Project Manager Hannu Kuikka following theerection of a 110 kilovolt transmission linetower south of Hyvinkää in early June.Nurmijärvi–Hyvinkää–Hikiätransmission line project in brief• total project budget 13.5 million euros• schedule• completed in September 2013• foundation work Jan <strong>2012</strong> to Feb 2013• 110 kV installation work Apr <strong>2012</strong> to Jun 2013• 400 kV installation work Jan 2013 to Sep 2013• dismantling work in Metsäkalteva areaSep 2013 to Oct 2013FINGRID 2/<strong>2012</strong> | 8