FEIR for Boitshepi Landfill Site .pdf - Zitholele.co.za
FEIR for Boitshepi Landfill Site .pdf - Zitholele.co.za FEIR for Boitshepi Landfill Site .pdf - Zitholele.co.za
133August 2010 8848Table 53: Impact Rating Matrix for Social Environment during the Decommissioningphase (Alternative 1-3).Type of Source of Significance Spatial Temporal Probability RatingImpactImpactRe-claimers livelihoodsAlternative 1 and2MODERATE Local MediumtermVery Likely 2.7 –ModeratePositiveAlternative 3 LOW StudyareaShort-Term Very Likely 1.6 – LowPositiveInitial impact Health and NuisanceAlternative 1 VERY HIGH Local Short-term Will happen 3.3- HighAlternative 2 MODERATE Local Short-term Will happen 2.6 –ModerateAlternative 3 VERY LOW Local Short-term Will happen 1.9 – LowAdditionalimpactCumulativeimpactResidualImpactTrafficTrafficLess traffic onroads andtherefore lessdeterioration ofroadsDecreased safetyriskforpedestrians dueto the decreaseof heavy vehiclesJob Creation /LoseCrimeNuisanceHealthandVERY HIGHHIGHAs per additional impactAs per additional impactStudysiteMediumTermIs occurring3.33 – HighLOW Local Permanent Very Likely 2.6 –Moderate –POSITIVELOWLOWHIGHStudysiteStudysiteStudyareaStudyareaPermanent Very Likely 2.4 –ModeratePOSITIVEPermanent Will occur 3.6- HighIncidental Couldhappen0.9- Very lowPermanent Very Likely 2.9 –Moderate –POSITIVEZITHOLELE CONSULTING
134August 2010 884812 IMPACT SUMMARYThe environmental impacts for each alternative for the proposed extension with view ofclosure of the Boitshepi Waste Disposal Site have been summarised below. The followingbroad conclusions can be drawn from the impact assessment.• The current baseline environment in the study area is highly impacted upon from anenvironmental and social perspective;• The receiving environment is not of a sensitive nature with the exception of a wetlandsouth east of the site.• There are no sensitive features on site as most of the environmental aspects are alreadyhighly disturbed and therefore, the ecosystems found on site have adapted to theconditions of a waste disposal site.• The most significantly impacted baseline elements in the area are soils and landcapability, topography, terrestrial ecology, visual aesthetics, air quality, health andnuisance. These elements have already been highly impacted by the existing waste siteoperations.• During the construction phase for the extension of the site, the impacts will range fromVERY LOW to HIGH. The most significant impacts will be to air quality and health andnuisance the significance of these impacts is dependent on the preferred buffer zonealternative. Mitigation measures employed will adequately reduce the significance ofimpacts that may be sustained by the construction activities with the exception of airquality for the 0 metre buffer zone (alternative 1) as the specialist has indicated that thisis unacceptable.• During the operational phase, the impacts range from VERY LOW to HIGH. The mostsignificant impacts will be to visual aesthetics, air quality and health and nuisance.Mitigation measures together with the OMP for the site will reduce the significance of theimpacts during operations significantly;• It is important to note that all three alternatives are adjacent to each other and as suchhave the same or similar potential impacts. The alternative with the smaller footprintnaturally has a smaller impact than the other alternatives however the differences of thefootprint sizes is so small that it is hardly evident in the assessment with the exception ofsocial and health issues relating to the distance of the site from the surrounding landusers. As such the difference in ranking of the alternatives is insignificant with theexception of the 0 metre buffer (alternative 1).• From a size of impact perspective only the smaller footprint, that is Alternative 3, 100metre buffer zone would be the preferred alternative, however as mentioned thisalternative is no longer feasible as it would not accommodate the waste disposal needsof the area for the full period until the new waste disposal site is commissioned.Therefore the preferred alternative is Alternative 2 – the 50 metre buffer zone.ZITHOLELE CONSULTING
- Page 98 and 99: 83August 2010 884810.3 Duration Sca
- Page 100 and 101: 85August 2010 884811 IMPACT ASSESSM
- Page 102 and 103: 87August 2010 8848• Link the exte
- Page 104 and 105: 89August 2010 8848Type ofImpactCumu
- Page 106 and 107: 91August 2010 8848Figure 28: Piezom
- Page 108 and 109: 93August 2010 884811.1.4 Surface wa
- Page 110 and 111: 95August 2010 8848seepage of ground
- Page 112 and 113: 97August 2010 8848Table 29: Impact
- Page 114 and 115: 99August 2010 8848Table 30: Impact
- Page 116 and 117: 101August 2010 8848• As a minimum
- Page 118 and 119: 103August 2010 8848Table 32: Impact
- Page 120 and 121: 105August 2010 8848material. Not on
- Page 122 and 123: 107August 2010 8848Safety• Access
- Page 124 and 125: 109August 2010 8848Type ofImpactCum
- Page 126 and 127: 111August 2010 884811.2.2 Topograph
- Page 128 and 129: 113August 2010 8848It is understood
- Page 130 and 131: 115August 2010 8848Additional Impac
- Page 132 and 133: 117August 2010 8848Cumulative Impac
- Page 134 and 135: 119August 2010 8848Additional Impac
- Page 136 and 137: 121August 2010 8848TrafficDuring th
- Page 138 and 139: 123August 2010 884811.3 Decommissio
- Page 140 and 141: 125August 2010 884811.3.3 Groundwat
- Page 142 and 143: 127August 2010 884811.3.5 Geotechni
- Page 144 and 145: 129August 2010 8848Additional Impac
- Page 146 and 147: 131August 2010 8848Additional Impac
- Page 150 and 151: 135August 2010 884812.1.1 Preferred
- Page 152: August 2010 137884813 CONCLUSION AN
134August 2010 884812 IMPACT SUMMARYThe environmental impacts <strong>for</strong> each alternative <strong>for</strong> the proposed extension with view ofclosure of the <strong>Boitshepi</strong> Waste Disposal <strong>Site</strong> have been summarised below. The followingbroad <strong>co</strong>nclusions can be drawn from the impact assessment.• The current baseline environment in the study area is highly impacted upon from anenvironmental and social perspective;• The receiving environment is not of a sensitive nature with the exception of a wetlandsouth east of the site.• There are no sensitive features on site as most of the environmental aspects are alreadyhighly disturbed and there<strong>for</strong>e, the e<strong>co</strong>systems found on site have adapted to the<strong>co</strong>nditions of a waste disposal site.• The most significantly impacted baseline elements in the area are soils and landcapability, topography, terrestrial e<strong>co</strong>logy, visual aesthetics, air quality, health andnuisance. These elements have already been highly impacted by the existing waste siteoperations.• During the <strong>co</strong>nstruction phase <strong>for</strong> the extension of the site, the impacts will range fromVERY LOW to HIGH. The most significant impacts will be to air quality and health andnuisance the significance of these impacts is dependent on the preferred buffer zonealternative. Mitigation measures employed will adequately reduce the significance ofimpacts that may be sustained by the <strong>co</strong>nstruction activities with the exception of airquality <strong>for</strong> the 0 metre buffer zone (alternative 1) as the specialist has indicated that thisis unacceptable.• During the operational phase, the impacts range from VERY LOW to HIGH. The mostsignificant impacts will be to visual aesthetics, air quality and health and nuisance.Mitigation measures together with the OMP <strong>for</strong> the site will reduce the significance of theimpacts during operations significantly;• It is important to note that all three alternatives are adjacent to each other and as suchhave the same or similar potential impacts. The alternative with the smaller footprintnaturally has a smaller impact than the other alternatives however the differences of thefootprint sizes is so small that it is hardly evident in the assessment with the exception ofsocial and health issues relating to the distance of the site from the surrounding landusers. As such the difference in ranking of the alternatives is insignificant with theexception of the 0 metre buffer (alternative 1).• From a size of impact perspective only the smaller footprint, that is Alternative 3, 100metre buffer zone would be the preferred alternative, however as mentioned thisalternative is no longer feasible as it would not ac<strong>co</strong>mmodate the waste disposal needsof the area <strong>for</strong> the full period until the new waste disposal site is <strong>co</strong>mmissioned.There<strong>for</strong>e the preferred alternative is Alternative 2 – the 50 metre buffer zone.ZITHOLELE CONSULTING