European Railway Agency<br />
Collection <strong>of</strong> examples <strong>of</strong> risk assessments and <strong>of</strong> some possible tools<br />
supporting the <strong>CSM</strong> Regulation<br />
<br />
ANNEX I - EXPLANATION OF THE PROCESS<br />
IN THE <strong>CSM</strong> REGULATION<br />
1. GEN<strong>ERA</strong>L PRINCIPLES APPLICABLE TO THE RISK<br />
MANAGEMENT PROCESS<br />
1.1. General principles and obligations<br />
1.1.1. The risk management process covered by this Regulation shall start from a definition <strong>of</strong><br />
the system under assessment and comprise the following activities:<br />
(a) the risk assessment process, which shall identify the hazards, the risks, the<br />
associated safety measures and the resulting safety requirements to be fulfilled by<br />
the system under assessment;<br />
(b) demonstration <strong>of</strong> the compliance <strong>of</strong> the system with the identified safety<br />
requirements and;<br />
(c) management <strong>of</strong> all identified hazards and the associated safety measures.<br />
This risk management process is iterative and is depicted in the diagram <strong>of</strong> the<br />
Appendix (<strong>of</strong> the <strong>CSM</strong> Regulation). The process ends when the compliance <strong>of</strong> the system<br />
with all safety requirements necessary to accept the risks linked to the identified<br />
hazards is demonstrated.<br />
[G 1] The risk management framework <strong>for</strong> the <strong>CSM</strong> and the associated risk assessment process<br />
are illustrated in Figure 1. When judged necessary, each box/activity <strong>of</strong> this figure is<br />
described further in a specific section <strong>of</strong> this document.<br />
[G 2] CENELEC advises that the risk management and risk assessment processes are described<br />
in a safety plan. But if this is not convenient <strong>for</strong> the project, the associated description can<br />
be included in any other relevant document. Refer to section 1.1.6.<br />
[G 3] The risk assessment process starts from a preliminary system definition. During the project<br />
development, the preliminary system definition is updated progressively and is replaced by<br />
the system definition. If there is no preliminary system definition, the <strong>for</strong>mal system definition<br />
is used <strong>for</strong> per<strong>for</strong>ming the risk assessment. But then, it is useful that all the actors<br />
concerned by the significant change meet at the beginning <strong>of</strong> the project in order:<br />
(a) to agree on the overall system principles, system functions, etc. In principle this could<br />
be described in a preliminary system definition;<br />
(b) to agree on the project organisation;<br />
(c) to agree on the sharing <strong>of</strong> the roles and responsibilities between the different actors<br />
already involved, including the NSA, NOBO and ISA where relevant.<br />
Such a co-ordination, during the preliminary system definition <strong>for</strong> example, provides the opportunity<br />
to the proposer, the sub-contractors, NSA, NOBO and ISA, if relevant, to agree at<br />
an early stage regarding the codes <strong>of</strong> practice or reference systems that are acceptable to<br />
use within the project<br />
<br />
Reference: <strong>ERA</strong>/GUI/02-2008/SAF Version: 1.1 Page 22 <strong>of</strong> 105<br />