Evaluation and Repair of Wrought Iron and - Purdue e-Pubs ...

Evaluation and Repair of Wrought Iron and - Purdue e-Pubs ... Evaluation and Repair of Wrought Iron and - Purdue e-Pubs ...

10.07.2015 Views

56completed, but before the surface was ground flush to make the welds blend into theoriginal eyebar connection.Eyebar B was modeled to be a worst case scenario of section loss due to corrosionin an eyebar end connection. In this eyebar, half the thickness of the original eyebar’smaterial was removed from the center two and a half inches around the hole andperpendicular to the direction of loading. Figure 3.28 shows Eyebar B after this materialwas removed and prepared for welding.Once this material was removed, the area simulating corrosion needed to be filledwith weld material. To do this an E7024 SMAW 1/8” diameter welding rod was utilizedwith a DC reverse polarity electric source, similar to Eyebar A. An initial pass aroundthe hole in the eyebar and along the open edges were placed to create a dam for the fillermaterial, as can been seen in Figure 3.29.Once the initial passes were placed, filler passes were then placed in the open areain the direction of loading of the eyebar to reduce heat distortion. In between passes thetemperature of the base metal was also monitored to ensure the metal was not to hot toweld and to reduce the amount of heat distortion in the metal. It was necessary to takebreaks and allow the metal cool between sets of passes. The welds were also cleanedusing a chisel hammer and wire brush in between each pass. Figures 3.30 and 3.31 showthe eyebar end connection after all the welding was completed.As can been seen in Figure 3.31 there was a slight amount of heat distortion andcurvature in the wrought iron eyebar connection from the filler weld. To straighten thispiece, the eyebar was heated until it was red hot, as seen in Figure 3.32, and thenstraightened by striking the eyebar with large hammer. The color of the eyebar wassimilar to the color of the iron that was heat straightened in the tension testing couponsand therefore at the adequate temperature to straighten the iron without inducing

57significant strain damage in the metal. The eyebar was then allowed to cool slowly andthen surface ground to make the filler weld blend into the original eyebar.After surface grinding to a flush condition, Measurements Group CEA-06-250UN-350 type strain gages were placed on both faces of the shank of the eyebarconnections of Eyebars A and B. Figures 3.33 and 3.34 are photographs of the eyebarsafter being surface ground and directly before testing. The same fixture that was utilizedwith the MTS testing machine when testing the eyebar connection that had not beenrepaired was also used in testing Eyebar A and B.This fixture, which consisted of three thick plates that were bolted together, wasplaced in the upper grip of the testing machine. A 2 3 / 16 inch steel pin was placed throughtwo of these plates and hole in the eyebars. The bottom of the eyebar was then placed inthe bottom grip of the MTS testing machine. A two inch extensometer was then attachedat the shank of the eyebar connection above the lower grip with strong elastic bands.Figures 3.35 and 3.36 are front and side view photographs of Eyebar A immediatelybefore testing.The eyebar connections were then tested in the same manner than the eyeconnections that had not experienced any repair. The eye connections were initiallyloaded only in the elastic region of the stress-strain curve. In this test, load was applied ata fixed rate while the amount of strain in the specimen was recorded. The readings fromthe strain gages, extensometer, load cell and stroke were recorded during this test. Thistest was done at a rate of five thousand pounds per minute. The sample was only stresseduntil a stress of 10 ksi or less was reached in the shank of the specimen. This test wascompleted to ensure that the testing and data recording equipment was working properly.After the initial test, both Eyebar A and B were loaded completely until failure.The eye connections were pulled at a constant rate of 1/12 inch per minute until failure.The failure location of the eye connections was recorded along with the strain gage

57significant strain damage in the metal. The eyebar was then allowed to cool slowly <strong>and</strong>then surface ground to make the filler weld blend into the original eyebar.After surface grinding to a flush condition, Measurements Group CEA-06-250UN-350 type strain gages were placed on both faces <strong>of</strong> the shank <strong>of</strong> the eyebarconnections <strong>of</strong> Eyebars A <strong>and</strong> B. Figures 3.33 <strong>and</strong> 3.34 are photographs <strong>of</strong> the eyebarsafter being surface ground <strong>and</strong> directly before testing. The same fixture that was utilizedwith the MTS testing machine when testing the eyebar connection that had not beenrepaired was also used in testing Eyebar A <strong>and</strong> B.This fixture, which consisted <strong>of</strong> three thick plates that were bolted together, wasplaced in the upper grip <strong>of</strong> the testing machine. A 2 3 / 16 inch steel pin was placed throughtwo <strong>of</strong> these plates <strong>and</strong> hole in the eyebars. The bottom <strong>of</strong> the eyebar was then placed inthe bottom grip <strong>of</strong> the MTS testing machine. A two inch extensometer was then attachedat the shank <strong>of</strong> the eyebar connection above the lower grip with strong elastic b<strong>and</strong>s.Figures 3.35 <strong>and</strong> 3.36 are front <strong>and</strong> side view photographs <strong>of</strong> Eyebar A immediatelybefore testing.The eyebar connections were then tested in the same manner than the eyeconnections that had not experienced any repair. The eye connections were initiallyloaded only in the elastic region <strong>of</strong> the stress-strain curve. In this test, load was applied ata fixed rate while the amount <strong>of</strong> strain in the specimen was recorded. The readings fromthe strain gages, extensometer, load cell <strong>and</strong> stroke were recorded during this test. Thistest was done at a rate <strong>of</strong> five thous<strong>and</strong> pounds per minute. The sample was only stresseduntil a stress <strong>of</strong> 10 ksi or less was reached in the shank <strong>of</strong> the specimen. This test wascompleted to ensure that the testing <strong>and</strong> data recording equipment was working properly.After the initial test, both Eyebar A <strong>and</strong> B were loaded completely until failure.The eye connections were pulled at a constant rate <strong>of</strong> 1/12 inch per minute until failure.The failure location <strong>of</strong> the eye connections was recorded along with the strain gage

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!