2.5 Financial <strong>Report</strong>ing<br />
A breakdown of the program finances is presented in Table 2-5.<br />
Table 2-5: Summary of Residential Appliance Turn-In <strong>Program</strong> Finances<br />
IQ<br />
($1,000)<br />
PYTD<br />
($1,000)<br />
CPITD<br />
($1,000)<br />
EDC Incentives to Participants $102 $221 $417<br />
EDC Incentives to Trade Allies<br />
Subtotal EDC Incentive Costs $102 $221 $417<br />
Design & Development<br />
Administration' 11 ($18) $28 $128<br />
Management 121<br />
Marketing' 3 ' $67 $276 $831<br />
Technical Assistance $165 $492 $943<br />
Subtotal EDC Implementation Costs $213 $796 $1,902<br />
EDC Evaluation Costs $5 $23 $84<br />
SWE Audit Costs<br />
Total EDC Costs 141 $321 $1,040 $2,403<br />
Participant Costs' 5 ' $102 $221 $417<br />
Total TRC Costs' 61 $321 $1,040 $2,403<br />
Total Lifetime Energy Benefits $132 $1,893 $3,255<br />
Total Lifetime Capacity Benefits $9 $131 $262<br />
Total TRC Benefits' 71 N/A $2,024 $3,516<br />
TRC Ratio E8i N/A 1.95 1.46<br />
NOTES<br />
Par PUCdirection, TRC inputs ond calculations are required in the <strong>Annual</strong> <strong>Report</strong> only and should comply with the 2011 Total Resource Cost Test<br />
Order approved July 28, 2011. Please see the "<strong>Report</strong> Definitions" section of this repon for more details.<br />
[1] Includes the administrative'CSP (rebiite processing), tracking system, and general administration and clerical.cost.<br />
[2j Includes EOC program management, CSP program management, general management oversight, and major accounts.<br />
[3] Includes the marketing CSP and marketing costs by program CSPs.<br />
U] Per the 2011 Totai Resource Cost Test Order, the Total EDC Costs refer to EDC incurred expenses only.<br />
[5] Per the 2011 Total Resource Cost Test Order, the net Participant Costs are die costs for the end-use cuslomer.<br />
(6] Total TRC Costs includes EDC Evaluation.Costs, Total EDC Implementation Costs and Participant Costs.<br />
[7] Total TRC Benefits equals the sum of Total Lifetime Energy Benefits and Total Lifetime Capacity Benefits. Based upon verified gross kWh and kW<br />
savings. Benefils include; avoided supply cosls, including the reduction in costs of electnc energy, generation, transmission, and distribution<br />
capacity, and natural gas valued at marginal cost for periods when there is a load reduction.<br />
[10] TRC Ratio equals Total TRCBenefits divided by Total TRC Costs.<br />