FEIR for Boitshepi Landfill Site .pdf - Zitholele.co.za
FEIR for Boitshepi Landfill Site .pdf - Zitholele.co.za FEIR for Boitshepi Landfill Site .pdf - Zitholele.co.za
August 2010 19 8848Application Forms and Landowner consentThe EIA application form (Appendix A1) for the proposed project was submitted to theGDARD on 10 April 2008. (Refer to Appendix A6). Acknowledgement of receipt of theapplication form by the GDARD was received on 8 July 2008.Site VisitsMonthly site visits were conducted by Mrs Jacqui Hex from ZC and Mr Elias Barnard fromGAA from April 2007 to November 2009 in order to identify all environmental aspects to beassessed during the EIA phase.Draft Scoping Report and Plan of Study for EIAThe Draft Scoping Report (SR) was prepared based on the information gathered and issuesidentified during the Scoping Phase activities. The PoS for EIA including the Terms ofReference (ToR) for the envisaged specialist studies were also included in the Final ScopingReportFinal Scoping Report and Plan of Study for EIAThe Draft SR and PoS were updated based on comments obtained from I&APs and wereconsolidated into the Final Scoping Report and the PoS for the EIA. This report was submittedto the GDARD for acceptance and approval to proceed was received on the 9 April 2009(Appendix A7).3.1.2 Public Participation ProcessPublic participation is an essential and legislative requirement in an EIA processes. Theprinciples that demand communication with society at large are best embodied in theprinciples of the NEMA (Act 107 of 1998, Chapter 1), South Africa’s overarchingenvironmental law. In addition, Section 24 (5), Regulation 56 of GN R385 under the NEMA,guides the PPP that is required for an EIA. The NEM:WA, Part 2, Section 73 also makesprovision for public participation.The PPP for this project has been designed and undertaken to satisfy the requirements laiddown in the above legislation. Figure 3 below provides an overview of the EIA technical andPP processes, and shows how issues and concerns raised by the public are used to informthe technical investigations of the EIA at various milestones during the process. This sectionof the report highlights the key elements of the PPP to date.ZITHOLELE CONSULTING
August 2010 20 8848Objectives of public participation in an Environmental Impact AssessmentThe objectives of public participation in an EIA are to provide sufficient and accessibleinformation to I&APs in an objective manner to assist them:• During Scoping:- Encourage the I&APs to provide of issues of concern and suggestions forenhanced benefits and alternatives.- Contribute their local knowledge and experience.- Verify that their issues have been considered and to help define the scope of thetechnical studies to be undertaken during the Impact Assessment.The key objective of public participation is to ensure transparency throughout the process andpromote informed decision making.Identification of Interested and Affected PartiesThe identification of stakeholders is an ongoing process, refined throughout the process ason-the-ground understanding of affected stakeholders improves through interaction withvarious stakeholders in the area. The identification of key stakeholders and communityrepresentatives (landowners and occupiers) is important and was done in collaboration withthe local municipality and other organisations in the study area.Stakeholders’ details are captured on Maximiser 9, an electronic database managementsoftware programme that automatically categorises every mailing to stakeholders, thusproviding an ongoing record of communications - an important requirement by the authoritiesfor public participation. In addition, comments and contributions received from stakeholdersare recorded, linking each comment to the name of the person who made it.Announcement of opportunity to become involvedThe opportunity to participate in the EIA Process was announced in August 2008 as follows:• Distribution of a letter of invitation to become involved, addressed to individuals andorganisations by name, accompanied by a BID containing details of the proposed project,including maps of the project area, and a registration sheet (Appendix B6);• Advertisements were placed in the following newspapers (Appendix B1):According to the NEMA, Section 24 (5), EIA Regulations, Section 56 of GN R385, a register ofI&APs must be kept by the public participation practitioner. Such a register has been compiledand is being kept updated with the details of involved I&APs throughout the process (SeeAppendix B3).ZITHOLELE CONSULTING
- Page 1: August 2010Authorisation PhaseENVIR
- Page 4: August 2010 iii 8848consultation wi
- Page 8 and 9: August 2010 vii 8848GNRGPSHHDIH:hH:
- Page 10 and 11: August 2010 ix 8848SECTIONTABLE OF
- Page 12 and 13: August 2010 xi 8848LIST OF FIGURESF
- Page 14 and 15: August 2010 xiii 8848Table 31: Impa
- Page 16 and 17: August 2010 1 88481 INTRODUCTIONAnt
- Page 18 and 19: August 2010 3 8848Figure 1: Locatio
- Page 20 and 21: August 2010 5 88481.5 The Project T
- Page 22 and 23: August 2010 7 8848EAP Contact Detai
- Page 24 and 25: August 2010 9 88482 LEGAL REQUIREME
- Page 26 and 27: August 2010 11 8848On 1 May 2009, N
- Page 28 and 29: August 2010 13 8848• The role of
- Page 30 and 31: August 2010 15 8848• To provide a
- Page 32 and 33: August 2010 17 8848• Lay down gen
- Page 36 and 37: August 2010 21 8848APPLICATION /REG
- Page 38 and 39: August 2010 23 8848were received as
- Page 40 and 41: August 2010 25 8848• A descriptio
- Page 42 and 43: August 2010 27 8848(KV3 Engineers a
- Page 44 and 45: August 2010 29 88485 PROJECT DESCRI
- Page 46 and 47: August 2010 31 8848Capping of the W
- Page 48 and 49: August 2010 33 88485.6 Overall EIA
- Page 50 and 51: August 2010 35 8848Construction of
- Page 52 and 53: August 2010 37 8848There are differ
- Page 54 and 55: August 2010 39 88486 TECHNOLOGY REV
- Page 56 and 57: August 2010 418848Figure 10: Boitsh
- Page 58 and 59: August 2010 4388487 BASELINE RECEIV
- Page 60 and 61: August 2010 458848• Soil depth;
- Page 62 and 63: 47August 2010 8848Figure 12: Soil T
- Page 64 and 65: August 2010 4988487.1.3 Drainage Fe
- Page 66 and 67: August 2010 518848Figure 15: Upper
- Page 68 and 69: 53August 2010 8848Figure 16: Topogr
- Page 70 and 71: August 2010 558848Soweto Highveld G
- Page 72 and 73: August 2010 578848Figure 18: Alien
- Page 74 and 75: 59August 2010 8848Species ListThe f
- Page 76 and 77: 61August 2010 8848Common Name Scien
- Page 78 and 79: 63August 2010 8848five decades ago
- Page 80 and 81: 65August 2010 8848steel industry, I
- Page 82 and 83: 67August 2010 88488 WASTE LICENSE A
August 2010 20 8848Objectives of public participation in an Environmental Impact AssessmentThe objectives of public participation in an EIA are to provide sufficient and accessiblein<strong>for</strong>mation to I&APs in an objective manner to assist them:• During S<strong>co</strong>ping:- En<strong>co</strong>urage the I&APs to provide of issues of <strong>co</strong>ncern and suggestions <strong>for</strong>enhanced benefits and alternatives.- Contribute their local knowledge and experience.- Verify that their issues have been <strong>co</strong>nsidered and to help define the s<strong>co</strong>pe of thetechnical studies to be undertaken during the Impact Assessment.The key objective of public participation is to ensure transparency throughout the process andpromote in<strong>for</strong>med decision making.Identification of Interested and Affected PartiesThe identification of stakeholders is an ongoing process, refined throughout the process ason-the-ground understanding of affected stakeholders improves through interaction withvarious stakeholders in the area. The identification of key stakeholders and <strong>co</strong>mmunityrepresentatives (landowners and occupiers) is important and was done in <strong>co</strong>llaboration withthe local municipality and other organisations in the study area.Stakeholders’ details are captured on Maximiser 9, an electronic database managementsoftware programme that automatically categorises every mailing to stakeholders, thusproviding an ongoing re<strong>co</strong>rd of <strong>co</strong>mmunications - an important requirement by the authorities<strong>for</strong> public participation. In addition, <strong>co</strong>mments and <strong>co</strong>ntributions received from stakeholdersare re<strong>co</strong>rded, linking each <strong>co</strong>mment to the name of the person who made it.Announcement of opportunity to be<strong>co</strong>me involvedThe opportunity to participate in the EIA Process was announced in August 2008 as follows:• Distribution of a letter of invitation to be<strong>co</strong>me involved, addressed to individuals andorganisations by name, ac<strong>co</strong>mpanied by a BID <strong>co</strong>ntaining details of the proposed project,including maps of the project area, and a registration sheet (Appendix B6);• Advertisements were placed in the following newspapers (Appendix B1):Ac<strong>co</strong>rding to the NEMA, Section 24 (5), EIA Regulations, Section 56 of GN R385, a register ofI&APs must be kept by the public participation practitioner. Such a register has been <strong>co</strong>mpiledand is being kept updated with the details of involved I&APs throughout the process (SeeAppendix B3).ZITHOLELE CONSULTING