament plastic line having not less than 200-lb. tensile strength. Leave not lessthan 12 inches of slack at each end of the pull wire.Z Flexible Connections: Use maximum of 6 ft of flexible metallic conduit forrecessed and semi-recessed lighting fixtures; for equipment subject to vibration, noisetransmission, or movement; and for all motors. Use liquid-tight flexible metallic conduitin wet or damp locations. Install separate ground conductor across flexible connections.AA. Metal conduits must be mechanically and electrically continuous between outlets,junctions and pull boxes, panels, cabinets and similar equipment.BB. Conduits must enter and be secured to enclosures so that each system iselectrically continuous throughout.CC. Provide grounding connections for raceway, boxes, and components as indicatedand instructed by manufacturer. Tighten connectors and terminals, including screws andbolts, according to equipment manufacturer's published torque-tightening values forequipment connectors. Where manufacturers torquing requirements are not indicated,tighten connectors and terminals according to tightening torques specified in UL Standard486A.DD. Provide conduit support members required for proper and secure installation.Include stud supports, stems, mounting brackets, frames, and, if applicable, plaster rings.1. Conduit supports must employ materials which are suitable for thepurpose. Cast metal parts other than malleable iron and cast-on rolled threads must bedesigned to ensure structural adequacy.EE. Field Cut Conduit: Where conduit has to be cut in the field, it must be cut squareusing a hand or power hacksaw or approved pipe cutter using cutting knives. The cutends of the field-cut conduit must be reamed to remove burrs and sharp edges. Wherethreads have to be cut on conduit, the threads must have the same effective length andPage 159 of 190


VESDA FIRE ALARM SYSTEM UPGRADE PROJECT NOVEMBER, 2010NEW YORK AIR ROUTE TRAFFIC CONTROL CENTER (ZNY) (REVISED AUGUST, 2011)RONKONKOMA, NEW YORKmust have the same thread dimensions and taper as specified for factory-cut threads onconduit.3.4 INSTALLATION - BOXESA. Boxes: Must be provided in the wiring or raceway system for pulling wires,making connections, and mounting devices or fixtures. Each box must have the volumerequired by NFPA 70 for the number and size of conductors in the box.1. Outlet Boxes: Each outlet box must have a machine screw which fits into atapped hole in the box for the ground connection.2. Mounting light fixtures: Boxes for mounting fixtures must be not less than 4inches square.3. Concealed wiring: Boxes installed for concealed wiring must be provided withextension rings or plaster covers. The front edge of the box must be flush or recessed notmore than 1/4 inch from the finished wall surface (whether the finished surface isdrywall, or drywall and a sound-absorbing material.4. Boxes in masonry block, tile and sheet rock walls: Must be square-cornered tiletype,or standard boxes must have square-cornered tile-type covers.5. Wet locations: Cast metal boxes installed in wet locations and boxes installedflush with exterior surfaces must be gasketed.B. Fixture Boxes: Attach boxes in at least two places to ceilings which arenot suspended. Distribute lighting fixture load over the ceiling boxes.C. Mounting:1. Install switch box on the strike side of the door at mounting heightof 48 inches. Unless otherwise indicated, mounting height of receptacle boxes must be18 inches.2. Height of a wall mounted outlet box is defined as the height fromfinished floor to horizontal center line of the cover plate.3. Where outlets are indicated adjacent to each other, mount outlets ina symmetrical pattern with tops at the same elevation. Where outlets are indicatedadjacent, but with different mounting heights, line up outlets on a vertical line.4. Verify the final location of each outlet before installation. Removeand relocate outlet boxes placed in an unacceptable position.5. At fire rated partitions, offset boxes to prevent back-to-backinstallation.D. Box openings: Provide only the openings necessary to accommodate theconduits at the individual location. When this is not practical, plug unused openings.E. Junction, transition and pull boxes:Page 160 of 190


VESDA FIRE ALARM SYSTEM UPGRADE PROJECT NOVEMBER, 2010NEW YORK AIR ROUTE TRAFFIC CONTROL CENTER (ZNY) (REVISED AUGUST, 2011)RONKONKOMA, NEW YORK1. Install junction, transition and pull boxes so that covers are readilyaccessible. Boxes in concealed areas of ceiling or wall must be accessible throughremovable panels.2. Locate pull boxes to permit easy pulling of wire or cables.3. Securely attach boxes to structural and framing members usingcompatible fasteners of adequate size.4. Bolt wall mounted boxes to steel profiles fastened to the wall.F. Grounding: Provide each box with a green machine screw. Screw intotapped hole in the box for ground wire or lug connection.3.5 PROTECTIONA. Provide final protection and maintain conditions, in a manner acceptable tomanufacturer and Installer, to ensure that coatings, finishes, and cabinets are withoutdamage or deterioration at Substantial Completion.1. Repair damage to galvanized finishes with zinc-rich paint recommended bymanufacturer.2. Repair damage to PVC or paint finishes with matching touch-up coatingrecommended by the manufacturer.B. Cap stubbed up raceways, including raceways in cabinets, immediatelyupon installation. The use of paper or rag wads is not acceptable.C. Galvanic corrosion protection: Avoid dissimilar metals in contactanywhere in conduit runs. Where contact cannot be avoided at conduit terminations, treatthe connection with joint compound that eliminates galvanic corrosion. Where dissimilarmetals are in contact, such as at aluminum cable tray or enclosures and steel supports,separate contact surfaces by using gaskets, nonabsorptive tape, or coating to preventgalvanic corrosion.3.6 CLEANINGA. Upon completion of installation of system, including outlet fittings and devices,inspect exposed finish. Remove burrs, dirt, and construction debris and repair damagedfinish, including chips, scratches, and abrasions.END OF SECTION 16100Page 161 of 190


VESDA FIRE ALARM SYSTEM UPGRADE PROJECT NOVEMBER, 2010NEW YORK AIR ROUTE TRAFFIC CONTROL CENTER (ZNY) (REVISED AUGUST, 2011)RONKONKOMA, NEW YORKSECTION 16120 - WIRES AND CABLESPART 1 - GENERAL1.1 SUMMARYA. This Section includes building wires and cables and associated splices,connectors, and terminations for wiring systems rated 600 volts and less.1.2 REFERENCE STANDARDSA. Reference standards noted are applicable only to the extent specified.B. American Society for Testing and Materials (ASTM)1. B3: Standard Specification for Soft or Annealed Copper Wire.2. B8: Standard Specification for concentric-lay-stranded copperconductors; hard, medium hard, or soft.3. D1000: Standard Test Method for Pressure-Sensitive Adhesive-CoatedTapes used for electrical and electronic applications.C. <strong>Federal</strong> <strong>Aviation</strong> <strong>Administration</strong> (FAA)1. FAA-C-1217f Electrical Work, Interior.2. FAA-STD-019e Lightning, Grounding, Bonding and Shielding Requirementsfor FacilitiesD. <strong>Federal</strong> Standards (FS)1. WS610: Splice Connectors.2. QQW343: Wire, Electrical, Copper, Uninsulated.E. National Electrical <strong>Contract</strong>ors Association (NECA)1. Standard of Installation.F. National Electrical Manufacturers Association (NEMA)Page 162 of 190


VESDA FIRE ALARM SYSTEM UPGRADE PROJECT NOVEMBER, 2010NEW YORK AIR ROUTE TRAFFIC CONTROL CENTER (ZNY) (REVISED AUGUST, 2011)RONKONKOMA, NEW YORK1. WC3: Rubber-Insulated Wire and Cable for the Transmission andDistribution of Electrical Energy.2. WC5: Thermoplastic-Insulated Wire and Cable for the Transmission andDistribution of Electrical Energy.3. WC8: Ethylene-Propylene-Rubber-Insulated Wire and Cable for theTransmission and Distribution of Electrical Energy.4. WC26: Wire and Cable Packaging.G. International Electrical Testing Association (NETA)1. ATS: Acceptance Testing Specification for Electric Power DistributionEquipment and Systems.H. National Fire Protection Association (NFPA)1. 70: 2008 National Electrical Code (NEC).I. Occupational Safety and Health <strong>Administration</strong> (OSHA)1. 29CFR 1910.7: Definitions and Requirements for a Nationally RecognizedTesting Laboratories (NRTL).J. Underwriters Laboratories (UL)1. 486A: Wire Connectors and Soldering Lugs for Use with CopperConductors.1.3 SUBMITTALSA. Field test reports indicating and interpreting test results relative to compliancewith performance requirements of testing standard.1.4 QUALITY ASSURANCEA. Testing Firm Qualifications: An independent testing firm must meet OSHAcriteria for accreditation of testing laboratories, Title 29, Part 1910.7, or must bea full member company of the International Electrical Testing Association(NETA).Page 163 of 190


VESDA FIRE ALARM SYSTEM UPGRADE PROJECT NOVEMBER, 2010NEW YORK AIR ROUTE TRAFFIC CONTROL CENTER (ZNY) (REVISED AUGUST, 2011)RONKONKOMA, NEW YORK1. Testing Firm's Field Supervisor Qualifications: A person currently certifiedby the NETA National Institute for Certification in EngineeringTechnologies to supervise on-site testing specified in Part 3.B. Comply with NFPA 70, NEC, for components and installation.C. Listing and Labeling: Provide products specified in this Section that are listedand labeled.1. The Terms "Listed and Labeled": As defined in the NEC, Article 100.2. Listing and Labeling Agency Qualifications: A NRTL as defined in OSHARegulation 1910.7.D. Installer Qualifications: Cable splices must be performed by experienced andqualified cable splicers. The workmen must be licensed if required by theauthority having jurisdiction.1.5 SEQUENCING AND SCHEDULINGA. Coordination: Coordinate layout and installation of cable with otherinstallations.1. Revise locations and elevations from those indicated as required to suit fieldconditions and as approved by the COTR.1.6 DELIVERY, STORAGE, AND HANDLINGA. Deliver wire and cable according to NEMA WC-26.PART 2 - PRODUCTS2.1 BUILDING WIRES AND CABLESA. UL-listed building wires and cables with conductor material, insulation type,cable construction, and rating as specified in Part 3 "Applications" Article.B. Rubber Insulation: Conform to NEMA WC 3.C. Thermoplastic Insulation: Conform to NEMA WC 5.Page 164 of 190


VESDA FIRE ALARM SYSTEM UPGRADE PROJECT NOVEMBER, 2010NEW YORK AIR ROUTE TRAFFIC CONTROL CENTER (ZNY) (REVISED AUGUST, 2011)RONKONKOMA, NEW YORKD. Solid conductor for 10 AWG and smaller; stranded conductor for larger than 10AWG. Stranded conductors must be tin coated, ASTM B8, Class B.E. All wire and conduit sizes are based on copper conductors with 75 deg Cinsulation.F. Size: Minimum 12 AWG. Minimum 10 AWG for 120 volt circuits wherecircuit length (one way) exceeds 75 ft from source, and 10 AWG for 277 voltcircuits where circuit length (one way) exceeds 150 ft from source. Fire alarmand control systems wiring size must be in accordance with Manufacturer’srequirements or as specified in Section 15900, “Control Systems-Electronic andDirect Digital Controls” and Section 13850, “Fire Alarm and DetectionSystems”.1. Stranded conductors may be used with wire compression connectors or apressure washer type lug.2. Stranded conductors smaller than 10 AWG are allowed in applicationswhere vibration and flexing may be encountered.G. Conductor type: Soft drawn, annealed copper (aluminum conductors are notacceptable).1. Power conductors must be single conductor type.2. Control interconnection between equipment must be jacketed typemulticonductor.3. Instrumentation conductor must be twisted pair, shielded, jacketed type.4. Conductors used for lighting and receptacle branch circuits must be singleconductor type.H. Conductor Color Codes: Refer to Section 16195, “Electrical Identification,” forconductors No. 4 AWG and larger, where factory color-coding is not available.1. Feeder conductors to panels and three phase circuits must be factory colorcoded as follows:a. 208/120 (240) Volt System:1) Phase A: Black.2) Phase B: Red.3) Phase C: Blue.Page 165 of 190


VESDA FIRE ALARM SYSTEM UPGRADE PROJECT NOVEMBER, 2010NEW YORK AIR ROUTE TRAFFIC CONTROL CENTER (ZNY) (REVISED AUGUST, 2011)RONKONKOMA, NEW YORK4) Neutral: White.5) Ground: Green.b. 480/277 Volt System:1) Phase A: Yellow*2) Phase B: Brown*3) Phase C: Orange*4) Neutral: Gray.5) Ground: Green.*Verify and confirm with COTR for site specific system compliance prior toordering.2. Single-phase branch circuits must be factory color coded as stated above, oridentified in accordance with Section 16195, “Electrical Identification.”3. Control Cables must be IAW NEMA WC5.I. Uninsulated conductors must be copper and comply with F.S. QQW-343.J. UL-listed building wires and cables with conductor material, insulation type,cable construction, and rating as specified in Part 3 "Applications" Article.2.2 CONNECTORS AND SPLICESA. UL-listed factory-fabricated wiring connectors of size, ampacity rating, material,and type and class for application and for service indicated. Select to complywith Project's installation requirements and as specified in Part 3 "Applications"Article.B. Connectors, Splice Sleeves and Terminal Lugs: Wire and cable connectors, lugs,and sleeves must be in compliance with UL 486A, and the following:1. For splices of 10 AWG and smaller building wires in lighting circuits, usetin plated copper compression type connector caps with nonflammable,self-extinguishing insulation grip with temperature rating equal to that ofconductor insulation; and2. Use ring tongue compression type terminators with insulated barrel on allstranded conductors used in control wiring.3. Crimp type connectors are not permitted on solid conductors.Page 166 of 190


VESDA FIRE ALARM SYSTEM UPGRADE PROJECT NOVEMBER, 2010NEW YORK AIR ROUTE TRAFFIC CONTROL CENTER (ZNY) (REVISED AUGUST, 2011)RONKONKOMA, NEW YORKC. Insulating Tape: ASTM D1000. As a minimum, rate equal to conductorinsulation. Rubber tape must be silicon rubber with silicon pressure sensitiveadhesive.D. Bundling Straps: Nylon straps with a locking hub or head on one end and a taperon the other.PART 3 - EXECUTION3.1 EXAMINATIONA. Examine raceways and building finishes to receive wires and cables forcompliance with installation tolerances and other conditions. Do not proceedwith installation until unsatisfactory conditions have been corrected.3.2 APPLICATIONSA. Feeders: Type THHN/THWN, copper conductor, in raceway.B. Indoor Branch Circuits: Type THHN/THWN, copper conductor, 90 deg Cinsulation in raceway. For use in dry locations only for lighting and receptaclecircuits.C. Fire Alarm Power Circuits: Type THHN/THWN, copper conductor, in raceway.D. Communication: System wiring must be as specified under applicable sectionsand specific requirements of the NEC. Use copper wire or fiber optic cableonly. Aluminum wire is not permitted.3.3 INSTALLATIONA. Install wires and cables as indicated, according to manufacturer's writteninstructions and the NECA "Standard of Installation."B. Remove existing wire from raceway before pulling in new wire and cable.C. Pull conductors into raceway simultaneously where more than one is beinginstalled in same raceway.Page 167 of 190


VESDA FIRE ALARM SYSTEM UPGRADE PROJECT NOVEMBER, 2010NEW YORK AIR ROUTE TRAFFIC CONTROL CENTER (ZNY) (REVISED AUGUST, 2011)RONKONKOMA, NEW YORK1. Use pulling compound or lubricant where necessary; compound used mustnot deteriorate conductor or insulation.2. Use pulling means, including fish tape, cable, rope, and basket-weavewire/cable grips that will not damage cables or raceway.3. Bend to radii not less than the minimum bending recommended bymanufacturer or 12 times the outer diameter of cable. Do not exceed thepulling tension recommended by manufacturer.D. Cable must be installed in a manner to prevent harmful stretching of theconductor, injury to the insulation or damage to the outer protective covering.E. Install exposed cable; parallel and perpendicular to surfaces or exposedstructural members, and follow surface contours where possible.F. Conductor Splices: Keep to minimum.1. Splices must be made only at outlets, junction boxes, or accessible raceways.2. Wire nuts may only be used to splice conductors sized No. 10 AWG andsmaller.3. Compression connectors must be used to splice conductors No. 8 and larger.4. All splices, including those made with insulated wire nuts, must be insulatedwith electrical tape or heat-shrink tubing to a level equal to that of thefactory insulated conductors.5. Splicing of ungrounded conductors in panelboards is not permitted.6. Splices must be made with solderless connectors conforming to UL 486A,UL 486C, UL 486E and FS W-S-610.7. No splices must be allowed on critical circuits. Critical circuits areidentified on drawings.8. Install splices and insulating tapes that possess equivalent or bettermechanical strength and insulation ratings than conductors being spliced.9. Use splice and tap connectors that are compatible with conductor material.10. Splicing methods and material must be of a type recommended by themanufacturer of the splicing material for the particular type of cable beingspliced and must be approved by the COTR prior to installation.G. Wiring at Outlets: Install with at least 6 inches of slack conductor at each outlet.H. Connect outlets and components to wiring and to ground as indicated andinstructed by manufacturer. Tighten connectors and terminals, including screwsand bolts, according to equipment manufacturer's published torque-tighteningPage 168 of 190


VESDA FIRE ALARM SYSTEM UPGRADE PROJECT NOVEMBER, 2010NEW YORK AIR ROUTE TRAFFIC CONTROL CENTER (ZNY) (REVISED AUGUST, 2011)RONKONKOMA, NEW YORKvalues for equipment connectors. Where manufacturer's torquing requirementsare not indicated, tighten connectors and terminals according to tighteningtorques specified in UL Standard 486A.I. Conductors for critical circuits, emergency lighting, security systems, and firealarm systems must be kept completely independent from any other system aswell as each other.J. Separate neutral and ground wires must be provided for each overcurrentprotection device. Each branch circuit must have its own neutral and groundconductor. Common neutral or ground conductors are not acceptable.K. Neutral conductors must extend from the neutral bus where the phaseconductors originate.L. Install conductors only after the raceway system is complete and must include apull string for future use.M. Install electrical identification devices specified in Section 16195, “ElectricalIdentification”, at terminations, immediately after installing wires and cables.3.4 FIELD QUALITY CONTROLA. Testing, General: Cables must be tested prior to installation and again uponcompletion of the installation. Testing must be accomplished before connectionis made. Tests must be performed in the presence of the COTR.1. Upon installation of wires and cables and before electrical circuitry has beenenergized, demonstrate product capability and compliance withrequirements.a. Procedures: Perform each visual and mechanical inspection andelectrical test stated in NETA Standard ATS, Section 7.3.1. Certifycompliance with test parameters.b. Test wire and cable for continuity or circuitry, and also for short circuits.B. Insulation Resistance Tests: Feeder and Branch Circuit insulation tests must beperformed after installation, but before connection to equipment.1. Conductors must test free from short circuits and grounds, and have aminimum phase-to-phase and phase-to-ground insulation resistance of 30Page 169 of 190


VESDA FIRE ALARM SYSTEM UPGRADE PROJECT NOVEMBER, 2010NEW YORK AIR ROUTE TRAFFIC CONTROL CENTER (ZNY) (REVISED AUGUST, 2011)RONKONKOMA, NEW YORKmegohms when measured with a 500-volt DC insulation resistance tester.The <strong>Contract</strong>or must submit a letter type test report to the COTR prior tofinal inspection of the Work. The report must list the tests performed andresults obtained.a. Apply the test voltage for at least one minute after the testing instrumentmotor reading has stabilized.2. The following cables must be tested: where the feeder cables are associatedwith an existing panel that is to be replaced, and where new and existingcables are to be spliced, both cables must be tested. The resistance valuesfor new cable must not be less than those recommended by the cablemanufacturer. Resistance values for existing cable insulation must not beless than 100 percent of the value for a comparable new cable. Report toCOTR, location of existing cable installation with less than 100 percentinsulation value of new cable to be spliced and replace existing cables withnew.C. Correct malfunctioning products at site, where possible, and retest todemonstrate compliance; otherwise, remove and replace with new units, andretest.END OF SECTION 16120Page 170 of 190


VESDA FIRE ALARM SYSTEM UPGRADE PROJECT NOVEMBER, 2010NEW YORK AIR ROUTE TRAFFIC CONTROL CENTER (ZNY) (REVISED AUGUST, 2011)RONKONKOMA, NEW YORKSECTION 16190 - SUPPORTING DEVICESPART 1 - GENERAL1.1 SUMMARYA. This Section includes secure support from the building structure for electricalitems by means of hangers, supports, anchors, sleeves, inserts, seals, andassociated fastenings.B. Devices must be installed per requirements for Seismic Zone 3.1.2 REFERENCE STANDARDSA. Reference standards noted are applicable only to the extent specified.B. National Fire Protection Association (NFPA)1. 70: 2008 National Electrical Code (NEC).C. Underwriters Laboratories (UL)1.3 SUBMITTALSA. Product data for each type of product specified.1.4 QUALITY ASSURANCEA. Electrical Component Standard: Components and installation must comply withNFPA 70.B. Electrical components must be listed and labeled by UL or other approved,nationally recognized testing and listing agency that provides third-partycertification follow-up services.PART 2 - PRODUCTS2.1 COATINGSA. Coating: Supports, support hardware, and fasteners must be protected with zinccoating or with treatment of equivalent corrosion resistance using approvedPage 171 of 190


VESDA FIRE ALARM SYSTEM UPGRADE PROJECT NOVEMBER, 2010NEW YORK AIR ROUTE TRAFFIC CONTROL CENTER (ZNY) (REVISED AUGUST, 2011)RONKONKOMA, NEW YORKalternative treatment, finish, or inherent material characteristic. Products for useoutdoors must be hot-dip galvanized.2.2 MANUFACTURED SUPPORTING DEVICESA. Raceway Supports: Clevis hangers, riser clamps, conduit straps, threadedC-clamps with retainers, ceiling trapeze hangers, wall brackets, and spring steelclamps.B. Fasteners: Types, materials, and construction features as follows:1. Expansion Anchors: Carbon steel wedge or sleeve type.2. Toggle Bolts: All steel springhead type.3. Powder Actuated fasteners: Not Allowed.C. U-Channel Systems: 16-gage steel channels, with 9/16-inch-diameter holes, at aminimum of 8 inches on center, in top surface. Provide fittings and accessoriesthat mate and match with U-channel and are of the same manufacture.D. Fasteners for plastic-laminated and metal signs: Self-tapping stainless steelscrews or No. 10/32 stainless steel machine screws with nuts and flat end lockwashers.E. Provide steel channel supports with 9/16-inch diameter holes at a maximum of 8inches on center, in at least 1 surface.1. Fittings and accessories to mate and match with channels and to be fromsame manufacturer.2.3 FABRICATED SUPPORTING DEVICESA. General: Shop- or field-fabricated supports or manufactured supports assembledfrom U-channel components.B. Steel Brackets: Fabricated of angles, channels, and other standard structuralshapes. Connect with welds and machine bolts to form rigid supports.C. Pipe Sleeves: ASTM A53, Type E, Grade A, Schedule 40, galvanized steel,plain ends.1. Sheet Metal: Fabricate from galvanized sheet metal; round tube closed withwelded spiral seams or welded longitudinal joint. Fabricate sleeves from thefollowing gage metal for sleeve diameter noted:Page 172 of 190


VESDA FIRE ALARM SYSTEM UPGRADE PROJECT NOVEMBER, 2010NEW YORK AIR ROUTE TRAFFIC CONTROL CENTER (ZNY) (REVISED AUGUST, 2011)RONKONKOMA, NEW YORKa. 3-inch and smaller: 20-gage.b. 4-inch to 6-inch: 16-gage.c. over 6-inch: 14-gage.2. Steel Pipe: Fabricate from Schedule 40 galvanized steel pipe.D. Supplementary Structural Supports: ASTM A36 steel shapes1. Supports and supporting devices must be designed and installed to withstandthe local code equivalent of a minimum UBC Seismic Zone 2B force.2. Provide the installation of supplementary structural supports required forattachment of hangers and other devices supporting electrical equipment andconduits.3. Members welded to main structural members must be equal to thespecification for the main structural member.4. Size support members for their actual loads and safety factors withoutexcessive deflection and with consideration for rigidity under vibration.PART 3 - EXECUTION3.1 INSTALLATIONA. Install supporting devices to fasten electrical components securely andpermanently in accordance with NEC requirements.B. Coordinate with the building structural system and with other electricalinstallation.C. Raceway Supports: Comply with the NEC and the following requirements:1. Conform to manufacturer's recommendations for selection and installationof supports.2. Strength of each support must be adequate to carry design load plus 25percent for future use, multiplied by a safety factor of at least four. Wherethis determination results in a safety allowance of less than 200 lb., provideadditional strength until there is a minimum of 200 lb. safety allowance inthe strength of each support.3. Install individual and multiple (trapeze) raceway hangers and riser clamps asnecessary to support raceways. Provide U-bolts, clamps, attachments, andPage 173 of 190


VESDA FIRE ALARM SYSTEM UPGRADE PROJECT NOVEMBER, 2010NEW YORK AIR ROUTE TRAFFIC CONTROL CENTER (ZNY) (REVISED AUGUST, 2011)RONKONKOMA, NEW YORKother hardware necessary for hanger assembly and for securing hanger rodsand conduits.4. Support parallel runs of horizontal raceways together on trapeze-typehangers.5. Support individual horizontal raceways by separate pipe hangers. Springsteel fasteners may be used in lieu of hangers only for 1-1/2-inch and smallerraceways serving lighting and receptacle branch circuits above suspendedceilings only. For hanger rods with spring steel fasteners, use1/4-inch-diameter or larger threaded steel. Use spring steel fasteners that arespecifically designed for supporting single conduits or tubing.6. Space supports for raceways in accordance with Table I of section 16100.Space supports for raceway types not covered by the above in accordancewith NEC.7. Support exposed and concealed raceway within 1 foot of an unsupportedbox and access fittings. In horizontal runs, support at the box and accessfittings may be omitted where box or access fittings are independentlysupported and raceway terminals are not made with chase nipples orthreadless box connectors.8. In vertical runs, arrange support so the load produced by the weight of theraceway and the enclosed conductors is carried entirely by the conduitsupports with no weight load on raceway terminals.9. Neither raceways nor boxes must be fastened to suspended ceiling supports.D. Miscellaneous Supports: Support miscellaneous electrical components asrequired to produce the same structural safety factors as specified for racewaysupports. Install metal channel racks for mounting cabinets, panelboards,disconnects, control enclosures, pull boxes, junction boxes, transformers, andother devices.E. In open overhead spaces, cast boxes threaded to raceways need not be supportedseparately except where used for fixture support; support sheet metal boxesdirectly from the building structure or by bar hangers. Where bar hangers areused, support the bar hanger from the building structure, not on the ceiling crossmembers.1. Cast metal boxes having threadless connectors and sheet-metal boxes mustbe supported directly from the building structure or by bar hangers.F. Sleeves: Install in concrete slabs and walls and all other fire- rated floors andwalls for raceways and cable installations. For sleeves through fire rated-wall orfloor construction, apply UL- listed fire stopping sealant in gaps betweenPage 174 of 190


VESDA FIRE ALARM SYSTEM UPGRADE PROJECT NOVEMBER, 2010NEW YORK AIR ROUTE TRAFFIC CONTROL CENTER (ZNY) (REVISED AUGUST, 2011)RONKONKOMA, NEW YORKsleeves and enclosed conduits and cables in accordance with requirement ofSection 07840 “Through-Penetration Fire stopping Systems.”G. Fastening: Unless otherwise indicated, fasten electrical items and theirsupporting hardware securely to the building structure, including but not limitedto conduits, raceways, cables, cable trays, busways, cabinets, panelboards,transformers, boxes, disconnect switches, lighting fixtures, and controlcomponents in accordance with the following:1. Fasten by means of wood screws, carriage bolts, or lag screws of equalholding strength on wood; toggle bolts on hollow masonry units; concreteinserts or expansion bolts on concrete or solid masonry; and machinescrews, or spring-tension clamps on steel. Do not weld conduit, pipe straps,to steel structures. In partitions of light steel construction, use sheet metalscrews.2. Holes cut to depth of more than 1-1/2 inches in reinforced concrete beams orto depth of more than 3/4 inch in concrete must not cut the main reinforcingbars. Patch holes that are not used with like and kind materials.3. Coordinate any cutting or boring of structural beams with StructuralEngineer prior to any work being done.4. Ensure that the load applied to any fastener does not exceed 25 percent ofthe proof test load. Use vibration- and shock- resistant fasteners forattachments to concrete slabs.5. Coordinate with structural engineer on expansion joints used to supportraceways.H. Tests: Test pull-out resistance of one of each type, size, and anchorage materialfor the following fastener types:1. Expansion anchors.2. Toggle bolts.I. Provide all jacks, jigs, fixtures, and calibrated indicating scales required forreliable testing. Obtain the structural Engineer's approval before transmittingloads to the structure. Test to 90 percent of rated proof load for fastener. Iffastening fails test, revise all similar fastener installations and retest untilsatisfactory results are achieved.END OF SECTION 16190Page 175 of 190


VESDA FIRE ALARM SYSTEM UPGRADE PROJECT NOVEMBER, 2010NEW YORK AIR ROUTE TRAFFIC CONTROL CENTER (ZNY) (REVISED AUGUST, 2011)RONKONKOMA, NEW YORKSECTION 16195 - ELECTRICAL IDENTIFICATIONPART 1 - GENERAL1.1 SUMMARYA. This Section includes identification of electrical materials, equipment, andinstallations.1.2 REFERENCE STANDARDSA. Applicable only to the extent specified.B. American National Standards Institute (ANSI)1. A 13.1: Scheme for the Identification of Piping Systems.2. C2: National Electrical Safety Code.C. <strong>Federal</strong> <strong>Aviation</strong> <strong>Administration</strong> (FAA)1. FAA-C-1217f : Electrical Work, Interior.D. National Fire Protection Association (NFPA)1. 70: 2008 National Electrical Code (NEC).1.3 SUBMITTALSA. Components and installation must comply with NFPA 70.B. Comply with requirements of ANSI standard A13.1, with regard to typeand size of lettering for raceway and cable labels.C. Samples for each color, lettering style, and other graphic representationrequired for tubing, tags, labels, markers, and other identification materials; samples oflabels and signs.D. Shop drawings showing installation method for each type of identificationdevice.1.4 QUALITY ASSURANCEPage 176 of 190


VESDA FIRE ALARM SYSTEM UPGRADE PROJECT NOVEMBER, 2010NEW YORK AIR ROUTE TRAFFIC CONTROL CENTER (ZNY) (REVISED AUGUST, 2011)RONKONKOMA, NEW YORKA. Components and installation must comply with NFPA 70.Comply with the requirements of ANSI A13.1 with regard to type and sizeof lettering for raceway and cable labels.1.5 SEQUENCING AND SCHEDULINGA. Coordinate installing electrical identification after completion of finishingwhere identification is applied to field-finished surfaces.B. Coordinate installing electrical identifying devices and markings prior toinstalling acoustical ceilings and similar finishes that conceal such items.PART 2 - PRODUCTS2.1 RACEWAY AND CABLE LABELSA. Manufacturer's Standard Products: Where more than one type is listed fora specified application, selection is Installer’s option, but provide single type for eachapplication category. Use colors prescribed by ANSI A13.1, NFPA 70, and these<strong>Specifications</strong>.B. Conform to ANSI A13.1, Table 3, for minimum size of letters for legendand minimum length of color field for each raceway or cable size.1. Color: Black legend on orange field.2. Legend: Indicates voltage and service.C. Adhesive Labels: Preprinted, flexible, self-adhesive vinyl. Legendoverlaminated with clear, weather- and chemical-resistant coating.D. Heat Shrink Tubing: Preprinted, embossed, permatized, 20-year life. Sizeto suit conductors; lettering must be legible after heat shrinking.E. Pretensioned, Wraparound Plastic Sleeves: Flexible, preprinted, colorcoded,acrylic bands sized to suit the diameter of the line it identifies and arranged to stayin place by pretensioned gripping action when placed in position.F. Colored Adhesive Tape: Self-adhesive vinyl tape not less than 3 mils thickby 1 inch wide.G. Tape Markers: Vinyl or vinyl-cloth, self-adhesive, wraparound type withpre-printed numbers and letters.Page 177 of 190


VESDA FIRE ALARM SYSTEM UPGRADE PROJECT NOVEMBER, 2010NEW YORK AIR ROUTE TRAFFIC CONTROL CENTER (ZNY) (REVISED AUGUST, 2011)RONKONKOMA, NEW YORKH. Plasticized Card-stock Tags: Vinyl cloth with pre-printed legends. Orangebackground, except as otherwise indicated, with eyelet for fasteners.I. Brass Tags: Metal tags with stamped legend, punched for fasteners.Dimensions: 2 inches by 2 inches by 0.05 inch.2.2 ENGRAVED NAMEPLATES AND SIGNSA. Manufacturer's Standard Products: Where more than one type is listed fora specified application, selection is Installer's option, but provide single type for eachapplication category. Use colors prescribed by ANSI A13.1, NFPA 70, and these<strong>Specifications</strong>.B. Engraving Stock: melamine plastic laminate, 1/16-inch minimum thick forsigns up to 20-sq. in., 1/8 inch thick for larger sizes.1. Engraved Legend: White letters on black field.2. Punched for mechanical fasteners.C. Interior Warning and Caution Signs: Pre-printed aluminum, baked enamelfinish with 1/4-inch grommets in corners for mounting.1. Color, size and legend: appropriate to the application.2. Punched for fasteners.D. Exterior, Metal-Backed, Butyrate Signs: Weather-resistant, non-fading,preprinted, cellulose acetate butyrate signs with 0.0396-inch, galvanized steel backing,with colors, legend, and size appropriate to the application. 1/4-inch grommets in cornersfor mounting.E. Fasteners for Plastic-Laminated and Metal Signs: Self-tapping stainlesssteelscrews or No. 10/32 stainless-steel machine screws with nuts and flat and lockwashers.2.3 MISCELLANEOUS IDENTIFICATION PRODUCTSA. Cable Ties: Fungus-inert, self-extinguishing, 1-piece, self-locking,Type 6/6-nylon cable ties with the following features:1. Minimum Width: 3/16 inch.2. Tensile Strength: 50-lb. minimum.3. Temperature Range: Minus 40 to 185 deg F.4. Color: As indicated where used for color-coding.Page 178 of 190


VESDA FIRE ALARM SYSTEM UPGRADE PROJECT NOVEMBER, 2010NEW YORK AIR ROUTE TRAFFIC CONTROL CENTER (ZNY) (REVISED AUGUST, 2011)RONKONKOMA, NEW YORKB. Paint: Alkyd-urethane enamel over primer as recommended by enamelmanufacturer.PART 3 - EXECUTION3.1 INSTALLATIONA. Install identification devices according to manufacturer's writteninstructions.B. Install labels where indicated and at locations for best convenience ofviewing without interference with operation and maintenance of equipment.C. Lettering, Colors, and Graphics: Coordinate names, abbreviations, colors,and other designations used for electrical identification with corresponding designationsused in the <strong>Contract</strong> Documents or required by codes and standards. Use consistentdesignations throughout the Project.D. Sequence of Work: Where identification is to be applied to surfaces thatrequire finish, install identification after completion of finish work.E. Self-Adhesive Identification Products: Clean surfaces of dust, loosematerial, and oily films before applying.F. Install painted identification as follows:1. Clean surfaces of dust, loose material, and oily films beforepainting.2. Prime Surfaces: For galvanized metal, use single-component,acrylic vehicle coating formulated for galvanized surfaces. For concrete masonry units,use heavy-duty, acrylic-resin block filler. For concrete surfaces, use clear, alkaliresistant,alkyd binder-type sealer.3. Apply one intermediate and one finish coat of silicone alkydenamel.4. Apply primer and finish materials according to manufacturer'sinstructions.G. Refer to Section 13850, “Fire Alarm and Detection System” foridentification painting for fire alarm conduit and associated system.H. Identify Raceways with Color Banding: Band exposed and accessibleraceways of the systems listed below for identification.Page 179 of 190


VESDA FIRE ALARM SYSTEM UPGRADE PROJECT NOVEMBER, 2010NEW YORK AIR ROUTE TRAFFIC CONTROL CENTER (ZNY) (REVISED AUGUST, 2011)RONKONKOMA, NEW YORK1. Bands: Pretensioned, snap-around, colored plastic sleeves; coloredadhesive tape; or a combination of both. Make each color band 2 inches wide,completely encircling conduit, and place adjacent bands of 2-color markings in contact,side by side.2. Locate bands at changes in direction, at penetrations of walls andfloors, at 50-foot maximum intervals in straight runs, and at 25 feet in congested areas.3. Colors: As follows:and yellow.blue.a) Fire-Alarm System: Red.b) Fire-Suppression Supervisory and Control System: Redc) Security System: Blue and yellow.d) Mechanical and Electrical Supervisory System: Green ande) Telecommunications System: Green and yellow.I. Install Circuit Identification Labels on Boxes, Wall Switches andReceptacle Outlets: Label externally as follows:1. Exposed Boxes: Pressure-sensitive, self-adhesive plastic label oncover.2. Concealed Boxes: Plasticized card-stock tags.3. Labeling Legend: Permanent, waterproof listing of panel andcircuit number or equivalent.4. Receptacles and Wall Switches: Identify the panelboardand circuit number from which served. Use machine-printed, pressuresensitive,abrasion-resistant label tape on both faces of plate and durable wiremarkers or tags within outlet boxes.J. Color-Code Conductors: The following field-applied color-codingmethods may be used in lieu of factory-coded wire listed in Section 16120 “Wires andCables” for sizes larger than No. 4 AWG. <strong>Contract</strong>or must demonstrate non-availabilityof factory colored wire before using this application.1. Colored, pressure-sensitive plastic tape in half-lapped turns for adistance of 6 inches from terminal points and in boxes where splices or taps are made.Apply the last 2 turns of tape with no tension to prevent possible unwinding. Use 1-inchwidetape in colors as specified. Adjust tape bands to avoid obscuring cableidentification markings.a. Where conductors are color coded by this method, theymust be color coded in accessible raceways, panelboards, outlets, and switches, as well asPage 180 of 190


VESDA FIRE ALARM SYSTEM UPGRADE PROJECT NOVEMBER, 2010NEW YORK AIR ROUTE TRAFFIC CONTROL CENTER (ZNY) (REVISED AUGUST, 2011)RONKONKOMA, NEW YORKat all terminations. Conductors in accessible raceways must be color coded so that byremoving or opening any cover, the coding will be visible.b. Phase, ground, and neutral conductors must be color codedin accordance with Section 16120, “Wires and Cables.”2. Green insulated conductors must not be re-identified for purposesother than grounding.3. White or neutral gray conductors must not be re-identified forpurposes other than grounded neutrals.K. Apply identification to conductors as follows:1. Conduits and Conductors to Be Extended in the Future: Indicatesource and circuit numbers.2. Power and Lighting Circuits at Enclosure and at terminations:Identify each conductor with panel designation, circuit number, voltage, and phase.3. Control and Communications Circuits at Enclosure and atterminations: Identify each conductor by its system and circuit designation. Use aconsistent system of tags, color-coding, or cable marking tape.L. Apply warning, caution, and instruction signs and stencils as follows:1. Install warning, caution, and instruction signs where indicated orrequired to ensure safe operation and maintenance of electrical systems and of items towhich they connect. Install engraved plastic-laminated instruction signs with approvedlegend where instructions or explanations are needed for system or equipment operation.2. Emergency-Operating Signs: Install engraved laminate signs withwhite legend on red background with minimum 3/8-inch-high lettering for emergencyinstructions on power transfer, and other emergency operations.M. Install identification as follows:1. Apply equipment identification labels of engraved plastic laminateon each major unit of equipment, including central or master unit of each system. Thisincludes communication, signal, and alarm systems, unless units are specified with theirown self-explanatory identification. Provide equipment, required under Division 16, asfollows: with nameplate indicating equipment name, system voltage(s) and phase. Exceptas otherwise indicated, provide a single line of text with 1/2-inch-high lettering on 1-1/2-inch-high label; where 2 lines of text are required, use 2-inch-high label. Apply labels foreach unit of the following categories of equipment:a) Panelboards, electrical cabinets, and enclosures.b) Access doors and panels for concealed electrical items.c) Motor starters.Page 181 of 190


VESDA FIRE ALARM SYSTEM UPGRADE PROJECT NOVEMBER, 2010NEW YORK AIR ROUTE TRAFFIC CONTROL CENTER (ZNY) (REVISED AUGUST, 2011)RONKONKOMA, NEW YORKd) Control devices.e) Dimming panels2. Label conduit at each end and at pull boxes with characters aminimum 1/4-inch high.3. Apply designation labels of engraved plastic laminate fordisconnect switches, breakers, push buttons, pilot lights, and similar items for powerdistribution and control components above, except panelboards and alarm/signalcomponents where labeling is specified elsewhere. For panelboards, provide framed,typed circuit schedules with explicit description and identification of items controlled byeach individual breaker.END OF SECTION 16195Page 182 of 190


VESDA FIRE ALARM SYSTEM UPGRADE PROJECT NOVEMBER, 2010NEW YORK AIR ROUTE TRAFFIC CONTROL CENTER (ZNY) (REVISED AUGUST, 2011)RONKONKOMA, NEW YORKSECTION 16452 - GROUNDINGPART 1 - GENERAL1.1 SUMMARYA. This Section includes solid grounding of electrical systems and equipment andbasic requirements for grounding for protection of life, equipment, circuits, andsystems. Grounding requirements specified in this Section may be supplementedin other Sections of these <strong>Specifications</strong>.B. Related Sections in addition to Division 16:1. Division 13850, “Fire Alarm and Detection Systems” contains therequirements that relate to this Section.2. Division 13900, “Fire Suppression Sprinkler System” contains therequirements that relate to this Section.3. Division 15900, “Control Systems – Electronic And Direct DigitalControl” contains the requirement that relate to this Section.1.2 REFERENCE STANDARDSA. American Society for Testing and Materials (ASTM)1. B3: Soft or Annealed Copper Wire.2. B8: Concentric-Lay-Stranded Copper Conductors, Hard, Medium Hard, orSoft.3. B33: Tinned Soft or Annealed Copper Wire for Electrical Purposes.B. <strong>Federal</strong> <strong>Aviation</strong> <strong>Administration</strong> (FAA)1. FAA-C-1217f Electrical Work, Interior.2. FAA STD-019e: Lightning Protection, Grounding, Bonding and ShieldingRequirements for Facilities.C. Institute of Electrical and Electronic Engineers (IEEE)1. 81: Guide for Measuring Earth Resistivity, Ground Impedance, andEarth Surface Potentials of a Ground System.Page 183 of 190


VESDA FIRE ALARM SYSTEM UPGRADE PROJECT NOVEMBER, 2010NEW YORK AIR ROUTE TRAFFIC CONTROL CENTER (ZNY) (REVISED AUGUST, 2011)RONKONKOMA, NEW YORK2. 1100: Powering and grounding sensitive electronic equipment.D. InterNational Electrical Testing Association (NETA)E. National Fire Protection Association (NFPA)1. 70: 2008 National Electrical Code (NEC).2. 780: Lightning Protection Code.F. Occupational Safety and Health <strong>Administration</strong> (OSHA)1. 29CFR 1910.7: Definitions and requirements for Nationally RecognizedTesting Laboratories (NRTL).G. Underwriters Laboratories (UL)1. 486A: Wire Connectors and Soldering Lugs for Use with CopperConductors.2. 467: Grounding and Bonding Equipment.1.3 SUBMITTALSA. Product data for connectors and connection materials, and grounding fittings.B. Qualification data for firms and persons specified in "Quality Assurance"Article to demonstrate their capabilities and experience. Include lists ofcompleted projects with project names and addresses, names and addresses ofarchitects and owners, and other information specified.C. Field tests and observation reports certified by the testing organization andindicating and interpreting the test reports for compliance with performancerequirements.1.4 QUALITY ASSURANCEA. Testing Agency Qualifications: A NRTL as defined in OSHA Regulation1910.7, or a full member company of NETA.1. Testing Agency Field Supervision: Use persons currently certified byNETA or the National Institute for Certification in EngineeringTechnologies to supervise on-site testing specified in Part 3.Page 184 of 190


VESDA FIRE ALARM SYSTEM UPGRADE PROJECT NOVEMBER, 2010NEW YORK AIR ROUTE TRAFFIC CONTROL CENTER (ZNY) (REVISED AUGUST, 2011)RONKONKOMA, NEW YORKB. Comply with NFPA 70, National Electrical Code.C. Comply with UL 467.D. Listing and Labeling: Provide products specified in this Section that are listedand labeled.1. The Terms "Listed" and "Labeled": As defined in the National ElectricalCode, Article 100.2. Listing and Labeling Agency Qualifications: A NRTL as defined in OSHARegulation 1910.7.PART 2 - PRODUCTS2.1 MANUFACTURERSA. Manufacturers: Subject to compliance with requirements, provide products byone of the following:1. Erico Inc.; Electrical Products Group.2. ILSCO.3. Kearney.4. Salisbury: W.H. Salisbury & Co.5. Thomas & Betts, Electrical.6. Utilco Co.2.2 WIRE AND CABLE GROUNDING CONDUCTORSA. Comply with Section 16120, "Wires and Cables." Conform to NEC Table 8,except as otherwise indicated, for conductor properties, including stranding.1. Material: Copper. Use only copper wire for both insulated and baregrounding conductors in direct contact with earth, concrete, masonry,crushed stone and similar materials.2. Size: Minimum allowable size must not be less than #12 AWG, in additionto compliance with NEC.B. Equipment Grounding Conductors: Insulated with green color insulation andmust be the same size as the associated phase conductors.Page 185 of 190


VESDA FIRE ALARM SYSTEM UPGRADE PROJECT NOVEMBER, 2010NEW YORK AIR ROUTE TRAFFIC CONTROL CENTER (ZNY) (REVISED AUGUST, 2011)RONKONKOMA, NEW YORKC. Bare Copper Conductors: Conform to the following:1. Solid Conductors: ASTM B3.2. Assembly of Stranded Conductors: ASTM B8.3. Tinned Conductors: ASTM B33.2.3 MISCELLANEOUS CONDUCTORSA. Braided Bonding Jumpers: Where electrical continuity across the shock mountsis necessary, bonding jumpers must be installed across each shock mount.Jumpers of this application should have a maximum thickness of 0.025 inch, sothat the damping efficiency of the mount is not impaired. In severe shock andvibration environments, solid straps may be corrugated, or flexible wire braidmay be used. Braids are to be terminated with copper ferrules.B. Raceway Bonding Jumpers: Copper, minimum size #6 AWG unless otherwisenoted.2.4 CONNECTOR PRODUCTSA. Exothermic-Welded Connections: Provided in kit form and selected permanufacturers written instructions for specific types, sizes, and combinations ofconductors and connected items. exothermic welds in the FAA occupied areasmust be low odor and smokeless products.2.5 POWER DISTRIBUTION SYSTEM GROUNDINGA. The facility electrical grounding must comply with the National Electric Code(NEC). The Electronic Grounding Systems must not replace or be used in lieu ofthe Power Distribution System grounding conductors.2.6 GROUND STRAPA. Provide a flexible ground strap, #6 AWG or braided equal, for electricalcontinuity at each flexible duct connection of each air handler, and fan.PART 3 – EXECUTION3.1 APPLICATIONPage 186 of 190


VESDA FIRE ALARM SYSTEM UPGRADE PROJECT NOVEMBER, 2010NEW YORK AIR ROUTE TRAFFIC CONTROL CENTER (ZNY) (REVISED AUGUST, 2011)RONKONKOMA, NEW YORKA. General: FAA grounding requirements often exceed those of NEC; therefore,grounding system must be as indicated in <strong>Contract</strong> Drawings, and as specifiedherein.B. Equipment Grounding Conductors: All metallic non-current carrying parts ofelectrical equipment must be grounded with equipment grounding conductorswhether or not shown on the drawings. Equipment grounding conductors mustbe green insulated copper conductors unless otherwise indicated. Minimum sizeequipment grounding conductors for grounding raceway and equipment must bethe same size as the associated phase conductors. In no case, however, mustthese conductors be smaller than No. 12 AWG.1. Install green, equipment grounding conductor with all feeder and branchcircuit conductors.2. Busway Supply Circuits: Install separate green, equipment groundingconductor from the grounding bus in the switchgear, switchboard, ordistribution panel to equipment grounding-bar terminal on busway.3. Computer Outlet Circuits: Install separate equipment grounding conductorin branch circuit runs from power panels serving computer loads or powerdistribution units.4. Air-Duct Equipment Circuits: Install an equipment grounding conductor toduct-mounted electrical devices operating at 120 V and above, including aircleaners and heaters. Bond conductor to each unit and to air duct.C. Conduit or cable shields must not be used as the equipment groundingconductor.D. Separately Derived System Grounding Electrode Conductor: bare or insulatedcopper installed in metal raceway. Both ends of the raceway must by bonded.3.2 INSTALLATIONA. General: The grounding requirements exceed those of the NEC. Groundingsystem must be as indicated on the contract drawings and as specified herein.Reference IEEE-1100-1999, “Recommended Practice for Powering andGrounding Sensitive Electronic Equipment,” when installing equipment. In nocase must the NEC be violated.B. Grounding Conductor: Use of a shared/common ground is not permitted. Eachovercurrent protection device must have its own separate grounding conductor.Page 187 of 190


VESDA FIRE ALARM SYSTEM UPGRADE PROJECT NOVEMBER, 2010NEW YORK AIR ROUTE TRAFFIC CONTROL CENTER (ZNY) (REVISED AUGUST, 2011)RONKONKOMA, NEW YORKC. Route grounding conductors along the shortest and straightest paths possible,except as otherwise indicated. Avoid obstructing access or placing conductorswhere they may be subjected to strain, impact, or damage.D. Equipment Enclosure Grounding: Bare wire, wrapped around connectingscrews or mounting bolts and screws is not acceptable as a groundingconnection. All ground lugs must be of a noncorrosive material suitable for useas a grounding connection, and must be compatible with the type of metal beinggrounded. Ground lugs must be mounted on clean, bare metal surfaces that arefree of paint, rust, etc.E. Raceway Grounding: Surface metal raceways, wireways, or cable rack systemsmust be installed in a manner that ensures electrical continuity, or short barecopper bonding jumpers must be installed between adjacent raceway sections toensure proper bonding. Unless otherwise indicated, the minimum size for thesebonding jumpers must be No. 6 AWG.F. Fault Protection: Prevent equipment parts subject to human contact duringoperation and maintenance from being electrically energized when poweringfaults or components fail. Ground parts with a low impedance path to thechassis or cabinets in which they are mounted.3.3 CONNECTIONSA. General: Make connections so possibility of galvanic action or electrolysis isminimized. Select connectors, connection hardware, conductors, andconnection methods so metals in direct contact will be galvanically compatible.1. Use electroplated or hot-tin-coated materials to assure high conductivity andto make contact points closer in order of galvanic series.2. Make connections with clean, bare metal at points of contact.3. Coat and seal connections having dissimilar metals with inert material toprevent future penetration of moisture to contact surfaces.B. Exothermic-Welded Connections: Use for connections to structural steel and forgrounding electrode conductor. Comply with manufacturers writteninstructions. Welds that are puffed up or that show convex surfaces indicatingimproper cleaning are not acceptable. Indoor exothermic welds must be lowodor and smokeless type.Page 188 of 190


VESDA FIRE ALARM SYSTEM UPGRADE PROJECT NOVEMBER, 2010NEW YORK AIR ROUTE TRAFFIC CONTROL CENTER (ZNY) (REVISED AUGUST, 2011)RONKONKOMA, NEW YORKC. Terminate insulated equipment grounding conductors for feeders with pressuretypegrounding lugs. Where metallic raceways terminate at non-metallic or nonconductivehousings, terminate each conduit with a grounding bushing. Connectgrounding bushings with a bare grounding conductor to the ground bus in thehousing. Bond electrically non-continuous conduits at both entrances and exitswith grounding bushings and bare grounding conductors .D. Raceway Grounding: Surface metal raceways, wireways, or cable rack systemsmust be installed in a manner that assures electrical continuity. Insulated copperbonding jumpers must be installed between adjacent raceway sections to assureproper bonding. Uninsulated conductors must not be used. Unless otherwiseindicated, the minimum size for these bonding jumpers must be No. 6 AWG.E. Tighten grounding and bonding connectors and terminals, including screws andbolts, in accordance with torque tightening values specified in UL 486A.F. Compression-Type Connections: Use hydraulic compression tools to providecorrect circumferential pressure for compression connectors. Mechanicalconnections using a Burndy “Hyground Connector” or equipment whenoperated at a force of 24,000 pounds are acceptable as FAA approved pressureconnectors. Provide embossing die code or other standard method to make avisible indication that a connector has been adequately compressed on groundconductor. Hydraulically crimped connectors are not acceptable in a lightningprotection system.3.4 SYSTEM AND EQUIPMENT GROUNDINGA. Install a grounding conductor for each overcurrent device. The equipmentgrounding conductor must be installed in the same conduit as the branch orfeeder conductors. Grounding conductor must have insulation rating equivalentto phase conductor insulation. Insulated grounding conductors must beconnected to the ground terminal at both ends and to junction, transition, pulland fixtures boxes along the route. Under no circumstances must this conductorbe omitted from the electrical system, nor must a separate grounding system,such as the signal grounding, be used as a substitute.B. Metallic raceway housing the equipment grounding conductor must bemechanically and electrically continuous.Page 189 of 190


VESDA FIRE ALARM SYSTEM UPGRADE PROJECT NOVEMBER, 2010NEW YORK AIR ROUTE TRAFFIC CONTROL CENTER (ZNY) (REVISED AUGUST, 2011)RONKONKOMA, NEW YORKC. Where there are parallel conductors of a feeder installed in more than oneraceway, install an equipment grounding conductor in each raceway.D. Ground the ends of all conduit runs using grounding bushings, except forreceptacle and lighting branch circuits.E. Splices of grounding conductors inside conduits are not acceptable.F. Control wiring conduits, raceways without a separate equipment groundingconductor must be bonded to the multi-point grounding system at every fifty feetintervals.3.5 FIELD QUALITY CONTROLA. Bolting Resistance: Spot test to verify that ground cable bolted connectionshave a DC resistance of one milliohm maximum, when measured with a bridgetype milliohmeter or similar instrument.B. Continuity: Test grounding conductors, sheet metal, metallic conduits,equipment enclosure, metallic enclosures, and lighting fixtures for continuity togrounding system.END OF SECTION 16452Page 190 of 190

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!