COF Skimmer Wall During and After ConstructionDuring Skimmer Wall Construction04-2002Potential Savingabout $20 Millionsfor the next 25 yearsResultsWall Construction Finished07-2002Cost = $1.4 MillionsNo debris cleaning since theconstruction of the wall.<strong>TVA</strong> lost 0 MWh due to debrisbuildup at COF since construction.An average improvement ofabout 0.25 °F in intake watertemperature.Lower Base line 316(b) ruling