Conceptual Site Model - Argonne National Laboratory
Conceptual Site Model - Argonne National Laboratory Conceptual Site Model - Argonne National Laboratory
WVDP Phase 1 CSAP• If a sample indicates contamination impacts above background levels for the 15 cm-1 mdepth interval, an additional sample from a depth of 1-2 m will be collected and analyzedfrom that location. This will be repeated, as necessary, until the vertical extent ofcontamination impact is bounded at that location. [contingent]• If the eastern-most ditch sampling point indicates contamination above the surface soilCG w requirement, systematic sampling will continue eastward following the ditch with a30 m spacing until results are below the surface soil CG w .I.9.6Buried Infrastructure Soil SamplingSoils associated with buried infrastructure within WMA 10 will be sampled to determine theircontamination status.• For a minimum of five selected locations along the main storm sewer line within WMA10, excavation will take place to expose the line. These locations will be selected tomaximize the possibility that contamination will be encountered (e.g., locations wherehistorical or current GWS data indicate surface contamination exists). During excavation,exposed soils will be monitored by scans for evidence of elevated gross activity. Thepurpose of this sampling is to evaluate the presence of contamination associated withburied infrastructure. [required]oIf elevated readings are encountered below a depth of 1 m, soils exhibiting thehighest levels of gross activity will be sampled and analyzed.oIf elevated readings are not encountered below a depth of 1 m, a samplerepresentative of soils deeper than 1 m but above the storm sewer line will beobtained.• If contamination above background conditions is encountered at any selected location,trenching will continue to depth until background conditions are observed. An additionalsample will be collected from the base of the trench to verify background conditions. Thepurpose is to vertically bound observed contamination. [contingent]Rev. 1 I-14
WVDP Phase 1 CSAP• For any additional buried infrastructure of potential concern that is identified, a minimumof at least one soil sample from at least one biased location will collected following theprotocols described for the main storm sewer line for each buried infrastructure lineidentified that is of potential concern. Infrastructure of potential concern is infrastructurethat either carried waste or was installed after 1968. Examples of the type of additionalburied infrastructure that might be encountered are water supply lines, gas lines, electricallines, telecommunication lines, etc. The purpose of this sampling is to evaluate thepresence of contamination associated with buried infrastructure. [contingent]• If buried infrastructure soil sampling identifies contamination impacts greater thanbackground, biased sampling will continue following the line away from the WMA 1, 3,and 5, until at least two consecutive locations yield soil samples below surface soil CG wrequirements. Location spacing will be based on engineering judgment, including thegeometry of the line, the distance from WMA 1, 3, and 5, the level of contaminationencountered, and surface evidence of contamination. The purpose of this sampling is tobound the extent of contamination associated with buried infrastructure, as necessary.[contingent]I.9.7Additional ContingenciesSampling and/or GWS data may indicate that contamination exists or extends beneath surfacescurrently covered by existing structures, concrete, asphalt, or gravel. In this case, “surface soil”will be defined as soil immediately beneath the cover. If sampling or GWS data indicate thatcontamination may exist beneath existing structures (e.g., the Administration Building, SecurityGatehouse, or hardstand areas), then sampling locations will be offset along thefoundation/hardstand edge to determine contamination extent. The purpose of the offset is toallow safe acquisition of data. Data collection through the floors of existing buildings or throughhardstands in WMA 10 will not be required as part of this effort.WMA 10 abuts up to several other areas that have the potential for subsurface soil contaminationconcern at depths greater than one meter (e.g., WMA 1). Sampling efforts associated with thoseareas may result in soil core collection that extends into WMA 10 as necessary.Rev. 1 I-15
- Page 396 and 397: WVDP Phase 1 CSAPFigure G.10 WMA 7
- Page 398 and 399: WVDP Phase 1 CSAPFigure G.12 WMA 7
- Page 400 and 401: WVDP Phase 1 CSAPSS-15137Cs: 4.7 pC
- Page 402 and 403: WVDP Phase 1 CSAPFigure G.16 WMA 7
- Page 404 and 405: WVDP Phase 1 CSAPThis page intentio
- Page 406 and 407: WVDP Phase 1 CSAPcompleted in 1990.
- Page 408 and 409: WVDP Phase 1 CSAP• In 1990 and 19
- Page 410 and 411: WVDP Phase 1 CSAPH.9.1 Gamma Walkov
- Page 412 and 413: WVDP Phase 1 CSAPdepth interval, an
- Page 414 and 415: WVDP Phase 1 CSAPA select portion o
- Page 416 and 417: WVDP Phase 1 CSAPTable H.1 Historic
- Page 418 and 419: WVDP Phase 1 CSAPEmpty Waste Contai
- Page 420 and 421: WVDP Phase 1 CSAPFigure H.3 WMA 9 A
- Page 422 and 423: WVDP Phase 1 CSAPFigure H.5 WMA 9 A
- Page 424 and 425: WVDP Phase 1 CSAPFigure H.7 WMA 9 A
- Page 426 and 427: WVDP Phase 1 CSAPFigure H.9 WMA 9 A
- Page 428 and 429: WVDP Phase 1 CSAPFigure H.11 WMA 9
- Page 430 and 431: WVDP Phase 1 CSAPFigure H.13 Histor
- Page 432 and 433: WVDP Phase 1 CSAPFigure H.15 WMA 9
- Page 434 and 435: WVDP Phase 1 CSAPA steel security f
- Page 436 and 437: WVDP Phase 1 CSAPFigure I.4 shows W
- Page 438 and 439: WVDP Phase 1 CSAPshine from facilit
- Page 440 and 441: WVDP Phase 1 CSAPI.7 Conceptual Sit
- Page 442 and 443: WVDP Phase 1 CSAPA complete (100%)
- Page 444 and 445: WVDP Phase 1 CSAPgross activity lev
- Page 448 and 449: WVDP Phase 1 CSAPI.9.8Required Labo
- Page 450 and 451: WVDP Phase 1 CSAPTable I.1 Historic
- Page 452 and 453: WVDP Phase 1 CSAPContractor Fab Sho
- Page 454 and 455: WVDP Phase 1 CSAPFigure I.3 WMA 10
- Page 456 and 457: WVDP Phase 1 CSAPFigure I.5 WMA 10
- Page 458 and 459: WVDP Phase 1 CSAPFigure I.7 WMA 10
- Page 460 and 461: WVDP Phase 1 CSAPFigure I.9 WMA 10
- Page 462 and 463: WVDP Phase 1 CSAPFigure I.11 WMA 10
- Page 464 and 465: WVDP Phase 1 CSAPFigure I.13 WMA 10
- Page 466 and 467: WVDP Phase 1 CSAPFigure I.15 Initia
- Page 468 and 469: WVDP Phase 1 CSAPBrook northwest of
- Page 470 and 471: WVDP Phase 1 CSAP• Lagoon 3 (in W
- Page 472 and 473: WVDP Phase 1 CSAPThe limited Cs-137
- Page 474 and 475: WVDP Phase 1 CSAPcontaminating subs
- Page 476 and 477: WVDP Phase 1 CSAPdistribution of su
- Page 478 and 479: WVDP Phase 1 CSAPoIf GWS results in
- Page 480 and 481: WVDP Phase 1 CSAPon historical info
- Page 482 and 483: WVDP Phase 1 CSAPA select portion o
- Page 484 and 485: WVDP Phase 1 CSAPTable J.1 Historic
- Page 486 and 487: WVDP Phase 1 CSAPFigure J.1 WMA 12
- Page 488 and 489: WVDP Phase 1 CSAPFigure J.3 WMA 12
- Page 490 and 491: WVDP Phase 1 CSAPFigure J.5 1982 WM
- Page 492 and 493: WVDP Phase 1 CSAPWMA 12 NorthWMA 12
- Page 494 and 495: WVDP Phase 1 CSAPFigure J.9 WMA 12
WVDP Phase 1 CSAP• If a sample indicates contamination impacts above background levels for the 15 cm-1 mdepth interval, an additional sample from a depth of 1-2 m will be collected and analyzedfrom that location. This will be repeated, as necessary, until the vertical extent ofcontamination impact is bounded at that location. [contingent]• If the eastern-most ditch sampling point indicates contamination above the surface soilCG w requirement, systematic sampling will continue eastward following the ditch with a30 m spacing until results are below the surface soil CG w .I.9.6Buried Infrastructure Soil SamplingSoils associated with buried infrastructure within WMA 10 will be sampled to determine theircontamination status.• For a minimum of five selected locations along the main storm sewer line within WMA10, excavation will take place to expose the line. These locations will be selected tomaximize the possibility that contamination will be encountered (e.g., locations wherehistorical or current GWS data indicate surface contamination exists). During excavation,exposed soils will be monitored by scans for evidence of elevated gross activity. Thepurpose of this sampling is to evaluate the presence of contamination associated withburied infrastructure. [required]oIf elevated readings are encountered below a depth of 1 m, soils exhibiting thehighest levels of gross activity will be sampled and analyzed.oIf elevated readings are not encountered below a depth of 1 m, a samplerepresentative of soils deeper than 1 m but above the storm sewer line will beobtained.• If contamination above background conditions is encountered at any selected location,trenching will continue to depth until background conditions are observed. An additionalsample will be collected from the base of the trench to verify background conditions. Thepurpose is to vertically bound observed contamination. [contingent]Rev. 1 I-14