11.07.2015 Views

Asphalt Overlay of CDC Roads - Clark Freeport Zone

Asphalt Overlay of CDC Roads - Clark Freeport Zone

Asphalt Overlay of CDC Roads - Clark Freeport Zone

SHOW MORE
SHOW LESS

You also want an ePaper? Increase the reach of your titles

YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.

43.2. A Change Order may be issued by the implementing <strong>of</strong>ficial to coverany increase/decrease in quantities <strong>of</strong> original Work items in thecontract. Change Orders resulting from design errors, omissions ornon-conformance with the performance specifications and parametersand contract documents by the contractor shall be implemented by thecontractor at no additional cost to the procuring entity.43.3. An Extra Work Order may be issued by the implementing <strong>of</strong>ficial tocover the introduction <strong>of</strong> new work necessary for the completion,improvement or protection <strong>of</strong> the project which were not included asitems <strong>of</strong> Work in the original contract, such as, where there aresubsurface or latent physical conditions at the site differing materiallyfrom those indicated in the contract, or where there are duly unknownphysical conditions at the site <strong>of</strong> an unusual nature differing materiallyfrom those ordinarily encountered and generally recognized as inherentin the Work or character provided for in the contract.43.4. Any cumulative Variation Order beyond ten percent (10%) shall besubject <strong>of</strong> another contract to be bid out if the works are separablefrom the original contract. In exceptional cases where it is urgentlynecessary to complete the original scope <strong>of</strong> work, the Head <strong>of</strong> theProcuring Entity may authorize a positive Variation Order go beyondten percent (10%) but not more than twenty percent (20%) <strong>of</strong> theoriginal contract price, subject to the guidelines to be determined bythe GPPB: Provided, however, That appropriate sanctions shall beimposed on the designer, consultant or <strong>of</strong>ficial responsible for theoriginal detailed engineering design which failed to consider theVariation Order beyond ten percent (10%).43.5. In claiming for any Variation Order, the Contractor shall, within seven(7) calendar days after such work has been commenced or after thecircumstances leading to such condition(s) leading to the extra cost,and within twenty-eight (28) calendar days deliver a writtencommunication giving full and detailed particulars <strong>of</strong> any extra cost inorder that it may be investigated at that time. Failure to provide either<strong>of</strong> such notices in the time stipulated shall constitute a waiver by thecontractor for any claim. The preparation and submission <strong>of</strong> VariationOrders are as follows:(a)<strong>Clark</strong> Development CorporationIf the Procuring Entity’s representative/Project Engineer believesthat a Change Order or Extra Work Order should be issued, heshall prepare the proposed Order accompanied with the noticessubmitted by the Contractor, the plans therefore, hiscomputations as to the quantities <strong>of</strong> the additional worksinvolved per item indicating the specific stations where suchworks are needed, the date <strong>of</strong> his inspections and investigationsthereon, and the log book there<strong>of</strong>, and a detailed estimate <strong>of</strong>the unit cost <strong>of</strong> such items <strong>of</strong> work, together with his71Section IV General Conditions <strong>of</strong> the Contract<strong>Asphalt</strong> <strong>Overlay</strong> <strong>of</strong> <strong>CDC</strong> <strong>Roads</strong>

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!