LIPA METERED SERVICE THE FOLLOWING 2 ONE-LINE SCHEMATICS OUTLINE THE CONNECTIONS LIPA WILL ALLOW FOR THE INTERCONNECTION OF OPTIONAL STANDBY SYSTEM EQUIPMENT. THE INTENT OF THE INTERCONNECTION SCHEMES IS TO PREVENT BOTH BACKFEED INTO THE LIPA ELECTRIC DISTRIBUTION SYSTEM, AND UNINTENTIONAL PARALLEL OPERATION WITH AN ENERGIZED LIPA SYSTEM. IMPROPER PARALLEL OPERATION CAN RESULT IN SERIOUS DAMAGE TO THE GENERATOR, THE LIPA DISTRIBUTION SYSTEM, OR BOTH, AND BE A SAFETY HAZARD TO PERSONNEL. MAIN DISCONNECT NOTE: CUSTOMER'S METERING EQUIPMENT MUST BE PLACARDED THAT A GENERATOR IS PRESENT LIPA METERED SERVICE TO ENTIRE LOAD GENERATOR PROTECTIVE CIRCUIT BREAKER DOUBLE THROW SWITCH FIG. 1: STANDBY GENERATOR FOR ENTIRE LOAD. MAIN DISCONNECT NOTE: CUSTOMER'S METERING EQUIPMENT MUST BE LOADS NOT BACKED UP BY GENERATOR PLACARDED THAT A GENERATOR IS PRESENT STANDBY LOAD GENERATOR PROTECTIVE CIRCUIT BREAKER DOUBLE THROW SWITCH FIG. 2: STANDBY GENERATOR FOR PARTIAL LOADS OPTIONAL STANDBY SYSTEMS D35 Section 11 - Drawings G GENERATOR G GENERATOR

2012 Edition Redbook 12.0 SECONDARY NETWORK AREAS NOTES TO CONTRACTORS Before commencing work in any of the towns on the next page, see the appropriate map to determine if the work location is in the proximity of a secondary network area. If so, contact the appropriate Distribution Design Office to determine if there are any special construction requirements. The maps indicate certain areas which are secondary “NETWORK” areas. IN ALL OF THE NETWORK AREAS, ONLY COPPER CONDUCTORS MAY BE INSTALLED. IMPORTANT NOTICE To avoid any misunderstanding, complete specifications and voltage characteristics must be obtained from the appropriate Distribution Design Department division office before planning or starting any work in any of these areas. 75

2012 Edition <strong>Red</strong>book<br />

12.0 SECONDARY NETWORK AREAS<br />

NOTES TO CONTRACTORS<br />

Before commencing work in any of the towns on the next page, see the appropriate map to determine if the<br />

work location is in the proximity of a secondary network area. If so, contact the appropriate Distribution<br />

Design Office to determine if there are any special construction requirements.<br />

The maps indicate certain areas which are secondary “NETWORK” areas.<br />

IN ALL OF THE NETWORK AREAS, ONLY COPPER CONDUCTORS MAY BE INSTALLED.<br />

IMPORTANT NOTICE<br />

To avoid any misunderstanding, complete specifications and voltage characteristics must be obtained from<br />

the appropriate Distribution Design Department division office before planning or starting any work in any of<br />

these areas.<br />