12.5 Financial <strong>Report</strong>ing<br />

A breakdown of the program finances is presented in Table 12-5.<br />

Table 12-5: Summary of Customer Load Response <strong>Program</strong> Finances<br />

IQ<br />

($1,000)<br />

PYTD<br />

($1,000)<br />

CPITD<br />

($1,000)<br />

EDC Incentives to Participants $0 $15 $15<br />

EOC Incentives to Trade Allies<br />

Subtotal EDC Incentive Costs $0 $15 $15<br />

Design & Development $4 $88<br />

Administration 111 $6 $41 $78<br />

Management' 21<br />

Marketing' 31 $0 $1 $2<br />

Technical Assistance $5 $18 $41<br />

Subtotal EDC Implementation Costs $11 $63 $209<br />

EDC Evaluation Costs $2 $5 $14<br />

SWE Audit Costs<br />

Total EDC Costs 1 ' 11 $13 $83 $238<br />

Participant Costs' 51<br />

Total TRC Costs 161 $13 $68 $238<br />

Total Lifetime Energy Benefits<br />

Total Lifetime Capacity Benefits<br />

Total TRC Benefits" 1<br />

N/A<br />

TRC Ratio' 81<br />

N/A<br />

NOTES<br />

Per PUC direction, TRC inputs and calculations are required in the <strong>Annual</strong> <strong>Report</strong> only and should comply with the 2011 Total Resource Cost Test<br />

Order approved July 28, 2011. Please see the "<strong>Report</strong> Definitions" section of this report for more details.<br />

[11 Includes the administrative CSP (rebate processing), tracking system, and general administration and clerical cost.<br />

[2| fndudes EDC program management, CSP program management, general management oversf'gfit, and major accounts.<br />

[3|. Includes the marketing CSP and marketing costs by program CSPs.<br />

HrPor the 2011 Total Resource Cost Test Order, the Total EDC Costs refer to EDC incurred expenses only.<br />

|5| F>er the 2011 Total Resource Cost Test Order, the net Participant Costs are the costs for the end-use customer.<br />

[6| Total TRC Costs includes EDC Evaluation Costs, Total EDC Implementation Costs and Participant Cosls.<br />

[7| Total TRC Benefits equals the sum of Total Lifetime Energy Benefils and Total Lifetime Capacity Benefits. Based upon verified gross kWh and kW<br />

savings. Benefits include: avoided supply costs, including the reduction in costs of electric energy, generation, transmission, and distribution<br />

capiicity, and natural gas valued at marginal cost for periods when there is a load reduction.<br />

[10] TRC Ratio equals Total TRC Benefits divided.by Total TRC Costs.<br />

<strong>West</strong> <strong>Penn</strong> <strong>Power</strong> Company | Page 84