IRPMUINDIAN RAILWAYS PROJECT MANAGEMENT UNITLocal office: Office of Deputy Chief Signal & Telecommunication Eng<strong>in</strong>eer/CTC,Near Jhakarkati Bus stand, GT road, KanpurHead Office: Chief Adm<strong>in</strong>istrative Officer, Shivaji Bridge (IRCOT Complex),Beh<strong>in</strong>d Shankar Market, New Delhi – 110 001<strong>TENDER</strong> <strong>DOCUMENT</strong><strong>for</strong>‘Outdoor works <strong>in</strong> connection with the provision of Multi section digital axle counter <strong>for</strong>dual detection <strong>in</strong> 15 block section of PNK-ALJN section of ALD division. (JJK-KNS,KNS-PHD,PHD-PTX,PTX-ULD,ULD-SHW,SHW-BNT,BNT-EKL,EKL-ETW,TDL-MTI,JLS-PRA,PRA-HRS,HRS-SNS,SNS-MXK,MXK-DAQ,DAQ-ALJN)’Tender No. SIG/WS/CNB/Dual detection (Outdoor) dated 08.10.12Copy No. ………Sold to M/s ………………Price Rs. 10000/-By Post Rs. 10500/-Signature of contractor Page 1 of 111 Dy CSTE /CTC/CNB


T O P S H E E T1) Tender Notice No : SIG/WS/CNB/Dual detection (Outdoor) dated 08.10.122) Name of Work : ‘Outdoor works <strong>in</strong> connection with the provision of Multisection digital axle counter <strong>for</strong> dual detection <strong>in</strong> 15 blocksection of PNK-ALJN section of ALD division. (JJK-KNS,KNS-PHD,PHD-PTX,PTX-ULD,ULD-SHW,SHW-BNT,BNT-EKL,EKL-ETW,TDL-MTI,JLS-PRA,PRA-HRS,HRS-SNS,SNS-MXK,MXK-DAQ,DAQ-ALJN ).’3) Approximate Cost : Rs. 25,80,34,809.37/- (Twenty five crore eighty lakhsthirty four thousand eight hundred n<strong>in</strong>e and paisa thirtyseven only)4) Completion period : 08 months from the date of issue of letter of acceptance.5) Earnest Money : Rs. 14,40,175/-(Fourteen lakhs <strong>for</strong>ty thousand onehundred seventy five only)6) Date of submission and open<strong>in</strong>g : 29-11-12 up to 14.00 Hrs and will be openedsimultaneously at 15.00 Hrs on the same day <strong>in</strong> the officeof Dy CSTE/CTC, North Central Railway, OldMicrowave build<strong>in</strong>g, Juhi, Kanpur and <strong>in</strong> the office ofCAO/IRPMU/NDLS.7) Cost of Tender document : Rs. 10000/- (Rs. 10500/- if reqd. by post).8) Sold to : M/s:____________________________________9) Details of deposit of cost of :Tender documentM.R./BD No. ……………………Dt………………: Rs. ………………………………………………….Issued bySignatures of Issu<strong>in</strong>g officialSignatures of ContractorSignature of contractor Page 2 of 111 Dy CSTE /CTC/CNB


INDEXSECTION CHAPTER SUBJECTI 1 Tender Notice2 Preamble3 Schedule of Items, rates and QuantitiesII 1 Instructions to tenderer &Conditions of tender<strong>in</strong>g2 Special conditions of contract3 Tender FormsIII 1 Technical Specification and InstallationPracticesSignature of contractor Page 3 of 111 Dy CSTE /CTC/CNB


Section – IChapter – 1Tender NoticeSignature of contractor Page 4 of 111 Dy CSTE /CTC/CNB


<strong>TENDER</strong> NOTICEDy Chief Signal & Telecom Eng<strong>in</strong>eer /CTC, North Central Railway, Near Jhakarkati Busstand, GT road, Kanpur, <strong>for</strong> and on behalf of the President of India, <strong>in</strong>vites sealed opentender on the prescribed <strong>for</strong>ms <strong>for</strong> the under noted work:-Tender No. Name of Work Outdoor works <strong>in</strong> connection with the provision of Multi sectiondigital axle counter <strong>for</strong> dual detection <strong>in</strong> 15 block section of PNK-ALJN section of ALD division. (JJK-KNS,KNS-PHD,PHD-PTX,PTX-ULD,ULD-SHW,SHW-BNT,BNT-EKL,EKL-ETW,TDL-MTI,JLS-PRA,PRA-HRS,HRS-SNS,SNS-MXK,MXK-DAQ,DAQ-ALJN )Tender No. Approximate 25,80,34,809.37/- (Twenty five crore eighty lakhs thirty four thousandSIG/WS/CN Costeight hundred n<strong>in</strong>e and paisa thirty seven only)B/Dual Earnest Money 14,40,175/-(Forteen lakhs <strong>for</strong>ty thousand one hundred seventy fivedetectiononly)(outdoor)Completion 08 months from the date of issue of letter of acceptance.Dated08.10.12PeriodLast Date andTime ofsubmission andopen<strong>in</strong>g ofTenderValidity ofOfferDate FromWhich TenderDocuments willbe Available <strong>for</strong>Sale.29-11-12 up to 14.00 Hrs and will be opened simultaneously at 15.00Hrs on the same day <strong>in</strong> the office of Dy CSTE/CTC, North CentralRailway, Old Microwave build<strong>in</strong>g, Juhi, Kanpur and <strong>in</strong> the office ofCAO/IRPMU/NDLS.90 days25-10-2012 to 27-11-2012 from 10.30 Hrs. to 16.00 hrs. on everywork<strong>in</strong>g day <strong>in</strong> the office of DyCSTE/IRPMU/CTC, North Central Railway, Near Jhakarkati Busstand, GT road, KanpurTenders without earnest money will be summarily rejected.Further particulars and tender <strong>for</strong>m can be received from the office of Dy CSTE/CTC,North Central Railway, Near Jhakarkati Bus stand, GT road, Kanpur, on any work<strong>in</strong>g dayon furnish<strong>in</strong>g a Demand Draft <strong>in</strong> favour of FA & CAO/IRPMU/New Delhi, of Rs.10,000/- (Rs. Ten Thousands only) per set and Rs.10,500/- per set if required by post. Costof the Tender documents is non-refundable and Tender documents are non-transferable.M<strong>in</strong>imum Eligibility CriterionI. Tenderer(s) should have successfully executed dur<strong>in</strong>g last three f<strong>in</strong>ancial years (i.e.current year and three previous f<strong>in</strong>ancial years), at least one work of similar nature* of notless than 35% of the value of the present tender.II. As proof of sufficient f<strong>in</strong>ancial capacity and organizational resources, contractor shouldhave received total contract amount dur<strong>in</strong>g the last three f<strong>in</strong>ancial years and <strong>in</strong> current yeara m<strong>in</strong>imum of 150% of the advertised value of work. As a proof of these qualify<strong>in</strong>gcriteria, the tenderer should submit the audited balance sheet duly certified by CharteredAccountant or attested certificates from the employer/ client.JVs/ Consortiums/MOU’s shall be considered.Signature of contractor Page 5 of 111 Dy CSTE /CTC/CNB


(*) Def<strong>in</strong>ition of Similar Nature Works:“Work <strong>in</strong>volv<strong>in</strong>g Provision of track circuit<strong>in</strong>g by digital Axle count<strong>in</strong>g system”.Or “Any work <strong>in</strong>volv<strong>in</strong>g <strong>in</strong>stallation and commission<strong>in</strong>g of BPAC by digital axle count<strong>in</strong>gsystem.”Tender Forms complete <strong>in</strong> all respect with all credentials duly sealed <strong>in</strong> an envelope andmention<strong>in</strong>g the name of work, should be deposited <strong>in</strong> the tender box allotted <strong>for</strong> thepurpose <strong>in</strong> the office of Dy CSTE/CTC, Old Microwave Build<strong>in</strong>g, N. C. Railway, Juhi,Kanpur. Tender duly sealed <strong>in</strong> the prescribed manner can also be sent through registeredpost so as to reach <strong>in</strong> the office of Dy CSTE/CTC, Old Microwave Build<strong>in</strong>g, N C Railway,Juhi, Kanpur, not later than date and time specified above. Any tender received after thespecified date/ time shall be a late / delayed tender. In case of last date of submission oftender papers happens to be a holiday, the tender paper will be received and opened on thenext work<strong>in</strong>g day at the same time.Tender notice is also available on NCR website www.ncr.<strong>railnet</strong>.<strong>gov</strong>.<strong>in</strong>,www.tenders.<strong>gov</strong>.<strong>in</strong> and IRPMU website www.<strong>irpmu</strong>.<strong>railnet</strong>.<strong>gov</strong>.<strong>in</strong>. Tender documentwill also be available on these websites from the date of sale of tender <strong>for</strong>ms. Tendererswho are submitt<strong>in</strong>g their bid <strong>in</strong> downloaded tender <strong>for</strong>m are required to deposit the cost oftender document separately (Rs.10,000/-) as per <strong>in</strong>structions given above.If the tenderer/s deliberately gives wrong <strong>in</strong><strong>for</strong>mation/Credentials/documents <strong>in</strong> his/theirtenders and thereby create(s) circumstances <strong>for</strong> acceptance of his / their tender, Railwayreserves the right to reject such tender at any stage, besides, shall suspend the Bus<strong>in</strong>ess <strong>for</strong>one year.Dy CSTE/CTC/NCR/KanpurFor and on Behalf of President of IndiaNo.: Tender No. SIG/WS/CNB/Dual detection (outdoor) Dated: 08.10.12Copy to:1. The CPRO, North Central Railway, Allahabad <strong>for</strong> publication <strong>in</strong> lead<strong>in</strong>g NationalNewspapers <strong>in</strong> India. One copy may please be sent to the Editor, Indian Railways,Allahabad and New Delhi <strong>for</strong> publication <strong>in</strong> Magaz<strong>in</strong>e. The cost is to be debited toWC 330039 and Allocation 43337304.Orig<strong>in</strong>al advertisement published <strong>in</strong> variousnewspapers may also be sent to this office as soon as these are available <strong>for</strong>perusal.2. CAO/IRPMU/N C Railway, Shivaji Bridge, New Delhi.3. CSTE/IRPMU/N C Railway, Shivaji Bridge, New Delhi.4. Dy FA & CAO/IRPMU/N C Railway/Shivaji Bridge, New Delhi is requested todepute his representative <strong>for</strong> open<strong>in</strong>g of tenders on date and time mentioned above.5. Dy CSTEs /IRPMU/ALJN and ALD.6. All DRMs/ N C Railway ALD, JHS & AGC.7. ASC / RPF, New Delhi. <strong>for</strong> mak<strong>in</strong>g security arrangements.8. DCPM / NCR / Allahabad.9. Sr. Audit officer / Const. / NCR / Allahabad.Signature of contractor Page 6 of 111 Dy CSTE /CTC/CNB


fufonk lwpukmi eq[; ladsr ,oa nwj lapkj vfHk;Urk@lhVhlh @ mRRkj e/; jsyos] >djdVh cl LVs'ku ds lehi] th- VhjksM]dkuiqj Hkkjr ds jk"V~ifr ds fy, ,oa mudh vksj ls fuEufyf[kr dk;Z ds fy, eqgjcUn [kqyh fufonk,]afu/kkZfjr izi= ij vkeaf=r dh tkrh gSa%&fufonk la[;k dk;Z dk uke bykgkckn eaMy ds iudh &vyhxMz [kaM ds 15 mi[kaM esa ckg; dk;Zftlesa ³wÓy fMVsD’ku ds fy, cgq[kaMh; vadh; èkqjkx.kd ds izko/kku dslacU/k esa gS A (JJK-KNS,KNS-PHD, PHD-PTX,PTX-ULD,ULD-SHW,SHW-BNT,BNT-EKL, EKL-ETW,TDL-MTI,JLS-PRA, PRA-HRS,HRS-SNS,SNS-MXK,MXK-DAQ,DAQ-ALJN )SIG/WS/CNB/Dualdetection (outdoor)fnukad 08.10.12vuqekfur ewY; :0 25,80,34,809.37/-/kjksgj jkf'k :0 14,40,175/-dk;Z iwjk djus dh vof/k 08 ekgfufonk tek djus dh vfUrefrfFk rFkk [kqyus dk le;rFkk LFkku A29-11-2012 dks 14.00 cts rd vkSj mlh fnu 15-00 cts mi eq-la-,oa nw-la-vfHk;Urk@vkbZ vkj ih,e ;w @iqjkuh ekbdzksoso Hkou]mRrj e/;jsyos] twgh] dkuiqj ,oa eq[; iz’kklfud vf/kdkjh@vkbZ-vkj-ih-,e-;w@ ubZfnYyh ds dk;kZy; esa fufonk ,d lkFk [kksyh tk,xhAoS/krk 90 fnu ¼uCcs fnu½frfFk ftl fnu ls fufonkizi= fcØh gsrq miyC/k jgsxh25-1010-2012ls 27-1111-2012rd mi eq-la-,oa nw-la-vfHk@vkbZvkjih,e;w@>djdVh cl LVs'ku ds lehi] th- Vh- jksM]] dkuiqj lsa 10-30cts ls lk;a 16 cts rd fdlh Hkh dk;Zfnol ij izkIr dj ldrs gSaAfcuk /kjksgj jkf'k ds fufonk vekU; jgsxhAfufonk fooj.k ,oa izi= mi eq- la-,oa nw-la-vfHk;ark@ lhVhlh @vkbZ vkj ih,e ;w @>djdVh cl LVs'ku dslehi] th- Vh- jksM]] dkuiqj ls ds dk;kZy; ls fdlh Hkh dk;Zfnol- dks :i, 10000@& dk vkSj Mkd ls eaxkusij :i, 10500@& dk fdlh Hkh jk"V~zh;d`r cSad dk fMekaM M~zkWQ~V ;k is& vkMZj ;k fMiksftV fjflIV foRrlykgdkj ,oa eq[; ys[kk vf/kdkjh @ vkbZvkjih,e;w @ ubZ fnYyh ds i{k esa ns; gks tek djkdj izkIr dh tkldrh gSA fufonk jkf'k izfrns; jfgr ,oa fufonk izi= vUrZns; jfgr gSAU;wure Ikk=rk ekunaM(i)(ii)Bsdsnkj us fiNys yxkrkj rhu foRr o"kZ ,oa orZeku o"kZ dks ysdj de ls de bl fufonk esaizdkf'kr ewY; ds 35% ewY; dk leku :ih ,d dk;Z fd;k gksAvkfFkZd {kerk vkSj laxBukRed lzksr ds izek.k Lo:i Bsdsnkj us fiNys yxkrkj rhu foRr o"kZ ,oaorZeku o"kZ dks ysdj bl fufonk esa izdkf'kr ewY; dk 150% Hkqxrku izkIr fd;k gksA ik=rk ds ;ksX;gsrq fuosnd dks cSysUl 'khV tks fd pkVZMZ ,dkmUVsaV ls izekf.kr gks ;k fu;kstd@DykbUV ls izkIrlR;kfir izfrfyfi Hkh yxkuk vko';d gSATokbaV osaplZ dUlksfVZ;e @eseksj.Me vkWQ v.MjLVSf.Max ij fopkj fd;k tk;sxk A(.) ifjHkk"kk leku :ih dk;Z gsrq %&“ftlesa fMthVy ,Dly dkWmUVj flLVe }kjk VSz~d lfdZfVax dk dk;Z** fd;k gks vFkok dskbZ Hkh dk;Zftlesa ^^fMthVy ,Dly dkWmUVj flLVe }kjk chih,lh dk bULVkys’ku vkSj dfe’kfuax** dk;Z fd;k x;k gksASignature of contractor Page 7 of 111 Dy CSTE /CTC/CNB


fufonk izi= iw.kZ:i ls Hkjus o lHkh ;ksX;rk dks layXu djus ds ckn fyQkQs esa cUn dj lhy djus dsckn fyQkQs ds mij dk;Z dk uke fy[kus ds i'pkr~ fufonk ckDl tks fd bl iz;kstu gsrq mi eq-la-,oanw-la-vfHk-@lhVhlh @vkbZ vkj ih,e ;w @iqjkuh ekbdzksoso Hkou]mRrj e/; jsyos] twgh] dkuiqj dsdk;kZy; esa j[kk gS] esa Mkyk tk,xkA mijksDr rjg ls iw.kZ:i ls Hkjus ds ckn ,oa vU; vko';ddk;Zokgh ds ckn lhycan fyQkQk jftLVMZ Mkd }kjk mijksDr dk;kZy; dks bl rjg Hkstk tk, fdvfUre frfFk ls iwoZ igq¡p tk,A fu/kkZfjr frfFk ds ckn izkIr fufonk Lohd`r ugha dh tk,xhA vxj tekdjus dh frfFk dks dksbZ vodk'k iM+ tkrk gS rks fufonk ifji= vxys dk;Zfnol dks Lohdkj fd,tk,axs ,oa [kksysa tk,axs A;g fufonk lwpuk mRrj e/; jsyos dh osolkbZV www.ncr.<strong>railnet</strong>.<strong>gov</strong>.<strong>in</strong> ,www.tenders.<strong>gov</strong>.<strong>in</strong> ,oa vkbZvkjih,e;w dh osolkbZV www.<strong>irpmu</strong>.<strong>railnet</strong>.<strong>gov</strong>.<strong>in</strong> ij HkhmiyC/k gSs A fufonk izi= (VsaMj MkSD;wesaV) mijksDr of.kZr osolkbZV ij fufonk izi= ds fcdzh rkjh[kls miyC/k gksxhA tks fuosnd bl fufonk dks MkmuyksM djds fufonk Mkysaxsa mudks fufonk Mkyrsle; fufonk dh ewy ykxr :Ik;s 10000@& mij crk;s x;s funsZ’kksa ds vuqlkj tek djuk iM+sxk A;fn Bsdsnkj tkucw>dj xyr lwpuk nsdj ¼ik=rk@;ksX;rk lEcU/kh½ ,sls volj mRiUu djrk gS rksjsyos dks ;g vf/kdkj gksxk fd fdlh Hkh Lrj ij mlds fufonk dks vLohd`r dj ns ,oa mlds O;kikjdks ,d lky ds fy, izfrcfU/kr dj fn;k tk,xkAmi eq[; ladsr ,oa nwj lapkj bathfu;j@lhVhlhvkbZvkjih,e;w mRrj e/; jsyos] dkuiqjd`rs Hkkjr ds jk"Vªifr ds fy,@dh vksj lsla- SIG/WS/CNB/Dual detection (outdoor) fnukad 08.10.12izfrfyfi %&1- eq[; tulEidZ vf/kdkjh@ m-e-jsyos] bykgkckn esa 6 izfr izdk’ku gsrq @Hkkjr ds vxz.kh lekpkj i=ksa esadÌ;k ,d izfr lEiknd] Hkkjrh; jsyos] bykgkckn ,oa ubZ fnYyh dks eSXthu esa izdk’kukFkZ Hkstsa A izdk’ku dsewY; dks MsfcV odZ dksM& 330039 ,yksds’ku& 43337304 dks djsa A izdkf’kr fufonk dh izfr dks bldk;kZy; dks Hkh Hkstsa A2- ,l-Mh-th-,e- mRrj e/; jsyos] bykgkcknA3- eq[; iz’kklfud vf/kdkjh@vkbZ vkj ih ,e ;w @mRrj e/; jsyos] f’kokth fczt] ubZ fnYyh A4- eq[; ldsr-,oa nwj lapkj vfHk-@vkbZ vkj ih-,e- ;w @ mRrj e/; jsyos] f’kokth] fczt] ubZ fnYyh A5- mi eq[; foRr lykgdkj ,oa eq[; ys[kk vf/kdkjh @ vkbZ vkjbZih,e;w @ mRrj e/;jsyos] f’kokth fczt] ubZ fnYyh A6- mi eq[; ldsr-,oa nwj lapkj vfHk-@vkbZ vkj ih-,e- ;w @mRrj e/; jsyos] bykgkckn7- ea-js-izca/kd@ m-e-jsyos] bykgkckn] >kWalh] vkxjk A8- lgk;d lqj{kk vk;qDr ] vkjih,Q ] ubZ fnYyh dks bl vk’k; ds lkFk fd fufonk[kqyus dh frfFk ij vko’;d lqj{kk izca/k djsa A9- e.My dks"k izca/kd @bykgkckn ASignature of contractor Page 8 of 111 Dy CSTE /CTC/CNB


PREAMBLE1 Tender Notice: SIG/WS/CNB/Dual detection (Outdoor) dated 08.10.121.1 Name of work: “Outdoor works <strong>in</strong> connection with the provision of Multi section digital axlecounter <strong>for</strong> dual detection <strong>in</strong> 15 block section of PNK-ALJN section of ALD division. (JJK-KNS,KNS-PHD,PHD-PTX,PTX-ULD,ULD-SHW,SHW-BNT,BNT-EKL,EKL-ETW,TDL-MTI,JLS-PRA,PRA-HRS,HRS-SNS,SNS-MXK,MXK-DAQ,DAQ-ALJN )1.2 General Conditions of the Contract, <strong>in</strong>structions to tenderer and Special Conditions of theContract shall <strong>gov</strong>ern the tender. Wherever Preamble differs from Special Conditions, GeneralCondition or Instruction to Tenderer, the provisions of Preamble shall override. WhereverSpecial Conditions of Contract differ from General Conditions of Contract and <strong>in</strong>structions totenderer, the provisions of Special Conditions of Contract shall override.1. 2 Please note that a clause-by-clause compliance/deviation statement has to be submitted by thebidder mention<strong>in</strong>g specifically the page no of his offer file on which the documentary evidenceof their compliance of the follow<strong>in</strong>g clause is placed.2.0 Eligibility criteria2.1 M<strong>in</strong>imum eligibility criteria - As per Para 18.2 of Section II Chapter I ‘Instructions toTenderers and Conditions of Tender<strong>in</strong>g’.2.2 Experience, Expertise, Infrastructure & Human Resource Availability with the Tenderer(s)a) Tenderer should submit details of works to qualify similar nature of the work,b) List of works <strong>in</strong> hand,c) list of <strong>in</strong>frastructure andd) List of qualified staff to execute signall<strong>in</strong>g work.2.3 a) The tenderer(s) should submit the details of experience <strong>in</strong> works of similar nature <strong>in</strong>follow<strong>in</strong>g pro<strong>for</strong>ma –List of Works CompletedDescription ofWorkOrganization <strong>for</strong>whomexecutedApprox.value ofcontract at thetime of awardDateofawardDate ofscheduledcompletion of workDate of actualStartCompletionF<strong>in</strong>al valueof contractList of Works <strong>in</strong> HandDescription ofworkContract ValueApprox. value ofbalance work yet to bedoneDate of Award2.4 The tenderer shall provide a satisfactory evidence acceptable to the Railway to show that he orhis consortium/collaboration partner –Not applicableSignature of contractor Page 9 of 111 Dy CSTE /CTC/CNB


2.5 Further <strong>in</strong><strong>for</strong>mation regard<strong>in</strong>g capacity and capability, if required by the Railway, shall bepromptly furnished by the tenderer and he would offer all facilities to representative ofRailway <strong>for</strong> assess<strong>in</strong>g capacity and capability by visit to his works/office.2.6 Offer of the tenderer(s) not submitt<strong>in</strong>g the requisite <strong>in</strong><strong>for</strong>mation is liable to be ignored.2.7 The tenderer(s) shall have adequate telecom facilities, computer and data network facilities,transport arrangement, construction mach<strong>in</strong>eries, tools and plants etc. <strong>for</strong> smooth execution ofthe project.2.8 The tenderer (s) shall furnish such documents as to establish the f<strong>in</strong>ancial soundness of hiscompany.3.0 LAST DATE OF SUBMISSION29-11-12 up to 14.00 Hrs <strong>in</strong> the office of Dy CSTE/CTC, North Central Railway, OldMicrowave build<strong>in</strong>g, Juhi, Kanpur.4.0 DATE OF OPENING OF <strong>TENDER</strong>29-11-12 at 15.00 Hrs will be opened simultaneously <strong>in</strong> the office of Dy CSTE/CTC, NorthCentral Railway, Old Microwave build<strong>in</strong>g, Juhi, Kanpur and <strong>in</strong> the office ofCAO/IRPMU/NDLS.5.0 COMPLETION PERIOD OF WORKThe entire work is to be completed with<strong>in</strong> 08 months from the date of issue of Letter ofAcceptance of the Tender.6.0 THE LIST OF ADDRESS TO WHICH CORRESPONDENCE AND <strong>DOCUMENT</strong>SRELATING TO THE CONTRACT SHOULD BE SENT(a) Prior to award of the contract:Dy Chief Signal and Telecommunication Eng<strong>in</strong>eer /CTC (Dy CSTE/CTC),Indian railway project management unit (IRPMU),Near Jhakarkati Bus stand, GT road, KanpurTelephone No. +91 512 2324167, 9794835864 (mobile).(b) After the award of the Contract:Dy Chief Signal and Telecommunication Eng<strong>in</strong>eer /CTC (Dy CSTE/CTC),Indian railway project management unit (IRPMU),Near Jhakarkati Bus stand, GT road, KanpurTelephone No. +91 512 2324167, 9794835864 (mobile).7.0 EARNEST MONEYThe Tenderer should furnish the requisite Earnest Money offer <strong>in</strong> favour of the ‘FA & CAO,IRPMU, New Delhi’ along with their offer as <strong>in</strong>dicated <strong>in</strong> Para-5 of Instructions to Tenderersand Conditions of Tender<strong>in</strong>g.8.0 SCOPE OF WORK:8.1 Exist<strong>in</strong>g Signall<strong>in</strong>g:1. The signall<strong>in</strong>g system of work<strong>in</strong>g which is proposed to be modified <strong>in</strong> the presenttender is Electronic Interlock<strong>in</strong>g (EI) based Station signall<strong>in</strong>g and automatic blocksignall<strong>in</strong>g.2. The automatic block signall<strong>in</strong>g is controlled by Electronic Interlock<strong>in</strong>g <strong>in</strong>stalled <strong>in</strong>LSCs(L<strong>in</strong>e Side Cab<strong>in</strong>ets) provided every 3 to 3.5 km approx.3. There is relay <strong>in</strong>terface between EIs controll<strong>in</strong>g station <strong>in</strong>terlock<strong>in</strong>g and auto blockwork<strong>in</strong>g.4. The block section EIs are slaves controlled by the Master EIs provided <strong>in</strong> Auto BlockSignature of contractor Page 10 of 111 Dy CSTE /CTC/CNB


acks of the stations.5. Note: The exist<strong>in</strong>g Signal Interlock<strong>in</strong>g Plans (SIPs) of the 15 block sections where dualdetection work is proposed to be carried out can be seen at the office of DyCSTE/CTC/CNB or Dy CSTE/D&D/IRPMU/NDLS.6. All the EIs are ASTS make (Micro Lock-II type)Dual detection of track circuits compris<strong>in</strong>g AFTC & Axle Counters are functional <strong>in</strong> entirePNK-ALJN section, except 15 block sections. 15 Automatic block sections is track circuitedby only Audio Frequency track circuits which control the work<strong>in</strong>g of Automatic Signals.The scope of work <strong>in</strong> the tender <strong>in</strong>cludes:1. This work <strong>in</strong>volves the trench<strong>in</strong>g and track cross<strong>in</strong>g and lay<strong>in</strong>g of 6 quad cable, supplyand erection of location boxes <strong>for</strong> track side electronic units, junction boxes, supplyand fix<strong>in</strong>g of ARA term<strong>in</strong>als and cable term<strong>in</strong>ations, supply and lay<strong>in</strong>g of GI/RCCpipes at bridges/culverts etc and also supply of general tool kit <strong>for</strong> future ma<strong>in</strong>tenanceof the section.2. This work <strong>in</strong>volves the supply, <strong>in</strong>stallation and commission<strong>in</strong>g of MSDAC completesystem <strong>in</strong>clud<strong>in</strong>g Central Evaluator(s)/Processor(s), f<strong>in</strong>al track clearance relay <strong>for</strong> eachtrack section, detection po<strong>in</strong>ts, mushroom hous<strong>in</strong>g <strong>for</strong> track side electronic equipmentunit with complete assembly and fix<strong>in</strong>g arrangement <strong>for</strong> each detection po<strong>in</strong>t, clampsdeflectors on each side of detection po<strong>in</strong>t and all other accessories fully wired to theultimate capacity and fully equipped <strong>for</strong> 15 Detection Po<strong>in</strong>ts and 13 Track Sections asper RDSO specification no. RDSO/SPN/176/2005 (Ver. 2) and OEM's specification.3. Supply and fix<strong>in</strong>g of earth electrode as per standard practice. The item <strong>in</strong>cludes digg<strong>in</strong>gof pit <strong>in</strong> earth, 3 meters and fix<strong>in</strong>g of earth electrode pipes. Cast<strong>in</strong>g of cement concreteenclosures as per Drg no. NR/S&T/CON/6.3/97. The soil treatment should be done asper the standard practice. The item <strong>in</strong>cludes provision of MS flat of size 35x6 mm2,wires and solder<strong>in</strong>g of lead wires. The other end of the MS flat to be connected by bolt/solder<strong>in</strong>g to the signall<strong>in</strong>g equipment.4. The work would <strong>in</strong>clude items as covered <strong>in</strong> the Schedule of requirement of Items andquantities.8.1.2 RAILWAY SUPPLYTenderer’s special attention is <strong>in</strong>vited to the list of materials to be supplied/ arranged by theRailways <strong>for</strong> commission<strong>in</strong>g of the systemApproved Signall<strong>in</strong>g and <strong>in</strong>terlock<strong>in</strong>g Plan and Cables shall be supplied by Railways.Any items that if required to be supplied by railways will be done so from the stores ofSSE/Sig /IRPMU/TDL.8.1.3 CONTRACTOR’S SUPPLY1. All the materials <strong>for</strong> the worki) CPU Card, PSU Card, Central Evaluator Empty sub rack, term<strong>in</strong>al block M-6 Hylemsheet, location boxes(Apparatus case) full, quarter with m<strong>in</strong>iature E type lock, GI pipe,RCC pipe etc as per specific item of ‘schedule of items and quantities’.ii) All materials such as earth electrode, cement, solder<strong>in</strong>g material cement, sand, aggregateand anchor bolt shall be supplied by the contractor. All fitt<strong>in</strong>gs required <strong>for</strong> fix<strong>in</strong>g of GIpipe B class 100mm dia, 3 mm thick B class to be supplied by contractor8.2 SERVICESProper arrangement should be made to hand over the draw<strong>in</strong>gs <strong>in</strong> the office of DyCSTE/CTC/IRPMU/Near Jhakarkati Bus stand, GT road, Kanpur. Tra<strong>in</strong><strong>in</strong>g of Railwaypersonnel at Manufacturer’s premises <strong>in</strong> India or abroad.Signature of contractor Page 11 of 111 Dy CSTE /CTC/CNB


8.2.1 The supply of materials shall be as per schedule of work. However, the quantities taken <strong>in</strong> theschedule are based on Railways’ past experience. The tenderer may give the quantities ofequivalent items <strong>in</strong> addition to Railways items. As described earlier also, the change <strong>in</strong>quantity after acceptance of tender will be acceptable only if the requirement of Railwayschange.8.3 Tenderer should note that the material/equipment/ documents supplied are complete andcompatible to requirements.8.4 The tenderer shall undertake study / survey of signall<strong>in</strong>g systems / practices used <strong>in</strong> NorthCentral Railway and make his own arrangement of draw<strong>in</strong>gs/documents so as to make theentire system successful / functional.9.0 TECHNICAL SPECIFICATION9.1 The works shall be carried out accord<strong>in</strong>g with draw<strong>in</strong>gs approved by the Railway and shallcon<strong>for</strong>m to the provisions of the ‘Signal Eng<strong>in</strong>eer<strong>in</strong>g Manual’ Schedule of “Dimension” and“Manual of Instructions <strong>for</strong> Installation of S&T equipment on 25 KV, 50 cycles, A. C.electrified sections as modified from time to time unless deviations, if any, are specificallyapproved by the Eng<strong>in</strong>eer. The contractor shall be solely responsible <strong>for</strong> the proper executionof the work as per the said deviation and specifications.9.2 Axle Counter1. Multi section digital axle counter as per specification no. RDSO/SPN/176/2005 (Ver. 2) andOEM's specification complete set consist<strong>in</strong>g of Evaluator /Processor, Vital relays <strong>for</strong> each tracksection, track site unit with detection po<strong>in</strong>t complete assembly & fix<strong>in</strong>g arrangement <strong>for</strong> eachdetection po<strong>in</strong>t, clamps deflectors <strong>for</strong> either side of each detection po<strong>in</strong>ts , monitor<strong>in</strong>g consoleand a reset box <strong>for</strong> resett<strong>in</strong>g each track section and detection po<strong>in</strong>t as specified <strong>in</strong> tenderschedule.2. Evaluator /processor <strong>for</strong> multi section digital axle counter equipped <strong>for</strong> specific tracksections complete set as per RDSO Specification no RDSO/SPN/176/2005 (Ver. 2) and OEM'sspecification.a) Track site unit <strong>for</strong> MSDAC as per RDSO Specification no. RDSO/SPN/176/2005 (Ver. 2) andOEM's specification complete set of track site unit <strong>for</strong> detection po<strong>in</strong>ts.b) Detection Po<strong>in</strong>ts /track device/ Double Rail Contact unit <strong>for</strong> Multi Section Digital Axlecounter as per RDSO Specification no. RDSO/SPN/176/2005 (Ver. 2) and OEM's specification,detection, po<strong>in</strong>t complete assembly and fix<strong>in</strong>g arrangement.c) Track section of MSDAC con<strong>for</strong>m<strong>in</strong>g to Specification no. RDSO/SPN/176/2005 (Ver. 2) andOEM's specification.d) Deflector <strong>for</strong> detection po<strong>in</strong>t <strong>for</strong> MSDAC as per RDSO/SPN/176/2005 (Ver. 2) and OEM'sspecification.9.3 Tool kits <strong>for</strong> Digital Axle counter (ETU 001) Specification no. RDSO/SPN/176/2005 (Ver. 2) andOEM's specification consist<strong>in</strong>g of follow<strong>in</strong>g items:(1) True RMS Digital Multimeter with probe set-- 1no.(2) Extended wired socket to <strong>in</strong>terface with diagnostic plug--1 no.(3) Selector switch on panel base-- 1 no.(4) Adjustable torque wrench with 13 mm and 19 mm <strong>in</strong>serts-- 1 set(5) 19 mm double ended spanner-- 1 no.(6) Dummy wheel-- 1 no.(7) Screw driver set with ma<strong>in</strong>s tester-- 1no. Note: All the mechanical tools should be ofgood quality like Taparia, BOSCH etc. Make9.4 Term<strong>in</strong>al blocks M-6 (ARA term<strong>in</strong>al as per IRS spc. No. IRS-S-75/2006(Rev 2) or latest andIRS drg no. SA-23741/A Alt-4.Signature of contractor Page 12 of 111 Dy CSTE /CTC/CNB


9.5 DWC Pipe HDPE (ElectREX/TeleREX or similar) <strong>for</strong> under groungsignall<strong>in</strong>g/communication cable protection, 103.5mm <strong>in</strong>ner dia & 120mm outer dia <strong>in</strong> 6 mstaright length as per BSEN 50086-1 & BSEN 50086-2,4 & BIS draft spec DOC HQ LTD14(5071) & ETD 5072) to spec IS 14930 part II. Note-One coupler <strong>for</strong> jo<strong>in</strong><strong>in</strong>g shall besupplied with each 6 mtr length. Inspection by RITES only.9.6 Apparatus cases full with m<strong>in</strong>iature E type lock as per drg no. RE/S&T/ALD/SK/219/82 withAlt 'A' and 221/82 with Alt ’B’ or latest and Apparatus cases quarter type lock as per drg no.RE/S&T/ALD/SK/227/82 or latest’. The keys of ward no 42 and handle should be supplied atthe rate of one per four location boxes.9.7 Earth<strong>in</strong>g System (supply and fix<strong>in</strong>g of Earth electrode) as per standard practice. The item<strong>in</strong>cludes digg<strong>in</strong>g of pit <strong>in</strong> earth, 3 meters and fix<strong>in</strong>g of earth electrode pipes. Cast<strong>in</strong>g of cementconcrete enclosures as per Drg no. NR/S&T/CON/6.3/97. The soil treatment should be done asper the standard practice. The item <strong>in</strong>cludes provision of MS flat of size 35x6 mm2, wires andsolder<strong>in</strong>g of lead wires. The other end of the MS flat to be connected by bolt/solder<strong>in</strong>g to thesignall<strong>in</strong>g equipment as per <strong>in</strong>struction of Railway site eng<strong>in</strong>eer.10. INSPECTION AND TEST10.1 Inspection of non RDSO/RITES <strong>in</strong>spected items will be done by the consignee (Railwayofficer/supervisor) at firm’s factory premises or at the railway supply depot, as decided byRailways. Decision <strong>in</strong> this regard to be taken by the contractor <strong>in</strong> advance.11.0 M<strong>in</strong>imum eligibility criteria11.1 I. Tenderer(s) should have successfully executed dur<strong>in</strong>g last three f<strong>in</strong>ancial years (i.e. currentyear and three previous f<strong>in</strong>ancial years), at least one work of similar nature* of not less than35% of the value of the present tender.II. As proof of sufficient f<strong>in</strong>ancial capacity and organizational resources, contractor shouldhave received total contract amount dur<strong>in</strong>g the last three f<strong>in</strong>ancial years and <strong>in</strong> current year am<strong>in</strong>imum of 150% of the advertised value of work. As a proof of these qualify<strong>in</strong>g criteria, thetenderer should submit the audited balance sheet duly certified by Chartered Accountant orattested certificates from the employer/ client.(*) Def<strong>in</strong>ition of Similar Nature Works:“Work <strong>in</strong>volv<strong>in</strong>g Provision of track circuit<strong>in</strong>g by digital Axle count<strong>in</strong>g system”.Or “Any work <strong>in</strong>volv<strong>in</strong>g <strong>in</strong>stallation and commission<strong>in</strong>g of BPAC by digital axle count<strong>in</strong>gsystem.”The Digital Axle Count<strong>in</strong>g system should be supplied by the tenderer should be from RDSOapproved/cross accepted source. The tenderer must have an MOU/collaboration with theRDSO approved source <strong>for</strong> the supply, <strong>in</strong>stallation, test<strong>in</strong>g and commission<strong>in</strong>g of the DigitalAxle Count<strong>in</strong>g System.11.2 Experience, Expertise, Infrastructure & Human Resource Availability with the Tenderer(s)b) Tenderer should submit details of works to qualify similar nature of the work,b) list of works <strong>in</strong> hand,c) list of <strong>in</strong>frastructure andd) List of qualified staff to execute signall<strong>in</strong>g work.11.3 a) The tenderer(s) should submit the details of experience <strong>in</strong> works of similar nature <strong>in</strong>follow<strong>in</strong>g pro<strong>for</strong>ma –List of Works CompletedSignature of contractor Page 13 of 111 Dy CSTE /CTC/CNB


Description ofWorkOrganization <strong>for</strong>whomexecutedApprox.value ofcontract at thetime of awardDateofawardDate ofscheduledcompletion of workDate of actualStartCompletionF<strong>in</strong>al valueof contractList of Works <strong>in</strong> HandDescription ofworkContract ValueApprox. value ofbalance work yet to bedoneDate of Award11.4 The tenderer shall provide satisfactory evidence acceptable to the Railway to show his and hisconsortium/collaboration partnership.Not applicable11.5 Further <strong>in</strong><strong>for</strong>mation regard<strong>in</strong>g capacity and capability, if required by the Railway, shall bepromptly furnished by the tenderer and he would offer all facilities to representative ofRailway <strong>for</strong> assess<strong>in</strong>g capacity and capability by visit to his works/office.11.6 Offer of the tenderer (s) not submitt<strong>in</strong>g the requisite <strong>in</strong><strong>for</strong>mation is liable to be ignored.11.7 The tenderer (s) shall have adequate telecom facilities, computer and data network facilities,transport arrangement, construction mach<strong>in</strong>eries, tools and plants etc. <strong>for</strong> smooth execution ofthe project.11.8 The tenderer (s) shall furnish such documents as to establish the f<strong>in</strong>ancial soundness of hiscompany.12 Supply ScheduleThe time schedule <strong>for</strong> the entire work is of utmost importance. The entire work is required tobe fully completed with<strong>in</strong> 8 month from date of issue of Letter of Acceptance (LOA).13 PACKING AND FORWARDING13.1 The contractor shall pack at his own cost the stores sufficiently and properly <strong>for</strong> transit byrail/road/air/ and/or sea as provided <strong>in</strong> the contract so as to ensure their be<strong>in</strong>g free from loss ordamage on arrival at their dest<strong>in</strong>ation.13.2 All conta<strong>in</strong>ers (<strong>in</strong>clud<strong>in</strong>g pack<strong>in</strong>g cases, boxes, t<strong>in</strong>s, drums and wrapp<strong>in</strong>gs) <strong>in</strong> which thecontractor supplies the stores shall be considered as non-returnable and their cost as deemed tohave been <strong>in</strong>cluded <strong>in</strong> the contract price.13.3 The Contractor at his own expense shall mark each bale or package delivered under thecontract. Such mark<strong>in</strong>g shall be dist<strong>in</strong>ct (all previous irrelevant mark<strong>in</strong>g be<strong>in</strong>g carefullyobliterated) and shall clearly <strong>in</strong>dicate the description and quantity of the stores, the name andaddress of the consignee, the gross weight of the package and the name of the contractor with adist<strong>in</strong>ctive number of mark sufficient <strong>for</strong> the purpose of identification. All mark<strong>in</strong>gs shall becarried out with such material as may be found satisfactory by the <strong>in</strong>spect<strong>in</strong>g officer as regardquickness of dry<strong>in</strong>g, fastness and <strong>in</strong>delibility.Signature of contractor Page 14 of 111 Dy CSTE /CTC/CNB


13.4 Materials & Equipment meant <strong>for</strong> each station shall be packed <strong>in</strong> separate boxes and markedwith the name of station, consignee and railway.13.5 The <strong>in</strong>spect<strong>in</strong>g officer may reject the stores if the stores are not packed and/or marked asa<strong>for</strong>esaid and <strong>in</strong> case where the pack<strong>in</strong>g materials are separately prescribed, if such materialsare not <strong>in</strong> accordance with the terms of the contract. Such rejection of the stores by theInspect<strong>in</strong>g Officer shall be b<strong>in</strong>d<strong>in</strong>g on the Contractor.13.6 Each bale or package shall conta<strong>in</strong> note specify<strong>in</strong>g the name and address of the Contractor thenumber and date of the acceptance of tender and the designation of the Controll<strong>in</strong>g officer.1414.114.2SUPPLY AND CUSTODY OF MATERIALAll materials shall be supplied by the contractor at the stores Sr. SectionEng<strong>in</strong>eer/Sig./IRPMU/ Tundla. The transportation of all material from the consignee’s storesto site (station) <strong>for</strong> <strong>in</strong>stallation and commission<strong>in</strong>g shall also be the responsibility of thecontractor at his own cost.The contractor shall be entirely responsible and shall bear all expenses towards load<strong>in</strong>g,transport, handl<strong>in</strong>g and unload<strong>in</strong>g <strong>for</strong> all materials equipment, mach<strong>in</strong>es, tools and plants etc.from the source of supply to the store of Sr. Section Eng<strong>in</strong>eer/Sig./IRPMU/ Tundla. Theresponsibility <strong>for</strong> damage to any equipment dur<strong>in</strong>g transportation and till it is taken over byRailways shall be that of the contractor.15 FUTURE DEVELOPMENTThe contractor shall supply to the railway free of charge all update, data and specifications thatmay result from developments effected by him or his collaborator <strong>in</strong> the period of currency ofcontract. The Railway reserves the right <strong>for</strong> such modified or improved versions <strong>in</strong> lieu ofthese orig<strong>in</strong>ally quoted <strong>for</strong>, based on prices and other conditions mutually agreed upon.**********Signature of contractor Page 15 of 111 Dy CSTE /CTC/CNB


Section – IChapter – 3Schedule ofItems, rates & quantitiesSignature of contractor Page 16 of 111 Dy CSTE /CTC/CNB


Outdoor works <strong>in</strong> connection with the provision of Multi section digital axle counter <strong>for</strong> Dual Detection <strong>in</strong> 15 blocksections of PNK-ALJN section of ALD division (JJK-KNS,KNS-PHD,PHD-PTX,PTX-ULD,ULD-SHW,SHW-BNT,BNT-EKL,EKL-ETW,TDL-MTI,JLS-PRA,PRA-HRS,HRS-SNS,SNS-MXK,MXK-DAQ,DAQ-ALJN ).S.No Description of Items units QTY. Rates Amount1.0 AXLE COUNTERSupply1.1 Supply of High Frequency Digital Axle counterMulti section type complete system <strong>in</strong>clud<strong>in</strong>gCentral Evaluator(s)/Processor(s), f<strong>in</strong>al trackclearance relay <strong>for</strong> each track section, detectionpo<strong>in</strong>ts, mushroom hous<strong>in</strong>g <strong>for</strong> track side electronicequipment unit with complete assembly and fix<strong>in</strong>garrangement <strong>for</strong> each detection po<strong>in</strong>t, clampsdeflectors on each side of detection po<strong>in</strong>t and allother accessories fully wired to the ultimatecapacity and fully equipped <strong>for</strong> 15 Detection Po<strong>in</strong>tsand 13 Track Sections as per RDSO specificationno. RDSO/SPN/176/2005 (Ver. 2) and OEM'sspecification1.2 Tool kit <strong>for</strong> Digital Axle counter(ETU 001)consist<strong>in</strong>g of follow<strong>in</strong>g items:(1) True RMS Digital Multimeter with probe set--1no. (2)Extended wired socket to <strong>in</strong>terface with diagnosticplug--1 no.(3) Selector switchon panel base-- 1 no. (4) Adjustable torque wrenchwith 13 mm and 19 mm <strong>in</strong>serts-- 1 set(5) 19 mm double ended spanner-- 1 no. (6)Dummy wheel-- 1 no.(7) Screwdriver set with ma<strong>in</strong>s tester-- 1no. Note: All themechanical tools should be of good quality likeTaparia, BOSCH etc. make1.3 Supply and <strong>in</strong>stallation of enclosure of dimension600W x 42U x 600D basic frame with 9 foldedprofile, top panel cutout and slotted with 3 part andbottom front glass door, rear sheet steel door,standard lock and key etc., RITTAL make orsimilar, suitable <strong>for</strong> hous<strong>in</strong>g theEvaluator/processor sub rack of Digital AxleCounter and all the associated cards.Nos 33 6606850.00 218026050.00Nos. 4 109200.00 436800.00Nos 33 30101.20 993339.60INSTALLATIONSignature of contractor Page 17 of 111 Dy CSTE /CTC/CNB


1.4 Installation, wir<strong>in</strong>g, test<strong>in</strong>g and commission<strong>in</strong>g ofMulti section digital axle counter's CentralEvaluator/Processor <strong>for</strong> the section/station<strong>in</strong>clud<strong>in</strong>g its associated all <strong>in</strong>door equipments andwir<strong>in</strong>g of the same to <strong>in</strong>tegrate with the exist<strong>in</strong>gMicro Lock-II system at stations/LSCs. This<strong>in</strong>cludes lay<strong>in</strong>g and term<strong>in</strong>ation of any cablerequired <strong>for</strong> <strong>in</strong>terfac<strong>in</strong>g <strong>in</strong>side the DWC pipe as perrailway representative at site.1.5 Installation of track device ( double rail contact )<strong>in</strong>clud<strong>in</strong>g digg<strong>in</strong>g of trench, track cross<strong>in</strong>g, lay<strong>in</strong>gof ant rodent, antioxidant and non flamepropagat<strong>in</strong>g type DWC pipe as per IS-14930 Part-1or II or latest and all other accessories as per siterequirement <strong>for</strong> lay<strong>in</strong>g of transmitter and receivercable. Installation of Track side electronic unitfoundation and earth<strong>in</strong>g as per OEM's guidel<strong>in</strong>esand specifications.SpareNos. 33 8000.00 264000.00Nos. 468 12600.00 5896800.001.6 CPU card <strong>for</strong> Multi section digital axle counter. Nos 7 247500 1732500.001.7 PSU card <strong>for</strong> Multi section digital axle counter. Nos 7 106700 746900.001.8 Central Evaluator Empty sub rack <strong>for</strong> Multi sectiondigital axle counter.Nos 7 185100 1295700.00Sub Total 229392089.602.0 Outdoor Execution2.1 Excavat<strong>in</strong>g and refill<strong>in</strong>g of trench as per cable routeplan 1 m deep and 300 mm wide after lay<strong>in</strong>g thecable to the level of ground with rammed earth. Itshall con<strong>for</strong>m to the safe distance from the track. Italso <strong>in</strong>cludes clear<strong>in</strong>g of the cable route of thebushes, trees etc. Lesser depth shall be paidproportionately as certified by Railway supervisor<strong>in</strong> charge at site. Cables shall be supplied byRailways.2.2 Horizontal bor<strong>in</strong>g under railway track/ road <strong>for</strong>lay<strong>in</strong>g 125 mm dia., DWC (Double WalledCorrugated) pipes at the depth of 1.4 meter to 2.1meter from <strong>for</strong>mation level (Level of earth belowballast) as per draw<strong>in</strong>g and directed by eng<strong>in</strong>eer-<strong>in</strong>chargeby trenchless technology exclud<strong>in</strong>g the costof DWC pipes (a) The cost shall <strong>in</strong>clude horizontalbor<strong>in</strong>g through any <strong>in</strong>termediate structure eithernatural or man made or any boundary or strata.(b) The rate is <strong>in</strong>clusive of all the materials,equipments and labour required <strong>for</strong> do<strong>in</strong>gtrenchless horizontal bor<strong>in</strong>g. Noth<strong>in</strong>g extra shall bePerMtr.PerMtr.102000 37.74 3849467.002800 3268.02 9150445.92Signature of contractor Page 18 of 111 Dy CSTE /CTC/CNB


payable on any account other than the rates above.(c) The pipes are to be laid under the railwaytrack/road. All necessary arrangements,precautions are to arranged by the contractor sothat the bore com<strong>in</strong>g out at the other end is notdeviated by more than 250 mm <strong>in</strong> horizontal andvertical direction. (d) The rate shall <strong>in</strong>clude thedetection and protection of the railway utilitiesencountered underground dur<strong>in</strong>g bor<strong>in</strong>g work.(e)The payment shall be done only when the DWCpipe is laid <strong>in</strong> the bore.2.3 Lay<strong>in</strong>g of Signall<strong>in</strong>g / Telecom / Power cables ofdifferent sizes as per cable route plan approved byrailways and as per Railway representative at site.Meggar<strong>in</strong>g of cable to be done be<strong>for</strong>e and after thelay<strong>in</strong>g <strong>for</strong> the realisation of the payment under thisitem.2.4 Term<strong>in</strong>ation of all the core of all type of outdoorcable after its lay<strong>in</strong>g on both ends under thesupervision of railway representative. This also<strong>in</strong>cludes preparation of test report <strong>for</strong> core to coreand core to earth on prescribed <strong>for</strong>mat <strong>for</strong> eachcore of the cable. This also <strong>in</strong>cludes dress<strong>in</strong>g andlac<strong>in</strong>g of the cable on both ends. Per<strong>for</strong>ma <strong>for</strong>test<strong>in</strong>g and lac<strong>in</strong>g material to be supplied by thecontractor.2.5 Supply of DWC Pipe HDPE (ElectREX/TeleREX orsimilar) <strong>for</strong> under ground signal<strong>in</strong>g/communicationcable protection, 103.5mm <strong>in</strong>ner dia & 120mmouter dia <strong>in</strong> 6 m straight length as per BSEN 50086-1 & BSEN 50086-2,4 & BIS draft spec DOC HQLTD 14(5071) & ETD 5072) to spec IS 14930 partII. Note-One coupler <strong>for</strong> jo<strong>in</strong><strong>in</strong>g shall be suppliedwith each 6 mtr length. Inspection by RITES only.2.6 Excavation, Cast<strong>in</strong>g, Concret<strong>in</strong>g & cur<strong>in</strong>g offoundation and erection of Appt. case (s<strong>in</strong>gle) as perdrg no. RE/S&T/ALD/SK/219/82 with Alt'A' and221/82 with Alt'B. All materials such as cement,sand, aggregate and anchor bolt shall be suppliedby the contractor. Contractor shall carry out allprior preparations <strong>for</strong> the above scope of work.2.7 Excavation, Cast<strong>in</strong>g, Concret<strong>in</strong>g & cur<strong>in</strong>g offoundation and erection of Appt. case (quarter) asper drg no. RE/S&T/ALD/SK/227/82 or latest. Allmaterials such as cement, sand, aggregate andanchor bolt shall be supplied by the contractor.Contractor shall carry out all prior preparations <strong>for</strong>the above scope of work.2.8 Fabrication and fix<strong>in</strong>g of Hylum board <strong>in</strong> locationboxes by provid<strong>in</strong>g all fixtures with contractor ownmaterialPerMtr.PercorePerMtr.112000 4.00 447550.4930000 8.20 246015.002800 366.39 1025897.46Nos 410 7084.62 2904696.23Nos 66 3439.54 227009.64NosSignature of contractor Page 19 of 111 Dy CSTE /CTC/CNB


a Apparatus Case Full Nos 410 1726.71 707951.10b Apparatus Case Quarter Nos 66 778.10 51354.602.9 Supply of term<strong>in</strong>al block M-6 (ARA term<strong>in</strong>al as perIRS spc. No. IRS-S-75/2006(Rev 2) or latest and IRSdrg no. SA-23741/A Alt-4.2.10 Fix<strong>in</strong>g of ARA term<strong>in</strong>al and fuse blocks withprovision of holes on Hylum sheet and fix<strong>in</strong>g bygalvanised nuts and bolts. This <strong>in</strong>cludes provision oftwo additional holes on the hylem board on eitherside <strong>for</strong> cable entry. The work shall be done as perthe <strong>in</strong>structions of railway supervisor at site.2.11 Supply of Hylem sheet, res<strong>in</strong> bonded 10mm thick,grade P3 <strong>in</strong> standard size of 1.22x1.22 mtr as perspec no. IS 2036 of 1974.2.12 Supply of location boxes (Apparatus case) full withm<strong>in</strong>iature E type lock as per drg no.RE/S&T/ALD/SK/219/82 with Alt'A' and 221/82with Alt'B' . The keys of ward no 42 and handleshould be supplied at the rate of one per fourlocation boxes.2.13 Supply of location boxes (Apparatus case) quarterwith m<strong>in</strong>iature E type lock a spe rdrg no.RE/S&T/ALD/SK/220/82 with Alt'A' and 221/82with Alt'B' . The keys of ward no 42 and handleshould be supplied at the rate of one per fourlocation boxes.2.14 Pa<strong>in</strong>t<strong>in</strong>g of two coats of Red oxide and Enamel<strong>in</strong>side and outside of location boxesNos 15000 77.05 1155791.25Nos 15000 11.48 172210.50Nos 110 5254.10 577951.32Nos 410 13188.4698 5407272.62Nos 66 8517.58 562160.28(a) Full Loc Box Nos 410 501.52 205623.20(b) Qtr Loc Box Nos 66 184.93 12205.382.15 Letter<strong>in</strong>g, Number<strong>in</strong>g, Term<strong>in</strong>ation particulars<strong>in</strong>side and outside the Loc boxesNos(a) Full Loc Box Nos 410 278.51 114189.10(b) Qtr Loc Box Nos 66 88.19 5820.54Signature of contractor Page 20 of 111 Dy CSTE /CTC/CNB


2.16 Supply of GI pipe B class 100mm dia, 3 mm thick Bclass(as per Spec no. IS 1239PT.1/19900 per<strong>for</strong>atedat a distance of 20 cm or less of required length.RITES or authorised representative of railways willcarry out the <strong>in</strong>spection.PerMtr.800 795.31 636248.042.17 Fix<strong>in</strong>g of GI pipe B class 100mm dia, 3 mm thick Bclass(as per Spec no. IS 1239PT.1/19900 per<strong>for</strong>atedat a distance of 20 cm or less of required length atculverts/ bridges suitably concreted at both ends tobe filled with chattered compound. All fitt<strong>in</strong>gsrequired <strong>for</strong> fix<strong>in</strong>g to be supplied by contractor2.18 Supply & lay<strong>in</strong>g of RCC pipe <strong>in</strong>clud<strong>in</strong>g split pipewhere required 150mm dia withcollars9specification no. IS-460/1974)<strong>in</strong> the trenchacross the track/road & LC gates etc. as per drg.No. NR/S&T/CON/1.3.97PerMtr.PerMtr.800 45.92 36738.24100 196.2 19620.002.19 Supply and fix<strong>in</strong>g of earth electrode as per standard Nos. 477 2336.98 1114740.77practice. The item <strong>in</strong>cludes digg<strong>in</strong>g of pit <strong>in</strong> earth, 3meters and fix<strong>in</strong>g of earth electrode pipes. Cast<strong>in</strong>gof cement concrete enclosures as per Drg no.NR/S&T/CON/6.3/97. The soil treatment should bedone as per the standard practice. The item <strong>in</strong>cludesprovision of MS flat of size 35x6 mm2, wires andsolder<strong>in</strong>g of lead wires. The other end of the MS flatto be connected by bolt/solder<strong>in</strong>g to the signall<strong>in</strong>gequipment as per <strong>in</strong>struction of Railway siteeng<strong>in</strong>eer. All material like earth electrode, cement,solder<strong>in</strong>g material etc to be supplied by contractor.2.20 Supply of Ma<strong>in</strong>tenance kit: Each kit consists <strong>for</strong> P/Set 4 2940.27 11761.09items as per list below: -i) Spanner D/E 30x32 mm =1No ii)Spanner D/E 18x19 mm =1No iii) Spannercomb<strong>in</strong>ation R<strong>in</strong>g and open end 19 mm =1Noiv) Spanner open end 50mm = 2 No v) Spannercomb<strong>in</strong>ation r<strong>in</strong>g and open end 30mm = 1No.vi)Spanner comb<strong>in</strong>ation R<strong>in</strong>g and open end40mm=2 Nos.vii) Handleextension =1Noviii) ‘L’ Handle=1No.ix) Box 30 and 19mm=1Nox) Cutter 4” cum stripp<strong>in</strong>g=1Noxi) Screwdriver 6” = 2 No.xii) Adjustable Wrench 375 mm = 1 No. xiii)Hammer Ball pan 1 ½ lb =1No.Sub Total 28642719.77Total 258034809.37Signature of contractor Page 21 of 111 Dy CSTE /CTC/CNB


OFFER LETTERToThe President of India,Act<strong>in</strong>g through the Deputy CSTE/CTC/CNB,IRPMU, NC Railway,KanpurName of Work: “Outdoor works <strong>in</strong> connection with the provision of Multi section digitalaxle counter <strong>for</strong> Dual Detection <strong>in</strong> 15 block sections of PNK-ALJN section of ALDdivision (JJK-KNS,KNS-PHD,PHD-PTX,PTX-ULD,ULD-SHW,SHW-BNT,BNT-EKL,EKL-ETW,TDL-MTI,JLS-PRA,PRA-HRS,HRS-SNS,SNS-MXK,MXK-DAQ,DAQ-ALJN )”..Sir, I/We …………………………… have read various conditions to tender heretoattached and hereby agree to abide by the said conditions. I/We also agree to keep thisTender open <strong>for</strong> acceptance <strong>for</strong> a period of 90 days from the date fixed <strong>for</strong> open<strong>in</strong>g thesame and <strong>in</strong> default thereof, I / We will be liable <strong>for</strong> <strong>for</strong>feiture of my/our SecurityDeposit. I / We offer to do this work as detailed below at the rates quoted below:S.NoSchedule Approximate Cost ofScheduleRates quoted by the tenderer (% Above/Below/At Par) (Both <strong>in</strong> figures and Words)1. Schedule Rs. 258034809.37/-(Twenty five crore eightylakhs thirty four thousandeight hundred n<strong>in</strong>e andpaisathirtyseven only)In FiguresIn WordsABOVE/BELOWI/We hereby b<strong>in</strong>d myself/ourselves to complete the work with<strong>in</strong> the time limits specified<strong>in</strong> the conditions of Tender. I/We also hereby agree to abide by the General conditions ofContract with latest amendments and special conditions of Contract and to carry out theworks accord<strong>in</strong>g to the specifications of materials and works laid down by the Railway<strong>for</strong> present contract.I/We declare that I/We have gone through the Rules, Regulations of Tender and ContractGeneral Conditions, Special conditions, Technical specifications and other particularsembodied <strong>in</strong> Volume-2 and have fully understood and agree to abide by them.Signature of contractor Page 22 of 111 Dy CSTE /CTC/CNB


Until a <strong>for</strong>mal agreement is prepared and executed, acceptance of this Tender shallconstitute, subject to modifications as may be mutually agreed to, a b<strong>in</strong>d<strong>in</strong>g contract,between us and the President of India act<strong>in</strong>g through the Chief Adm<strong>in</strong>istrative officer,North Central Railway, New Delhi or the authority as <strong>in</strong>dicated <strong>in</strong> the letter of acceptanceof my/our offer <strong>for</strong> this work.SIGNATURE OF <strong>TENDER</strong>ER [S](Please affix your Seal also, if any)Contractor's Address:Date:Signature of contractor Page 23 of 111 Dy CSTE /CTC/CNB


Section – IIChapter – 1Instructions to Tenderer&Conditions of Tender<strong>in</strong>gSignature of contractor Page 24 of 111 Dy CSTE /CTC/CNB


INDEX1. GENERAL INSTRUCTIONS2. INTERPRETATIONS3. LOCAL CONDITIONS4. COMPLIANCE TO <strong>TENDER</strong> CONDITIONS, TECHNICALSPECIFICATION & DRAWINGS5. EARNEST MONEY/BID GUARANTEE6. SUBMISSION OF OFFERS7. CONSTITUTION OF FIRM & POWER OF ATTORNEY8. UNIT PRICES9. VALIDITY OF OFFER10. RATES DURING NEGOTIATION11. INCOME TAX CLEARANCE CERTIFICATE12. PERIOD OF COMPLETION & TIME PROGRESS GRAPH13. OPENING OF <strong>TENDER</strong>14. NON-TRANSFERABILITY & NON-REFUNDABILITY15. ERRORS OMISSIONS & DISCREPANCIES16. WRONG INFORMATION BY <strong>TENDER</strong>ER17. CONSORTIUM BIDS18. QUALIFICATION CRITERIA19 DETERMINATION OF RESPONSIVENESS20. CORRECTION OF ERRORS21. CONVERSION TO SINGLE CURRENCY i.e. RUPEESSignature of contractor Page 25 of 111 Dy CSTE /CTC/CNB


22. SYSTEM PERFORMANCE GUARANTEE23. AUTHORITY FOR ACCEPTANCE24. PURCHASE PREFERENCE25. AGREEMENT26. <strong>TENDER</strong>ER'S ADDRESS27. FOREIGN EXCHANGESignature of contractor Page 26 of 111 Dy CSTE /CTC/CNB


Instructions to Tenderer & Conditions of Tender<strong>in</strong>g1 GENERAL INSTRUCTIONS1.1 Tenders are <strong>in</strong>vited on behalf of President of India act<strong>in</strong>g through ChiefAdm<strong>in</strong>istrative Officer/ IRPMU, Shivaji Bridge, New Delhi from established andreliable contractors <strong>for</strong> the work:‘Outdoor works <strong>in</strong> connection with the provision of Multi section digital axlecounter <strong>for</strong> dual detection <strong>in</strong> 15 block section of PNK-ALJN section of ALDdivision.(JJK-KNS,KNS-PHD,PHD-PTX,PTX-ULD,ULD-SHW,SHW-BNT,BNT-EKL,EKL-ETW,TDL-MTI,JLS-PRA,PRA-HRS,HRS-SNS,SNS-MXK,MXK-DAQ,DAQ-ALJN ).’1.2 The Preamble, Schedule of requirement of items, rates & quantities, GeneralConditions of contract, Special Conditions of Contract, Instructions to tenderers andconditions of tender<strong>in</strong>g, all Annexure & Forms etc. shall, hereafter, be collectivelyreferred to as the "Tender papers".Any clarifications required by the tenderer may be obta<strong>in</strong>ed from theDy Chief Signal and Telecommunication Eng<strong>in</strong>eer /CTC (Dy CSTE/CTC),Indian railway project management unit (IRPMU),Near Jhakarkati Bus stand, GT road, KanpurTelephone No. +91 512 2324167, 9794835864 (mobile).Kanpur- 208014.2. INTERPRETATIONSThe follow<strong>in</strong>g terms wherever occurr<strong>in</strong>g <strong>in</strong> the tender papers and wherever usedthroughout the execution of the work, shall, unless excluded by or repugnant to thecontext, have the mean<strong>in</strong>g attributed there to as follows: -"CONTRACT" Means the Agreement or Work Order result<strong>in</strong>g from the acceptanceby the Purchaser of this tender either <strong>in</strong> whole or <strong>in</strong> part."CONTRACTOR” Means the successful Tenderer, i.e., the Tenderer whose Tenderhas been accepted either <strong>in</strong> whole or <strong>in</strong> part.“CONTRACTOR’S REPRESENTATIVE” Shall mean a person <strong>in</strong> supervisorycapacity who shall be so declared by the contractor and who shall be authorisedunder a duly executed power of attorney to receive materials issued by the Purchaserto the Contractor <strong>for</strong> the works. He shall be responsible <strong>for</strong> proper execution ofworks at each or all places and shall take orders from Purchaser's Eng<strong>in</strong>eers andcarry out the same.Signature of contractor Page 27 of 111 Dy CSTE /CTC/CNB


"ENGINEER" Shall mean the Divisional Eng<strong>in</strong>eer/Divisional ElectricalEng<strong>in</strong>eer/Divisional Signal & Telecom. Eng<strong>in</strong>eer or the Assistant Eng<strong>in</strong>eers <strong>in</strong>executive charge of the Railway works and shall <strong>in</strong>clude the superior officers of theRailway. He is responsible <strong>for</strong> ensur<strong>in</strong>g that all field works covered by the contractare carried out <strong>in</strong> accordance with approved designs, draw<strong>in</strong>gs and specificationsand conditions of contract as agreed to.“ENGINEER’S REPRESENTATIVE" shall mean the Sr. Section Eng<strong>in</strong>eers/Section Eng<strong>in</strong>eers <strong>in</strong> direct charge of the works of Signal &Telecom./Civil/Electrical Eng<strong>in</strong>eer<strong>in</strong>g department of Railway."EQUIPMENT” Means all or any equipment considered necessary by thePurchaser's Eng<strong>in</strong>eers <strong>for</strong> the satisfactory operation, as a whole, of the <strong>in</strong>stallations.“GENERAL MANAGER" Means the officer <strong>in</strong> Adm<strong>in</strong>istrative charge of thisRailway and shall mean and <strong>in</strong>clude the officers to whom the functions aredelegated. His postal address shall be <strong>in</strong>timated to the successful Tenderers <strong>in</strong> duecourse."MONTH” Means One English Calendar Month."MATERIALS” Means all equipment, components, fitt<strong>in</strong>gs and other materials<strong>in</strong>clud<strong>in</strong>g raw materials required to complete the work."PURCHASER” Means the President of India act<strong>in</strong>g through his accredited officersor any one of them. The Chief Project Manager / IRPMU, North Central RailwayNew Delhi shall be deemed to be one of such accredited officers.Subject as otherwise provided <strong>in</strong> this contract, all notices to be given and all otheraction to be taken on behalf of President of India may be given or taken on hisbehalf by General Manager, North Central Railway Allahabad/ Chief Adm<strong>in</strong>istrativeOfficer, North Central Railway New Delhi or any other representative of the NorthCentral Railway Adm<strong>in</strong>istration nom<strong>in</strong>ated by him.“PURCHASER’S ENGINEERS" Means the Chief Adm<strong>in</strong>istrative Officer / IRPMUNorth Central Railway or successor who will decide all matters relat<strong>in</strong>g tosurvey, design, manufacture, <strong>in</strong>stallation and commission<strong>in</strong>g of the plant andequipment at site."RAILWAY” Shall mean the President of the Republic of India or theAdm<strong>in</strong>istrative Officers of the Railway or of the successor Railway authorised todeal with any matters with which these present are concerned on his behalf."SUB-CONTRACTOR" Means an <strong>in</strong>dividual or a firm of Contractor or aCompany registered under Indian Company Act or an approved supplier of materialsto whom the Contractor sublets portions of the contract after obta<strong>in</strong><strong>in</strong>g specific priorSignature of contractor Page 28 of 111 Dy CSTE /CTC/CNB


approval of the Purchaser <strong>in</strong> writ<strong>in</strong>g to sub-lett<strong>in</strong>g of contract."SITE" Means the areas to be taken up <strong>for</strong> the execution of works, togetherwith any other area or areas as shall be determ<strong>in</strong>ed by the Purchaser's Eng<strong>in</strong>eers,which may be placed at the disposal of the Contractor <strong>for</strong> the purpose of thecontract and also such area or areas used <strong>for</strong> store yards, works yards or workshop<strong>in</strong> proximity of the works as the Purchaser' Eng<strong>in</strong>eers may have authorised as anextension of the site, irrespective of the terms and conditions under which they areoccupied by the Contractor."<strong>TENDER</strong>ER" Means and <strong>in</strong>cludes any firm of eng<strong>in</strong>eers or Contractors or anycompany or body, corporate or otherwise, who submit the Tender which has been<strong>in</strong>vited.“WORK OR WORKS" Means all or any of the items of the work <strong>for</strong> which theTenderer/ Contractor has Tendered/contracted accord<strong>in</strong>g to the specifications,draw<strong>in</strong>gs and Annexure hereto annexed or to be implied there from, or <strong>in</strong>cidentalthereto or to be hereafter specified or required <strong>in</strong> such explanatory<strong>in</strong>structions and draw<strong>in</strong>gs, be<strong>in</strong>g <strong>in</strong> con<strong>for</strong>mity with the orig<strong>in</strong>al specifications,draw<strong>in</strong>gs, Annexure and schedules, and also such <strong>in</strong>structions and draw<strong>in</strong>gsadditional to the a<strong>for</strong>ementioned as may from time to time be issued by thePurchaser's Eng<strong>in</strong>eer dur<strong>in</strong>g the progress of the contracted work."WRITING" Includes all matters written, typewritten or pr<strong>in</strong>ted either <strong>in</strong> whole or<strong>in</strong> part.3. LOCAL CONDITIONS3.1 It will be imperative <strong>for</strong> each tenderer to fully acqua<strong>in</strong>t himself with all the localconditions and factors which would have any effect on the per<strong>for</strong>mance of thecontract and cost of the stores. The purchaser shall not enterta<strong>in</strong> any request <strong>for</strong>clarifications from the tenderer regard<strong>in</strong>g such local conditions. No request <strong>for</strong> thechange of price or time schedule of delivery of stores shall be enterta<strong>in</strong>ed after theoffer is accepted by the purchaser on account of any local condition or factor.3.2 In the event of the tenderer desir<strong>in</strong>g to have a field survey be<strong>for</strong>e furnish<strong>in</strong>g hisquotations, he may apply to Railways <strong>for</strong> permission <strong>in</strong> this regard. Suchpermission will be given <strong>in</strong> writ<strong>in</strong>g by the Railways but the expenses <strong>in</strong> this regardwill be borne by the tenderer completely.3. 3 The <strong>in</strong>tend<strong>in</strong>g tenderer is advised to study the tender papers carefully. Anysubmission of a quotation by the tenderer shall be deemed to have been done after acareful study and exam<strong>in</strong>ation of these documents with full understand<strong>in</strong>g of theimplication thereof. These conditions and specifications shall be deemed to havebeen accepted unless otherwise, specifically commented upon by the Tenderer <strong>in</strong> hisSignature of contractor Page 29 of 111 Dy CSTE /CTC/CNB


quotation. Failure to adhere to anyone or all these <strong>in</strong>structions may render his offerliable to be ignored without any reference.3.4 Should a tenderer f<strong>in</strong>d discrepancies <strong>in</strong> or omission from the draw<strong>in</strong>g or any of theTender papers or he has any doubt to their mean<strong>in</strong>g, he should at once notify theRailway who may send a written clarification to all tenderers.4. COMPLIANCE TO <strong>TENDER</strong> CONDITIONS, SPECIFICATION &DRAWINGS4.1 Tenderer should note works shall con<strong>for</strong>m to relevant specifications as mentioned <strong>in</strong>Preamble or schedule of requirement or elsewhere. Any equipment /work required tomake the <strong>in</strong>terface equipments match with exist<strong>in</strong>g equipment is the responsibility of thecontractor. Indian Railway will not undertake any change <strong>in</strong> their exist<strong>in</strong>g equipment, norshall bear any extra cost on account of changes/addition required <strong>for</strong> ensur<strong>in</strong>gcompatibility of <strong>in</strong>terface devices with exist<strong>in</strong>g equipments/mechanisms.4.2 The tenderer shall <strong>in</strong>dicate paragraph by paragraph <strong>for</strong> each section and each clauseand sub-clause of the tender document - Pre-amble, Instructions to tenderers andconditions of tender<strong>in</strong>g, Special conditions of Contract, Technical Specifications &Installation practices, that either his tender complies <strong>in</strong> every respect with therequirements of each clause and sub-clause or if not, precisely how they differ fromthe requirements of the tenderer. In later case, the tenderer shall enclose a separatestatement as per pro-<strong>for</strong>ma given, <strong>in</strong>dicat<strong>in</strong>g only the deviations <strong>for</strong> any clause orsub-clause which he proposes with "detailed justifications <strong>for</strong> deviations proposed".The purchaser, reserves the right to accept or reject these deviations and his decisionthereon shall be f<strong>in</strong>al. (See Form 5).4.3 The equipment & material offered shall be <strong>in</strong> accordance with the draw<strong>in</strong>gs andspecifications. Details of variation from the draw<strong>in</strong>gs and specifications, if any,should be clearly <strong>in</strong>dicated and <strong>in</strong> such an event, a certificate from the users must befurnished to the effect that the product offered per<strong>for</strong>ms the requisite functionssatisfactorily, & is an alternative acceptable <strong>in</strong> one or more other countries. Thename of users <strong>in</strong> those <strong>for</strong>eign countries should also be <strong>in</strong>dicated.4.4 Firms who have not carried out the works and supplied the items tendered <strong>for</strong> <strong>in</strong> thiscase <strong>for</strong> the Indian Railways <strong>in</strong> the past should give details of supplies and workscarried out and the customers along with their per<strong>for</strong>mance certificates.5. EARNEST MONEY/BID GUARANTEE5.1 The Tenderer shall deposit <strong>in</strong> favour of the F<strong>in</strong>ancial Adviser & Chief AccountsOfficer/IRPMU/New Delhi, North Central Railway, the desired earnest money is14,40,175/-(Forteen lakhs <strong>for</strong>ty thousand one hundred seventy five only).1) The tenderer shall be required to deposit Earnest Money with the tender <strong>for</strong> the dueSignature of contractor Page 30 of 111 Dy CSTE /CTC/CNB


per<strong>for</strong>mance with the stipulation to keep the offer open till such date as specified <strong>in</strong> thetender, under the conditions of tender.Value of the work (Tender value)For works estimated to cost upto Rs. 1crore.For works estimated to cost more thanRs. 1 crore.EMD2% of the estimated cost of the work.Rs. 2 Lakhs plus ½% (half percent) of the excessof estimated cost of work beyond Rs. 1 croresubject to a maximum of Rs. 1 crore.The Earnest Money shall be rounded to the nearest Rs. 10/-. (on the higher value side)2) The Earnest Money should be <strong>in</strong> cash or <strong>in</strong> any of the follow<strong>in</strong>g <strong>for</strong>ms:-i ) Deposit Receipts, Pay orders, Demand Drafts,. These <strong>for</strong>ms of Earnest Money could beeither of the State Bank of India or of any of the nationalized Banks. No confirmatory advicefrom the Reserve Bank of India will be necessary.ii) Deposit receipts executed by the scheduled banks (other than the State Bank of India andthe Nationalized Banks) approved by the Reserve Bank of India <strong>for</strong> this purpose. TheRailways will not, however, accept deposit receipt without gett<strong>in</strong>g <strong>in</strong> writ<strong>in</strong>g the concurrenceof the Reserve Bank of India.iii) In case the Earnest money is deposited <strong>in</strong> cash the payment should be made to the ChiefCashier, North Central Railway, Allahabad and cash receipts obta<strong>in</strong>ed from him should befurnished along with the tender.5.2 No reference to the previous deposit of Earnest Money and Security Deposit <strong>for</strong>adjustment aga<strong>in</strong>st the present tender will be accepted and any request <strong>for</strong>recovery from any security deposit aga<strong>in</strong>st present tender will not be enterta<strong>in</strong>ed.5.3 The Earnest Money shall rema<strong>in</strong> deposited with the Purchaser <strong>for</strong> the period of 90days from the date of open<strong>in</strong>g of the tender. If the validity of the offer is extended,the earnest Money deposit duly extended shall also be furnished, fail<strong>in</strong>g which theoffer after the expiry of the a<strong>for</strong>esaid period shall not be considered by thePurchaser.5.4 No <strong>in</strong>terest will be payable by the Railway on the Earnest Money.5.5 The Earnest Money deposited is liable to be <strong>for</strong>feited if the tenderer withdraws oramends, impairs or derogates from the tender <strong>in</strong> any respect with<strong>in</strong> the period ofvalidity of his offer.5.6 The Earnest Money of the successful tenderer will be reta<strong>in</strong>ed as <strong>in</strong>itial securitydeposit <strong>for</strong> the due and faithful fulfilment of the contract. This amount ofSecurity Deposit will be <strong>for</strong>feited if the tenderer fails to execute the agreementwith<strong>in</strong> seven days after receipt of notice issued by Railway that such documentsare ready or to commence the work with<strong>in</strong> 15 days after receipt of the orders tothat effect.Signature of contractor Page 31 of 111 Dy CSTE /CTC/CNB


5.7 The Earnest Money of all unsuccessful tenderer will be returned by the Purchaserwith<strong>in</strong> reasonable time after the f<strong>in</strong>alisation of the tender.5.8 Any tender not accompanied by Earnest Money <strong>in</strong> one of the approved <strong>for</strong>ms willbe summarily rejected.6. SUBMISSION OF OFFERS6.1 All offers <strong>in</strong> the prescribed <strong>for</strong>ms should be submitted be<strong>for</strong>e the time and date fixed<strong>for</strong> the receipt of the offers. Offers received after the stipulated time and date willbe dealt with as per rules <strong>in</strong> vogue <strong>in</strong> the Railways.6.2 In case the date of open<strong>in</strong>g happens to be a holiday or Bandh, the tender will bereceived and opened at the same time on the next work<strong>in</strong>g day.6.3 All offers shall be either type written or written neatly <strong>in</strong> <strong>in</strong>delible <strong>in</strong>k <strong>in</strong> English.Each page of the offer must be numbered consecutively. A reference to total numberof pages compris<strong>in</strong>g the offer must be made at the top right hand corner of the toppage. All the support<strong>in</strong>g documents should be submitted either <strong>in</strong> orig<strong>in</strong>al or dulyattested by a gazetted officer or notary public unless stated otherwise <strong>in</strong> thesedocuments. The orig<strong>in</strong>al documents shall be produced <strong>for</strong> verification when called<strong>for</strong>.6.4 All copies of the tender paper shall be signed <strong>in</strong> <strong>in</strong>k by the tenderer on each page<strong>in</strong>clud<strong>in</strong>g clos<strong>in</strong>g page, <strong>in</strong> token of his hav<strong>in</strong>g studied the Tender papers carefully.6.5 RATES IN FIGURES & WORDS: - All prices and other <strong>in</strong><strong>for</strong>mation like discountsetc. hav<strong>in</strong>g a bear<strong>in</strong>g on the price shall be written both <strong>in</strong> figures and <strong>in</strong> words <strong>in</strong> theprescribed offer <strong>for</strong>m. In case of difference <strong>in</strong> words and figures the amount written<strong>in</strong> words will be taken <strong>in</strong>to consideration.6.6 ATTESTATION OF ALTERATION: - No scribbl<strong>in</strong>g is permissible <strong>in</strong> the tenderdocuments. Tender conta<strong>in</strong><strong>in</strong>g erasures and alterations <strong>in</strong> the tender documents areliable to be rejected. Any correction made by the tenderer/tenderers <strong>in</strong> his/theirentries must be attested by him/them.6.7 The tenderer shall submit his tender <strong>in</strong> sealed cover. The tender shall be complete <strong>in</strong>all respects.6.8 The envelope should bear the tender number with description and date ofclos<strong>in</strong>g/open<strong>in</strong>g clearly written on it and addressed to the Deputy Chief Signal &Telecommunication Eng<strong>in</strong>eer/CTC/CNB, Old Microwave Build<strong>in</strong>g, Juhi, Kanpur.(a)The bid shall consist of the follow<strong>in</strong>g:-i) Offer letter complete. Form No.1Signature of contractor Page 32 of 111 Dy CSTE /CTC/CNB


ii)iii)iv)Schedule of Supply and Execution offer percentage above & below the estimatedprice.Earnest money <strong>in</strong> prescribed <strong>for</strong>m. (Para 5.0 of I.T.T.(Instructions to Tenderers))Clause-wise compliance to tender conditions & Statements of deviations.Form No. 5 (Para 4 of I.T.T.)v) Tenderer's credentials and will<strong>in</strong>gness of orig<strong>in</strong>al manufacturer as per Form No.13Qualify<strong>in</strong>g Criteria (General) (Para 18.1 of I.T.T.).vi)Similar works executed. (Para 18.2 of I.T.T.).vii) Works <strong>in</strong> hand (para 18.2 of I.T.T.).viii) Income Tax Clearance Certificate, audited balance sheet (Para 18.3 of I.T.T.).ix)Eng<strong>in</strong>eer<strong>in</strong>g Organization (Para 18.5 of I.T.T.).x) Construction Mach<strong>in</strong>ery (Para 18.6 of I.T.T.).xi) Details of recommended Spares with quantities (S.C.C. Para 13).xii) Details of special tools & <strong>in</strong>stallation materials (S.C.C. Para 11).xiii) System Per<strong>for</strong>mance Guarantee (Para 22 of I.T.T.).xiv) Tenderers scheme of work and Time Schedule (Para 12 of I.T.T.).xv)Complete technical data and particulars of the equipment offered, as specified <strong>in</strong> theTender papers together with descriptive literature, leaflets etc. Draw<strong>in</strong>gs, if any,complete with list (Para 18.4 of I.T.T.).xvi) Name of manufacturers, place of manufacture and the certificate <strong>for</strong> proven designand per<strong>for</strong>mance (Para 18.4 of I.T.T.)xvii) Technical proposal of the tenderer <strong>in</strong> con<strong>for</strong>mity with system design or alternativeproposal of the tenderer, if any.xviii) Any other <strong>in</strong><strong>for</strong>mation desired to be submitted by the tenderer.7. CONSTITUTION OF FIRM & POWER OF ATTORNEY7.1 Any <strong>in</strong>dividual(s) sign<strong>in</strong>g the tender or other documents connected therewith shouldSignature of contractor Page 33 of 111 Dy CSTE /CTC/CNB


specify whether he is sign<strong>in</strong>g: -(a)As sole proprietor of the concern or as attorney of the sole proprietor;(b) As a Director, Manager or Secretary <strong>in</strong> the case of Limited Company dulyauthorised by a resolution passed by the Board of Directors or <strong>in</strong> pursuance of theauthority conferred by Memorandum of Association.7.2 In the case of the firm not registered under the Indian Partnership act, the names of allthe exist<strong>in</strong>g partners and their full particulars at the time of submitt<strong>in</strong>g the tender and allthe partners with their full particulars or the attorney duly authorized by all of them shouldsign the tender and all the other connected documents. The orig<strong>in</strong>al power of attorney orother documents empower<strong>in</strong>g the <strong>in</strong>dividual or <strong>in</strong>dividuals to sign should be furnished tothe purchaser <strong>for</strong> verification, if required.7.3 The Railway will not be bound by Power of Attorney granted by the tenderer or bythe changes <strong>in</strong> the composition of the firm made subsequent to the execution of thecontract. It may, however, recognize such power of attorney and advice, the cost ofwhich will be chargeable to the contractor. These charges have been fixed atRs.100/- (Rs. One Hundred only) payable by the tenderer at the time of submitt<strong>in</strong>gthe Power of Attorney <strong>for</strong> Scrut<strong>in</strong>y and legal advice.7.4 In case where the Power of Attorney partnership deed has not been executed <strong>in</strong>English, the true and authenticated copies of the translation of the same byAdvocate, authorised translators of Courts and Licensed Petition Writers should besupplied by the Contractor(s) while tender<strong>in</strong>g <strong>for</strong> the work.7.5 The cancellation of any documents such as Power of Attorney etc. should be <strong>for</strong>thwithcommunicated by the contractor to the Railway Adm<strong>in</strong>istration <strong>in</strong> writ<strong>in</strong>g fail<strong>in</strong>gwhich the Railway Adm<strong>in</strong>istration shall have neither responsibility nor liability <strong>for</strong> anyact so taken on the strength of the said documents.8. UNIT PRICES8.1 The Unit Prices should be quoted by the Contractor after tak<strong>in</strong>g all the relevantfactors <strong>in</strong>to consideration and these should be Firm and all <strong>in</strong>clusive without anyvariation clauses. The prices shall be quoted <strong>in</strong> Indian rupees <strong>for</strong> the units undermetric system. Reference may be made to Para-38 of Special Conditions ofContract.8.2 Necessary ‘D’ <strong>for</strong>m shall be issued if applicable, by the Railway adm<strong>in</strong>istration oncontractor’s name only <strong>for</strong> supply of materials where central sales tax is levied. Thetenderer shall take it <strong>in</strong>to consideration while quot<strong>in</strong>g the rates.9. VALIDITY OF OFFERSignature of contractor Page 34 of 111 Dy CSTE /CTC/CNB


9.1 The tenderer shall keep the offer open <strong>for</strong> a m<strong>in</strong>imum period of 90 days from thedate of open<strong>in</strong>g of the tender. With<strong>in</strong> that period, the tenderer can not withdraw hisoffer subject to the period be<strong>in</strong>g extended further if required by mutual agreementfrom time to time. Any contravention of the above condition will make the tendererliable <strong>for</strong> <strong>for</strong>feiture of his Earnest Money Deposit.10. RATES DURING NEGOTIATION10.1 The tenderer/s shall not <strong>in</strong>crease his/their quoted rates <strong>in</strong> case the RailwayAdm<strong>in</strong>istration negotiate <strong>for</strong> reduction of rates, such a negotiation shall not amountto cancellation or withdrawal of the orig<strong>in</strong>al offer and the rates orig<strong>in</strong>ally quotedwill be b<strong>in</strong>d<strong>in</strong>g on the tenderer/s.11. INCOME TAX CLEARANCE CERTIFICATE11.1 The Tenderers are required to enclose along with the tender a Photostat copy of thevalid Income Tax clearance certificate duly attested by Notary Public. The Tendererwill however submit the orig<strong>in</strong>al Income Tax clearance certificate whenever asked<strong>for</strong> by the purchaser <strong>for</strong> verification.12. PERIOD OF COMPLETION & TIME PROGRESS GRAPH12.1 The works/work are/is to be completed with<strong>in</strong> a period as mentioned <strong>in</strong> preamblefrom the date of issue of Letter of Acceptance of the tender.12.2 The Tenderer shall enclose with his offer the scheme of work and time schedule <strong>in</strong>the <strong>for</strong>m of PERT chart <strong>in</strong>dicat<strong>in</strong>g all activities & show<strong>in</strong>g the period of time that hewill take <strong>for</strong> the various items of work listed there<strong>in</strong>. The Tenderer shall <strong>in</strong>dicate <strong>in</strong>the <strong>for</strong>m of notes to the schedule the assumptions and the basis adopted <strong>for</strong> thepreparation of the time schedule.12.3 The Successful Tenderer shall, however, submit their f<strong>in</strong>al programme <strong>in</strong>consultation with Eng<strong>in</strong>eer of the project <strong>in</strong> terms of clause 6 of Special Conditionof Contract.13. OPENING OF <strong>TENDER</strong>13.1 The tender will be opened at the time & date of open<strong>in</strong>g of the tender given <strong>in</strong> thepreamble <strong>in</strong> presence of such Tenderers /Representatives who choose to be present.13.2 If the offers are sent by post, should be sent only by registered post withacknowledgement duly addressed to The Deputy Chief Signal &Telecommunication Eng<strong>in</strong>eer/CTC/CNB, Old Microwave Build<strong>in</strong>g, Juhi, Kanpurclearly <strong>in</strong>dicat<strong>in</strong>g the contents as given <strong>in</strong> para 6.8. Offer sent by post must reach theSignature of contractor Page 35 of 111 Dy CSTE /CTC/CNB


office of Deputy Chief Signal & Telecommunication Eng<strong>in</strong>eer/CTC, OldMicrowave Build<strong>in</strong>g, Juhi, Kanpur be<strong>for</strong>e the clos<strong>in</strong>g time and date given <strong>in</strong> thepreamble.14. NON-TRANSFERABILITY & NON-REFUNDABILITYThe tender documents are not transferable. The cost of tender paper is notrefundable.15. ERRORS OMISSIONS & DISCREPANCIESThe Contractor(s) shall not take any advantage of any mis<strong>in</strong>terpretation of theconditions due to typ<strong>in</strong>g or any other error and if <strong>in</strong> doubt shall br<strong>in</strong>g it to the noticeof the Eng<strong>in</strong>eer, without delay. In case of any contradiction only the pr<strong>in</strong>ted rules,and books should be followed and no claim <strong>for</strong> the mis<strong>in</strong>terpretation shall beenterta<strong>in</strong>ed.16. WRONG INFORMATION BY <strong>TENDER</strong>ERIf the tenderer/s deliberately gives/give wrong <strong>in</strong><strong>for</strong>mation <strong>in</strong> his/their tender,creates/create circumstances <strong>for</strong> the acceptance of his/their tender, the Railwayreserve the right to reject such tender at any stage.17. JV/CONSORTIUM/MOU BIDSConsortium bids are applicable. Documents to this regard shall be submitted withthe tender offer.CONSORTIUM BIDS:17.1 In view of nature of work covered <strong>in</strong> the Bid documents, it is anticipated that some of the<strong>in</strong>tend<strong>in</strong>g bidders will pool their resources and experience to <strong>for</strong>m consortia. In their own<strong>in</strong>terest, the bidders who <strong>for</strong>m such consortia are advised to <strong>in</strong>vestigate capabilities,availability of resources, experienced personnel, f<strong>in</strong>ancial soundness, past experience andconcurrent engagements of constitut<strong>in</strong>g partners.17.2 Consortia of bidders, if any must clearly def<strong>in</strong>e role/scope of work of eachpartner/member. Further the legal agreement <strong>for</strong> a consortium must accompany the bidand should clearly def<strong>in</strong>e the leader of such a consortium who will be the primecontractor and will be responsible <strong>for</strong> timely completion of work as also dur<strong>in</strong>gexecution of work, if awarded, co-ord<strong>in</strong>ate with Purchaser on behalf of the consortium,receive payments <strong>for</strong> the works executed and be liable <strong>for</strong> due per<strong>for</strong>mance of thecontract <strong>in</strong> all respect. The tenderer must clearly write whether the offer isConsortium Bid or not. Remarks like ‘Complied’, ‘Noted’ will not suffice. Inabsence of clear submission, the offer will not be considered as Consortium Bid.17.3 Qualification documents, details etc., must however, be provided <strong>for</strong> each member firmcomplete <strong>in</strong> all respects strictly <strong>in</strong> requisite pro-<strong>for</strong>ma.17.4 A consortium <strong>for</strong>med will not be subject to alteration with regard to change <strong>in</strong>constitut<strong>in</strong>g firms and/or reorientation of roles. Any changes if proposed by consortiumSignature of contractor Page 36 of 111 Dy CSTE /CTC/CNB


to take advantage of certa<strong>in</strong> developments dur<strong>in</strong>g evaluation stage will render the bidliable to be rejected. As all details are required to be furnished along with the bids andshould be critically exam<strong>in</strong>ed dur<strong>in</strong>g evaluation of bids, it is imperative that such detailsshould have been thoroughly exam<strong>in</strong>ed as a safeguard aga<strong>in</strong>st a possible disqualificationof bids on these grounds.17.5 All partners of the consortium shall be jo<strong>in</strong>tly and severally liable to the purchaser <strong>for</strong> theexecution of the entire contract <strong>in</strong> accordance with its terms.18. QUALIFICATION CRITERIA18.1 GENERAL18.1.1 Qualification criteria under this para lays down m<strong>in</strong>imum acceptable qualifications<strong>in</strong> various areas to ensure that qualified bidder has necessary experience, expertise,f<strong>in</strong>ancial and human resources to successfully complete the project.18.1.2 If the tenderer proposes to buy any equipment from other suppliers/sources,documents <strong>in</strong>dicat<strong>in</strong>g their will<strong>in</strong>gness to supply the equipment and providetechnical support to the tenderer that may be required dur<strong>in</strong>g <strong>in</strong>stallation,commission<strong>in</strong>g and warranty period and later on directly to the railways, shall be<strong>in</strong>cluded <strong>in</strong> the tender. Qualification documents and other details <strong>for</strong> such suppliershall be <strong>in</strong>cluded <strong>in</strong> the tender.18.1.3 The tenderer should submit the details of experience <strong>in</strong> works and services <strong>in</strong>projects of similar nature br<strong>in</strong>g<strong>in</strong>g out clearly the expertise <strong>in</strong> the equipmentmanufacture, <strong>in</strong>stallation etc.18.1.4 The tenderer shall complete the pro-<strong>for</strong>ma at Form No.13 and submit a certificatefrom the orig<strong>in</strong>al user <strong>for</strong> whom the project was undertaken certify<strong>in</strong>g the date ofaward of contract, date of completion, date of commission<strong>in</strong>g and the presentwork<strong>in</strong>g state of the system so established. The tenderer shall provide these details<strong>for</strong> all the projects that he has executed which satisfy the m<strong>in</strong>imum requirements <strong>in</strong>each case.18.2 MINIMUM ELIGIBILITYThe tenderer should have m<strong>in</strong>imum eligibility criteria as given below:1. Tenderer(s) should have successfully executed dur<strong>in</strong>g last three f<strong>in</strong>ancial years (i.e.current year and three previous f<strong>in</strong>ancial years), at least one work of similar nature*of not less than 35% of the value of the present tender.2. As proof of sufficient f<strong>in</strong>ancial capacity and organizational resources, contractorshould have received total contract amount dur<strong>in</strong>g the last three f<strong>in</strong>ancial years and<strong>in</strong> current year a m<strong>in</strong>imum of 150% of the advertised value of work. As a proof ofthese qualify<strong>in</strong>g criteria, the tenderer should submit the audited balance sheet dulycertified by Chartered Accountant or attested certificates from the employer / client.(*) Def<strong>in</strong>ition of Similar Nature Works:Signature of contractor Page 37 of 111 Dy CSTE /CTC/CNB


“Work <strong>in</strong>volv<strong>in</strong>g Provision of track circuit<strong>in</strong>g by digital Axle count<strong>in</strong>g system”.Or “Any work <strong>in</strong>volv<strong>in</strong>g <strong>in</strong>stallation and commission<strong>in</strong>g of BPAC by digital axle count<strong>in</strong>gsystem.”18.3 FINANCIAL18.3.1 The tenderer should produce:i) Latest Income Tax clearance certificate.ii)Audited Balance Sheet and Income statement of just concluded year.18.3.2 The tenderer shall furnish such documents as to establish the f<strong>in</strong>ancial soundnessof his company as well as that of other companies if more than one company is<strong>in</strong>volved <strong>in</strong> bidd<strong>in</strong>g <strong>for</strong> this tender. The latest balance sheet, audited or certified bya neutral agency shall be furnished.18.3.3 The bidder shall submit required <strong>in</strong><strong>for</strong>mation <strong>in</strong> a separate Annexure and also acertificate from the user <strong>for</strong> whom the project was executed about the correctnessof the dates <strong>in</strong>volved and satisfactory per<strong>for</strong>mance of the equipment/system.18.4 TECHNOLOGY & EQUIPMENT18.4.1 The tenderer shall clearly identify the sources from which the equipment to besupplied under this tender will be obta<strong>in</strong>ed.18.4.2 All equipment proposed to be used shall be of proven design and per<strong>for</strong>mance. Theequipment of same family shall have been successfully commissioned andrema<strong>in</strong>ed <strong>in</strong> service at least <strong>for</strong> a period of one year on the date of tendersubmission. However, the tenderer shall supply latest version of the equipmentunder the standard. Certificate from the actual user of the equipment aboutsatisfactory per<strong>for</strong>mance shall be enclosed with the tender. Any equipmentproposed to be manufactured with <strong>for</strong>eign collaborator shall be covered by theper<strong>for</strong>mance guarantee of the <strong>for</strong>eign collaborator. Certificate from the actual userof the equipment about the satisfactory per<strong>for</strong>mance shall be enclosed with thetender. The tenderer should submit a declaration from that orig<strong>in</strong>al equipmentmanufacturer regard<strong>in</strong>g their Indian agent and the service support available with<strong>in</strong>the country.18.4.3 SOFTWARESoftware version of the equipment be<strong>in</strong>g supplied should be latest and must be<strong>in</strong>dicated.18.4.4 All the software upgrades and / or patches required <strong>for</strong> the ma<strong>in</strong>tenance of theSignature of contractor Page 38 of 111 Dy CSTE /CTC/CNB


system supplied will be implemented free of cost at each site <strong>for</strong> seven years byrespective bidders. Acceptance Test<strong>in</strong>g of the system will be got done by himthrough authority designated by Railways <strong>for</strong> all functions of all systems after theimplementation of the ma<strong>in</strong>tenance Software Upgrades / Patches <strong>in</strong> each system.18.5 ENGINEERING ORGANISATION18.5.1 The tenderer shall make an assessment of the requirement of personnel <strong>for</strong>execution of this project and shall give details as to how he proposes to mobiliseall technical manpower required <strong>for</strong> the project. Details of the qualification andexperience of the personnel identified <strong>for</strong> project execution shall be <strong>in</strong>cluded <strong>in</strong> thetender.18.5.2 The successful tenderer shall appo<strong>in</strong>t a Project Manager who has adequateexperience <strong>in</strong> project management of similar nature, unless the railway so desire,the Project Manager should preferably be reta<strong>in</strong>ed till all the obligations under thecontract have been fulfilled.18.5.3 Tenderer shall advise the number of Eng<strong>in</strong>eers, Supervisors and CableJo<strong>in</strong>ters/Artisans employed by him or go<strong>in</strong>g to be employed by him with theirnames, qualifications bio-data and experience <strong>in</strong> this particular trade underconsideration along with the Tender positively. Irrevocable letters of commitmentof the said Supervisors and Key Technicians/Artisans <strong>for</strong> do<strong>in</strong>g the work shall befurnished along with Tender Papers if they are not already <strong>in</strong> employment of theTenderer.18.6 CONSTRUCTION MACHINERYThe firm should have m<strong>in</strong>imum construction mach<strong>in</strong>ery, Tools and plants, test &measur<strong>in</strong>g <strong>in</strong>struments, Vehicles etc. <strong>for</strong> carry<strong>in</strong>g out the work. No tools, plants,scaffold<strong>in</strong>g, mach<strong>in</strong>ery etc. shall be supplied by railways and contractor shall makehis own arrangements <strong>for</strong> execut<strong>in</strong>g the work.19 DETERMINATION OF RESPONSIVENESSNot applicable.20. CORRECTION OF ERRORSBids determ<strong>in</strong>ed to be substantively responsive will be checked by the Purchaser <strong>for</strong>any arithmetic errors <strong>in</strong> computation and summation. The Purchaser will correcterrors as follows: -a) Where there is a discrepancy between amounts <strong>in</strong> figures and <strong>in</strong> words, theamount <strong>in</strong> words will <strong>gov</strong>ern; andSignature of contractor Page 39 of 111 Dy CSTE /CTC/CNB


) Where there is a discrepancy between the unit rate and the total amount derivedfrom the multiplication of the unit rate and the quantity, the unit rate as quoted will<strong>gov</strong>ern, unless <strong>in</strong> the op<strong>in</strong>ion of the Purchaser there is an obviously grossmisplacement of the decimal po<strong>in</strong>t <strong>in</strong> the unit rate, <strong>in</strong> which event the total amountas quoted will <strong>gov</strong>ern and the unit rate will be corrected.20.2 The amount stated <strong>in</strong> the Form of Bid will be adjusted by the Purchaser <strong>in</strong>accordance with the above procedure <strong>for</strong> the correction of errors and with theconcurrence of the bidder, shall be considered as b<strong>in</strong>d<strong>in</strong>g upon the bidder. If thebidder does not accept the corrected amount of bid, his bid will be rejected and thebid security will be <strong>for</strong>feited.21. CONVERSION TO SINGLE CURRENCY i.e. RUPEESShould there be any necessity of conversion to a s<strong>in</strong>gle currency i.e. Indian Rupees<strong>for</strong> the purpose of evaluation and comparison of offers, the Purchaser will convertthe <strong>for</strong>eign currency content of each tender received <strong>in</strong>to Rupees at the sell<strong>in</strong>gexchange rate <strong>for</strong> each currency established by the Reserve Bank of India or anyother Commercial Bank <strong>in</strong> the Purchaser's country, <strong>for</strong> similar transactions on theearlier of the follow<strong>in</strong>g date, namely, on the day twenty eight days be<strong>for</strong>e the latestdate of tender open<strong>in</strong>g.22. SYSTEM PERFORMANCE GUARANTEE22.1 S<strong>in</strong>ce the design of the system to achieve the end objective shall be checked andconfirmed by the contractor the tenderer shall give unqualified and unconditionalguarantee that when the design supplied by him is <strong>in</strong>stalled and commissioned atsite, it shall achieve the desired objective and that <strong>in</strong> the event of per<strong>for</strong>mance of thesystem when <strong>in</strong>stalled not comply<strong>in</strong>g with the end objective or with thespecifications, he shall provide further <strong>in</strong>puts to enable the Railways to realise theend objectives with full compliance of the specifications conta<strong>in</strong>ed <strong>in</strong> thesedocuments. No additional payment will be made to the contractor <strong>for</strong> supply ofany additional goods and service required <strong>in</strong> this regard.22.2 This certificate <strong>in</strong> the pro-<strong>for</strong>ma given <strong>in</strong> Form No.7, shall accompany the offer.Absence of this certificate which will <strong>for</strong>m part of the agreement shall disqualify thetenderer automatically.23. AUTHORITY FOR ACCEPTANCEThe authority <strong>for</strong> the acceptance of the tender will rest with the Purchaser. Thepurchaser shall not be bound to accept the lowest or any tender or to assign anyreason <strong>for</strong> non-acceptance or rejection of a tender. The purchaser reserves the rightto accept any tender <strong>in</strong> respect of the whole or any portion of the work specified <strong>in</strong>Signature of contractor Page 40 of 111 Dy CSTE /CTC/CNB


the tender paper or to sub-divide the work among different Tenderers or to reducethe work or to accept any tender <strong>for</strong> less than the tendered quantities withoutassign<strong>in</strong>g any reason whatsoever.24. PURCHASE PREFERENCE10% purchase preference of lowest valid bid price or as applicable, other th<strong>in</strong>gsbe<strong>in</strong>g equal <strong>for</strong> product & services will be admissible <strong>for</strong> Central Public SectorUnder tak<strong>in</strong>g <strong>in</strong> this tender subject to satisfaction of all other Terms & Conditions.25. AGREEMENTThe successful tenderer/s shall be required to execute an agreement with thePresident of India act<strong>in</strong>g through the Chief Adm<strong>in</strong>istrative Officer, IRPMU, ShivajiBridge (IRCOT complex) New Delhi 110001 or his accredited officer <strong>for</strong> carry<strong>in</strong>gout the work accord<strong>in</strong>g to the tender documents as <strong>in</strong>dicated <strong>in</strong> para 2 of SpecialConditions of Contract.26. <strong>TENDER</strong>ER'S ADDRESSTenderer shall state <strong>in</strong> the tender his postal address fully and clearly. Anycommunication sent to the tenderers by post at his said address, shall be deemed tohave reached the tenderer duly & timely, not withstand<strong>in</strong>g the fact that thecommunication could not reach the tenderer at all or <strong>in</strong> time <strong>for</strong> whatever reason.Important documents shall be sent by Registered post.27. FOREIGN EXCHANGENo <strong>for</strong>eign exchange and/or import license will be released/provided to thecontractor <strong>in</strong> connection with this contract.Clause 65 to IR's General Conditions of Contract (GCC):Clause-65. Participation of Jo<strong>in</strong>t Venture (JV) Firms In Works Tender.This clause shall be applicable <strong>for</strong> works tenders of value as approved and communicatedby Railway Board from time to time.65.1 Separate identity /name shall be given to the Jo<strong>in</strong>t Venture Firm.65.2 Number of members <strong>in</strong> a JV firm shall not be more than three, if the work <strong>in</strong>volvesonly one department (say Civil or S&T or Electrical or Mechanical) and shall not be morethan five, if the work <strong>in</strong>volves more than one department.65.3 A member of JV firm shall not be permitted to participate either <strong>in</strong> <strong>in</strong>dividualcapacity or as a member of another JV firm <strong>in</strong> the same tender.65.4 The tender <strong>for</strong>m shall be purchased and submitted only <strong>in</strong> the name of the JV firmand not <strong>in</strong> the name of any constituent member.65.5 Normally EMD shall be submitted only <strong>in</strong> the name of the JV Firm and not <strong>in</strong> thename of constituent member. However, <strong>in</strong> exceptional cases EMD <strong>in</strong> the name of LeadSignature of contractor Page 41 of 111 Dy CSTE /CTC/CNB


Member can be accepted subject to submission of specific request letter from LeadMember stat<strong>in</strong>g the reasons <strong>for</strong> not submitt<strong>in</strong>g EMD <strong>in</strong> the name of JV Firm and giv<strong>in</strong>gwritten confirmation from JV members to the effect that EMD submitted by the LeadMember may be deemed as EMD submitted by JV Firm.65.6 One of the members of the JV Firm shall be its Lead Member who shall have amajority (at least 51%) share of <strong>in</strong>terest <strong>in</strong> the JV firm and also , must have satisfactorilycompleted <strong>in</strong> the last three previous f<strong>in</strong>ancial years and the current f<strong>in</strong>ancial year upto thedate of open<strong>in</strong>g of the tender, one similar s<strong>in</strong>gle work <strong>for</strong> a m<strong>in</strong>imum value of 35% ofadvertised tender value. The othermembers shall have a share of not less than 20% each <strong>in</strong> case of JV Firms with up to threemembers and not less than 10% each <strong>in</strong> case of JV Firms with more than three members.In case of JV Firm with <strong>for</strong>eign member(s), the Lead Member has to be an Indian Firmwith a m<strong>in</strong>imum share of 51%.65.7 A copy of Memorandum of Understand<strong>in</strong>g (MOU) executed by the JV membersshall be submitted by the JV Firm alongwith the tender. The complete details of themembers of the JV Firm, their share and responsibility <strong>in</strong> the JV Firm etc. particularlywith reference to f<strong>in</strong>ancial, technical and other obligations shall be furnished <strong>in</strong> the MOU.(The MOU <strong>for</strong>mat <strong>for</strong> this purposeshall be f<strong>in</strong>alized by the Railway <strong>in</strong> consultation with their Law Branch and shall beenclosed alongwith the tender as Annexure-U.)65.8 Once the tender is submitted, the MOU shall not be modified/ altered/ term<strong>in</strong>ateddur<strong>in</strong>g the validity of the tender. In case the tenderer fails to observe/ comply with thisstipulation, the full Earnest Money Deposit (EMD) shall be liable to be <strong>for</strong>feited.65.9 Approval <strong>for</strong> change of constitution of JV Firm shall be at the sole discretion of theEmployer (Railways). The constitution of the JV firm shall not be allowed to be modifiedafter submission of the tender bid by the JV Firm, except when modification becomes<strong>in</strong>evitable due to succession laws etc. and <strong>in</strong> any case the m<strong>in</strong>imum eligibility criteriashould not get vitiated. However, the Lead Member shall cont<strong>in</strong>ue to be the Lead Memberof the JV Firm. Failure to observe this requirement would render the offer <strong>in</strong>valid.65.10 Similarly, after the contract is awarded, the constitution of JV Firm shall not beallowed to be altered dur<strong>in</strong>g the currency of contract except when modification become<strong>in</strong>evitable due to succession laws etc and <strong>in</strong> any case the m<strong>in</strong>imum eligibility criteriashould not get vitiated. Failure to observe this stipulation shall be deemed to be breach ofcontract with all consequentialpenal action as per contract conditions.65.11 On award of contract to a JV Firm, a s<strong>in</strong>gle Per<strong>for</strong>mance Guarantee shall besubmitted by the JV Firm as per tender conditions. All the Guarantee like Per<strong>for</strong>manceGuarantee, Bank Guarantee <strong>for</strong> Mobilization advance, Mach<strong>in</strong>ery Advance etc. shall beaccepted only <strong>in</strong> the name of the JV firm and no splitt<strong>in</strong>g of guarantees amongst themembers of the JV Firm shall be permitted.65.12 On issue of LOA (Letter of Acceptance), an agreement among the members of theJV Firm (to whom the work has been awarded) shall be executed and got registered be<strong>for</strong>ethe Registrar of the Companies under Companies Act or be<strong>for</strong>e the Registrar/ Sub-Registrar under the Registration Act, 1908. This JV agreement shall be submitted by theSignature of contractor Page 42 of 111 Dy CSTE /CTC/CNB


JV Firm to the Railways be<strong>for</strong>e sign<strong>in</strong>g the contract agreement <strong>for</strong> the work. In case thetenderer fails to observe/ comply with this stipulation, the full Earnest Money Deposit(EMD) shall be <strong>for</strong>feited and other penal actions due shall be taken aga<strong>in</strong>st partners of theJV and the JV. This Jo<strong>in</strong>t Venture Agreement shall have, <strong>in</strong>ter-alia, follow<strong>in</strong>g clauses :65.12.1 Jo<strong>in</strong>t and several liability – The members of the JV Firm to which the contract isawarded shall be jo<strong>in</strong>tly and severally liable to the Employer (Railways) <strong>for</strong> execution ofthe project <strong>in</strong> accordance with General and Special Conditions of Contract. The JVmembers shall also be liable jo<strong>in</strong>tly and severally <strong>for</strong> the loss, damages caused to theRailways dur<strong>in</strong>g the course of execution of the contract or due to non-execution of thecontract or part thereof.65.12.2 Duration of the Jo<strong>in</strong>t Venture Agreement - It shall be valid dur<strong>in</strong>g the entirecurrency of the contract <strong>in</strong>clud<strong>in</strong>g the period of extension, if any and the ma<strong>in</strong>tenanceperiod after the work is completed.65.12.3 Govern<strong>in</strong>g Laws - The Jo<strong>in</strong>t Venture Agreement shall <strong>in</strong> all respect be <strong>gov</strong>ernedby and <strong>in</strong>terpreted <strong>in</strong> accordance with Indian Laws.65.13 Authorized Member – Jo<strong>in</strong>t Venture members shall authorize one of the memberson behalf of the Jo<strong>in</strong>t Venture Firm to deal with the tender, sign the agreement or enter<strong>in</strong>to contract <strong>in</strong> respect of the said tender, to receive payment, to witness jo<strong>in</strong>tmeasurement of work done, to sign measurement books and similar such action <strong>in</strong> respectof the said tender/ contract. All notices/ correspondences with respect to the contractwould be sent only to this authorized member of the JV Firm.65.14 No member of the Jo<strong>in</strong>t Venture Firm shall have the right to assign or transfer the<strong>in</strong>terest right or liability <strong>in</strong> the contract without the written consent of the other membersand that of the employer (Railways) <strong>in</strong> respect of the said tender/ contract.65.15 Documents to be enclosed by the JV Firm along with the tender :65.15.1 In case one or more of the members of the JV Firm is/ are partnership firm(s),follow<strong>in</strong>g documents shall be submitted:(a) Notary certified copy of the Partnership Deed.(b) Consent of all the partners to enter <strong>in</strong>to the Jo<strong>in</strong>t Venture Agreement on a stamp paperof appropriate value (<strong>in</strong> orig<strong>in</strong>al).(c) Power of Attorney (duly registered as per prevail<strong>in</strong>g law) <strong>in</strong> favour of one of thepartners of the partnership firm to sign the JV Agreement on behalf of the partnership firmand create liability aga<strong>in</strong>st the firm.65.15.2 In case one or more members is/ are Proprietary Firm or HUF, the follow<strong>in</strong>gdocuments shall be enclosed :Affidavit on Stamp Paper of appropriate value declar<strong>in</strong>g that his/ her concern is aProprietary Concern and he/ she is sole proprietor of the Concern OR he/ she is <strong>in</strong> positionof “KARTA” of H<strong>in</strong>du Undivided Family (HUF) and he/ she has the authority, power andconsent given by other partners to act on behalf of HUF.65.15.3 In case one or more members is/ are limited companies, the follow<strong>in</strong>g documentsshall be submitted :(a) Notary certified copy of resolutions of the Directors of the Company, permitt<strong>in</strong>g thecompany to enter <strong>in</strong> to a JV agreement, authoriz<strong>in</strong>g MD or one of the Directors orManagers of the Company to sign JV agreement, such other documents required to beSignature of contractor Page 43 of 111 Dy CSTE /CTC/CNB


signed on behalf of the Company and enter <strong>in</strong>to liability aga<strong>in</strong>st the company and/ or doany other act on behalf of the company.(b) Copy of Memorandum and articles of Association of the Company.(c) Power of Attorney (duly registered as per prevail<strong>in</strong>g law) by the company authoriz<strong>in</strong>gthe person to do/ act mentioned <strong>in</strong> the para (a) above.65.15.4 All the members of the JV shall certify that they are not black listed or debarredby Railways or any other M<strong>in</strong>istry/ Department of the Govt. of India/ State Govt. fromparticipation <strong>in</strong> tenders/ contract on the date of open<strong>in</strong>g of bids either <strong>in</strong> their <strong>in</strong>dividualcapacity as members of the JV, or the JV Firm <strong>in</strong> which they were / are members.65.16 Credentials & Qualify<strong>in</strong>g criteria – Technical and F<strong>in</strong>ancial eligibility of the JVFirm shall be adjudged based on satisfactory fulfillment of the follow<strong>in</strong>g Criteria :65.16.1 Technical eligibility criteria – (‘a’ or ‘b’ mentioned hereunder):(a) Either the JV Firm or Lead Member of the JV Firm must have satisfactorily completed<strong>in</strong> the last three previous f<strong>in</strong>ancial years and the current f<strong>in</strong>ancial year up to the date ofopen<strong>in</strong>g of the Tender, one similar s<strong>in</strong>gle work <strong>for</strong> a m<strong>in</strong>imum of 35% of advertised valueof the Tender.OR(b) (i) In case of composite works (e.g. works <strong>in</strong>volv<strong>in</strong>g more than one dist<strong>in</strong>ctcomponent, such as Civil Eng<strong>in</strong>eer<strong>in</strong>g works, S&T works, Electrical works, OHE worksetc. and <strong>in</strong> the case of major bridges - substructure, superstructure etc.), <strong>for</strong> eachcomponent, at least 35% of the value of any of such components <strong>in</strong>dividually <strong>for</strong> s<strong>in</strong>glesimilar nature of work should have been satisfactorily completed by the JV Firm or by anymember of the JV Firm <strong>in</strong> the previous three F<strong>in</strong>ancial years and the current F<strong>in</strong>ancial yearup to the date of open<strong>in</strong>g of tender. The member satisfy<strong>in</strong>g technical eligibility criteria <strong>for</strong>the largest component of the work shall be the Lead Member and that Member shall havea majority (at least 51%) share of <strong>in</strong>terest <strong>in</strong> the JV Firm.(ii) In such cases, what constituents a component <strong>in</strong> a composite work shall be clearly predef<strong>in</strong>edwith estimated tender cost of it, as part of the tender documents without anyambiguity. Any work or set of works shall be considered to be a separate component, onlywhen cost of the component is more than 2 crore each.(iii) However, as long as the JV Firm or any member of the JV Firm meets with therequirements, <strong>in</strong> one or more components of the work, and has completed a m<strong>in</strong>imum of35% of the advertised value of the tender <strong>for</strong> the same value of the component, andresultantly, all the members of the JV collectively, then meet the prescribed technicaleligibility criteria, the JV shall stand technically qualified.Note:- Value of a completed work done by a Member <strong>in</strong> an earlier JV Firm shall bereckoned only to the extent of the concerned member’s share <strong>in</strong> that JV Firm <strong>for</strong> thepurpose of satisfy<strong>in</strong>g his/ her compliance to the above mentioned Technical Eligibilitycriteria <strong>in</strong> the tender under consideration.65.16.2 F<strong>in</strong>ancial Eligibility Criteria:The contractual payments received by the JV Firm or the arithmetic sum of contractualpayments received by all the members of JV Firm <strong>in</strong> the previous three f<strong>in</strong>ancial years andSignature of contractor Page 44 of 111 Dy CSTE /CTC/CNB


the current f<strong>in</strong>ancial year upto the date of open<strong>in</strong>g of tender shall be at least 150% of theestimated value of the work as mentioned <strong>in</strong> the tender.Note :Contractual payment received by a Member <strong>in</strong> an earlier JV Firm shall be reckoned onlyto the extent of the concerned member’s share <strong>in</strong> that JV Firm <strong>for</strong> the purpose of satisfy<strong>in</strong>gcompliance of the above mentioned f<strong>in</strong>ancial eligibility criteria <strong>in</strong> tender underconsideration.Signature of contractor Page 45 of 111 Dy CSTE /CTC/CNB


Section – IIChapter – 2Special Conditions ofContractSignature of contractor Page 46 of 111 Dy CSTE /CTC/CNB


Special Conditions of Contract1. <strong>TENDER</strong> <strong>DOCUMENT</strong>S2. AGREEMENT3. SECURITY DEPOSIT & CONTRACT PERFORMANCE GUARANTEE4. CONTRACTOR'S OFFICE & STORES DEPOT5. USE OF RAILWAY LAND6. PROGRAMME OF WORK/OBLIGATION TO CARRY OUT ENGINEER’SINSTRUCTIONS7. COMPETENT SUPERVISORS8. MATERIAL SUPPLIED BY RAILWAYS9. MATERIAL SUPPLIED BY CONTRACTOR10. OTHER RAILWAY STORES:11. TESTING & MEASURING INSTRUMENTS, SPECIAL TOOLS ANDINSTALLATION MATERIAL12. SUPPLY OF TECHNICAL LITERATURES, <strong>DOCUMENT</strong>ATION,DRAWINGS & COMPLETION PLANS ETC.13. SPARES14. LONG TERM AVAILABILITY OF SPARES AND SYSTEM SUPPORT15. QUALITY ASSURANCE16. EQUIPMENT EVALUATION AND APPROVAL17. INSPECTION OF MATERIALS18. INSPECTION OF WORKS19. QUANTUM OF WORK AND VARIATION IN QUANTITIESSignature of contractor Page 47 of 111 Dy CSTE /CTC/CNB


20. ADDITION/REDUCTION OF WORK21. SUBLETTING AND ASSIGNMENT22. EXECUTION OF WORK23. PROGRESS REPORTING24. MAINTENANCE OF WORKS25 CLEARANCE OF SITE26. PROVISIONAL ACCEPTANCE27. PLACING IN SERVICE & MAINTENANCE SUPERVISION28 FINAL ACCEPTANCE29. WARRANTY30. TRAINING31. INFRINGEMENT OF PATENTS32. LICENSE AS PER GOVT. OF INDIA CONTRACT LABOUR ACT33. DEFAULT & DELAYS34. LOSS SUSTAINED DUE TO DEFAULT AND DELAY35. PENALTY FOR DELAY IN COMPLETION36. EXTENSION OF TIME37. CONTRATOR'S LIABILITIES FOR COSTS AND DAMAGES38. UNIT PRICES39. MEASUREMENT OF WORKS40. TERMS OF PAYMENT41. ON ACCOUNT PAYMENTSignature of contractor Page 48 of 111 Dy CSTE /CTC/CNB


42. FINAL SETTLEMENT43. CERTIFICATE FOR MODVAT BENEFITS ON BILLS:44. DEDUCTION FROM ON ACCOUNT PAYMENT BILLS45. TAXES46. INSURANCE47. FORCE MAJEURE CLAUSE48. SETTLEMENT OF DISPUTE AND ARBITRATION*****Signature of contractor Page 49 of 111 Dy CSTE /CTC/CNB


SPECIAL CONDITIONS OF CONTRACT1. <strong>TENDER</strong> <strong>DOCUMENT</strong>S1.1 The goods and services required, bidd<strong>in</strong>g procedure and contract terms areprescribed <strong>in</strong> the tender documents. Bid documents can be obta<strong>in</strong>ed from 25-10-2012 to 27-11-2012 from 10.30 Hrs. to 16.00 hrs. on every work<strong>in</strong>g day <strong>in</strong> theoffice of Dy CSTE/CTC/CNB, NC Railway, Near Jhakarkati Bus stand, GT road,Kanpur after deposit<strong>in</strong>g Rs 10,000/- (Rupees Ten Thousands only) <strong>in</strong> the <strong>for</strong>m ofDemand draft/ Pay Order/Deposit Receipt made <strong>in</strong> favour of FA & CAO, IRPMU,New Delhi. The attention of tenderer is <strong>in</strong>vited to the follow<strong>in</strong>g documents:Section-I:Section-II:Preamble along with Schedule of Requirement of quantities.Chapters1. Instructions to Tenderers and conditions of tender<strong>in</strong>g.2. Special Conditions of Contract.3. Tender Forms.Misc. I) General Conditions of Contract (G.C.C.) as amended by advancecorrection slips issued up to date.II) IRS conditions of contract <strong>for</strong> the stores department with up tomodification (CCSS).dateGeneral Conditions of Contract (G.C.C.) as amended by advance correction slipsissued up to-date and IRS conditions of contract <strong>for</strong> the stores department withup to date modification (CCSS) can be obta<strong>in</strong>ed, if need be, from the office of theCAO/IRPMU/New Delhi after pay<strong>in</strong>g the cost prescribed <strong>for</strong> it <strong>in</strong> the <strong>for</strong>m ofBank Draft <strong>in</strong> favour of FA&CAO/IRPMU, New Delhi.1.2 If the Tender submitted by a tenderer is accepted and the contract awarded to theTenderer, the various works com<strong>in</strong>g under purview of the contract shall be<strong>gov</strong>erned by tender documents mentioned above. Where there is any conflictbetween the <strong>in</strong>structions to tenderers and conditions of tender<strong>in</strong>g and specialconditions of contract, Tender <strong>for</strong>ms, annexures etc. on one hand and GeneralConditions of Contract on the other, the <strong>for</strong>mer shall prevail.1.3 Any Special conditions stated by the Tenderer <strong>in</strong> the cover<strong>in</strong>g letter submittedalong with the tender shall be deemed to be a part of the Contract to such extentonly, as have been explicitly accepted by the Railway.Signature of contractor Page 50 of 111 Dy CSTE /CTC/CNB


1.4 The expression General conditions of contract (GCC), wherever occurr<strong>in</strong>g <strong>in</strong> thesepapers shall be deemed to mean the General conditions of contract, 1969 ofNorthern Railway department as amended by advance correction slips issued upto-date.2. AGREEMENTThe successful Tenderer shall with<strong>in</strong> 15 days after hav<strong>in</strong>g been called upon bynotice to do so be bound to execute an agreement based on accepted rates andconditions, <strong>in</strong> such <strong>for</strong>m as the Railways may prescribe, and lodge the same withthe Railway together with the conditions of contract, specifications andSchedule of prices referred to there<strong>in</strong> duly completed. The <strong>for</strong>m <strong>for</strong> agreement is<strong>in</strong>cluded <strong>in</strong> Section II, Chapter-III (Form No.3).3. SECURITY DEPOSIT & CONTRACT PERFORMANCE GUARANTEE3.1 SECURITY DEPOSIT(i)(ii)(iii)(iv)Security deposit shall be 5% of the contract value.The rate of recovery shall be @10% of the bill amount till the full security depositis recovered. The EMD of successful tenderer will be reta<strong>in</strong>ed as part of Securitydeposit and will be adjusted <strong>in</strong> Security deposit, with only money over and abovethe Earnest money that will be recovered.Security deposit will be recovered only from the runn<strong>in</strong>g bill of the contract andno other mode of collect<strong>in</strong>g SD as <strong>in</strong> the <strong>for</strong>m of <strong>in</strong>struments like BG, FD etcshall be accepted towards Security Deposit.No <strong>in</strong>terest will be payable upon the Security Deposit or amounts payable to thecontractor under this contract.Security Deposit will be returned to the contractor after physical completion ofwork, ma<strong>in</strong>tenance period and warranty if any as certified by competent authorityand settlement of all dues and disputes. The competent authority shall normally bethe authority, who is competent to sign the contract. If this competent authority isof the rank lower than the JA grade, then a JA grade officer (concerned with thework) should issue the certificate. The certificate <strong>in</strong>ter alia should mention thatthe work has been completed <strong>in</strong> all respects & that all the contractual obligationshave been fulfilled by the contractors and that there is no due from the contractorto Railways aga<strong>in</strong>st the contract concerned. Be<strong>for</strong>e releas<strong>in</strong>g the Security Deposit,contractor concerned should submit an unconditional & unequivocal no claimcertificate.3.2 PERFORMANCE GUARANTEE(a) The successful bidder shall have to submit a Per<strong>for</strong>mance Guarantee (PG)with<strong>in</strong> 30 (thirty) days from the date of issue of LOA. Extension of time <strong>for</strong>submission of PG beyond 30 days & up to 60 days from the date of issue of LOASignature of contractor Page 51 of 111 Dy CSTE /CTC/CNB


may be given by the authority who is competent to sign the contract agreement.However, a panel <strong>in</strong>terest of 15% per annum shall be charged <strong>for</strong> the delaybeyond 30 days, i.e. from 31 st day after the date of issue of LOA. In case thecontractor fails to submit the requisite PG even after 60 days from the date ofissue of LOA, the contract shall be term<strong>in</strong>ated duly <strong>for</strong>feit<strong>in</strong>g EMD and otherdues, if any payable aga<strong>in</strong>st that contract. The failed contractor shall be debarredfrom participat<strong>in</strong>g <strong>in</strong> re-tender <strong>for</strong> that work.(b) The successful bidder shall submit the Per<strong>for</strong>mance Guarantee <strong>in</strong> any of thefollow<strong>in</strong>g <strong>for</strong>ms, amount<strong>in</strong>g to 5% of the contract value:(i) A deposit of Cash;(ii) Irrevocable Bank guarantee;(iii) Government Securities <strong>in</strong>clud<strong>in</strong>g State Loan Bonds at 5% below themarket value;(iv) Deposit Receipt, Pay Orders, Demand Drafts & Guarantee Bonds. These<strong>for</strong>ms of Per<strong>for</strong>mance Guarantee could be either of the State Bank of Indiaor of any of the Nationalized Banks;(v) Guarantee Bonds executed or Deposits receipts tendered by all scheduledBanks;(vi) A deposit <strong>in</strong> the Post Office sav<strong>in</strong>g bank;(vii) A deposit <strong>in</strong> the National Sav<strong>in</strong>gs Certificates;(viii) Twelve years National defence Certificates;(ix) Ten years defence Deposits;(x) National defence Bonds and(xi) Unit trust certificates at 5% below market value or at the face valuewhichever is less.Also, FDR <strong>in</strong> favour of FA&CAO (Free from any encumbrance) may beaccepted.Note: The <strong>in</strong>struments as listed above will also be acceptable <strong>for</strong> Guarantees <strong>in</strong> caseof Mobilization Advance.(c) The Per<strong>for</strong>mance guarantee shall be submitted by the successful bidder afterthe LOA has been issued, but be<strong>for</strong>e sign<strong>in</strong>g of the contract agreement. This P.G.shall be <strong>in</strong>itially valid up to the stipulated date of completion plus 60 days beyondthat. In case the time <strong>for</strong> completion of work gets extended, the contractor shallget the validity of P.G. extended to cover such extended time <strong>for</strong> completion ofwork plus 60 days.(d) The value of PG to be submitted by the contractor will not change <strong>for</strong>variation up to 25% (either <strong>in</strong>crease or decrease). In case dur<strong>in</strong>g the course ofexecution, value of the contract <strong>in</strong>creases by more than 25% of the orig<strong>in</strong>alcontract value, an additional per<strong>for</strong>mance guarantee amount<strong>in</strong>g to 5% <strong>for</strong> theSignature of contractor Page 52 of 111 Dy CSTE /CTC/CNB


excess value over the orig<strong>in</strong>al contract value shall be deposited by the contractor.(e) Per<strong>for</strong>mance guarantee will be released after physical completion of the workbased on ‘Completion Certificate’ issued by the competent authority stat<strong>in</strong>g thatthe contractor has completed the work <strong>in</strong> all respects satisfactorily. The securitydeposit shall, however, be released only after expiry of the ma<strong>in</strong>tenance period &after pass<strong>in</strong>g the f<strong>in</strong>al bill based on ‘No claim certificate’ from the contractor.(f) Whenever the contract is resc<strong>in</strong>ded the security deposit will be <strong>for</strong>feited andper<strong>for</strong>mance guarantee shall be encashed. The balance work shall be got done<strong>in</strong>dependently without risk and cost of the failed contractor. The failed contractorshall be debarred from participat<strong>in</strong>g <strong>in</strong> the tender <strong>for</strong> execut<strong>in</strong>g the balance work.If the failed contractor is a JV or a partnership firm, then every member/ partnerof such a firm shall be debarred from participat<strong>in</strong>g <strong>in</strong> the tender <strong>for</strong> the balancework <strong>in</strong> his/her <strong>in</strong>dividual capacity or as a partner of any other JV/partnershipfirm.(g) The eng<strong>in</strong>eer shall not make a claim under the per<strong>for</strong>mance guarantee except<strong>for</strong> amounts to which the President of India is entitled under the contract.(notwithstand<strong>in</strong>g and/or without prejudice to any other provisions <strong>in</strong> the contractagreement) <strong>in</strong> the event of:(i) Failure by the contractor to extend the validity of the per<strong>for</strong>mance guarantee asdescribed here<strong>in</strong> above, <strong>in</strong> which event the eng<strong>in</strong>eer may claim the full amount ofthe per<strong>for</strong>mance guarantee.(ii) Failure by the contractor to pay President of India any amount due, either asagreed by the contractor or determ<strong>in</strong>ed under any of the clauses/ conditions of theAgreement, with<strong>in</strong> 30 days of the service of notice to this effect by Eng<strong>in</strong>eer.(iii) The contract be<strong>in</strong>g determ<strong>in</strong>ed or resc<strong>in</strong>ded under provision of the GCC, theper<strong>for</strong>mance guarantee shall be <strong>for</strong>feited <strong>in</strong> full & shall be absolutely at thedisposal of the President of India.4. CONTRACTOR'S OFFICE & STORES DEPOTThe Contractor shall, with<strong>in</strong> a month of issue of letter of acceptance of tender,establish an office and stores depot at a convenient place <strong>for</strong> receiv<strong>in</strong>g andstor<strong>in</strong>g equipments and materials and progress<strong>in</strong>g field work expeditiously <strong>in</strong>consultation and with the approval of the purchaser. He shall <strong>in</strong>timate thepurchaser and address thereof to which all correspondence should be sent. Anycommunication sent to the contractor by post at his said address shall be deemedto have reached the contractor duly and <strong>in</strong> time. Important documents shall besent by Registered post.Signature of contractor Page 53 of 111 Dy CSTE /CTC/CNB


5. USE OF RAILWAY LANDUse of Railway land required by the Contractor <strong>for</strong> constructions of temporaryoffices, quarter(s), hutments etc. <strong>for</strong> the staff and <strong>for</strong> stor<strong>in</strong>g materials etc., will bepermitted to him/them free by Railway, if available. The location of these offices,hutments, stores etc. will be subject to the approval of the Eng<strong>in</strong>eer or hisrepresentative. The land will be restored to Railways by the Contractor(s) <strong>in</strong> thesame condition as when taken over or <strong>in</strong> vacant condition as desired by theEng<strong>in</strong>eer, after completion of the work or at any earlier day, as specified by theEng<strong>in</strong>eer. The failure to do so will make the Contractor(s) liable to pay the cost<strong>in</strong>curred by the Railway <strong>for</strong> gett<strong>in</strong>g possession of land.6. PROGRAMME OF WORK/OBLIGATION TO CARRY OUTENGINEER’S INSTRUCTIONS6.1 The Contractor shall have necessary resources to execute the work so that theentire work is completed with<strong>in</strong> a period as mentioned <strong>in</strong> the preamble from thedate of issue of Letter of Acceptance of the tender. He shall also have necessaryresources to take up the work of <strong>in</strong>stallation commission<strong>in</strong>g etc. simultaneously attwo <strong>in</strong>dependent places.6.2 With<strong>in</strong> a period of 7 days beg<strong>in</strong>n<strong>in</strong>g from the date of issue of Letter ofAcceptance of Tender, the Contractor shall submit the detailed time schedule <strong>for</strong>the execution of work based on the conditions <strong>in</strong> consultation with the Railway tothe authority mentioned <strong>in</strong> the Preamble and approved by the latter <strong>in</strong> writ<strong>in</strong>gbe<strong>for</strong>e commencement of the work.6.3 The Contractor shall be held responsible <strong>for</strong> the execution of the work accord<strong>in</strong>gto the Programme given above <strong>for</strong> the execution of the work <strong>in</strong> full compliance ofthe approved cable route plans and also the various clauses of the technicalsupplement, Technical specifications, <strong>in</strong>structions and draw<strong>in</strong>gs availableseparately. Failure to comply with any of these will be dealt with as per provisionlaid down <strong>in</strong> General Conditions of Contract.6.4 The Contractor on his part will have to employ supervisors, technicians andlabour <strong>in</strong> full strength commensurate with work<strong>in</strong>g area available. He will alsoarrange match<strong>in</strong>g materials and equipment to complete the job most expeditiouslyso as to ensure that the work is completed <strong>in</strong> phases with<strong>in</strong> the stipulated period.6.5 Inspection Register shall be ma<strong>in</strong>ta<strong>in</strong>ed at the site of work by the Railwaywhere<strong>in</strong> <strong>in</strong>structions regard<strong>in</strong>g the work<strong>in</strong>g etc. shall be recorded by the Eng<strong>in</strong>eeror his executive subord<strong>in</strong>ates. It is expected of the Contractor or his representativeat the site to note such <strong>in</strong>structions whenever asked upon to do so and take actionaccord<strong>in</strong>gly.Signature of contractor Page 54 of 111 Dy CSTE /CTC/CNB


6.6 No facility whatsoever, e.g. provisions of approach road and provision oftemporary level cross<strong>in</strong>g etc. will be provided by Railway <strong>for</strong> cart<strong>in</strong>g materials.Approach roads with<strong>in</strong> the Railway limits can be used <strong>for</strong> cart<strong>in</strong>g materials.6.7 The contractor will programme his work <strong>in</strong> such a manner so as not to <strong>in</strong>terfere <strong>in</strong>the work<strong>in</strong>g and movement of tra<strong>in</strong>s. No extra payment shall be allowed on thisaccount and <strong>for</strong> tak<strong>in</strong>g any precautions or wastage of contractor's labour, time etc.due to tra<strong>in</strong> work<strong>in</strong>g.7. COMPETENT SUPERVISORS7.1 The Contractor shall place and keep competent Representatives /Supervisors/Eng<strong>in</strong>eers, as his representative on the works who will be authorised to receiveand acknowledge materials issued by the Railway and take all orders issued by theRailway.7.2 The contractor shall employ the follow<strong>in</strong>g technical staff as a m<strong>in</strong>imum, dur<strong>in</strong>gthe execution of the work:a) One graduate Eng<strong>in</strong>eer when the cost of the work to be executed isRs.15 Lacs and above.b) One Identified diploma holder when the cost of work to be executed ismore than 5 Lacs but less than Rs. 15 Lacs.7.2.1 The technical staff should be available at site whenever required by the Eng<strong>in</strong>eer<strong>in</strong>-chargeto take <strong>in</strong>structions. In case the Contractor/s fails/fail to employ thetechnical staff as a<strong>for</strong>esaid, he/they shall be liable to pay a reasonable amount notexceed<strong>in</strong>g a sum of Rs.2,000/- (Rupees Two thousand only) <strong>for</strong> each month ofdefault <strong>in</strong> case of graduate eng<strong>in</strong>eer and Rs.1,000/- (Rs. One thousand only) <strong>for</strong>each month of default <strong>in</strong> case of Diploma Holder.7.2.2 The decision of the Eng<strong>in</strong>eer-<strong>in</strong>-charge as to the period <strong>for</strong> which the requiredtechnical staff was not employed by the contractors and as to the reasonablenessof the amount to be deducted on this account shall be f<strong>in</strong>al and b<strong>in</strong>d<strong>in</strong>g on theContractor.7.3 The said representatives shall be present at site dur<strong>in</strong>g work<strong>in</strong>g hours and anywritten orders or <strong>in</strong>structions which the purchaser's Eng<strong>in</strong>eer may give to the saidrepresentatives of the contractor shall be deemed to have been duly given orcommunicated to the contractor.7.4 The contractor or his representative will accompany the Purchaser's Eng<strong>in</strong>eer orEng<strong>in</strong>eer on <strong>in</strong>spection or proceed to their offices whenever called upon to do so.Signature of contractor Page 55 of 111 Dy CSTE /CTC/CNB


8 MATERIAL SUPPLIED BY RAILWAYS8.1 No material is to be supplied by Railways from Railway depot as has already been<strong>in</strong>dicated <strong>in</strong> the Preamble except otherwise clearly specified <strong>in</strong> the schedule ofquantities. The present work, however <strong>in</strong>volves work<strong>in</strong>g on exist<strong>in</strong>g <strong>in</strong>stallationwhich is Railway property.8.2 The contractor will be responsible <strong>for</strong> safe custody of material directly brought tothe site <strong>for</strong> exist<strong>in</strong>g work, and <strong>for</strong> which the consignee has given his acceptance<strong>for</strong> use. The material will be treated as Railway material at site and <strong>for</strong> which thecontractor shall furnish a stand<strong>in</strong>g <strong>in</strong>demnity bond <strong>in</strong> <strong>for</strong>m No.6. (Section IIChapter III).8.3 RECONCILIATION OF MATERIALS SUPPLIED BY RAILWAYS(Form 10,Sec-II, Chapter -3)All the materials supplied by the Purchaser shall be correctly accounted <strong>for</strong>and the quantities reconciled on completion of the work by the contractor. Oncompletion of the work all surplus materials supplied by the Purchaser togetherwith the ones found defective or that have became defective or broken onaccount of defective materials and/or workmanship shall be returned to him by thecontractor.If the contractor fails to return excess and unused materials supplied by therailway or if there are any shortages dur<strong>in</strong>g f<strong>in</strong>al reconciliation, their cost there ofshall be recovered by the Purchaser from the Contractor at the books rate plusrailway freight, handl<strong>in</strong>g, load<strong>in</strong>g, supervision and other <strong>in</strong>cidental charges at therates fixed by the railway to this will be added an <strong>in</strong>crease of 100%.9 MATERIAL SUPPLIED BY CONTRACTOR9.1 All materials required <strong>for</strong> the execution of the contract other than thosespecifically shown as be<strong>in</strong>g supplied by the Railways <strong>in</strong> this document shall bearranged and supplied by the contractor as detailed <strong>in</strong> the scope so as to realizethe end objective.9.2 The list of the material (and their approximate quantity) to be supplied by thecontractor have been <strong>in</strong>dicated <strong>in</strong> Schedule of requirement of items, rates &quantities – Section I Chapter 3. The list is however, not limited and any othermaterial as required <strong>for</strong> complet<strong>in</strong>g the work as per standard plans, draw<strong>in</strong>g etc.will be supplied by the contractor free of cost. The supply of equipment andmaterials shall also <strong>in</strong>clude required <strong>in</strong>stallation and other materials anddocuments etc., which may not be specifically mentioned there<strong>in</strong>, but which areusually necessary <strong>for</strong> complet<strong>in</strong>g the work <strong>in</strong> all respects. In addition to the above,if any other petty material which may be considered necessary <strong>for</strong> execution ofthe work accord<strong>in</strong>g to specification of draw<strong>in</strong>g is required, the same shall besupplied by the contractor free of cost.Signature of contractor Page 56 of 111 Dy CSTE /CTC/CNB


9.3.1 The materials supplied and used by the contractor shall be of best availablequality and shall con<strong>for</strong>m to relevant specifications, design and draw<strong>in</strong>gs duly<strong>in</strong>spected by RITES/RDSO/Railway consignee as the case may be.The materials to be supplied by the contractor as per schedule enclosed with thetender document will be procured from RDSO approved sources if the itemappears <strong>in</strong> RDSO approved list as per guidel<strong>in</strong>e mentioned by RDSO <strong>in</strong> theirbooklet. In case of items not appear<strong>in</strong>g <strong>in</strong> RDSO approved list of material, thematerials shall be supplied from reputed suppliers or their authorizedrepresentatives, shall be of best quality and shall con<strong>for</strong>m to relevantspecifications, design and draw<strong>in</strong>gs duly <strong>in</strong>spected by RITES/RDSO/Railwayconsignee. The contractor may be required to produce test certificates from themanufacturers whenever called <strong>for</strong> by the Eng<strong>in</strong>eer <strong>in</strong> charge.9.4 Be<strong>for</strong>e procur<strong>in</strong>g the material to be supplied by contractor, the contractor shallsubmit the names and addresses of suppliers from whom it is proposed to procurethe materials required to be supplied <strong>in</strong> the tender and shall take approval ofrailways <strong>for</strong> the same.9.5 CONSIGNEEThe contractor should consign, if need be, all the materials to 'self' to the neareststations where materials can be booked <strong>for</strong> stack<strong>in</strong>g be<strong>for</strong>e erection. Such items,where part payment is admissible on receipt by the Railway, can be booked tostore of Sr. Section Eng<strong>in</strong>eer/Sig/Tundla from where the materials shall behanded over to the contractor <strong>for</strong> <strong>in</strong>stallation. All transportation charges to thesite of work, taxes, octroi etc. and all handl<strong>in</strong>g charges <strong>for</strong> each such item shall beborne by the contractor.10 OTHER RAILWAY STORES10.1 See<strong>in</strong>g the tight completion targets, Railways may decide to supply any materialother than those specified <strong>in</strong> Para 8, either at the Contractor's request or suo motto<strong>in</strong> order to prevent any possible delay <strong>in</strong> the execution of the works likely to occurdue to the contractor’s <strong>in</strong>ability to make adequate arrangements <strong>for</strong> supply thereo<strong>for</strong> otherwise, recovery will be made from the contractor’s bill at 1.5 times the costof procurement which is <strong>in</strong>clusive of freight or rate given <strong>in</strong> schedule whicheveris higher. Freight between the Railway sources of supply and RailwayStores/depot shall be to the Contractor's account.10.2 If however, the material required by the Contractor is not available <strong>in</strong> Railwaysstock or the Railways decide not to supply the same, be that <strong>for</strong> whatever reasons,the Railway will not be bound to arrange <strong>for</strong> the supply nor will this fact beaccepted as an excuse <strong>for</strong> delay <strong>in</strong> execution of works.11 TEST & MEASURING INSTRUMENTS, SPECIAL TOOLS ANDSignature of contractor Page 57 of 111 Dy CSTE /CTC/CNB


INSTALLATION MATERIAL11.1 Special tools and <strong>in</strong>struments required <strong>for</strong> <strong>in</strong>stallation and ma<strong>in</strong>tenance of allthe equipment shall be arranged by the tenderer <strong>in</strong> adequate quantities. All<strong>in</strong>stallation material <strong>for</strong> complete commission<strong>in</strong>g of the system shall be providedby the tenderer. Details of special tools, their quantities and unit prices shall be<strong>in</strong>dicated.11.2 All tests and measur<strong>in</strong>g <strong>in</strong>struments and other arrangements required <strong>for</strong> all theacceptance tests shall be provided by the contractor free of cost.12. SUPPLY OF TECHNICAL LITERATURES, <strong>DOCUMENT</strong>ATION,DRAWINGS & COMPLETION PLANS ETC.Not applicable.13. SPARES13.1 The contractor should keep sufficient stock of spares as required by him <strong>for</strong>replacement of defective equipment under warranty.13.2 The spares procured by the contractor will be subject to <strong>in</strong>spections(RDSO/RITES/Consignee) as per policy <strong>in</strong> vogue.13.3 The spares procured <strong>for</strong> meet<strong>in</strong>g warranty requirements will be beyond thepurview of quantity restrictions under variation. (Refer Para 19.6).14. LONG TERM AVAILABILITY OF SPARES AND SYSTEM SUPPORTNot applicable.15. QUALITY ASSURANCE15.1 The tenderer shall certify that they have <strong>in</strong> place a Quality managementsystem to deliver the design con<strong>for</strong>m<strong>in</strong>g to desired quality and safety norms.15.2 In the event of Railways wav<strong>in</strong>g off the <strong>in</strong>spection, all tests provided <strong>in</strong> the testschedules approved by Railway shall be carried out by the Quality AssuranceOrganization and proper record of all such tests and results thereof shall bema<strong>in</strong>ta<strong>in</strong>ed and supplied to the Railway on demand.16. REJECTION16.1 INSPECTING OFFICER – POWER OF REJECTIONSignature of contractor Page 58 of 111 Dy CSTE /CTC/CNB


a) Be<strong>for</strong>e any stores or part thereof are submitted <strong>for</strong> <strong>in</strong>spection, to certify that theyare not <strong>in</strong> accordance with the contract/ow<strong>in</strong>g to the adoption of any unsatisfactorymethod of manufacture.b) To reject any stores submitted as not be<strong>in</strong>g <strong>in</strong> accordance with the particulars.c) To reject the whole of the <strong>in</strong>stallment tendered <strong>for</strong> <strong>in</strong>spection if after <strong>in</strong>spection ofsuch portion thereof, as he may <strong>in</strong> his discretion th<strong>in</strong>k fit, he is satisfied that thesame is unsatisfactory.d) To mark the rejected stores with a rejection mark, so that they may be easilyidentified if resubmitted.The Inspect<strong>in</strong>g officer’s decision as regards the rejection shall be f<strong>in</strong>al and b<strong>in</strong>d<strong>in</strong>gon the contractor.16.2 CONSIGNEE’S RIGHT OF REJECTIONNotwithstand<strong>in</strong>g any approval which the <strong>in</strong>spect<strong>in</strong>g Officer may have given <strong>in</strong>respect of the stores or any materials or the work or workmanship <strong>in</strong>volved <strong>in</strong> theper<strong>for</strong>mance of the contract (whether with or without any test carried out by thecontractor or the <strong>in</strong>spect<strong>in</strong>g officer or under the direction of the Inspect<strong>in</strong>g officer)and notwithstand<strong>in</strong>g delivery of the stores where so provided to the <strong>in</strong>terimconsignee it shall be lawful <strong>for</strong> the consignee, on behalf of the purchaser, to rejectthe stores or any part, portion of consignment thereof with<strong>in</strong> a reasonable time afteractual delivery thereof to him at the place or dest<strong>in</strong>ation fixed <strong>in</strong> the contract if suchstores or part, portion of consignment thereof is not <strong>in</strong> all respects <strong>in</strong> con<strong>for</strong>mitywith the terms and conditions of the contract whether on account of any loss,deterioration or damage be<strong>for</strong>e dispatch or delivery or dur<strong>in</strong>g transit or otherwisehowsoever.16.3 REJECTED STORESWhen any stores delivered at the consignee’s depots are rejected, this shall beremoved by the contractor with<strong>in</strong> 21 days from the date of rejection. Such rejectedstores shall lie at the contractor’s risk from the date of rejection. If the stores are notremoved by the contractor with<strong>in</strong> this period, the purchaser or his nom<strong>in</strong>ee shallhave the right to dispose of such stores, as deemed fit, at the contractor’s risk andaccount.The purchaser shall also be entitled to recover from the contractor, handl<strong>in</strong>g andground rent / demurrage and any other charges <strong>for</strong> the period the rejected stores arenot removed after the a<strong>for</strong>ementioned period.Signature of contractor Page 59 of 111 Dy CSTE /CTC/CNB


Stores that have been dispatched by rail and rejected after arrival at dest<strong>in</strong>ation maybe taken back by the contractor either at the station where they were rejected or atthe station from which they were dispatched. If the contract is placed <strong>for</strong> deliveryF.O.R. station of dispatch, the contractor shall pay the carriage charges on therejected consignment at Public traffic Rates from the station of dispatch to thestation where they were rejected. If the contractor prefers to take back the goods atthe station from which they were dispatched, the goods shall, <strong>in</strong> addition, bebooked back to him, freight to pay at Public Traffic Rates and at owner’s risk.16.4 CONSEQUENCES OF REJECTIONIf on the stores be<strong>in</strong>g rejected by the Inspect<strong>in</strong>g Officer or consignee at thedest<strong>in</strong>ation, the contractor fails to make satisfactory supplies with<strong>in</strong> the stipulatedperiod of delivery, the purchaser shall be at liberty to:-a) Request the contractor to replace the rejected store <strong>for</strong>thwith but <strong>in</strong> any event notlater than period of 21 days from the date of rejection and the contractor shall bearall the cost of such replacement, <strong>in</strong>clud<strong>in</strong>g freight, if any on such replac<strong>in</strong>g andreplaced stores but without be<strong>in</strong>g entitled to any extra payment on that or any otheraccount.b) Purchase or authorise the purchase of quantity of the stores, rejected or others of asimilar description (when stores exactly comply<strong>in</strong>g with the particulars are notreadily available <strong>in</strong> the op<strong>in</strong>ion of the purchaser, which shall be f<strong>in</strong>al), withoutnotice to the contractor, at his risk and cost and without affect<strong>in</strong>g the contractor’sliability as regards to the supply of any further <strong>in</strong>stallment due under the contractor.c) Cancel the contract and purchase or authorize the purchase of the stores or other ofa similar description (when stores exactly comply<strong>in</strong>g with the particulars are notreadily available, <strong>in</strong> the op<strong>in</strong>ion of the purchaser, which shall be f<strong>in</strong>al ) at the riskand cost of the contractor. In the event of action be<strong>in</strong>g taken under sub-clauseabove or this sub clause, the provisions relevant clauses of the General Conditionsof contract, shall apply as far as applicable.d) Where under a contract, the price payable is fixed on F.O.B. part of export orF.O.R. dispatch<strong>in</strong>g station, the contractor shall, if the stores are rejected at thedest<strong>in</strong>ation by the consignee, be liable <strong>in</strong> addition to his other liabilities <strong>in</strong>clud<strong>in</strong>grefund of price recoverable <strong>in</strong> respect of the stores so rejected, to reimburse to thepurchase, the freight and all other expenses <strong>in</strong>curred by the purchase <strong>in</strong> this respect.17. INSPECTION OF MATERIALSSignature of contractor Page 60 of 111 Dy CSTE /CTC/CNB


17.1 All equipment, materials, fitt<strong>in</strong>gs and components will be subject to <strong>in</strong>spection bythe purchaser or his representative at the manufacturer's premises be<strong>for</strong>e dispatchexcept imported material which will be accepted based on Orig<strong>in</strong>al factoryAcceptance Test Report and physical <strong>in</strong>spection at site/ store depot. No materialsshall be despatched from the manufacturer's premises until these are <strong>in</strong>spectedand/or approved. Materials also be <strong>in</strong>spected by the purchaser or hisrepresentative at the contractor’s depot at the purchaser’s discretion. Thepurchaser or his representative shall have the right to be present dur<strong>in</strong>g allstages of manufacture, and shall be af<strong>for</strong>ded, free of charge all reasonablefacilities <strong>for</strong> <strong>in</strong>spection and test<strong>in</strong>g so as to satisfy himself that the materials are<strong>in</strong> accordance with specifications, approved draw<strong>in</strong>g and designs.17.2 Materials appear<strong>in</strong>g <strong>in</strong> RDSO approved list as per IRS/RDSO design orspecification shall be <strong>in</strong>spected by RDSO as per guidel<strong>in</strong>es mentioned <strong>in</strong> RDSObooklet regard<strong>in</strong>g the cost aspect of materials to be supplied. Telecomm items ofITD/TEC specification which are <strong>in</strong>spected by RDSO usually shall also be got<strong>in</strong>spected by RDSO as per guidel<strong>in</strong>es mentioned <strong>in</strong> RDSO booklets. Materialsother than this will be <strong>in</strong>spected by Purchaser Eng<strong>in</strong>eer or hisrepresentative/RITES. Inspection by Purchaser’s representative will be atfactory/site.17.3 All materials that are not covered under the specification, designs and draw<strong>in</strong>gs ofRDSO/TEC etc. shall be procured from the reputed manufacturers or theirauthorised dealers. Such materials are to be approved by the purchaser’sEng<strong>in</strong>eer. The Contractor may be required to produce test certificate from themanufacturer wherever called <strong>for</strong> by the Eng<strong>in</strong>eer.17.4 Dur<strong>in</strong>g the execution of the contract, samples may be taken from all thematerials employed <strong>for</strong> the purpose of test and/or analysis under the conditionslaid down <strong>in</strong> specification; such samples to be prepared <strong>for</strong> test<strong>in</strong>g and<strong>for</strong>warded to the test<strong>in</strong>g entity shall be free of all costs to the Railway.17.5 The decision of the purchaser or his successor shall be f<strong>in</strong>al <strong>in</strong> respect ofacceptability or otherwise of any material, equipment etc. required <strong>for</strong> the work.17.6 The cost of <strong>in</strong>spection of equipment and materials, all tests and/or analysisper<strong>for</strong>med shall be borne by the Contractor.17.7 All expenses of the purchasers representative shall be borne by the purchaserwhether the <strong>in</strong>spected materials is utilised <strong>in</strong> the work or not.17.8 In case any material be found not accord<strong>in</strong>g to the standard specifications afterdelivery at site, the contractor shall immediately remove such materials with<strong>in</strong> 48hours from Railway premises at his own cost.Signature of contractor Page 61 of 111 Dy CSTE /CTC/CNB


18. INSPECTION OF WORKS18.1 The Eng<strong>in</strong>eer or his representative may <strong>in</strong>spect and test the various portions of thework at all stages and shall have full power to reject all or any portion of thework that he may consider to be defective or <strong>in</strong>ferior <strong>in</strong> quality of materialsworkmanship of design <strong>in</strong> comparison to what is called <strong>for</strong> <strong>in</strong> the specification.18.2 All material brought to site can be erected only after <strong>in</strong>spection and acceptance bythe Eng<strong>in</strong>eer <strong>in</strong> charge or his authorised representative. Similarly, dur<strong>in</strong>g theexecution of the contract, samples may be taken <strong>for</strong> the purpose of test and/oranalysis under the conditions laid down <strong>in</strong> specification, such samples to beprepared <strong>for</strong> test<strong>in</strong>g and <strong>for</strong>warded free of all cost to the Railway. The contractorshall carryout such tests at the cost as are necessary <strong>in</strong> the op<strong>in</strong>ion of the Railway toensure necessary compliance of the specifications of the contractor.18.3 In the event of rejection of any work already executed and not <strong>in</strong> accordancewith specification as <strong>in</strong> this tender and/or as determ<strong>in</strong>ed by the Eng<strong>in</strong>eer orwhich the Contractor has been apprised, the Contractor shall carry outalterations/replacements to such works to the satisfaction of the Eng<strong>in</strong>eer <strong>for</strong> whichno additional expenses will be borne by the Railway.18.4 Be<strong>for</strong>e the cables are actually laid contractor's representative and theEng<strong>in</strong>eer's representative shall jo<strong>in</strong>tly <strong>in</strong>spect the quality and depth of trenches,chases, quality of bricks and arrangements <strong>for</strong> tamped fill<strong>in</strong>g. The measurementsof length <strong>for</strong> all these items will be suitably recorded by the Eng<strong>in</strong>eer'srepresentative who will permit the lay<strong>in</strong>g of cables after issu<strong>in</strong>g the certificatethat the above works have been done as required by the Specifications.18.5 Inspection of completed worksThe contractor shall advise the railway 15 days <strong>in</strong> advance the time when hisportion of the work will be completed by him and be ready <strong>for</strong> <strong>in</strong>spection. TheRailway will make <strong>in</strong>spection after the advice of completion of work is receivedfrom the Contractor.Although the contractor’s portion of the work shall be <strong>in</strong>spected by the Railway as<strong>in</strong>dicated above, it is possible that certa<strong>in</strong> defects may appear at the time of<strong>in</strong>stallation. The Contractor shall be responsible to rectify these defects to thesatisfaction of the Railway.Dur<strong>in</strong>g <strong>in</strong>spection of <strong>in</strong>stallation by Railway Eng<strong>in</strong>eer the contractor shall makesuch tests as would be necessary to demonstrate to the satisfaction of the Railwaythat the work as completed by him is <strong>in</strong> accordance with the specifications of thecontract. The contractor shall provide such <strong>in</strong>struments and apparatus as may benecessary <strong>for</strong> mak<strong>in</strong>g these tests.Signature of contractor Page 62 of 111 Dy CSTE /CTC/CNB


19. QUANTUM OF WORK AND VARIATION IN QUANTITIES19.1 The quantities of various items given <strong>in</strong> the schedules <strong>for</strong> the works to beexecuted are only approximate and are only <strong>for</strong> the guidance of the contractor. Asfar as possible, they have been assessed correctly but are likely to vary dur<strong>in</strong>g theexecution of the work.19.2 Individuals NS items <strong>in</strong> contracts shall be operated with variation of plus or m<strong>in</strong>us25% and payment would be made as per the agreement rate. For this, no f<strong>in</strong>anceconcurrence would be required.19.3 In case an <strong>in</strong>crease <strong>in</strong> quantity of an <strong>in</strong>dividual item by more than 25% of theagreement quantity is considered unavoidable, the same shall be got executed byfloat<strong>in</strong>g a fresh tender. If float<strong>in</strong>g a fresh tender <strong>for</strong> operat<strong>in</strong>g that item isconsidered not practicable, quantity of that item may be operated <strong>in</strong> excess of125% of the agreement quantity subject to the follow<strong>in</strong>g conditions:(a) Operation of an item by more than 125% of the agreement quantity needs theapproval of an officer of the rank not less than S.A. Grade;(i) Quantities operated <strong>in</strong> excess of 125% but upto 140% of the agreement quantityof the concerned item, shall be paid at 98% of the rate awarded <strong>for</strong> that item <strong>in</strong>that particular tender;(ii) Quantities operated <strong>in</strong> excess of 140% but upto 150% of the agreement quantityof the concerned item, shall be paid at 96% of the rate awarded <strong>for</strong> that item <strong>in</strong>that particular tender;(iii) Variation <strong>in</strong> quantities of <strong>in</strong>dividual items beyond 150% will be prohibited &would be permitted only <strong>in</strong> exceptional unavoidable circumstances with theconcurrence of associate f<strong>in</strong>ance & shall be paid at 96% of the rate awarded <strong>for</strong>that item <strong>in</strong> that particular tender.(b) The variation <strong>in</strong> quantities as per the above <strong>for</strong>mula will apply only to the<strong>in</strong>dividual items of the contract & not on the overall contract value.(c) Execution of quantities beyond 150% of the overall agreemental value should notbe permitted and, if found necessary, should be only through fresh tenders or bynegotiat<strong>in</strong>g with exist<strong>in</strong>g contractor, with prior personal concurrence ofFA&CAO/IRPMU & approval of GM.19.4 In cases where decrease is <strong>in</strong>volved dur<strong>in</strong>g execution of contract:(a) The contract sign<strong>in</strong>g authority can decrease the items upto 25% of <strong>in</strong>dividual itemwithout f<strong>in</strong>ance concurrence.(b) For decrease beyond 25% <strong>for</strong> <strong>in</strong>dividual items or 25% of contract agreementvalue, the approval of an officer not less than rank of S.A. Grade may be taken,after obta<strong>in</strong><strong>in</strong>g ‘No claim certificate’ from the contractor & with f<strong>in</strong>anceconcurrence, giv<strong>in</strong>g detailed reasons <strong>for</strong> each such decrease <strong>in</strong> the quantities.Signature of contractor Page 63 of 111 Dy CSTE /CTC/CNB


(c) It should be certified that the work proposed to be reduced will not be required <strong>in</strong>the same work.19.5 The limit <strong>for</strong> vary<strong>in</strong>g quantities <strong>for</strong> m<strong>in</strong>or value items shall be 100% (as aga<strong>in</strong>st25% prescribed <strong>for</strong> other items). A m<strong>in</strong>or value item <strong>for</strong> this purpose is def<strong>in</strong>ed asan item whose orig<strong>in</strong>al agreement value is less than 1% of the total orig<strong>in</strong>alagreement value.19.6 No such quantity variation limit shall apply <strong>for</strong> foundation items.19.7 As far as SOR items are concerned, the limit of 25% would apply to the value ofSOR schedule as a whole and not on <strong>in</strong>dividual SOR items. However, <strong>in</strong> case ofNS items, the limit of 25% would apply on the <strong>in</strong>dividual items irrespective of themanner of quot<strong>in</strong>g the rate (s<strong>in</strong>gle percentage rate or <strong>in</strong>dividual item rate).20. ADDITION/REDUCTION OF QUANTITIES OF WORKIf dur<strong>in</strong>g the execution of the work the contractor is called upon to carry out anynew work not <strong>in</strong>cluded <strong>in</strong> orig<strong>in</strong>al scope of work, it should not be executed be<strong>for</strong>ea rate has been agreed to by the Railways <strong>in</strong> the manner as <strong>in</strong>dicated <strong>in</strong> GeneralConditions of Contract and Instructions <strong>for</strong> tenders of the Engg. Department ofRailways.The successful tenders will, however, have no claims or right <strong>in</strong> the execution ofany work which <strong>in</strong> the op<strong>in</strong>ion of the Eng<strong>in</strong>eer should be carried outdepartmentally or otherwise and the Railway reserves the right any time be<strong>for</strong>e orafter the acceptance of the tender to keep back from the contract and carry out thework or portion of work through any other agent it may th<strong>in</strong>k fit without assign<strong>in</strong>gany reason. No claim <strong>for</strong> compensation / loss or what so ever on this account willbe enterta<strong>in</strong>ed by the Railway.21. SUBLETTING AND ASSIGNMENT21.1 The contractor may sublet a part of the works under this contract and enter <strong>in</strong>tocontract with suppliers <strong>for</strong> supply of materials only with the approval of theRailway adm<strong>in</strong>istration.21.2 The names of all sub contractors proposed to be employed <strong>for</strong> execution of workor any part thereof <strong>in</strong>clud<strong>in</strong>g manufactur<strong>in</strong>g of equipment and other materialsshall be submitted by the contractor to the purchaser and got approved by himbe<strong>for</strong>e the contractor enter <strong>in</strong>to a agreement with the sub contractor <strong>for</strong> thepurpose.21.3 The contractor shall arrange <strong>for</strong> effective supervision of sub contractor's work andrema<strong>in</strong> solely responsible <strong>for</strong> materials supplied and <strong>for</strong> works carried out on hisbehalf by the sub contractor.Signature of contractor Page 64 of 111 Dy CSTE /CTC/CNB


21.4 The contractor shall not, save with the previous consent <strong>in</strong> writ<strong>in</strong>g of thePurchaser, sublet, transfer or assign the contract or any part thereof or <strong>in</strong>terestthere<strong>in</strong> or benefit or advantage thereof any manner whatsoever.21.5 In the event of the Contractor's sublett<strong>in</strong>g or assign<strong>in</strong>g this contract or any partthereof without such permission, the purchaser shall be entitled to cancel thecontract and to purchase the stores elsewhere on the contractor's account and riskand the contractor shall be liable <strong>for</strong> any loss or damage which the purchasermay susta<strong>in</strong> <strong>in</strong> consequence or aris<strong>in</strong>g out of such purpose.22. EXECUTION OF WORKAll the work shall be executed <strong>in</strong> strict con<strong>for</strong>mity to the provisions of thecontract document and accord<strong>in</strong>g to detailed draw<strong>in</strong>gs, specifications and<strong>in</strong>structions as may be approved from time to time by Railway based ondetailed design and eng<strong>in</strong>eer<strong>in</strong>g carried out by contractor <strong>in</strong> l<strong>in</strong>e withrequirements as per contract document. The contractor shall be responsible <strong>for</strong>ensur<strong>in</strong>g that the work throughout are executed <strong>in</strong> the most substantial, proper andworkman like manner with the quality of material and workmanship <strong>in</strong> strictaccordance with the specifications and as per sound <strong>in</strong>dustrial practices and to theentire satisfaction of the Railway. In case of any doubts regard<strong>in</strong>g any particularsof construction and any ambiguities <strong>in</strong> the plans, the decision of the purchaser’seng<strong>in</strong>eer shall be f<strong>in</strong>al and b<strong>in</strong>d<strong>in</strong>g on the contractor.23. PROGRESS REPORTING23.1 The contractor shall submit to Railways at his own cost periodic progressreports at regular <strong>in</strong>tervals regard<strong>in</strong>g the state and progress of work. Thedetails and pro-<strong>for</strong>ma of the report will mutually be agreed after award of theContract. Such reports shall be <strong>for</strong> daily man power, equipment and plantdevelopment, weekly work progress and monthly progress review reports. Allactions as directed by Railway pursuant to such reports shall be promptly attendedto by Contractor.23.2 The purchaser’s eng<strong>in</strong>eer shall also conduct monthly meet<strong>in</strong>gs with the contractorto assess and review the programme of works. The action proposed to progressthe work as planned, difficulties, assistance required etc. shall be clearly broughtout and remedial action taken. The m<strong>in</strong>utes of these meet<strong>in</strong>gs shall be jo<strong>in</strong>tlysigned by Railways and contractor.24. MAINTENANCE OF WORKS24.1 The contractor shall at all times dur<strong>in</strong>g the progress and cont<strong>in</strong>uance of the worksand also <strong>for</strong> the period of Warranty specified <strong>in</strong> the tender <strong>for</strong>m and after the dateof pass<strong>in</strong>g of the certificate of completion by the Railway's representative or anyother earlier date subsequent to the completion of the works that may be fixed bySignature of contractor Page 65 of 111 Dy CSTE /CTC/CNB


Railway's representative be responsible <strong>for</strong> and effectively ma<strong>in</strong>ta<strong>in</strong> and uphold<strong>in</strong> good, substantial, sound and perfect condition all and every part of the worksand shall make good from time to time and at all times, as often as theRailway's representative shall require, any damage or defect that may dur<strong>in</strong>g theabove period arise <strong>in</strong> or be discovered or be <strong>in</strong> any way connected with theworks, provided that such damage or defect is not directly caused by errors<strong>in</strong> the contract documents, act of providence or <strong>in</strong>struction or civil riot, and thecontractor shall be liable <strong>for</strong> and shall pay and make good to the Railways orother persons legally entitled thereto whenever required by the Railway'srepresentative so to do, all losses, damages, costs and expenses they or any ofthem may <strong>in</strong>cur or be put or be liable to, by reason or <strong>in</strong> consequence of theoperations of the contractor or his failure <strong>in</strong> any respect.25. ANNUAL MAINTENANCE CONTRACTNot applicable.26. CLEARANCE OF SITE26.1 Contractor at his own expenses clean the site, set out all works and provide allnecessary labours, pegs, str<strong>in</strong>g, steel to enable the purchaser or any of hisrepresentatives to check all sett<strong>in</strong>g out and the contractor will correct all errors athis own expenses.26.2 At the end of the work <strong>in</strong> each section the contractor shall as a part of hiscontractual obligation leave the area completely cleared of rubbish and obstructionsof all k<strong>in</strong>ds accord<strong>in</strong>g to the <strong>in</strong>structions of the Railway's representatives. Besides,he shall take execution of work to avoid the presence of loose earth and ballast onplat<strong>for</strong>ms, <strong>in</strong> dra<strong>in</strong>s, on the track <strong>for</strong>mation and pathways <strong>in</strong> the vic<strong>in</strong>ity. If with<strong>in</strong><strong>for</strong>tnight of completion of the particular item of site work, the refuge is not cleared,the Railway will arrange to get them removed at the cost of the Contractor.However, be<strong>for</strong>e the Railway actually gets the site cleared, <strong>in</strong>timation <strong>in</strong> writ<strong>in</strong>gshall be sent to the Contractor.27. PROVISIONAL ACCEPTANCE27.1 Immediately after the completion of the work at each station or aftercompletion of work <strong>in</strong> a block section here<strong>in</strong> after referred as sub-section, thecontractor shall certify and advise the purchaser <strong>in</strong> writ<strong>in</strong>g that the <strong>in</strong>stallationis (i) complete, (ii) ready <strong>for</strong> satisfactory service and (iii) ready to be handedover. He will also place at the disposal of the purchaser the required staff <strong>for</strong><strong>in</strong>spection, test<strong>in</strong>g and putt<strong>in</strong>g it <strong>in</strong>to operation.27.2 The test or tests specified <strong>in</strong> Pre-amble will be conducted jo<strong>in</strong>tly by thepurchaser and contractor as soon as possible after receipt of advice ofcompletion of one sub-section by the purchaser from the contractor. Thetest schedule shall be furnished by the tenderer which will be modified bySignature of contractor Page 66 of 111 Dy CSTE /CTC/CNB


mutual discussion between the contractor and Railway be<strong>for</strong>e f<strong>in</strong>alization.Any component, modules, sub-assemblies or equipment fail<strong>in</strong>g dur<strong>in</strong>g thecommission<strong>in</strong>g test shall be replaced/repaired free of cost by the tenderer.27.3 Purchaser's Eng<strong>in</strong>eer shall issue a Provisional Acceptance certificate <strong>for</strong>successful commission<strong>in</strong>g of whole system cover<strong>in</strong>g all materials and services<strong>in</strong>cluded <strong>in</strong> the Schedule of works, after the f<strong>in</strong>al acceptance test as per theapproved test procedure have been completed and the per<strong>for</strong>mance has beenfound to meet the specifications. Railways decision <strong>in</strong> this respect shall be f<strong>in</strong>al.The Provisional acceptance certificate shall be signed by both the parties.27.4 The Purchaser's Eng<strong>in</strong>eer may issue such a certificate with respect to any part ofthe works be<strong>for</strong>e the completion of the whole of the works or with respect to anysubstantial part of the works which has been both completed to the satisfactionof the Purchaser's Eng<strong>in</strong>eer and occupied or used by the Railway and when anysuch certificate is given <strong>in</strong> respect of a part of the works, such part shall beconsidered as completed.27.5 Should the result/s of <strong>in</strong>spection and test be not satisfactory, an extension ofone month will be granted to the contractor to make good the defects anddeficiencies po<strong>in</strong>ted out by the purchaser. Fresh <strong>in</strong>spection and test will thenbe carried out after the contractor has attended to the defects anddeficiencies. If these tests are also not satisfactory the purchaser may proceedat the contractor's expense by all means deemed expedient, to have the<strong>in</strong>stallation made satisfactory until they comply with the specifications, andapproved draw<strong>in</strong>gs and designs.27.6 In such a case or <strong>in</strong> the case of delay <strong>in</strong> complet<strong>in</strong>g the work under this contractwith<strong>in</strong> the time limit the purchaser reserves the right, if he deems it possibleto use <strong>in</strong> a reasonable manner any part of the <strong>in</strong>stallation even if some<strong>in</strong>stallations are not completely erected. The purchaser will give to the contractor<strong>for</strong> this purpose 7 days previous notice. The contractor shall then take at his ownexpense all necessary steps to complete the work <strong>in</strong> accordance with theprovisions of the contract. In case it becomes impossible to proceed with theabove mentioned tak<strong>in</strong>g over tests or reasons other than <strong>for</strong> which the contractoris responsible, the Provisional Acceptance Certificate shall be issued at or with<strong>in</strong>a mutually agreed reasonable period not exceed<strong>in</strong>g six months after completion of<strong>in</strong>stallation.27.7 The issue of provisional acceptance will not be withheld <strong>for</strong> rectification ofm<strong>in</strong>or defects as dist<strong>in</strong>ct from rejected equipment, which may not beessential <strong>for</strong> commission<strong>in</strong>g and operation of the <strong>in</strong>stallation. In such cases,only the value of the materials and cost of the rectification of the m<strong>in</strong>or defectsshall be withheld from the payments on provisional acceptance until rectificationis completed.Signature of contractor Page 67 of 111 Dy CSTE /CTC/CNB


28. FINAL ACCEPTANCE28.1 The f<strong>in</strong>al acceptance of the entire equipment <strong>in</strong>stalled <strong>in</strong> the section shall takeeffect from the date of expiry of the period of ma<strong>in</strong>tenance supervision as def<strong>in</strong>ed<strong>in</strong> Para- 24 or the expiry of the last of the respective period of Ma<strong>in</strong>tenanceSupervision of various sections <strong>for</strong> which Provisional Acceptance Certificatesare issued or brought <strong>in</strong>to full fledged operation, provided that the contractorhas complied fully with his obligations under Clause 27 <strong>in</strong> respect of eachsection under the contract.28.2 If on the other hand the contractor has not so complied with his obligation underPara 27 <strong>in</strong> respect of any section, the purchaser may either extend the period ofma<strong>in</strong>tenance supervision <strong>in</strong> respect of that section until the necessary works arecarried out by the contractor or carry out those works suo-moto on behalf of thecontractor at the contractor's expenses. After expiry of the period ofma<strong>in</strong>tenance supervision <strong>for</strong> each section, a certificate of F<strong>in</strong>al Acceptance <strong>for</strong>the section shall be issued by the purchaser and the last of such certificate will becalled the Last and F<strong>in</strong>al Acceptance Certificate. The contract shall not beconsidered as completed until the issue of F<strong>in</strong>al Acceptance Certificate bythe purchaser.28.3 The purchaser shall not be liable to the contractor <strong>for</strong> any dispute aris<strong>in</strong>g out o<strong>for</strong> <strong>in</strong> connection with the contract or execution of the work unless the contractorhave made a claim <strong>in</strong> writ<strong>in</strong>g <strong>in</strong> respect thereof be<strong>for</strong>e the issue of F<strong>in</strong>alAcceptance Certificate under this clause. The contractor shall be debarred fromdisput<strong>in</strong>g the correctness of the items caused by the no claim certificate ordemand<strong>in</strong>g a reference to Arbitration <strong>in</strong> respect thereof.28.4 Notwithstand<strong>in</strong>g the issue of F<strong>in</strong>al Acceptance Certificate, the contractor and thepurchaser (subject to Sub Clause as above) shall rema<strong>in</strong> liable <strong>for</strong> fulfillment ofany obligation <strong>in</strong>curred under the provision of the contract prior to the issue ofF<strong>in</strong>al Acceptance Certificate which rema<strong>in</strong>s unper<strong>for</strong>med at the time suchcertificate is issued and <strong>for</strong> determ<strong>in</strong><strong>in</strong>g the nature and extent of suchobligation, the contract shall be deemed to rema<strong>in</strong> <strong>in</strong> <strong>for</strong>ce between the partieshereto.29. WARRANTY29.1 The contractor shall warranty that all materials & equipment to be supplied and<strong>in</strong>stalled as per this tender shall be free from defects and faults <strong>in</strong> design, material,workmanship and manufacture and shall be of the highest grade and consistent withthe established and generally accepted standard <strong>for</strong> materials of the type orderedand <strong>in</strong> full con<strong>for</strong>mity with the contract specifications.Signature of contractor Page 68 of 111 Dy CSTE /CTC/CNB


29.2 This warranty shall start from the date of acceptance of commission<strong>in</strong>g by railwaysand plac<strong>in</strong>g <strong>in</strong> service. The date of the commission<strong>in</strong>g of the work will be after thesign<strong>in</strong>g of the provisional acceptance certificate by both the parties as per details atclause 2729.3 Dur<strong>in</strong>g the period of Warranty, the Contractor shall rema<strong>in</strong> responsible to arrangereplacement and <strong>for</strong> sett<strong>in</strong>g right at his own cost any equipment supplied by him,which is of defective manufacture or defective design or defectivematerial/component and becomes unworkable due to any cause whatsoever. Thedecision of railways to attend to any damage or defect <strong>in</strong> work shall be f<strong>in</strong>al andb<strong>in</strong>d<strong>in</strong>g on the Contractor.29.4 If it becomes necessary <strong>for</strong> the contractor to replace or renew any defective portionsof the system under this clause, the contractor shall make the system functional byprovid<strong>in</strong>g suitable replacements and restore back the orig<strong>in</strong>al card / equipment afterrepairs to the same. The card / equipment so repaired should bear warranty equal tothe end of orig<strong>in</strong>al warranty period or m<strong>in</strong>imum SIX months from the date ofrepair, whichever is later. If any defect is not remedied with<strong>in</strong> reasonable time, theRailway may proceed to do the work at contractor’s risk and expense, but withoutprejudice to any other rights, which the Railway may have aga<strong>in</strong>st the contractor <strong>in</strong>respect of such defects.29.5 All <strong>in</strong>spections, replacements or renewals carried out by the Contractor dur<strong>in</strong>g thewarranty period shall be subjected to the same conditions of the contract.29.6 All replacement and repairs and design change that the Railway shall call upon thecontractor to deliver or per<strong>for</strong>m under this warranty shall be delivered andper<strong>for</strong>med by the contractor with<strong>in</strong> one month, promptly and satisfactorily.29.7 The decision of the Railway <strong>in</strong> regard to contractor’s liability and the amount, ifany, payable under this warranty shall be f<strong>in</strong>al and conclusive.29.8 Due to analysis of failures, if any design deficiency is po<strong>in</strong>ted out by the Railway,the contractor shall rectify it at his own cost.30. TRAININGNot applicable.31. INFRINGEMENT OF PATENTS(a)The Contractor is <strong>for</strong>bidden to use any patents or registered draw<strong>in</strong>gs, processesor patterns <strong>in</strong> fulfill<strong>in</strong>g his contract without the previous consent <strong>in</strong> writ<strong>in</strong>g of theowner of such patents, draw<strong>in</strong>gs, patterns or trade marks, except where theseare specified by the purchaser himself. Royalties where payable <strong>for</strong> the use ofsuch patented processes, registered draw<strong>in</strong>gs or patterns shall be borneexclusively by the Contractor. The Contractor shall advise the purchaser of anySignature of contractor Page 69 of 111 Dy CSTE /CTC/CNB


proprietary rights that may exist on such processes, draw<strong>in</strong>gs or patterns which hemay use of his own accord.(b)In the case of patents taken out by the Contractor of the draw<strong>in</strong>gs or patternsregistered by him, or of those patents, draw<strong>in</strong>gs or patterns <strong>for</strong> which he holdsa license, the sign<strong>in</strong>g of the contract automatically gives the Purchaser theright to repair by himself the purchased articles covered by the patent or byany person or body chosen by him and to obta<strong>in</strong> from any sources he desires thecomponent parts required by him <strong>for</strong> carry<strong>in</strong>g out the repair work. In the eventof <strong>in</strong>fr<strong>in</strong>gement of any patent rights due to above action of the purchaser, heshall be entitled to claim damages from the contractor on the grounds of anyloss of any nature which he may suffer.32. LICENSE AS PER GOVT. OF INDIA CONTRACT LABOUR ACT32.1 The contractors are required to produce license as enjo<strong>in</strong>ed <strong>in</strong> the Government ofIndia Contract Labour (Regulation and Abolition) Act (1978). They shall not beallowed to undertake or execute any work through contract labour except underand <strong>in</strong> accordance with a license issued under the said Act <strong>in</strong> that behalf bythe authorised licens<strong>in</strong>g Officer.33. DEFAULT & DELAYSThe Contractor shall execute the work with due diligence and expedition, keep<strong>in</strong>gto the approved Time schedule. Should he refuse or neglect to comply with anyreasonable orders given to him <strong>in</strong> writ<strong>in</strong>g by the Purchaser's Eng<strong>in</strong>eers <strong>in</strong>connection with the work or contravene the provision of the contract or theprogress of work lags persistently beh<strong>in</strong>d the time schedule due to his neglect,the Purchaser shall be at liberty to give seven days notice <strong>in</strong> writ<strong>in</strong>g to theContractor requir<strong>in</strong>g him to make good the neglect or contravention compla<strong>in</strong>edof and should the contractor fail to comply with the requisitions made <strong>in</strong> thenotice with<strong>in</strong> seven days from the receipt thereof, it shall be lawful <strong>for</strong> thepurchaser to take the work wholly or <strong>in</strong> part out of the Contractor's handswithout any further reference and get the work or any part thereof, as the casemay be, completed by other agencies at the expense of the contractor withoutprejudice to any other right or remedy of the Purchaser.34. LOSS SUSTAINED DUE TO DEFAULT AND DELAYIn the event of any loss to the purchaser on account of execution and/orcompletion of the work or any part thereof by agencies other than thecontractor, the contractor shall be liable to reimburse the loss to purchaserwithout prejudice to the other rights and remedies of the purchaser, andSignature of contractor Page 70 of 111 Dy CSTE /CTC/CNB


the reimbursement <strong>in</strong> full or <strong>in</strong> part as the case may be, shall be met, at theoption of the purchaser from out of all or any of the follow<strong>in</strong>g sources viz:i) Any amount due and payable to the contractor by the purchaser on any accountwhatsoever;ii)The Contractor's security deposit <strong>in</strong> hands of the purchaser as far as availableand any other assets whatsoever of the contractor;In the event of re-imbursement from out of sources (i) and/or (ii) abovementioned, the purchaser shall have the right of appropriation suo-moto.35. PENALTY FOR DELAY IN COMPLETIONa) If the contractor fails to execute and complete the work with<strong>in</strong> the timespecified <strong>in</strong> the Agreement or with<strong>in</strong> the period of extension granted under Para36 except <strong>in</strong> so far as the delay is on the purchaser's account, the contractor shallbe levied Liquidated Damages @ 1/2% per week or part thereof of the entirecontract value of the work awarded to the contractor <strong>for</strong> delays <strong>in</strong>supply/execution of the work as per General Condition of contract.b) For the purpose of this clause, the contract value of the works shall be taken asvalue of work as per contract agreement <strong>in</strong>clud<strong>in</strong>g any supplementary workorder/contract agreement issued Provided also, that the total amount of liquidateddamages under this condition shall not exceed the under noted percentage value orof the total value of the item or groups of items of work <strong>for</strong> which a separatedist<strong>in</strong>ct completion period is specified <strong>in</strong> the contract.(i) For contract value up to Rs. 2 Lakhs(ii) For contracts valued above Rs. 2 Lakhs-- 10% of the total value of thecontract.-- 10% <strong>for</strong> the first Rs.2 Lakhsand the 5% of the balance.Provided further, that if the Railway is not satisfied that the works can becompleted by the Contractor and <strong>in</strong> the event of failure on the part of the contractorto complete the work with<strong>in</strong> further extension of time allowed as a<strong>for</strong>esaid, theRailway shall be entitled, without prejudice to any other right or remedy available<strong>in</strong> that behalf, to appropriate the contractor’s security deposit and resc<strong>in</strong>d thecontract under clause 62 of these conditions, whether or not actual damage iscaused by such default.36. EXTENSION OF TIMEIf such a failure as a<strong>for</strong>esaid shall have arisen from any cause which the Purchasermay agree as be<strong>in</strong>g a reasonable ground <strong>for</strong> extension of time, then suchSignature of contractor Page 71 of 111 Dy CSTE /CTC/CNB


additional time as IRPMU <strong>in</strong> their absolute discretion consider to be reasonablyjustified by the circumstances of the case, such extensions shall be granted withliquidated damages <strong>in</strong> the Form No.11. The Contractor will apply <strong>for</strong> extensionat least two months be<strong>for</strong>e the expiry of the period of completion. Form No.12will be applicable <strong>in</strong> case extension is on purchaser’s account and also <strong>in</strong> caseextension is on contractor's account but the purchaser is reasonably satisfied thatcontractor cannot be penalized <strong>for</strong> such delay. The terms and conditions of theorig<strong>in</strong>al contract will rema<strong>in</strong> operative dur<strong>in</strong>g the extended period and noth<strong>in</strong>gwill be allowed on this account.37. CONTRACTOR'S LIABILITIES FOR COSTS AND DAMAGES37.1 WITHHOLDING AND LIEN IN RESPECT OF SUMS CLAIMEDa) Whenever any claim or claims <strong>for</strong> payment of a sum of money arises out ofunder the contract aga<strong>in</strong>st the contractor, the Purchaser shall be entitled towithhold and also have lien to reta<strong>in</strong> such sum or sums <strong>in</strong> whole or <strong>in</strong> part fromthe security, if any, deposited by the contractor and <strong>for</strong> the purpose a<strong>for</strong>esaid thepurchaser shall be entitled to withhold the said cash security deposit or thesecurity, if any, furnished as the case may be and also have lien over the sumpend<strong>in</strong>g f<strong>in</strong>alization or adjudication of any such claim.b) In the event of the security be<strong>in</strong>g <strong>in</strong>sufficient to cover the claimed amount oramounts or if no security has been taken from the Contractor, the purchaser shallbe entitled to withhold and have lien to reta<strong>in</strong> to the extent of such claim amountor amounts referred to spura, from any sum or sums found payable or which atany time thereafter may become payable to the Contractor under the samecontract or any other department of the Central Government pend<strong>in</strong>gf<strong>in</strong>alisation or adjudication of any such claims.c) It is an agreed term of the contract that the sum of money or moneys so withheldor reta<strong>in</strong>ed under the lien referred to by the purchaser till the claim aris<strong>in</strong>g out o<strong>for</strong> under the contract is determ<strong>in</strong>ed by the Arbitrator. (If the contract is <strong>gov</strong>ernedby the Arbitration clause) or by the competent court as the case may be and thatthe contractor will have no claim <strong>for</strong> <strong>in</strong>terest of damages whatsoever on anyaccount <strong>in</strong> respect of such withhold<strong>in</strong>g or retention under the lien referred tospura and duly notified as such to the Contractor.d) For the purpose of this clause, where contractor is a partnership firm or alimited company, the purchaser shall be entitled to withhold and also have a liento reta<strong>in</strong> towards such claimed amount or amounts <strong>in</strong> whole or <strong>in</strong> part from anysum found payable to any partner/limited company, as the case may be,whether <strong>in</strong> his <strong>in</strong>dividual company or otherwise.Signature of contractor Page 72 of 111 Dy CSTE /CTC/CNB


37.2 LIEN IN RESPECT OF OTHER CONTRACTSa) Any sum or sums of money due and payable to the Contractor (<strong>in</strong>clud<strong>in</strong>g thesecurity deposit returnable to him under the contract) may be withheld orreta<strong>in</strong>ed by way of lien by the Purchaser aga<strong>in</strong>st any claim of this Railway orany other Railways or any other Departments of the Central Government <strong>in</strong>respect of payment of a sum of money aris<strong>in</strong>g out of or under any othercontract made by the Contractor with this or any other Railway or any otherdepartment of the Central Government.b) It is an agreed term of the contract that the sum of money so withheld or reta<strong>in</strong>edunder this clause by the purchaser will be kept withheld or reta<strong>in</strong>ed as such bythe purchaser till the claim aris<strong>in</strong>g out of or under any other contract iseither mutually settled or determ<strong>in</strong>ed by the Arbitrator if the other contract is<strong>gov</strong>erned by the Arbitration clause or by the competent court as the case maybe, and that the contractor shall have no claim <strong>for</strong> <strong>in</strong>terest or damages <strong>in</strong> respectof any sum of money withheld or reta<strong>in</strong>ed under this clause and duly notified tothe contractor.38. UNIT PRICES38.1 The prices quoted by the Tenderer shall <strong>in</strong>clude the prices of materials <strong>in</strong>clud<strong>in</strong>gall <strong>in</strong>cidental charges <strong>for</strong> transport, load<strong>in</strong>g/unload<strong>in</strong>g and handl<strong>in</strong>g ofmaterials, commission <strong>for</strong> arrang<strong>in</strong>g dispatch by rail / road direct frommanufacturer's factory and complet<strong>in</strong>g all necessary <strong>for</strong>malities <strong>in</strong> this respect,such as submission of <strong>for</strong>ward<strong>in</strong>g notes, arrang<strong>in</strong>g placement of Wagon,collection of banker's charges <strong>for</strong> Bank guarantee, Indemnity Bonds, <strong>in</strong>clusiveof cost of Stamp etc. as also sid<strong>in</strong>g or shunt<strong>in</strong>g charges, if any, levied by theRailway. The break up of the basic cost and other taxes and duties shall bepositively submitted.38.2 The prices shall <strong>in</strong>clude all taxes, duties, Royalty and levies (<strong>in</strong>clud<strong>in</strong>g Octroietc.) applicable on this Works Contract. There<strong>for</strong>e, they should quote their pricestak<strong>in</strong>g <strong>in</strong>to account the rate of sales tax as leviable <strong>in</strong> the event of sale to theCentral Government Organisation etc. It is clarified that required <strong>for</strong>m applicable<strong>for</strong> this purpose will be supplied to the contractor, as applicable <strong>in</strong> the state wherethe contract is be<strong>in</strong>g executed. The prices shall also <strong>in</strong>clude provision <strong>for</strong> lossesand wastage <strong>in</strong> transit and <strong>in</strong>stallation and commission<strong>in</strong>g.38.3 The prices quoted by the tenderer shall <strong>in</strong>clude cost of commission<strong>in</strong>g andtest<strong>in</strong>g and all costs of Adm<strong>in</strong>istration of Contract, Insurance Premium,Banker's charges <strong>for</strong> guarantees, cost of storage, load<strong>in</strong>g-unload<strong>in</strong>g and handl<strong>in</strong>gof materials and <strong>for</strong> any road transport which the contractor may use <strong>for</strong> carriageof materials to his depot and the site of work. The prices shall <strong>in</strong>clude the cost ofworks and adjustments necessary to be done by the contractor dur<strong>in</strong>g or after testscarried out by the purchaser.Signature of contractor Page 73 of 111 Dy CSTE /CTC/CNB


38.4 The price to be quoted by the tenderers should take <strong>in</strong>to account the credit availedon <strong>in</strong>puts under the MODVAT scheme <strong>in</strong>troduced w.e.f. Ist March 1986. Thetenderers should give a declaration that any let offs <strong>in</strong> respect of duties on <strong>in</strong>putsas admissible under law is be<strong>in</strong>g totally and unconditionally passed on to thepurchaser <strong>in</strong> the price quoted by him (see para 43).38.5 While the price quoted <strong>in</strong> the contract are <strong>in</strong>clusive of all taxes i.e. custom duty,excise duty, octroi, local levies, Sales tax levied by any statutory authority, thepurchaser shall make any deduction toward sales tax on works contract ifstatutorily required to do so. The deducted sales tax on works contract shall beremitted to the concerned sales tax authority and the purchaser shall <strong>in</strong> no waybe responsible <strong>for</strong> any disputes between the sales tax authorities and thecontractor <strong>in</strong> this regard.38.6 All taxes, duties and levies (Includ<strong>in</strong>g octroi etc.) aris<strong>in</strong>g out of the transactionbetween the contractor and his sub contractor/supplier <strong>for</strong> this work will be<strong>in</strong>cluded <strong>in</strong> the rates quoted by the contractor <strong>in</strong> the relevant schedule.38.7 Arrangement of permits/license <strong>for</strong> materials will not be made by the Railwayor any assistance given. The Contractor will have to make his ownarrangement. Also no import license shall be arranged by the Railway <strong>for</strong> thiswork.39. MEASUREMENT OF WORKS39.1 Payments <strong>for</strong> the works shall be made <strong>in</strong> accordance with approved designs &draw<strong>in</strong>gs and measured <strong>in</strong> relevant units except where provided or otherwise.The measurements will be made generally <strong>in</strong> accordance with standardeng<strong>in</strong>eer<strong>in</strong>g practice & <strong>in</strong> con<strong>for</strong>mity with the General conditions of Contract.39.2 Figures, Dimensions and Draw<strong>in</strong>gs shall supersede measurement by scale anddraw<strong>in</strong>gs to a larger scale shall take precedence over those to a smaller scale.Special dimensions or directions <strong>in</strong> the specification shall supersede all else.39.3 MEANING AND INTERPRETATION BY RAILWAY TO BE FINALAll measurement, method of measurement, mean<strong>in</strong>g and <strong>in</strong>tent of specificationsand <strong>in</strong>terpretation of Special Conditions of Contract, given and made by thePurchaser or by the Purchaser’s Eng<strong>in</strong>eer shall be f<strong>in</strong>al and b<strong>in</strong>d<strong>in</strong>g and shallbe considered "excepted matters" <strong>in</strong> terms of conditions laid down <strong>in</strong> theGeneral Conditions of Contract.40. TERMS OF PAYMENT40.1 Payment to contractor will be made through EFT/ECS. All bills shall besubmitted <strong>in</strong> the office of Dy CSTE /CTC/CNB/Kanpur.Signature of contractor Page 74 of 111 Dy CSTE /CTC/CNB


40.2 Subject to any deductions or recovery which the Railway may be entitled tomake under contract, the Contractor will be entitled to be paid from time totime by way of `on account payment' <strong>for</strong> supply of goods and `progresspayment' <strong>for</strong> works as <strong>in</strong> the op<strong>in</strong>ion of the Eng<strong>in</strong>eer he has executed <strong>in</strong> termsof Contract.41 ON ACCOUNT PAYMENT41.1 "On Account Payment" will be made <strong>for</strong> supply of equipment, materials <strong>in</strong>dicated<strong>in</strong> the schedule on receipt of materials <strong>in</strong> good condition at the Stores ofSr. Section Eng<strong>in</strong>eer/IRPMU/Kanpur. On Account payments made willsubsequently be adjusted aga<strong>in</strong>st payments due on Provisional Acceptance orF<strong>in</strong>al Acceptance. 80% of the value of Supply items of Schedule ‘A’ will be paidon production of the follow<strong>in</strong>g documents:a) Store receipt certificate issued by Railway official/Representative as perForm-14.b) Orig<strong>in</strong>al Inspection certificate issued by Inspect<strong>in</strong>g Officer viz. RDSO/RITES/Railway Representative or Inspection Waiver Certificate issued by competentauthority.c) Manufacturer’s certificate <strong>for</strong> equipments that the materials are <strong>in</strong> accordancewith the specifications of the contract.d) Challan / Invoice <strong>in</strong> duplicate.e) A certificate that the materials supplied are as per the contract and the amountclaimed <strong>in</strong> the <strong>in</strong>voice is correct as per terms of the contract.f) Current Sale Tax Clearance Certificate. (Form No.58)41.2 All on account payments shall be covered by a stand<strong>in</strong>g <strong>in</strong>demnity bond <strong>in</strong> theapproved <strong>for</strong>m (see Form No.6).41.3 80% payment aga<strong>in</strong>st Execution items of Schedule will be made after successfulexecution/<strong>in</strong>stallation of the item at site pend<strong>in</strong>g commission<strong>in</strong>g of work.41.4 Next 15% payment aga<strong>in</strong>st Items of Schedule will be made on successfulcompletion of Acceptance Test after <strong>in</strong>stallation and commission<strong>in</strong>g <strong>in</strong> which theequipment per<strong>for</strong>mance would have been demonstrated to the Railways by theContractor and on production of a certificate to that effect issued by the RailwayEng<strong>in</strong>eer. For Supply items, not to be <strong>in</strong>stalled/commissioned, their 15% paymentcan be released anytime after supply on satisfactory completion of AcceptanceTest and issue of certificate to that effect, by Railway Eng<strong>in</strong>eer.41.5 The balance 5% payment will be made after issue of F<strong>in</strong>al acceptance certificate.Signature of contractor Page 75 of 111 Dy CSTE /CTC/CNB


42. FINAL SETTLEMENTOn expiry of the ma<strong>in</strong>tenance and warranty period, if any, and issue of thecertificate by the competent authority, the security deposit will be refunded afteradjustment of any dues payable by the contractor. In case AMC is built <strong>in</strong> thecontract as part of the schedule of Items, rates and quantities, the security depositshall be released after submission of bank guarantee of an amount equivalent tototal value of AMC contract <strong>for</strong> 1 year (Bank Guarantee can be of reduc<strong>in</strong>g value,after every year equivalent to AMC charges of each lapsed year).43. CERTIFICATE FOR MODVAT BENEFITS ON BILLSa) The Contractor should submit the follow<strong>in</strong>g certificate along with the bills:-"We certify that no additional duty set off on the Goods supplied by us haveaccrued under the MODVAT Scheme <strong>in</strong> <strong>for</strong>ce on the date of supply after wesubmitted our quotations and submitted the present bill."b) In the event of MODVAT credit be<strong>in</strong>g extended by the Government of Indiato more items than that already covered, the firm should advise the purchaserabout the additional benefits accrued through a letter conta<strong>in</strong><strong>in</strong>g the follow<strong>in</strong>gcertificate or any variation thereof as may be considered necessary by<strong>in</strong>dividual Railway adm<strong>in</strong>istration :-“We hereby declare that we can avail additional duty set off as per latest MODVATscheme <strong>in</strong> <strong>for</strong>ce now and we hereby give a reduction of (___________) per unit andagree to revise the prices <strong>in</strong>dicated <strong>in</strong> the order. The current E.D. of (_________) ispayable on this reduced price. There<strong>for</strong>e, we request you to amend the orderaccord<strong>in</strong>gly."44. DEDUCTION FROM ON ACCOUNT PAYMENT BILLS(i)(ii)All costs, damages or expenses, which Railways may have paid or <strong>in</strong>curred, whichunder the provisions of contract are Contractor's obligations will be deductedby Railways from progress payment Bills/Invoice of contractor, as and when it isunderstood that such an expenses has been <strong>in</strong>curred or paid <strong>for</strong>.All such claims of Railways shall, however, be duly supported by appropriate andcertified vouchers, receipts or explanations as are available to enable the contractorto identify such claims.45. TAXES45.1 The Contractor and all personnel employed by him shall pay such taxes like IncomeTax as are payable under statutory laws of India and the Purchaser WILL NOTACCEPT any liability <strong>for</strong> the same.Signature of contractor Page 76 of 111 Dy CSTE /CTC/CNB


45.2 Deduction of Income Tax at source as per provisions of F<strong>in</strong>ance Act andIncome Tax Act <strong>in</strong> <strong>for</strong>ce shall be made from the Contractor/Sub-Contractor andthe amount so deducted may be credited to the Central Government.45.3 Wherever the law makes it statutory <strong>for</strong> the Purchaser to deduct any amounttowards Sales Tax on Works Contract, the same will be deducted and remitted tothe concerned authority.45.4 INFRASTRUCTURE BENEFIT COST45.4.1 The tenderer shall ensure the availability of <strong>in</strong>frastructure Benefit <strong>for</strong> reducedcustom duty, if applicable. The goods would be <strong>in</strong> Railways’ name. Thetenderers shall be responsible <strong>for</strong> custom clearance, transportation and <strong>in</strong>suranceetc, on behalf of the Railways <strong>in</strong>clud<strong>in</strong>g payment of custom duty, <strong>in</strong>surance,freight and other charges, if any tenderers shall also be responsible <strong>for</strong> avail<strong>in</strong>g<strong>in</strong>frastructure benefit, if any, on behalf of purchaser. Purchaser will issuenecessary letter of authorization required <strong>for</strong> the purpose. The equipment willrema<strong>in</strong> with the tenderer at his risk till it is f<strong>in</strong>ally taken over.If such <strong>in</strong>frastructure benefit is not applicable, tenderers shall quote the price ofgoods and services mentioned <strong>in</strong> price schedule with all duties applicable at thetime of submission of bids.46. INSURANCE46.1 The Contractor shall take out and keep <strong>in</strong> <strong>for</strong>ce a policy or policies of <strong>in</strong>suranceaga<strong>in</strong>st all liabilities of the Contractor or the Purchaser at common law or under anystatute <strong>in</strong> respect of accidents to persons who shall be employed by the contractor<strong>in</strong> or about the site <strong>for</strong> the purpose of carry<strong>in</strong>g out the works on the site. TheContractor shall also take out and keep <strong>in</strong> <strong>for</strong>ce a policy or policies of Insuranceaga<strong>in</strong>st all recognized risks to their offices and depots. Such <strong>in</strong>surance shall <strong>in</strong> allrespects be to the approval of the Purchaser and if he so requires <strong>in</strong> his name.46.2 INSURANCE OF MATERIALS & INSTALLATIONSThe Contractor shall take out and keep <strong>in</strong> <strong>for</strong>ce a policy or policies of Insurance <strong>for</strong>all materials <strong>in</strong>clud<strong>in</strong>g Railway supply materials equipment irrespective ofwhether used up <strong>in</strong> the portion of work already done or kept <strong>for</strong> the use <strong>in</strong> thebalance portion of the work until such works are provisionally handed over tothe Railways. For this purpose the works are deemed to have been provisionallyhanded over when Provisional Acceptance certificate is issued <strong>for</strong> the Sub-sectionas per Para 27 of SCC.46.3 The Contractor shall not be liable <strong>for</strong> losses/damages to the materials either usedup <strong>in</strong> the portion of work done or his material kept <strong>for</strong> use at site, <strong>in</strong> consequenceof mut<strong>in</strong>y, or other similar causes over which the Contractor has no control andSignature of contractor Page 77 of 111 Dy CSTE /CTC/CNB


which cannot be <strong>in</strong>sured. Such losses or damages shall be the liability of thePurchaser and if required by the Purchaser, be made good by the contractor, at thecost of the Purchaser.46.4 The Contractor should, however, <strong>in</strong>sure the stores brought to site, aga<strong>in</strong>st risks <strong>in</strong>consequence of war and <strong>in</strong>vasion, as required under the Emergency Risk (Goods)Insurance Act <strong>in</strong> <strong>for</strong>ce from time to time.46.5 It may be noted that the beneficiary of the <strong>in</strong>surance policy should be Railways orthe policies should be pledged <strong>in</strong> favour of Railway. The contractor shall keep thepolicy/policies current till the <strong>in</strong>stallations are provisionally handed over to thePurchaser. It may also be noted that <strong>in</strong> the event of contractor's failure to keepthe policy current and alive, renewal of the policy will be done by the purchaser <strong>for</strong>which the cost of the premium plus 20% of premium shall be recovered fromthe contractor.46.6 For purpose of enabl<strong>in</strong>g the contractor to take the <strong>in</strong>surance cover <strong>in</strong> connectionwith this contract, the purchaser's eng<strong>in</strong>eer will advise the approximate price ofall the Railway supply materials to the contractor.46.7 The Contractor shall take out all Insurance covers <strong>in</strong> connection with this contractwith any Government of India Undertak<strong>in</strong>g Insurance Company only.47. FORCE MAJEURE CLAUSEIf at any time, dur<strong>in</strong>g the cont<strong>in</strong>uance of this contract, the per<strong>for</strong>mance, <strong>in</strong> whole orpart, by either party, of any obligation under this contract shall be prevented ordelayed by reason of any war, hostility, act of the public enemy, CivilCommotion, Sabotage, Fires, Floods, Earth quakes, explosions, strikes,epidemics, quarant<strong>in</strong>e, restrictions lockouts, any statute, statutory rules,regulations, order of requisitions issued by any Government Department orCompetent Authority or acts of God (here-<strong>in</strong> after referred to as event) thenprovided notice of the happen<strong>in</strong>g of any such, event is given by either party tothe other with<strong>in</strong> twenty one days from the date of occurrence thereof neither partyshall by reason of such event be entitled to term<strong>in</strong>ate this Contract nor shalleither party have any claim <strong>for</strong> damage aga<strong>in</strong>st the other <strong>in</strong> respect of such nonper<strong>for</strong>manceor delay <strong>in</strong> per<strong>for</strong>mance, and the obligations under the Contractshall be resumed as soon as practicable after such event has come to an end orceased to exist, provided further that if the per<strong>for</strong>mance <strong>in</strong> whole or part ofany obligation under this contract is prevented or delayed by reason of anysuch event beyond a period as mutually agreed to by the Railways and theContractor after any event or 60 days <strong>in</strong> the absence of such an agreementwhichever is more, either party may at its option term<strong>in</strong>ate the Contractprovided also that if the contract is so term<strong>in</strong>ated under this clause the Railwaysmay at the time of such term<strong>in</strong>ation take over from the Contractor at prices asprovided <strong>for</strong> <strong>in</strong> the contract, all works executed or works under execution.Signature of contractor Page 78 of 111 Dy CSTE /CTC/CNB


48. SETTLEMENT OF DISPUTE AND ARBITRATION48.1 MATTERS FINALLY DETERMINED BY THE RAILWAYAll disputes or differences of any k<strong>in</strong>d whatsoever aris<strong>in</strong>g out of or <strong>in</strong> connectionwith the contract, whether dur<strong>in</strong>g the progress of the work or after its completionand whether be<strong>for</strong>e or after the determ<strong>in</strong>ation of the contract shall be referredby the contractor to the Railway and the Railway shall with<strong>in</strong> 120 days afterreceipt of the contractor's representation make and notify decisions on all mattersreferred to by the contractor <strong>in</strong> writ<strong>in</strong>g provided that matters <strong>for</strong> which provisionhas been made <strong>in</strong> clauses 8(a), 18, 22(5), 39, 43(2), 45(a) 55, 55-A(5), 57, 57A,61(1), 61(2) and 62(i)(b) of General Conditions of Contract or <strong>in</strong> any clause of theSpecial Conditions of the Contract shall be deemed as 'excepted matters' anddecision of the Railway authority, thereon shall be f<strong>in</strong>al and b<strong>in</strong>d<strong>in</strong>g on thecontractor provided further that 'excepted matters' shall stand specifically excludedfrom the purview of the arbitration clause and not be referred to arbitration.48.2 DEMANDS FOR ARBITRATION(i)(ii)In the event of any dispute or difference between the parties hereto as to theconstruction or operation of this contract, or the respective rights and liabilitiesof the parties on any matter <strong>in</strong> question, dispute or difference on any account or asto the withhold<strong>in</strong>g by the Railway of any certificate to which the contractor mayclaim to be entitled to, or if the Railway fails to make a decision with<strong>in</strong> 120 days,then and <strong>in</strong> any such case, but except <strong>in</strong> any of the 'excepted matters' referred to<strong>in</strong> clause 49.1 of these conditions, the contractor, after 120 days but with<strong>in</strong> 180days of his present<strong>in</strong>g his f<strong>in</strong>al claim on disputed matters shall demand <strong>in</strong> writ<strong>in</strong>gthat the dispute or difference be referred to Arbitration.The demand <strong>for</strong> arbitration shall specify the matters which are <strong>in</strong> question orsubject of the dispute or difference as also the amounts of claim item-wise.Only such dispute(s) or difference(s) <strong>in</strong> respect of which the demand has beenmade, together with counter claims or set off shall be referred to arbitration andother matters shall not be <strong>in</strong>cluded <strong>in</strong> the reference.(a) The Arbitration proceed<strong>in</strong>gs shall be assumed to have commenced from theday, a written and valid demand <strong>for</strong> arbitration is received by the Railway.(b)(c)The claimant shall submit his claim stat<strong>in</strong>g the facts support<strong>in</strong>g the claims alongwith all relevant documents and the relief or remedy sought aga<strong>in</strong>st each claimwith<strong>in</strong> a period of 30 days from the date of appo<strong>in</strong>tment of the Arbitral Tribunal.The Railway shall submit its defense statement and counter claims, if any with<strong>in</strong>a period of 60 days of receipt of copy of claims from Tribunal thereafter, unlessotherwise extension has been granted by Tribunal.Signature of contractor Page 79 of 111 Dy CSTE /CTC/CNB


(d) No new claim shall be added dur<strong>in</strong>g proceed<strong>in</strong>gs by either party. However party mayamend or supplement the orig<strong>in</strong>al claim or defense thereof dur<strong>in</strong>g the courseof arbitration proceed<strong>in</strong>gs subject to acceptance by Tribunal hav<strong>in</strong>g due regard tothe delay <strong>in</strong> mak<strong>in</strong>g it.(e)If the contractor(s) does/do not prefer his/their specific and f<strong>in</strong>al claims <strong>in</strong>writ<strong>in</strong>g, with<strong>in</strong> a period of 90 days of receiv<strong>in</strong>g the <strong>in</strong>timation from the Railwaysthat the f<strong>in</strong>al bill is ready <strong>for</strong> payment, he/they will be deemed to have waivedhis/their claim(s) and the Railway shall be discharged and released of allliabilities under the contract <strong>in</strong> respect of these claims.48.3 OBLIGATIONS DURING PENDENCY OF ARBITRATIONWork under the contract shall, unless otherwise directed by the Eng<strong>in</strong>eer, cont<strong>in</strong>uedur<strong>in</strong>g the arbitration proceed<strong>in</strong>gs, and no payment due or payable by theRailway shall be withheld on account of such proceed<strong>in</strong>gs, provided, however, itshall be open <strong>for</strong> Arbitral Tribunal to consider and decide whether or not suchwork should cont<strong>in</strong>ue dur<strong>in</strong>g arbitration proceed<strong>in</strong>gs.48.3(a)(i) In cases where the total value of all claims <strong>in</strong> question added together doesnot exceed Rs.10,00,000/- (Rupees Ten Lakhs only), the Arbitral Tribunalconsist of a sole arbitrator who shall be either the General Manager or a gazettedofficer of Rail not below the grade of JA Grade nom<strong>in</strong>ated by the GeneralManager <strong>in</strong> that behalf. The sole arbitrator shall be appo<strong>in</strong>ted with<strong>in</strong> 60 days fromthe day when a written and valid demand <strong>for</strong> arbitration is received by Railway.48.3(a)(ii) In cases not covered by clause 48.3(a)(i), the Arbitral Tribunal shallconsist of a panel of three Gazetted Railway Officers not below JA Grade, as thearbitrators. For this purpose, the Railway will send a panel of more than 3 namesof Gazetted Railway Officers of one or more departments, of the Railway to thecontractor who will be asked to suggest to General Manager upto 2 names out ofthe panel <strong>for</strong> appo<strong>in</strong>tments as contractor's nom<strong>in</strong>ee. The General Manager shallappo<strong>in</strong>t at least one out of them as the contractor's nom<strong>in</strong>ee and will, alsosimultaneously appo<strong>in</strong>t the balance number of arbitrators either from the panel orfrom outside the panel, duly <strong>in</strong>dicat<strong>in</strong>g the 'Presid<strong>in</strong>g arbitrator from amongstthe 3 arbitrators so appo<strong>in</strong>ted. While nom<strong>in</strong>at<strong>in</strong>g the arbitrators it will benecessary to ensure that one of them is from the Accounts department. An officerof Selection Grade of the Accounts department shall be considered of equalstatus to the officers <strong>in</strong> SA grade of other departments of the Railways <strong>for</strong> thepurpose of appo<strong>in</strong>tment of arbitrators.48.3(a)(iii) If one or more of the arbitrators appo<strong>in</strong>ted as above refuses to act asarbitrator, withdraws from his office as arbitrator, or vacates his/theiroffice/offices or is/are unable or unwill<strong>in</strong>g to per<strong>for</strong>m his functions as arbitrator<strong>for</strong> any reason whatsoever or dies or <strong>in</strong> the op<strong>in</strong>ion of the General ManagerSignature of contractor Page 80 of 111 Dy CSTE /CTC/CNB


fails to act without undue delay, General Manager shall appo<strong>in</strong>t newarbitrator/arbitrators to act <strong>in</strong> his/their place <strong>in</strong> the same manner <strong>in</strong> which theearlier arbitrator/arbitrators had been appo<strong>in</strong>ted. Such re-constituted Tribunal mayat its discretion, proceed with the reference from the stage at which it was left bythe previous arbitrator(s).48.3.3(a)(iv) The arbitral Tribunal shall have power to call <strong>for</strong> such evidence by way ofaffidavits or otherwise as the arbitral Tribunal shall th<strong>in</strong>k proper, and it shall bethe duty of the parties hereto to do or cause to be done all such th<strong>in</strong>gs as may benecessary to enable the Arbitral Tribunal to make the award without any delay.48.3(a)(v) While appo<strong>in</strong>t<strong>in</strong>g arbitrator(s) under Sub-clause (i), (ii) and (iii) above, duecare shall be taken that he/they is/are not the one/those who had an opportunity todeal with the matters to which the contract relates or who <strong>in</strong> the course ofhis/their duties as Railway servant(s) expressed views on all or any of the mattersunder dispute or differences. The proceed<strong>in</strong>gs of the Arbitral Tribunal or the awardmade by such Tribunal will, however, not be <strong>in</strong>valid merely <strong>for</strong> the reason that oneor more arbitrator had, <strong>in</strong> the course of his service, opportunity to deal with thematters to which the contract relates or who <strong>in</strong> the course of his/their dutiesexpressed views on all or any of the matters under dispute.48.3(b)(i) The arbitral award shall state <strong>in</strong> item-wise, the sum and reasons upon which itis based.48.3(b)(ii) A party may apply <strong>for</strong> corrections of any computational errors, anytypographical or clerical errors or any other error of similar nature occurr<strong>in</strong>g <strong>in</strong>the award and <strong>in</strong>terpretation of a specific po<strong>in</strong>t of award to tribunal with<strong>in</strong> 30 daysof receipt of the award.48.3(b)(iii) A party may apply to tribunal with<strong>in</strong> 30 days of receipt of award to makeon additional award as to claims presented <strong>in</strong> the arbitral proceed<strong>in</strong>gs butomitted from the arbitral award.48.4 In case of the Tribunal, compris<strong>in</strong>g of three Members, any rul<strong>in</strong>g or award shall bemade by a majority of Members of Tribunal. In the absence of such a majority theviews of the Presid<strong>in</strong>g Arbitrator shall prevail.48.5 Where the arbitral award is <strong>for</strong> the payment of money, no <strong>in</strong>terest shall be payableon whole or any part of the money <strong>for</strong> any period till the date on which the award <strong>in</strong>made.48.6 The cost of arbitration shall be borne by the respective parties. The cost shall<strong>in</strong>ter-alia <strong>in</strong>clude fees of the arbitrator(s) as per the rates fixed by the RailwayAdm<strong>in</strong>istration from time to time.Signature of contractor Page 81 of 111 Dy CSTE /CTC/CNB


48.7 Subject to the provisions of the a<strong>for</strong>esaid Arbitration and conciliation Act 1996and the rules there under and any statutory modification thereof shall apply to thearbitration proceed<strong>in</strong>gs under this clause.**********Signature of contractor Page 82 of 111 Dy CSTE /CTC/CNB


Section – IIChapter – 3Tender FormsSignature of contractor Page 83 of 111 Dy CSTE /CTC/CNB


FORM No. 1 : Offer letter.FORM No. 2 : Not Applicable.FORM No. 3 : Contract Agreement.FORM No. 4 : Bank Guarantee <strong>for</strong> Per<strong>for</strong>mance GuaranteeFORM No. 5 : Statement of Deviations.FORM No. 6 : Stand<strong>in</strong>g Indemnity Bond <strong>for</strong> on account Paymentsand Stores supplied by Railway.FORM No. 7 : System Per<strong>for</strong>mance Guarantee (Not applicable)FORM No. 8 : Not Applicable.FORM No. 9 : Jo<strong>in</strong>t Inspection of Cable Trench & ProtectiveWorks (Not applicable).FORM No. 10 : Acknowledgement <strong>for</strong> receiv<strong>in</strong>g material and Cablefrom Railways.FORM No. 11 : Extension of period of completion on account ofcontractor.FORM No. 12 : Extension of period of completion of work.FORM No. 13 : Qualification Experience.FORM No. 14 : Store Receipt Certificate.FORM No. 15 : Electronic Clear<strong>in</strong>g Service.Signature of contractor Page 84 of 111 Dy CSTE /CTC/CNB


OFFER LETTERToThe President of India,Act<strong>in</strong>g through the Deputy CSTE/CTC/CNB,IRPMU, NC Railway,KanpurFORM-1Para-6.8 (a), Section II Chapter 1Name of Work: ‘Outdoor works <strong>in</strong> connection with the provision of Multi section digitalaxle counter <strong>for</strong> dual detection <strong>in</strong> 15 block section of PNK-ALJN section of ALDdivision. (JJK-KNS,KNS-PHD,PHD-PTX,PTX-ULD,ULD-SHW,SHW-BNT,BNT-EKL,EKL-ETW,TDL-MTI,JLS-PRA,PRA-HRS,HRS-SNS,SNS-MXK,MXK-DAQ,DAQ-ALJN ).’Sir, I/We …………………………… have read various conditions to tender heretoattached and hereby agree to abide by the said conditions. I/We also agree to keep thisTender open <strong>for</strong> acceptance <strong>for</strong> a period of 90 days from the date fixed <strong>for</strong> open<strong>in</strong>g thesame and <strong>in</strong> default thereof, I / We will be liable <strong>for</strong> <strong>for</strong>feiture of my/our SecurityDeposit. I / We offer to do this work as detailed below at the rates quoted below:S.NoScheduleApproximateCost ofScheduleRates quoted by the tenderer (% Above/ Below/AtPar) (Both <strong>in</strong> figures and Words)In FiguresIn WordsABOVE/BELOWTOTALI/We hereby b<strong>in</strong>d myself/ourselves to complete the work with<strong>in</strong> the time limits specified<strong>in</strong> the conditions of Tender. I/We also hereby agree to abide by the General conditions ofContract with latest amendments and special conditions of Contract and to carry out theworks accord<strong>in</strong>g to the specifications of materials and works laid down by the Railway<strong>for</strong> present contract.I/We declare that I/We have gone through the Rules, Regulations of. Tender and ContractGeneral Conditions, Special conditions, Technical specifications and other particularsembodied <strong>in</strong> Volume-2 and have fully understood and agree to abide by them.Signature of contractor Page 85 of 111 Dy CSTE /CTC/CNB


Until a <strong>for</strong>mal agreement is prepared and executed, acceptance of this Tender shallconstitute, subject to modifications as may be mutually agreed to, a b<strong>in</strong>d<strong>in</strong>g contract,between us and the President of India act<strong>in</strong>g through the Chief Adm<strong>in</strong>istrative Officer,IRPMU, North Central Railway, New Delhi or the authority as <strong>in</strong>dicated <strong>in</strong> the letter ofacceptance of my/our offer <strong>for</strong> this work.SIGNATURE OF <strong>TENDER</strong>ER [S](Please affix your Seal also, if any)Contractor's Address:Date:Signature of contractor Page 86 of 111 Dy CSTE /CTC/CNB


FORM - 3Para-2/ Section II Chapter 2AGREEMENTAN AGREEMENT made this ........................................................... day of....................................... Two Thousand .......................... between the President of India,act<strong>in</strong>g <strong>in</strong> the premises through the Chief Adm<strong>in</strong>istrative Officer/IRPMU, North CentralRailway or his successor ......................................... of the M<strong>in</strong>istry of Railways, RailwayBoard (here<strong>in</strong> after referred to as “the Railway”) of one part and Messers.................................................. (here<strong>in</strong> after referred to as “Contractor”) of the other part,a .......................... Firm (Status of the firm) be<strong>in</strong>g represented by .....................................(Name & Designation of the proprietor <strong>in</strong> case of sole proprietorship bus<strong>in</strong>ess or all thenames and particulars <strong>in</strong> case of partnership firm etc.)Whereas <strong>in</strong> response to a call <strong>for</strong> Tenders “Outdoor works <strong>in</strong> connection with theprovision of Multi section digital axle counter <strong>for</strong> dual detection <strong>in</strong> 15 block section ofPNK-ALJN section of ALD division. (JJK-KNS,KNS-PHD,PHD-PTX,PTX-ULD,ULD-SHW,SHW-BNT,BNT-EKL,EKL-ETW,TDL-MTI,JLS-PRA,PRA-HRS,HRS-SNS,SNS-MXK,MXK-DAQ,DAQ-ALJN )” as per tender papers at Annexure-A hereto theContractor has submitted a tender as per Annexure-B hereto and whereas the said Tenderof the Contractor has been accepted <strong>for</strong> as per copy of Letter of AcceptanceNo..................................... dated ................... complete with enclosures at the acceptedrates and agreed deviations from Tender Papers ..................................................... as perAnnexure-C hereto and at an estimated contract value of Rs...................... (Rupees............................................................ only).In accordance with ‘Clause 3.2 of Special Conditions of Contract’, B. G. no……………………… <strong>for</strong> Rs………………….. valid up to …………….. issued by…………………………….(bank) has been submitted <strong>in</strong> favour of………………………...Now this agreement witnesses that <strong>in</strong> consideration of the premises and thepayment to be made by the purchaser to the contractor provided <strong>for</strong> here<strong>in</strong> below theContractor shall supply all equipment and materials and execute and per<strong>for</strong>m all works<strong>for</strong> which the said Tender of the Contractor has been accepted strictly accord<strong>in</strong>g to thevarious provisions <strong>in</strong> Annexure-B and C hereto and upon such supply, execute andper<strong>for</strong>m to the satisfaction of the purchaser and the purchaser shall pay to the Contractorat the rates accepted as per the said Annexure-C and <strong>in</strong> terms of provisions there<strong>in</strong>. Incase if the Contractor is not a company <strong>in</strong>corporated under the Companies Act, 1956, theexpression “Contractor” shall unless otherwise excluded by or repugnant to the subject orcontext mean and <strong>in</strong>clude each of the successors- <strong>in</strong>- <strong>in</strong>terest, agents, nom<strong>in</strong>ees, servants,beneficiaries etc. If it is a Sole Proprietorship bus<strong>in</strong>ess, <strong>in</strong> addition to this, suchSignature of contractor Page 87 of 111 Dy CSTE /CTC/CNB


expression Contractor will also <strong>in</strong>clude, each of his heirs, executors, and legalrepresentatives.In the witness where of the parties have hereunto set and subscribed their respectivehands and/or seals day and year respectively mentioned aga<strong>in</strong>st their respective signature.Signed and delivered at .................................................................... by Shri..................................................... <strong>for</strong> and on behalf of Messers....................................................................... the Contractor with<strong>in</strong> named <strong>in</strong> the presenceof :-(Signed)M/s ……(Signed)(Dy CSTE/IRPMU/CNBWitness:1. Signature :Date :Name <strong>in</strong> block Capitals :Address :2. Signature :Date :Name <strong>in</strong> block Capitals:Address:Annexure AAnnexure -BAnnexure -C: Bank Guarantee: Firm’s Tender Papers: Letter of Acceptance of TenderComplete with enclosures._________________________(Signature)Dated:Signature of contractor Page 88 of 111 Dy CSTE /CTC/CNB


FORM-4Para 3.2/Section II Chapter 2FORMAT OF BANK GURANTEE <strong>for</strong> PERFORMANCE GUARANTEE(On Stamp Paper of Appropriate value)(To be used by approved Scheduled Banks)1. In consideration of the President of India (here<strong>in</strong>after called “the Government”)hav<strong>in</strong>g agreed to exempt .................................................... (here<strong>in</strong>after called “Thesaid contractor(s)”) from the demand, under the terms and conditions of anagreement No........................................... dated .................... made between.............................. and .................... <strong>for</strong> .............................................................(here<strong>in</strong> after called “the said agreement”) of Security Deposit <strong>for</strong> the duefulfillment by the said contractor(s) of the terms and conditions conta<strong>in</strong>ed <strong>in</strong> thesaid Agreement, or production of a Bank Guarantee <strong>for</strong> Rs............. (Rupees....................................... only), we...............................................................(<strong>in</strong>dicate the name of Bank) (here<strong>in</strong>after referred to as‘the Bank”) at the request of ................................. Contractor(s) do herebyundertake to pay to the Government an amount not exceed<strong>in</strong>g Rs............................aga<strong>in</strong>st any loss or damage caused to or suffered or would be caused to orsuffered by the Government by reason of any breach by the said Contractor(s) ofany of the terms or conditions conta<strong>in</strong>ed <strong>in</strong> the said Agreement.2. We ...................................................................... Bank do hereby undertake to paythe amounts due and payable under this Guarantee without any demur, merely ondemand from the Government stat<strong>in</strong>g the amount is claimed is due by way of lossor damage caused to or would be caused to or suffered by the Government byreason of breach by the said Contractor(s) of any of terms or conditions conta<strong>in</strong>ed<strong>in</strong> the said Agreement or by reason of the Contractor(s) failure to per<strong>for</strong>m the saidAgreement. Any such demand made on the Bank shall be conclusive as regardsthe amount due and payable by the Bank under this guarantee. However, ourliability under this guarantee shall be restricted to an amount not exceed<strong>in</strong>gRs...............................3. We .................................................................... bank undertake to pay to theGovernment any money so demanded notwithstand<strong>in</strong>g any dispute or disputesraised by the Contractor(s)/Supplier(s) <strong>in</strong> any suit or proceed<strong>in</strong>gs pend<strong>in</strong>g be<strong>for</strong>eany court or Tribunal relat<strong>in</strong>g thereto our liability under this present be<strong>in</strong>gabsolute and unequivocal.The payment so made by us under this Bond shall be avalid discharge of our liability <strong>for</strong> payment there under and the Contractor(s)/Supplier(s) shall have no claim aga<strong>in</strong>st us <strong>for</strong> mak<strong>in</strong>g such payment.Signature of contractor Page 89 of 111 Dy CSTE /CTC/CNB


4. We ........................................................... Bank further agree that the Guaranteehere<strong>in</strong> conta<strong>in</strong>ed shall rema<strong>in</strong> <strong>in</strong> full <strong>for</strong>ce and effect dur<strong>in</strong>g the period that wouldbe taken <strong>for</strong> the per<strong>for</strong>mance of the said Agreement and that it shall cont<strong>in</strong>ue to been<strong>for</strong>ceable till all the dues of the Government under or by virtue of the saidagreement have been fully paid and its claims satisfied or discharged ortill.................... office/ department) M<strong>in</strong>istry of ...................... certifies that theterms and conditions of the said agreement have been fully and properly carriedout by the said contractor(s) and accord<strong>in</strong>gly discharges this Guarantee. Unless ademand or claim under the Guarantee is made on us <strong>in</strong> writ<strong>in</strong>g on or be<strong>for</strong>e the................................. we shall be discharged from all liability under this Guaranteethereafter.5. We ................................................................................ further agree with(Indicate the name of bank)the Government that the Government shall have the fullest liberty without ourconsent without affect<strong>in</strong>g <strong>in</strong> any manner our obligations hereunder to vary any ofthe terms and conditions of the Agreement or to extend time of per<strong>for</strong>mance bythe said Contractor(s) from time to time or to postpone <strong>for</strong> any time or from timeto time any of the powers exercisable by the Government aga<strong>in</strong>st the saidContractor(s) and to <strong>for</strong>ebear or en<strong>for</strong>ce any other terms and conditions relat<strong>in</strong>g tothe said Agreement and we shall not be relieved from our liability by reason ofany such variation, or extension to the said Contractor(s) or <strong>for</strong> any <strong>for</strong>bearance,act or omission on the part of Government or any <strong>in</strong>dulgence by the Governmentto the said Contractor(s) or by any such matter or th<strong>in</strong>g whatsoever which underthe law relat<strong>in</strong>g to sureties would but <strong>for</strong> this provision, have no effect of soreliev<strong>in</strong>g us.6. This Guarantee will not be discharged due to the change <strong>in</strong> the Constitution of theBank or the Contractor(s)/Supplier(s).7. We ...................................................... lastly undertake not to revoke this(Indicate the name of bank)Guarantee dur<strong>in</strong>g its currency except with the previous consent of theGovernment <strong>in</strong> writ<strong>in</strong>g.Dated the.......................... day of ..................20<strong>for</strong>......................................................................................(Indicate the name of the bank)Signature of contractor Page 90 of 111 Dy CSTE /CTC/CNB


STATEMENT OF DEVIATIONSPROFORMA FOR STATEMENT OF DEVIATIONSFORM-5Para 4/ Section II Chapter 21. The follow<strong>in</strong>g are the particulars of deviations from requirement of the<strong>in</strong>structions to Tenderers, General Conditions of Contract.1.1 Instructions to Tenderers & Condition of Tender<strong>in</strong>gCLAUSE DEVIATION REMARKS1.2 General Conditions of Contract(INCLUDING JUSTIFICATION)CLAUSE DEVIATION REMARKS1.3 Special Conditions of Contract(INCLUDING JUSTIFICATIONCLAUSE DEVIATION REMARKS(INCLUDING JUSTIFICATION)Note: Where there is no deviation, the statement should be returned duly signed withan endorsement <strong>in</strong>dicat<strong>in</strong>g no deviations.Signature of contractor Page 91 of 111 Dy CSTE /CTC/CNB


STANDING INDEMNITY BONDFORM-6Para-8.2/Section II Chapter 2(FOR ON ACCOUNT PAYMENTS & STORES SUPPLIED BY RAILWAYS)(On Stamp paper of Requisite Value)We, M/s............................................................. hereby undertake that we hold at ourstores Depot/s at ................................................ <strong>for</strong> and on behalf of the President of India<strong>in</strong> the premises through the CAO/IRPMU or his successor, North Central Railway (here<strong>in</strong>after referred to as “the Purchaser”) all materials <strong>for</strong> which “On Account” payments havebeen made to us aga<strong>in</strong>st the contract <strong>for</strong> ““Outdoor works <strong>in</strong> connection with theprovision of Multi section digital axle counter <strong>for</strong> dual detection <strong>in</strong> 15 block section ofPNK-ALJN section of ALD division. (JJK-KNS,KNS-PHD,PHD-PTX,PTX-ULD,ULD-SHW,SHW-BNT,BNT-EKL,EKL-ETW,TDL-MTI,JLS-PRA,PRA-HRS,HRS-SNS,SNS-MXK,MXK-DAQ,DAQ-ALJN )” vide letter of Acceptance of TenderNo....................................... dated ................ and the materials handed over to us by thepurchaser <strong>for</strong> the purpose of execution of the said Contract, until such time the materialsare duly erected or otherwise handed over to him.We shall be entirely responsible <strong>for</strong> the site custody and protection of the saidmaterials aga<strong>in</strong>st all risk till they are duly delivered as erected equipment to the purchaseror as he may direct otherwise and shall <strong>in</strong>demnify the Purchaser aga<strong>in</strong>st any loss, damageor deterioration what so ever <strong>in</strong> respect of the said materials while <strong>in</strong> our possession andaga<strong>in</strong>st disposal of surplus materials. The said materials shall at all times be open to<strong>in</strong>spection by any Officer authorized by the Chief Adm<strong>in</strong>istrative Officer/IRPMU, N CRailway, Shivaji Bridge, New Delhi.Should any loss, damage or deterioration of materials occur or surplus materialsdisposed off and refund becomes due, the purchaser shall be entitled to recover from usthe full cost as per prices <strong>in</strong>cluded <strong>in</strong> the Contract (as applicable) and alsocompensation <strong>for</strong> such loss or damage if any along withthe amount to be refunded without prejudice to any other remedies available to him bydeduction from any sum due or any sum which at any time hereafter becomes due to usunder the said or any other Contract.Signature of Witness:Name of Witness <strong>in</strong> block letters:Address:Dated this ...................... day of ........................, 20…..<strong>for</strong> and on behalf ofMessers ........................................ (Contractor)Signature of contractor Page 92 of 111 Dy CSTE /CTC/CNB


FORM-7Para-22.2/Section II Chapter 1SYSTEM PERFORMANCE GUARANTEEPROFORMA FOR THE SYSTEM PERFORMANCE GUARANTEEToThe President of India,I/We........................................................................................ hereby guarantee thatthe design on the basis of which we have submitted our TenderNo................................................. has been carefully made to con<strong>for</strong>m to the endobjectives <strong>in</strong> the tender documents and to technical specification there<strong>in</strong>. We furtherguarantee that <strong>in</strong> the event of the per<strong>for</strong>mance of the system, when <strong>in</strong>stalled, notcomply<strong>in</strong>g with the end objectives or with the specifications conta<strong>in</strong>ed <strong>in</strong> the tenderdocuments, we shall provide further <strong>in</strong>puts to enable the Railways to realise the endobjectives conta<strong>in</strong>ed <strong>in</strong> these documents without any additional payment <strong>for</strong> anyadditional equipment which may be required <strong>in</strong> this regard. We further guarantee that allthe expenses <strong>in</strong>clud<strong>in</strong>g the expenses <strong>in</strong>curred <strong>in</strong> India <strong>for</strong> provid<strong>in</strong>g the additional <strong>in</strong>putsunder the System guarantee will be borne by us. We further guarantee that theseadditional <strong>in</strong>puts will be provided by us to make the system workable with<strong>in</strong> 8 monthsfrom the date on which this guarantee is <strong>in</strong>voked by the Purchaser.(Signature of firm’s authorised officer)Seal:Signature of Witness:1..................................................2.................................................Signature of contractor Page 93 of 111 Dy CSTE /CTC/CNB


ACKNOWLEDGEMENT(FOR RECEIVING MATERIALS FROM RAILWAY)Station:Date:FORM-10Para-8.3/Section II Chapter 2Sub: - Receipt of Materials from RailwayIt is hereby acknowledged that the follow<strong>in</strong>g material as detailed have beenreceived <strong>in</strong> full and good condition by me on .................................................................................................. at ........................ <strong>for</strong> the work com<strong>in</strong>g under the AgreementNo......................................................dated ..........................................................................----------------------------------------------------------------------------------------Sl.No. Description of Material Quantity Remarks if any--------------------------------------------------------------------------------------------------------------------------------------------------------------------------------Witnessed by: --------------------------------- ------------------------------------(Signature of Purchaser’s(Signature of Contractor orRepresentative with Designation) Contractor’s Representative)Signature of contractor Page 94 of 111 Dy CSTE /CTC/CNB


FORM-11Para-35/Section II Chapter 2EXTENSION OF PERIOD OF COMPLETION OF WORKON CONTRACTOR’S ACCOUNT(Regd. With A/D)No. Date :To..........................................................................................Sub : (i) ................................................. (Name of Work)(ii) Acceptance Letter No. ....................................................(iii) Undertak<strong>in</strong>g /Agreement No. .......................................Dear Sir,Ref : ......................... (Quote specific application of the Contractor <strong>for</strong> extensionto date, if received).The stipulated date <strong>for</strong> completion of the work mentioned above is/was ................ However, the work is/was not completed on this date.Expect<strong>in</strong>g that you may be able to complete the work if some time is given and <strong>in</strong>consideration of your Letter No.............................., the General Manager (or hissuccessor) on behalf of the president of India, although not bound to do so, herebyextends the time <strong>for</strong> completion from ............. to ..............Please note that liquidated damages @1/2% per week or part thereof of the entirecontract value will be recovered <strong>for</strong> delay <strong>in</strong> the completion of the work after the expiryof (1) ....................... from you as mentioned <strong>in</strong> para 35 of the Special Conditions ofContract <strong>for</strong> the extended period.The above extension of the completion date will also be subject to the furthercondition that no <strong>in</strong>crease <strong>in</strong> rates on any account will be payable to you.Please note that <strong>in</strong> the event of decl<strong>in</strong><strong>in</strong>g to accept the extension on the above saidconditions or <strong>in</strong> the event of your failure after accept<strong>in</strong>g or act<strong>in</strong>g up to this extension tocomplete the work by (2)....................... (here mention the extended date), further actionwill be taken <strong>in</strong> terms of relevant para of Conditions of Contract.Yours’ faithfully,<strong>for</strong> & on behalf of President of India.Note:-1. Give here the stipulated date <strong>for</strong> completion without any penalty fixed earlier.2. Here mention the extended date.Signature of contractor Page 95 of 111 Dy CSTE /CTC/CNB


FORM-12Para-36/Section II Chapter 2EXTENSION OF PERIOD OF COMPLETION OF WORKNo. Date :To......................................................................................................Dear Sirs,Sub : (i) ............................................ (Name of work)(ii) Acceptance Letter No.........................................(iii) Undertak<strong>in</strong>g/Agreement No...............................Ref : .......................... (quote specific application of thecontractor <strong>for</strong> extension to the date, if received) .The stipulated date <strong>for</strong> completion of subject work under the above contract was............................ In consideration of the Contractor’s Letter No..............................., TheCAO/IRPMU (or his successor) behalf of the President of India, is pleased to grantextension of the time <strong>for</strong> completion of works without liquidated damages under para 36of Chapter II , Section II of the contract as mentioned below :“...................................................................................”It may be noted that unless repugnant to the context, all the terms andconditions of the Contract will rema<strong>in</strong> unaltered dur<strong>in</strong>g the extended period from...................... to ...................... also, and further no <strong>in</strong>creased additional rates and claimsof recoveries which have not been already envisaged <strong>in</strong> terms of the conditions of theContract will be leviable either by you or by the purchaser <strong>in</strong> respect of this extendedperiod.Yours faithfully,( )<strong>for</strong> and on behalf of President of IndiaSignature of contractor Page 96 of 111 Dy CSTE /CTC/CNB


FORM-13QUALIFICATION EXPERIENCEII.In support of Qualification criteriad) List of Works CompletedDescriptionof WorkOrganization<strong>for</strong> whomexecutedApprox.value ofcontract atthe time ofawardDate ofawardDate ofscheduledcompletionof workStartDate of actualCompletionF<strong>in</strong>al valueof contractb) List of Works <strong>in</strong> HandDescription ofworkContract ValueApprox. value ofbalance work yet to bedoneDate of AwardSignature of contractor Page 97 of 111 Dy CSTE /CTC/CNB


FORM-14RECEIPT CERTIFICATE (FOR SUPPLY ONLY)From: Sr. Section Eng<strong>in</strong>eer/Signal/IRPMU/TundlaNo.Date:1 Contract No2 Name of Work3 Item No. As <strong>in</strong> Rate Schedule4 Description of Item.5 Material <strong>in</strong>spected by6 Dispatch particular & date7 Qty as per dispatch particular8 Qty received9 Qty short received10 Condition of Stores Received11 Name of Firm & Address12 Place of receipt13 Date of receipt14 Ledger No.15 Name & designation of Stores Incharge--------------------------------------Signature of Stores-<strong>in</strong>-ChargeSignature of contractor Page 98 of 111 Dy CSTE /CTC/CNB


FORM-15ELECTRONIC CLEARING SERVICE (CREDIT CLEARING)(MODEL MANDATE FORM)(INVESTOR/CUSTOMER’S OPTION TO RECEIVE PAYMENTS THROUGHCREDIT CLEARLING MECHANISM)(Scheme name and the periodicity of payment)1. INVESTOR/CUSTOMER’S NAME2. PARTICULARS OF BANK ACCOUNTA. BANK NAMEB. BRANCH NAMEADDRESSTELEHPONEC. 9-DIGIT CODE NUMBER OFTHE BANK & BRANCH(Appear<strong>in</strong>g on the MICR cheque issued by the bank.)D. ACCOUNT TYPE(S.B. Account/Current Account orCash Credit with Code 10/11/13)E. LEDGER NO./LEDGER FOLIO NOF. ACCOUNT NUMBER( As appear<strong>in</strong>g on the Cheque Book)(In lieu of the bank certificate to be obta<strong>in</strong>ed as under, please attach a blank cancelledcheque, or photocopy of a cheque or front page of your sav<strong>in</strong>gs bank passbook issued byyour bank <strong>for</strong> verification of the above particulars).3. DATE OF EFFECT.I hereby declare that the particulars given above are correct and complete. If the transactionis delayed or not effected at all <strong>for</strong> reasons of <strong>in</strong>complete or <strong>in</strong>correct <strong>in</strong><strong>for</strong>mation, I wouldnot hold the User <strong>in</strong>stitution responsible. I have read the option <strong>in</strong>vitation letter and agree todischarge responsibility expected of me as a participant under the Scheme.Date:( )Signature of the Investor/Customer.Certified that the particulars furnished above are correct as per our records.( )Signature of the Authorized.Official from the Bank------ x------ x------ x------Signature of contractor Page 99 of 111 Dy CSTE /CTC/CNB


Section – IIIChapter – 1TechnicalSpecification andInstallation PracticesSignature of contractor Page 100 of 111 Dy CSTE /CTC/CNB


TECHNICAL SPECIFICATIONS & INSTALLATION PRACTICESThe works shall be carried out accord<strong>in</strong>g to the draw<strong>in</strong>gs approved by the Railway andshall con<strong>for</strong>m to the provisions of the ‘Signal Eng<strong>in</strong>eer<strong>in</strong>g Manual’ Schedule of“Dimension” and “Manual of Instructions <strong>for</strong> Installation of S&T equipment on 25 KV,50 Cycles, A. C. electrified sections as modified from time to time unless deviations, ifany, are specifically approved by the Eng<strong>in</strong>eer. The contractor shall be solely responsible<strong>for</strong> the proper execution of the work as per the said deviation and specifications.1). Supply of items should be with con<strong>for</strong>mity to the follow<strong>in</strong>g specifications-a) Multi section digital axle counter (MSDAC) as per specification no.RDSO/SPN/176/2005 (Ver.2) or latest amendment complete set consist<strong>in</strong>g of Evaluator,Vital relays <strong>for</strong> each track section, track site unit with detection po<strong>in</strong>t complete assembly& fix<strong>in</strong>g arrangement <strong>for</strong> each detection po<strong>in</strong>t, clamps deflectors <strong>for</strong> either side of eachdetection po<strong>in</strong>ts, monitor<strong>in</strong>g console and a reset box <strong>for</strong> resett<strong>in</strong>g each track section anddetection po<strong>in</strong>t as specified <strong>in</strong> tender schedule.b) Evaluator /processor <strong>for</strong> multi section digital axle counter equipped <strong>for</strong> specific tracksections complete set as per RDSO Specification no. RDSO/SPN/176/2005 (Ver.2).c) Track site unit <strong>for</strong> MSDAC as per RDSO Specification no. RDSO/SPN/176/2005(Ver.2).d) Detection Po<strong>in</strong>ts /track device/ Double Rail Contact unit <strong>for</strong> Multi Section DigitalAxle counter as per RDSO Specification no. RDSO/SPN/176/2005 (Ver.2) with latestamendment or specification, detection, po<strong>in</strong>t complete assembly and fix<strong>in</strong>g arrangement.e) Track section of MSDAC con<strong>for</strong>m<strong>in</strong>g to Specification no.RDSO/SPN/176/2005(Ver.2) or latest amendment or specification.f) Deflector <strong>for</strong> detection po<strong>in</strong>t <strong>for</strong> MSDAC as per RDSO specification no.RDSO/SPN/176/2005 (Ver.2) or latest amendment or specification.g) Tool Kit and measur<strong>in</strong>g <strong>in</strong>struments <strong>for</strong> MSDAC as per RDSO Specification no.RDSO/SPN/176/2005 (Ver.2) with latest amendment or specification2 (a). Installation & commission<strong>in</strong>g of Axle detectors, field units of MSDAC.a) Axle detector shall be <strong>in</strong>stalled at locations specified by the eng<strong>in</strong>eer.b) Any work to be done on the rails, such as drill<strong>in</strong>g holes <strong>in</strong> the web of rail,shift<strong>in</strong>g of sleepers associated with any disturbance to exist<strong>in</strong>g track fitt<strong>in</strong>gs/ railsshall be done <strong>in</strong> presence of Railway only.c) Different frequency shall be used <strong>for</strong> each set of transmitter & receiver coils.d) Double walled antirodent corrugated pipe of 90 mm outer dia <strong>in</strong>ner dia 76mmhav<strong>in</strong>g non flame propagation and anti rodent properties or similer as per TECspecifications GR/DWC-34/01 IS 14930 Part-II and technical specifications alongwith socket/ coupler and T jo<strong>in</strong>ts wherever required hav<strong>in</strong>g IP-67 protection <strong>for</strong>underground power/signall<strong>in</strong>g/telecommunication cable protection.Signature of contractor Page 101 of 111 Dy CSTE /CTC/CNB


e) The trench to lay the cable connect<strong>in</strong>g axle detectors to field unit shall be onemeter deep from the rail top & 150 mm dia wide (m<strong>in</strong>) & the cable pass<strong>in</strong>gthrough the double wall ant rodent corrugated pipe should be laid <strong>in</strong> the trench.The trench should be refilled & brought back to its orig<strong>in</strong>al position, properlyrammed <strong>in</strong>clud<strong>in</strong>g restoration of ballast after lay<strong>in</strong>g the cable. Both the enddouble wall ant rodent corrugated pipe should be properly closed and sealed, oneend term<strong>in</strong>at<strong>in</strong>g <strong>in</strong> the apparatus case connect<strong>in</strong>g field unit.f) Deflector required <strong>for</strong> the protection of axle detectors shall be fabricated out of10mm thick M.S. Steel plate of suitable size so as to properly protect the axledetectors & not to <strong>in</strong>fr<strong>in</strong>ge with the schedule of dimensions shall be mounted onrail web with nuts & bolts/ clamped with the rail flange to protect axle detectorsaga<strong>in</strong>st the damage from hang<strong>in</strong>g parts of mov<strong>in</strong>g tra<strong>in</strong>. The rail deflector shouldbe mounted on both sides of the fitt<strong>in</strong>g next to the axle detectors, about approx.300 to 400 mm away.g) The field unit along with vital relay box (wherever required) shall be placed &secured through clamps, nuts & bolts on the shelf.2 (b) Tool kits <strong>for</strong> Digital Axle counter, Specification no. RDSO/SPN/176/2005(Ver.2).or latest amendment or specification consist<strong>in</strong>g of follow<strong>in</strong>g items:(a) True RMS Digital Multimeter with probe set-- 1no.(b) Extended wired socket to <strong>in</strong>terface with diagnostic plug--1 no.(c) Selector Switch on panel base-- 1 no.(d) Adjustable torque wrench with 13 mm and 19 mm <strong>in</strong>serts-- 1 set(e) 19 mm double ended spanner-- 1 no.(f) Dummy wheel-- 1 no.(g) Screw driver set with ma<strong>in</strong>s tester-- 1no. Note: All the mechanical tools should be ofgood quality like Taparia, BOSCH etc. Make3. Interconnections / wir<strong>in</strong>g3.1 Installation of control panel, cable term<strong>in</strong>ation and relay racks at the respective placesshall have to be done. Wir<strong>in</strong>g of relay racks and control panel shall be carried out asper circuit diagram approved by the Railways provid<strong>in</strong>g <strong>in</strong>terconnection arrangementsbetween the racks and control panels.3.2 Interconnection between term<strong>in</strong>al racks / boards and relay racks shall be carried outby provid<strong>in</strong>g ladder arrangements or by any other arrangements as <strong>in</strong>structed byEng<strong>in</strong>eer’s representative.3.3 The equipments are to be wired <strong>in</strong> relay room, power supply arrangement, apparatuscase, cable term<strong>in</strong>ation box, and battery box and <strong>in</strong> other locations.3.4 Cable term<strong>in</strong>ation racks should be erected <strong>in</strong> the relay room, Suitable cable ducts asrequired, shall be provided to br<strong>in</strong>g all outside cable to the term<strong>in</strong>ation rack. RCCslabs shall be manufactured at site and covered. All the cables are to be neatly fixedand term<strong>in</strong>ated <strong>in</strong> order.Signature of contractor Page 102 of 111 Dy CSTE /CTC/CNB


3.5 It shall be possible to identify wires to all term<strong>in</strong>als by means of non- metallic tag orlevel on which is stamped the designation correspond<strong>in</strong>g to that is on the circuit andwir<strong>in</strong>g plan. Contractor may adopt any other means subject to approval of theRailways. Tag shall be applied <strong>in</strong> such a manner that if a wire is removed from theterm<strong>in</strong>al, the tag will rema<strong>in</strong> on the wire.3.6 Where practicable the tags or labels shall be securely fastened adjacent to the term<strong>in</strong>alsor suitably pa<strong>in</strong>ted so that the number can be easily read.3.7 All wir<strong>in</strong>g <strong>in</strong> the cab<strong>in</strong> and location shall be term<strong>in</strong>ated on suitable term<strong>in</strong>al block/tagblocks hav<strong>in</strong>g m<strong>in</strong>imum <strong>in</strong>sulation resistance of 500 Meg. ohms at 500 V DC. Theterm<strong>in</strong>al blocks/tag blocks shall be covered with plastic cover.3.8 Contact number<strong>in</strong>g <strong>for</strong> the relays shall be made by the contractor as per the circuitdiagram approved by the railway and type of relay proposed to be used on the<strong>in</strong>stallation.3.9 No jo<strong>in</strong>ts are permitted <strong>in</strong> the connection wires.3.10 Wir<strong>in</strong>g <strong>in</strong> relays hous<strong>in</strong>g shall be uni<strong>for</strong>m <strong>for</strong> like apparatus through out the<strong>in</strong>stallation.3.11 Wir<strong>in</strong>g <strong>in</strong>side one rack <strong>for</strong> plug <strong>in</strong> Contact relays type (Metal to Carbon)Relay rack wir<strong>in</strong>g hous<strong>in</strong>g plug <strong>in</strong> type relays shall be done with PVC <strong>in</strong>sulatedunsheathed flame retard<strong>in</strong>g type s<strong>in</strong>gle core flexible wire 1100V grade hav<strong>in</strong>gl6/0.2mm t<strong>in</strong>ned flexible s<strong>in</strong>gle core annealed copper conductor and nom<strong>in</strong>al crosssectional area of 0.5 Sq. mm of common colour code to the specification IS: 76/89or latest. For wir<strong>in</strong>g these relays the above wires shall be term<strong>in</strong>ated on eyelet /lugsof standard design.3.12 Solder<strong>in</strong>g at the tag block term<strong>in</strong>als shall be made us<strong>in</strong>g good quality solder andflux. Care must be taken to prevent dropp<strong>in</strong>g of excessive solder from term<strong>in</strong>althereby caus<strong>in</strong>g failure/unwanted connection or short by fus<strong>in</strong>g of PVC <strong>in</strong>sulation <strong>in</strong>the row below it. It is advisable to raise the wires by mechanical means andtemporarily <strong>in</strong>terpos<strong>in</strong>g a wooden or plastic sheet between the adjacent rows whilesolder<strong>in</strong>g, to collect the excessive solder that may be dropp<strong>in</strong>g out.3.13 After test<strong>in</strong>g, the loose wires on the cable ladder shall be neatly bunched and lacedwith tw<strong>in</strong>e black. The contractor shall adopt suitable colour code <strong>for</strong> wir<strong>in</strong>g asrequired by the Eng<strong>in</strong>eer <strong>in</strong>-charge. Spare conductors to an extent of 10% are to beprovided on the <strong>in</strong>terconnect<strong>in</strong>g wire runs <strong>for</strong> future developments <strong>in</strong> case of multicorecable are used.3.14 After the complete test<strong>in</strong>g by the Eng<strong>in</strong>eer <strong>in</strong>-charge and be<strong>for</strong>e commission<strong>in</strong>g the<strong>in</strong>stallation, the contractor shall arrange necessary seal<strong>in</strong>g leads and wires <strong>for</strong> seal<strong>in</strong>gthe relays.3.15 The nomenclature of each relay shall be pa<strong>in</strong>ted both <strong>in</strong> front and rear side of eachrelay with contact configuration. The relay <strong>in</strong>dex sheet duly pa<strong>in</strong>ted of details ofrelay and their position <strong>in</strong> the relay rack shall be manufactured out of Decolum/Nova pan sheet and fixed <strong>in</strong> the relay room. All the relays to be plugged shall bechecked visually and defect if any, noticed shall be replaced, duly report<strong>in</strong>g theSignature of contractor Page 103 of 111 Dy CSTE /CTC/CNB


same to the Railways. As made relay rack wir<strong>in</strong>g and contact chart of all relays shallbe prepared <strong>in</strong> l<strong>in</strong>en/polyester sheets, duly signed and handed over to Railways <strong>for</strong>preparation of hand<strong>in</strong>g -over documents to ma<strong>in</strong>tenance organisation.3.16 Suitable arrangements shall be made <strong>in</strong> the relay rack <strong>for</strong> fix<strong>in</strong>g condenser andresistance unit, required <strong>for</strong> slow to release feature. Letter pa<strong>in</strong>t<strong>in</strong>g shall be madeaga<strong>in</strong>st each unit to identify circuit <strong>for</strong> which it is used.4) Term<strong>in</strong>al blocks M-6 (ARA term<strong>in</strong>al as per IRS spc. No. IRS-S-75/2006(Rev 2) orlatest and IRS drg no. SA-23741/A Alt-4.5) DWC Pipe HDPE (Elect REX/Tele REX or similar) <strong>for</strong> under groungsignall<strong>in</strong>g/communication cable protection, 103.5mm <strong>in</strong>ner dia & 120mm outer dia <strong>in</strong> 6 mstraight length as per BSEN 50086-1 & BSEN 50086-2,4 & BIS draft spec DOC HQ LTD14(5071) & ETD 5072) to spec IS 14930 part II. Note-One coupler <strong>for</strong> jo<strong>in</strong><strong>in</strong>g shall besupplied with each 6 mtr length. Inspection by RITES only.6) Apparatus cases full with m<strong>in</strong>iature E type lock as per drg no.RE/S&T/ALD/SK/219/82 with Alt 'A' and 221/82 with Alt ’B’ or latest and Apparatuscases quarter type lock as per drg no. RE/S&T/ALD/SK/227/82 or latest’. The keys ofward no 42 and handle should be supplied at the rate of one per four location boxes.7) Evaluator /processor <strong>for</strong> multi section digital axle counter equipped <strong>for</strong> specific tracksections complete set as per RDSO Specification no RDSO/SPN/176/2005 (Ver. 2) andOEM's specification.8) Earth<strong>in</strong>g System8.1 Earth<strong>in</strong>g of SER/BER/LSC: Perimeter Ground<strong>in</strong>g System8.1.1 A perimeter ground<strong>in</strong>g system shall be created <strong>for</strong> each SER+BER, LSC. Theperimeter ground will be created by bond<strong>in</strong>g a network of earth electrodes(ma<strong>in</strong>tenance fee) together us<strong>in</strong>g GI strip – 5mm x 50mm. The number of earthelectrodes will depend on the soil receptivity and the depth to which electrodes canbe buried. The GI strip should be Cad welded to each of the earth electrodes to <strong>for</strong>ma r<strong>in</strong>g.The GI strip should be buried at least 0.5m below ground level, <strong>in</strong> a trench dugbetween the adjacent earth electrodes. Allowance must be made when digg<strong>in</strong>g thetrench <strong>for</strong> fitt<strong>in</strong>g the Cad weld<strong>in</strong>g equipment to the electrode and strip. The trenchback fill must be rammed down firmly.8.1.2 The earth electrode used <strong>for</strong> the purpose of earth<strong>in</strong>g should use “pipe <strong>in</strong> pipe”technology. A Galvanized Iron (GI) pipe of 3m length, and 25mm diameter, isplaced centrically <strong>in</strong>side a 50mm diameter Galvanized Iron (GI) pipe of the samelength. The space between the electrodes is tightly filled with a crystall<strong>in</strong>econductive mixture and then sealed. The crystall<strong>in</strong>e mixture should conta<strong>in</strong> naturalelements and compounds, that are high conductive and anti corrosive as well at theSignature of contractor Page 104 of 111 Dy CSTE /CTC/CNB


same time. The crystall<strong>in</strong>e mixture should not dis<strong>in</strong>tegrate or collapse if the outerelectrode becomes <strong>in</strong>active.Earth electrodes shall be buried as close as possible to the structure to m<strong>in</strong>imise thepossibility of theft.8.1.3 In each SER/BER/LSC, there shall be a Ma<strong>in</strong> Earth Busbar. This bus bar shall bemounted directly onto the metal walls and shall be <strong>in</strong>sulated from the walls. TheMa<strong>in</strong> Earth Busbar shall be approximately 300mm, 6mm by 70mm, copper bar.All earth<strong>in</strong>g cable will be fastened to the Ma<strong>in</strong> Earth Busbar us<strong>in</strong>g soldered, “eyelet”or lug type connectors (not spade) fastened with a brass nut, bolt and washer aboveand below the lug. All secondary bus bars with<strong>in</strong> the <strong>in</strong>stallation shall be connectedto the Ma<strong>in</strong> Earth Busbar <strong>in</strong> a star configuration us<strong>in</strong>g 5mm x 50mm GI tape.8.1.4 The Ma<strong>in</strong> Earth Busbar shall be mounted no more than 300mm above floor leveland as close as possible to those cables that could <strong>in</strong>troduce surges and EMI to theSER/BER/LSC.The Ma<strong>in</strong> Earth L<strong>in</strong>k, from the perimeter ground to the Ma<strong>in</strong> Earth Busbar shall be:• Cad welded to the closest earth electrode;• As short and straight as possible with no sharp turns (m<strong>in</strong>imum radius of 300mm);• Run <strong>in</strong> GI pipe from the earth electrode to the build<strong>in</strong>g wall to protect fromtheft; be 5mm x 50mm GI tape;• Shielded from the metal walls of the SER us<strong>in</strong>g a grummet;• Bolted to the Ma<strong>in</strong> Earth Busbar us<strong>in</strong>g a locknut (e.g. two nuts on a bolt).A sign shall be attached to the SER/BER/LSC wall with the words” DANGER – DONOT REMOVE EARTHING CABLE”.The earth<strong>in</strong>g system with<strong>in</strong> an equipment room is an extension of that which hasbeen developed to the Ma<strong>in</strong> Earth Busbar. All secondary earth busbars shall bebonded to the Ma<strong>in</strong> Earth Busbar us<strong>in</strong>g m<strong>in</strong>imum 10mm2 Copper cable.All connections to the Ma<strong>in</strong> and secondary busbars shall be via 10mm brass nuts andbolts. The nut shall be a “lock<strong>in</strong>g” type (or two nuts on the one bolt) to preventloosen<strong>in</strong>g due to external vibration.8.1.5 Rack and Cable Tray Earth<strong>in</strong>gEach rack will have its own secondary earth busbar directly bolted to the rackmetalwork, and positioned at the bottom of the rack, as close as possible to theMa<strong>in</strong> Earth Busbar. Each hold<strong>in</strong>g trays of the rack should be <strong>in</strong>dividuallyconnected through earth wire to the rack earth.Internal racks should be bonded to one another and to the cable trays to <strong>for</strong>m anequipotential zone.Cable trays shall also be bonded to the racks that they jo<strong>in</strong> us<strong>in</strong>g short bonds. Thebonds will consist of eyelets crimped to 10mm2 copper cable at each end. Thebond shall be bolted to the tray and frame.8.1.6 Earth<strong>in</strong>g Equipment with<strong>in</strong> RoomsSignature of contractor Page 105 of 111 Dy CSTE /CTC/CNB


The metallic covers of equipment such as power supplies and trans<strong>for</strong>mers that arenot located on racks shall be bonded directly to the nearest secondary earth busbarus<strong>in</strong>g 10mm2 <strong>in</strong>sulated copper cable (as specified by the manufacturer).Operat<strong>in</strong>g equipment such as mechanical lever frames, block <strong>in</strong>struments andoperat<strong>in</strong>g Panels also need to be bonded to the nearest busbar us<strong>in</strong>g 10mm2<strong>in</strong>sulated copper Cable (<strong>in</strong> accordance with AC immunisation requirements andsupplier requirements).8.1.7 Cable ShieldsShielded cable (other than high frequency coaxial cables) shall be earthed to aMa<strong>in</strong> or Secondary earth busbar at one end only. (NOTE: Cable armour is notshield<strong>in</strong>g and shall not be treated as shield<strong>in</strong>g.) The shields shall be earthed at theend farthest from the SER if the cable is run between a SER and another build<strong>in</strong>gor <strong>in</strong>stallation. SSI related serial data communications cables that orig<strong>in</strong>ate andterm<strong>in</strong>ate with<strong>in</strong> the SER/LSC shall have their shields term<strong>in</strong>ated on one end to theclosest secondary earth busbar.8.2 Way Side Equipment Earth<strong>in</strong>gWayside equipment, apart <strong>for</strong>m po<strong>in</strong>ts mach<strong>in</strong>es and associated rodd<strong>in</strong>g, shall be providedwith earth<strong>in</strong>g to protect the <strong>in</strong>stallation from lightn<strong>in</strong>g related surges and possible fallenoverhead traction conductors. If the equipment is isolated (no other equipment with<strong>in</strong>30m), the equipment shall be provided with its own earth<strong>in</strong>g electrode(s).The item <strong>in</strong>cludes digg<strong>in</strong>g of pit <strong>in</strong> earth, 3 meters and fix<strong>in</strong>g of earth electrode pipes.Cast<strong>in</strong>g of cement concrete enclosures as per Drg no. NR/S&T/CON/6.3/97. The soiltreatment should be done as per the standard practice.The equipment shall be bonded to the electrode us<strong>in</strong>g 6 SWG GI wire supported on MSflat size 5 mm x 40 mm. The other end of the MS flat to be connected by bolt/solder<strong>in</strong>g tothe signall<strong>in</strong>g equipment as per <strong>in</strong>struction of Railway site eng<strong>in</strong>eer.The cable shall beburied 500mm below ground level. The cable shall be Cadwelded to the electrode andattached to the equipment us<strong>in</strong>g a brass bolt (through a lug).Note: For the location boxes hous<strong>in</strong>g the Track side electronic unit of the MSDAC, theearth should be kept below 1 ohm.8.3 Follow<strong>in</strong>g is the list of generally recommended maximum values of Earthresistances <strong>for</strong> various equipments. Wherever, values prescribed here <strong>for</strong> theequipment are <strong>in</strong> contradiction to value prescribed by the manufacturer, the onewhich is lesser of the two should be achieved.S. No. Equipment Maximum Value ofSystem Earth<strong>in</strong>gResistanceI SER/BER/LSC 1 Ohms(Ma<strong>in</strong>tenance free as per latest RDSOspecifications)Signature of contractor Page 106 of 111 Dy CSTE /CTC/CNB


II Location Box Def<strong>in</strong>ed by ExternalGear bonded to it. (However <strong>for</strong> the location boxhous<strong>in</strong>g the track side electronic unit ofMSDAC, it should be less than 1 ohm)(i) Axle Counter 5 Ohms or as prescribed by the OEMspecifications(lesser value to be taken)(ii) Equipment <strong>in</strong> Station Masters 5 OhmsRoom(iii) AFTC 5 Ohms or as prescribed by the OEMspecifications(iv) Signal Post 10 Ohms(v) Level Cross<strong>in</strong>g 10 Ohms8.4 Earth Electrode shall be tested as per standard methodology of Earth<strong>in</strong>g test<strong>in</strong>g andtest results should be signed by the representative of the Contractor and the Eng<strong>in</strong>eer.9) Cable lay<strong>in</strong>g and term<strong>in</strong>ationa) Cable open<strong>in</strong>gs <strong>in</strong> Apparatus cases, junction boxes and <strong>in</strong> relay rooms should becovered by sand and top should be plastered by cement <strong>for</strong> apparatus cases andjunction boxes.b) The cables <strong>in</strong> sufficient spare lengths shall be kept coiled <strong>in</strong> a circle of suitable diameterat m<strong>in</strong>imum 1 meter depth be<strong>for</strong>e be<strong>in</strong>g taken <strong>in</strong>to the relay rooms/apparatus cases andfield operation <strong>for</strong> term<strong>in</strong>ation. Such coils of cables <strong>in</strong> pits shall be adequately coveredby concrete to provide protection aga<strong>in</strong>st damage.c) For each station/section, the cable route plan will be prepared be<strong>for</strong>e thecommencement of the cable lay<strong>in</strong>g work at the stations. This plan can be altered asrequired under the exigencies of local conditions or <strong>for</strong> any other consideration, bythe Eng<strong>in</strong>eer In charge. The Eng<strong>in</strong>eers representative <strong>in</strong> charge of the work will markthe route of the cable with chalk or lime, as per cable route plans/ cable plans as theEng<strong>in</strong>eers <strong>in</strong>structions to him that shall be taken by the contractor. He shall lay thecables only along this route. The contractor shall be present at the time of mark<strong>in</strong>g theroute of the cable and he shall furnish to the Eng<strong>in</strong>eers representative requiredquantities of l<strong>in</strong>e, rope, labour etc. but carry<strong>in</strong>g out this work at the cost of thecontractor.d) Cable lay<strong>in</strong>g should commence only after the depths and quality of trenches checked,quantity of bricks and arrangement <strong>for</strong> tempted fill<strong>in</strong>g etc. are <strong>in</strong>spected jo<strong>in</strong>ted by theEng<strong>in</strong>eer’s representative and Contractor’s representative and approved by theEng<strong>in</strong>eer’s representative. The measurements of length <strong>for</strong> all these items willbe suitably recorded by the Eng<strong>in</strong>eer's representative who will permit the lay<strong>in</strong>gof cables after issu<strong>in</strong>g the certificates that the above works have been done asrequired by the Specifications.Signature of contractor Page 107 of 111 Dy CSTE /CTC/CNB


e) Trench<strong>in</strong>g <strong>for</strong> track cross<strong>in</strong>g and lay<strong>in</strong>g of cable across the track should be done only<strong>in</strong> the presence of the Eng<strong>in</strong>eers representative.f) Cable shall not be normally taken over the track at the time of cable lay<strong>in</strong>g by thecontractor, as this is likely to cause accident to tra<strong>in</strong>s and damage to cable. If, at anytime, the cable has to be taken across the track, it shall be done only <strong>in</strong> the presence ofthe Eng<strong>in</strong>eer’s representative and after the safety precautions have been taken.g) The handl<strong>in</strong>g, lay<strong>in</strong>g and pull<strong>in</strong>g of wires and cable shall be <strong>in</strong> accordance with<strong>in</strong>structions and under supervision of the contractor. For lay<strong>in</strong>g the cables, the drumshall be mounted on axle at one end of the trench and the cable laid out and carried byContractor’s labourers guid<strong>in</strong>g the cable <strong>in</strong>to the trench.h) Cable should be properly term<strong>in</strong>ated <strong>in</strong> the term<strong>in</strong>al boards / racks.i) Bends <strong>in</strong> cables shall have a radius of not less than 20 times the diameter of the cablesj) Eyelet term<strong>in</strong>als shall be used on flexible wires, if necessary.k) Not more than two wires shall be connected to one term<strong>in</strong>als/ tag.l) Cables term<strong>in</strong>ated <strong>in</strong>side apparatus cases, junction boxes and <strong>in</strong> relay room should befixed by clamp or any other method <strong>in</strong>dicated by Eng<strong>in</strong>eers.m) Term<strong>in</strong>al shall be mounted so that they cannot be turned <strong>in</strong> base of frame to beapplied. They shall be properly <strong>in</strong>sulated from each other and other metallic parts.n) Term<strong>in</strong>al shall be <strong>in</strong>stalled <strong>in</strong> and accessible position and neatly arranged on term<strong>in</strong>alboards <strong>in</strong> hous<strong>in</strong>gs.o) The term<strong>in</strong>al block provided at the locations, and other places shall be provided withsuitable l<strong>in</strong>ks to facilitate isolation of the two sides of the circuits, which areconnected to the term<strong>in</strong>al l<strong>in</strong>ks.p) With the help of mega ohmmeter, <strong>in</strong>sulation resistance test shall be conducted on allcores of each cable jo<strong>in</strong>tly by the representative of the Eng<strong>in</strong>eer and the contractorbe<strong>for</strong>e the cable is connected or the wired to the signall<strong>in</strong>g equipment. The <strong>in</strong>sulationresistance shall be measured between a core and all other cores connected together tothe sheath and earth. The results of the <strong>in</strong>sulations resistance test shall be tabulated <strong>in</strong>a standard <strong>for</strong>mat as per Annexure-I and the <strong>for</strong>mat signed by the representative ofthe contractor and the Eng<strong>in</strong>eer.q) With the help of suitable multimeter, loop resistance test shall be conducted on allcores of each cable jo<strong>in</strong>tly by the representatives of the Eng<strong>in</strong>eer and the contractorbe<strong>for</strong>e the cable is connected or wired to the signall<strong>in</strong>g equipment. The result of theloop resistance test shall be tabulated <strong>in</strong> the <strong>for</strong>m given as Annexure –II and the <strong>for</strong>msigned by the representatives of the Contractor and the Eng<strong>in</strong>eer.10. FUSES, TERMINAL AND TERMINAL LINKSSignature of contractor Page 108 of 111 Dy CSTE /CTC/CNB


FUSESa) It shall not be possible to <strong>in</strong>sert a cartridge of a higher rat<strong>in</strong>g <strong>in</strong>to a holder of lowerrat<strong>in</strong>g.b) Fuses shall be of non-deteriorat<strong>in</strong>g type confirm<strong>in</strong>g to RDSO specification.c) Fuse clips shall be mounted on an <strong>in</strong>sulat<strong>in</strong>g base of fireproof material.d) Fuses or circuits breakers shall be <strong>in</strong>stalled accord<strong>in</strong>g to standard practice with priorapproval of the Railway.11. INSULATIONProvision of <strong>in</strong>sulation wherever required to follow standard approved Railwaypractice <strong>for</strong> the purpose. Material used <strong>for</strong> <strong>in</strong>sulation shall be such that it will not be<strong>in</strong>juriously affected by atmospheric conditions.12) Cast<strong>in</strong>g of concrete foundation & <strong>in</strong>stallation of Apparatus case: -This <strong>in</strong>cludesa) Excavation & cast<strong>in</strong>g of foundation and erection of apparatus case (Full/Quarter) withcontractor’s own cement, sand, aggregate and acchor bolts etc. The work shall be donegenerally comply<strong>in</strong>g to drg. No. RE/S&T/ALD/SK/219/82 with Alt 'A' and 221/82 with Alt'B and RE/S&T/ALD/SK/227/82.b) Apparatus cases should be provided with Hylam boards. Fabrication of Hylam boardshould be done from hylam sheet, res<strong>in</strong> bonded 10mm thick, grade-P3 <strong>in</strong> standred size of1.22 x1.22 mtr as per specification no. IS 2036 of 1974. This also <strong>in</strong>cludes fix<strong>in</strong>g ofterm<strong>in</strong>al block; fuse blocks with provision of holes on hylem sheet and fix<strong>in</strong>g of galvanisednuts & bolts etc.13) Pa<strong>in</strong>t<strong>in</strong>g of location boxes: - The contractor should arrange <strong>for</strong> supply of pa<strong>in</strong>ts and allother consumable stores <strong>for</strong> pa<strong>in</strong>t<strong>in</strong>g. Work should be carried out as per demarcation anddirection of authorized railway site supervisor.14) MISCELLANEOUS:14.1 WOOD WORK:Wherever woodwork is <strong>in</strong>volved, the wooden planks are to be supplied by the contractorand he shall ensure the wood of good quality, which shall be varnished / pa<strong>in</strong>ted asspecified. All teak wood boards shall be varnished and hard wood shelves should be blackpa<strong>in</strong>ted.14.2 Wooden cross of approved type should be provided <strong>for</strong> the newly erected colourlight signals, till they are commissioned.14.3 Wooden Board and shelves are to be properly polished be<strong>for</strong>e fix<strong>in</strong>g the term<strong>in</strong>alsand equipments on it, as advised by the Eng<strong>in</strong>eer.14.4 All the equipments, relays and term<strong>in</strong>als are to be marked by letter<strong>in</strong>g on it asadvised by the Eng<strong>in</strong>eer.Signature of contractor Page 109 of 111 Dy CSTE /CTC/CNB


ANNEXURE-IThe follow<strong>in</strong>g are the Insulation resistance test results conducted by us on___________Core capacity cable laid between___________ and ___________ on date ____________at _______________ station.___________________________________________________________________________Core 1 2 3 4 5 6 7 8 . . E12345678Signature of therepresentative of theContractorSignature of therepresentative ofthe Eng<strong>in</strong>eer.Signature of contractor Page 110 of 111 Dy CSTE /CTC/CNB


ANNEXURE-IIThe follow<strong>in</strong>g are the loop resistance test results conducted by us on _________ Corecapacity cable laid between___________ and ___________ on date __________at _______________ station.______________________________________________________________________________Core 1 2 3 4 5 6 7 8 . . E12345678Signature of therepresentative of theContractorSignature of therepresentative ofthe Eng<strong>in</strong>eer.Signature of contractor Page 111 of 111 Dy CSTE /CTC/CNB