Environmental Impacts of Multi-Storey Buildings Using Different ...
Environmental Impacts of Multi-Storey Buildings Using Different ... Environmental Impacts of Multi-Storey Buildings Using Different ...
- 78 -The Green Star NZ office design v 1.2 tool was developed for the design stage of officebuildings to evaluate the environmental initiatives and/or potential environmental impacts ofcommercial office base building designs.In Green Star, credits are awarded for certain activities. For example 1 point is awarded whereit can be demonstrated that the percentage of all steel in the design has a post-consumerrecycled content great than 60 % by mass, and 2 points for 90 % by mass. If the material costof steel represents less than 1 % of the project’s total contract value then this credit would be“not applicable”. Similarly 2 points are awarded where it is demonstrated that all timber andcomposite timber products are either post-consumer re-used timber or FSC certified timber ora combination thereof. In other categories points are awarded for land use, IEQ, transport etc(Figure 6.18).Figure 6.18: Green Star methodology (NZGBC 2008)All points are then weighted and summarised into a single score, where materials have acontribution of 10 % to the total score whereas energy has a contribution of 25 %. For allweightings see Table 6.12.Table 6.12: Weightings in Green Star toolManagement 10 %Indoor Environmental Quality 20 %Energy 25 %Transport 10 %Water 10 %Materials 10 %Land Use and Ecology 10 %Emissions 5 %100 %6.4.3 Research Approach for ComparisonDue to the differences in the scope of both tools, the comparison was restricted to thoseaspects which are taken into account in both tools, i.e. material use and energy use. Allfeatures of the buildings that are not strictly material or energy use related were therefore
- 79 -assumed to be identical for the four different building designs - Concrete, Steel, Timber andTimberPlus.Two scenarios were assessed in Green Star. A base scenario which took into account thedominant ‘core’ materials only, i.e. timber, steel and concrete only and a recycling scenariowhich is similar to the reutilisation scenario in the LCA study. Both Green Star scenarios areshown in Table 6.13. The justification for the credits is explained in section 6.4.3.1 for theGreen Star base scenario and in section 6.4.3.2 for the Green Star recycling scenario.6.4.3.1 Green Star Base ScenarioThe Green Star Base scenario took only the core materials of each building type into account,i.e. no points for concrete or steel were awarded in the Timber building. Otherwise the Timberbuilding would score credits for either steel or concrete whereas the intention was to analysethe credits awarded for the core materials of each building option only.Timber building• Not applicable (N/A) was ticked for recycled steel content and concrete contentrespectively although, according to the Green Star methodology N/A can only beticked if the material cost for steel or concrete respectively is less than 1 % of theproject’s total contract value.• Sustainable timber (FSC certified) was chosen for the timber option of the building.• Operational energy figure specific to the Timber building were included (73kWh/m 2 /yr metered electricity and 15 kWh/m 2 /yr metered natural gas).• All other assumptions were identical to the Timber, Steel and Concrete building.TimberPlus building• The amount of timber used cannot be accounted for in Green Star. The results for theTimberPlus building were therefore identical with the Timber building.• Operational energy figures specific to the TimberPlus building were included(70 kWh/m 2 /yr metered electricity and 16 kWh/m 2 /yr metered natural gas).• All other assumptions were identical to the TimberPlus, Steel and Concrete building.Concrete building• Recycled concrete was assumed for the Concrete building. The N/A option was tickedfor Steel and Timber respectively.• Operational energy figure specific to the Concrete building were included(68 kWh/m 2 /yr metered electricity and 16 kWh/m 2 /yr metered natural gas).• All other assumptions were the same as for Steel and Timber.Steel building• Recycled steel was assumed for the Steel building. The N/A option was ticked forConcrete and Timber respectively.• Operational energy figure specific to the Steel building were included (70 kWh/m 2 /yrmetered electricity and 16 kWh/m 2 /yr metered natural gas).• All other assumptions were the same as for Concrete and Timber.
- Page 27 and 28: - 27 -the building. The basement le
- Page 29 and 30: - 29 -4.3.2 Common Design Principle
- Page 31 and 32: - 31 -Figure 4.5: South-west façad
- Page 33 and 34: - 33 -the three longitudinal frames
- Page 35 and 36: - 35 -4.3.5.2 Floor and RoofThe str
- Page 37 and 38: - 37 -4.4 Multi-Storey Timber Build
- Page 39 and 40: - 39 -Several different solutions h
- Page 41 and 42: - 41 -5 Operational Energy5.1 Gener
- Page 43 and 44: - 43 -Table 5.1: Simulation inputs
- Page 45 and 46: - 45 -Table 5.3: Areas of office en
- Page 47 and 48: - 47 -Modifying the design to achie
- Page 49 and 50: - 49 -• Standards New Zealand (NZ
- Page 51 and 52: - 51 -6 Life Cycle Assessment6.1 In
- Page 53 and 54: - 53 -6.2.3.3 Impact AssessmentThe
- Page 55 and 56: - 55 -6.3.2.2 System BoundariesThe
- Page 57 and 58: - 57 -For more information see:http
- Page 59 and 60: - 59 -6.3.3 Inventory Analysis6.3.3
- Page 61 and 62: - 61 -Table 6.2: Net tonnes CO 2 eq
- Page 63 and 64: - 63 -Growing timber takes up CO 2
- Page 65 and 66: - 65 -6.3.4 Impact AssessmentTotal
- Page 67 and 68: - 67 -8000700060005000GWP (t CO2 eq
- Page 69 and 70: - 69 -As explained above, carbon st
- Page 71 and 72: - 71 -Figure 6.10: Total embodied e
- Page 73 and 74: - 73 -Table 6.9: Total GWP of each
- Page 75 and 76: - 75 -8,0007,0006,0005,000GWP (t CO
- Page 77: - 77 -45000400003500030000GWP (kg C
- Page 81 and 82: - 81 -6.4.3.2 Green Star Recycling
- Page 83 and 84: - 83 -Table 6.16: Green Star result
- Page 85 and 86: - 85 -The contribution of initial e
- Page 87 and 88: - 87 -results, the reutilisation sc
- Page 89 and 90: - 89 -7.1.1 Platform and Balloon Co
- Page 91 and 92: - 91 -buildings has been analysed a
- Page 93 and 94: - 93 -Figure 7.5: Construction sche
- Page 95 and 96: - 95 -8.2 Source and Availability o
- Page 97 and 98: - 97 -It would be incorrect, howeve
- Page 99 and 100: - 99 -8.5 Additional Opportunities
- Page 101 and 102: - 101 -example, removal of CCA trea
- Page 103 and 104: - 103 -The Waste Minimisation Bill
- Page 105 and 106: - 105 -9 Discussion9.1 The Building
- Page 107 and 108: - 107 -• The buildings tend to be
- Page 109 and 110: - 109 -9.4.3 Data Sets9.4.3.1 Gener
- Page 111 and 112: - 111 -The following assessment wil
- Page 113 and 114: - 113 -Table 9.1. GWP coefficients
- Page 115 and 116: - 115 -Figure 9.2 shows that the ne
- Page 117 and 118: - 117 -placing and retaining materi
- Page 119 and 120: - 119 -Net CO 2 emissions - that is
- Page 121 and 122: - 121 -The LVL specified for the st
- Page 123 and 124: - 123 -10 ConclusionsThe following
- Page 125 and 126: - 125 -building types, instead subs
- Page 127 and 128: - 127 -In summary, reutilisation sh
- 79 -assumed to be identical for the four different building designs - Concrete, Steel, Timber andTimberPlus.Two scenarios were assessed in Green Star. A base scenario which took into account thedominant ‘core’ materials only, i.e. timber, steel and concrete only and a recycling scenariowhich is similar to the reutilisation scenario in the LCA study. Both Green Star scenarios areshown in Table 6.13. The justification for the credits is explained in section 6.4.3.1 for theGreen Star base scenario and in section 6.4.3.2 for the Green Star recycling scenario.6.4.3.1 Green Star Base ScenarioThe Green Star Base scenario took only the core materials <strong>of</strong> each building type into account,i.e. no points for concrete or steel were awarded in the Timber building. Otherwise the Timberbuilding would score credits for either steel or concrete whereas the intention was to analysethe credits awarded for the core materials <strong>of</strong> each building option only.Timber building• Not applicable (N/A) was ticked for recycled steel content and concrete contentrespectively although, according to the Green Star methodology N/A can only beticked if the material cost for steel or concrete respectively is less than 1 % <strong>of</strong> theproject’s total contract value.• Sustainable timber (FSC certified) was chosen for the timber option <strong>of</strong> the building.• Operational energy figure specific to the Timber building were included (73kWh/m 2 /yr metered electricity and 15 kWh/m 2 /yr metered natural gas).• All other assumptions were identical to the Timber, Steel and Concrete building.TimberPlus building• The amount <strong>of</strong> timber used cannot be accounted for in Green Star. The results for theTimberPlus building were therefore identical with the Timber building.• Operational energy figures specific to the TimberPlus building were included(70 kWh/m 2 /yr metered electricity and 16 kWh/m 2 /yr metered natural gas).• All other assumptions were identical to the TimberPlus, Steel and Concrete building.Concrete building• Recycled concrete was assumed for the Concrete building. The N/A option was tickedfor Steel and Timber respectively.• Operational energy figure specific to the Concrete building were included(68 kWh/m 2 /yr metered electricity and 16 kWh/m 2 /yr metered natural gas).• All other assumptions were the same as for Steel and Timber.Steel building• Recycled steel was assumed for the Steel building. The N/A option was ticked forConcrete and Timber respectively.• Operational energy figure specific to the Steel building were included (70 kWh/m 2 /yrmetered electricity and 16 kWh/m 2 /yr metered natural gas).• All other assumptions were the same as for Concrete and Timber.