European Railway Agency<br />
Collection <strong>of</strong> examples <strong>of</strong> risk assessments and <strong>of</strong> some possible tools<br />
supporting the <strong>CSM</strong> Regulation<br />
<br />
(b) the <strong>CSM</strong> does not cover the phases "11", "12" and "14" <strong>of</strong> the system life-cycle:<br />
(1) the phases "11" and "12" are respectively related to the "operation and<br />
maintenance" and "per<strong>for</strong>mance monitoring" <strong>of</strong> the system after its acceptance<br />
based on the <strong>CSM</strong>. These two phases are covered by the RU and IM safety<br />
management system (SMS) – (See BOX 4 in Figure 5). However, if during the<br />
operation, the maintenance or the per<strong>for</strong>mance monitoring <strong>of</strong> the system it appears<br />
necessary to modify and retr<strong>of</strong>it the system (Phase 13 in Figure 5), whereas it is<br />
already in operation, the <strong>CSM</strong> is applied again on the new required changes in<br />
compliance with the Article 2. There<strong>for</strong>e, if the change is significant:<br />
(i) the risk management and risk assessment processes in the <strong>CSM</strong> are applied<br />
to these new changes;<br />
(ii) an acceptance is needed <strong>for</strong> these new changes in compliance with Article 6;<br />
(2) the "de-commissioning and disposal" <strong>of</strong> a system already in operation (Phase 14)<br />
could also be considered as a significant change, and there<strong>for</strong>e, the <strong>CSM</strong> could be<br />
applied again in compliance with the Article 2 <strong>for</strong> the phase 14 in Figure 5<br />
For more in<strong>for</strong>mation about the scope <strong>of</strong> each phase or activity in the CENELEC V-Cycle<br />
recalled in Figure 5, refer to section § 6. <strong>of</strong> the EN 50 126-1 standard {Ref. 8}<br />
2.1.2. The system definition should address at least the following issues:<br />
(a) system objective, e.g. intended purpose;<br />
(b) system functions and elements, where relevant (including e.g. human, technical<br />
and operational elements);<br />
(c) system boundary including other interacting systems;<br />
(d) physical (i.e. interacting systems) and functional (i.e. functional input and output)<br />
interfaces;<br />
(e) system environment (e.g. energy and thermal flow, shocks, vibrations,<br />
electromagnetic interference, operational use);<br />
(f) existing safety measures and, after iterations, definition <strong>of</strong> the safety requirements<br />
identified by the risk assessment process;<br />
(g) assumptions which shall determine the limits <strong>for</strong> the risk assessment.<br />
[G 1] Additional explanation is not judged necessary.<br />
2.1.3. A hazard identification shall be carried out on the defined system, according to section<br />
2.2.<br />
[G 1] Additional explanation is not judged necessary.<br />
2.1.4. The risk acceptability <strong>of</strong> the system under assessment shall be evaluated by using one<br />
or more <strong>of</strong> the following risk acceptance principles:<br />
(a) the application <strong>of</strong> codes <strong>of</strong> practice (section 2.3);<br />
(b) a comparison with similar systems (section 2.4);<br />
(c) an explicit risk estimation (section 2.5).<br />
In accordance with the general principle referred to in section 1.1.5, the assessment<br />
body shall refrain from imposing the risk acceptance principle to be used by the<br />
proposer.<br />
<br />
Reference: <strong>ERA</strong>/GUI/02-2008/SAF Version: 1.1 Page 35 <strong>of</strong> 105<br />
File Name: Collection_<strong>of</strong>_RA_Ex_and_some_tools_<strong>for</strong>_<strong>CSM</strong>_V1.1.doc<br />
European Railway Agency ● Boulevard Harpignies, 160 ● BP 20392 ● F-59307 Valenciennes Cedex ● France ● Tel. +33 (0)3 27 09 65 00 ● Fax +33 (0)3 27 33 40 65 ● http://www.era.europa.eu