10.06.2015 Views

A NEW PRIVATE HOSPITAL FOR WAIKATO

A NEW PRIVATE HOSPITAL FOR WAIKATO

A NEW PRIVATE HOSPITAL FOR WAIKATO

SHOW MORE
SHOW LESS

You also want an ePaper? Increase the reach of your titles

YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.

A <strong>NEW</strong> <strong>PRIVATE</strong><br />

<strong>HOSPITAL</strong> <strong>FOR</strong> <strong>WAIKATO</strong><br />

Work is well advanced on the<br />

construction of a new private hospital for<br />

Waikato; Braemar Hospital will relocate<br />

from Tainui Street in Hamilton to Ohaupo<br />

Road, Gower Park, during the Easter<br />

holidays of 2009. The new premises will<br />

be almost double the area of the existing<br />

premises, enhancing the hospital’s ability<br />

to meet the increasing needs of patients<br />

from as far afield as Taranaki and the<br />

Bay of Plenty. Complementing Waikato’s<br />

leading surgical hospital is Braemar Day<br />

Hospital in Knox Street, Hamilton, which<br />

provides an extensive range of surgical<br />

and medical procedures for patients on a<br />

same day basis.<br />

The structural consultants on the project<br />

are Holmes Consulting Group, and Project<br />

Engineer Blair Currie took cognizance of the<br />

stringent structural demands of modern health<br />

facilities, in particular the question of building<br />

vibration. “Modern engineering practice<br />

enables us to deal thoroughly with vibration,”<br />

says Blair. “All of the operating theatres are at<br />

ground level, and we needed to be satisfied<br />

that sensitive medical equipment would not be<br />

affected by vibrations caused by road traffic.<br />

In view of the future widening of adjacent<br />

Kahikatea Drive and Ohaupo Road, Tonkin<br />

and Taylor was engaged to provide specialist<br />

consulting services, assess ground vibration<br />

and see if mitigation measures are required.<br />

6 scnz


If tests show that they are, one solution would<br />

be to excavate a 6m deep trench around the<br />

boundary and lower pre-cast concrete panels<br />

120mm thick into the trench, grouting the<br />

joints together.”<br />

The design team consisted of Blair<br />

Currie and Alan Park from Holmes, and Paul<br />

Overdevest and Richard Hill from Chow:Hill<br />

Architects Ltd. Beca Carter Hollings & Ferner<br />

Ltd concentrated on the building services.<br />

They all became strong advocates of using<br />

structural steel for this project.<br />

“Key to the success of the project,” says<br />

Richard Hill, “was the need to take advantage<br />

of good autumn weather and complete a<br />

structure that was weatherproof. This was<br />

essential for the intense and complex fit out<br />

that a hospital requires. Speed was of the<br />

essence, and the off-site fabrication done by<br />

Auckland Steel Limited ensured high quality<br />

control in a factory environment. Deliveries<br />

to the site were programmed to maintain<br />

maximum momentum for erection and<br />

enclosure. And the swift integration of the<br />

Corus-supplied Comflor 210 steel decking<br />

system kept up the tempo.<br />

Far left: An artist’s impression.<br />

Left top: The new hospital will occupy a high profile<br />

position at the corner of State Highway 1 and<br />

Ohaupo Road.<br />

Left: Comflor 210 was selected for the composite<br />

steel decking system because of its spanning<br />

capability.<br />

Below: Auckland Steel fabricated and erected the<br />

structural steel.<br />

The isometric drawing<br />

shows the complexity of the<br />

structure but at the end of the<br />

day only 240 tonnes of structural<br />

steel were used.<br />

“From an architectural<br />

perspective,” adds Richard, “the steel<br />

frame enabled us to design a building<br />

whose low structural volume made minimum<br />

impact on the space. It also afforded<br />

tremendous freedom for the installation of<br />

services and provided something crucial<br />

to hospital operations: adaptability. The<br />

healthcare service delivery processes in<br />

hospitals are continuously subject to change;<br />

invariably these changes are technology<br />

driven. Steel affords Braemar Hospital a high<br />

degree of latent future-proofing.”<br />

There was another reason that steel was<br />

preferred; its lightness meant that foundation<br />

settlement issues were mitigated. Blair Currie<br />

again: “Designing for fast erection, we really<br />

had to forward plan exactly how it was all<br />

going to go together: Universal Columns<br />

were fabricated to full height and arrived on<br />

site ready to receive floor beams via bolted<br />

connections at economical locations. This<br />

allowed the structural steel to be erected<br />

with limited site welding. The building’s<br />

lateral bracing is via a ductile structural steel<br />

frame system in one direction and ductile<br />

eccentrically braced K-frames in the other<br />

direction. To maximise the ceiling cavity<br />

space while keeping the floor to floor height<br />

as small as possible, we designed the steel<br />

floor beams to be encased in the floor slab.<br />

Comflor 210 was specified over Comflor 80<br />

because of its greater spanning capability<br />

from beam to beam. Large areas of clear span<br />

floor space were dictated by the hospital’s<br />

operational needs.”<br />

As yet there is no rating system in<br />

New Zealand that can gauge the sustainability<br />

of the hospital’s construction, but Chow:Hill<br />

Architects have engaged e Cubed Building<br />

Workshop Ltd to compare it with models<br />

in Australia. From the initial design stage,<br />

building form, orientation and detailing<br />

responded to ESD (Environmentally<br />

Sustainable Design) principles. On site, skips<br />

are used to sort and manage waste materials<br />

such as paper, plastic and timber. Suffice it to<br />

say that this complex, purpose-built hospital<br />

has been designed with an eye on achieving a<br />

good sustainability rating.<br />

scnz 7

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!