10.06.2015 Views

A NEW PRIVATE HOSPITAL FOR WAIKATO

A NEW PRIVATE HOSPITAL FOR WAIKATO

A NEW PRIVATE HOSPITAL FOR WAIKATO

SHOW MORE
SHOW LESS

Create successful ePaper yourself

Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.

If tests show that they are, one solution would<br />

be to excavate a 6m deep trench around the<br />

boundary and lower pre-cast concrete panels<br />

120mm thick into the trench, grouting the<br />

joints together.”<br />

The design team consisted of Blair<br />

Currie and Alan Park from Holmes, and Paul<br />

Overdevest and Richard Hill from Chow:Hill<br />

Architects Ltd. Beca Carter Hollings & Ferner<br />

Ltd concentrated on the building services.<br />

They all became strong advocates of using<br />

structural steel for this project.<br />

“Key to the success of the project,” says<br />

Richard Hill, “was the need to take advantage<br />

of good autumn weather and complete a<br />

structure that was weatherproof. This was<br />

essential for the intense and complex fit out<br />

that a hospital requires. Speed was of the<br />

essence, and the off-site fabrication done by<br />

Auckland Steel Limited ensured high quality<br />

control in a factory environment. Deliveries<br />

to the site were programmed to maintain<br />

maximum momentum for erection and<br />

enclosure. And the swift integration of the<br />

Corus-supplied Comflor 210 steel decking<br />

system kept up the tempo.<br />

Far left: An artist’s impression.<br />

Left top: The new hospital will occupy a high profile<br />

position at the corner of State Highway 1 and<br />

Ohaupo Road.<br />

Left: Comflor 210 was selected for the composite<br />

steel decking system because of its spanning<br />

capability.<br />

Below: Auckland Steel fabricated and erected the<br />

structural steel.<br />

The isometric drawing<br />

shows the complexity of the<br />

structure but at the end of the<br />

day only 240 tonnes of structural<br />

steel were used.<br />

“From an architectural<br />

perspective,” adds Richard, “the steel<br />

frame enabled us to design a building<br />

whose low structural volume made minimum<br />

impact on the space. It also afforded<br />

tremendous freedom for the installation of<br />

services and provided something crucial<br />

to hospital operations: adaptability. The<br />

healthcare service delivery processes in<br />

hospitals are continuously subject to change;<br />

invariably these changes are technology<br />

driven. Steel affords Braemar Hospital a high<br />

degree of latent future-proofing.”<br />

There was another reason that steel was<br />

preferred; its lightness meant that foundation<br />

settlement issues were mitigated. Blair Currie<br />

again: “Designing for fast erection, we really<br />

had to forward plan exactly how it was all<br />

going to go together: Universal Columns<br />

were fabricated to full height and arrived on<br />

site ready to receive floor beams via bolted<br />

connections at economical locations. This<br />

allowed the structural steel to be erected<br />

with limited site welding. The building’s<br />

lateral bracing is via a ductile structural steel<br />

frame system in one direction and ductile<br />

eccentrically braced K-frames in the other<br />

direction. To maximise the ceiling cavity<br />

space while keeping the floor to floor height<br />

as small as possible, we designed the steel<br />

floor beams to be encased in the floor slab.<br />

Comflor 210 was specified over Comflor 80<br />

because of its greater spanning capability<br />

from beam to beam. Large areas of clear span<br />

floor space were dictated by the hospital’s<br />

operational needs.”<br />

As yet there is no rating system in<br />

New Zealand that can gauge the sustainability<br />

of the hospital’s construction, but Chow:Hill<br />

Architects have engaged e Cubed Building<br />

Workshop Ltd to compare it with models<br />

in Australia. From the initial design stage,<br />

building form, orientation and detailing<br />

responded to ESD (Environmentally<br />

Sustainable Design) principles. On site, skips<br />

are used to sort and manage waste materials<br />

such as paper, plastic and timber. Suffice it to<br />

say that this complex, purpose-built hospital<br />

has been designed with an eye on achieving a<br />

good sustainability rating.<br />

scnz 7

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!