05.06.2015 Views

2005 - Putzmeister

2005 - Putzmeister

2005 - Putzmeister

SHOW MORE
SHOW LESS

Create successful ePaper yourself

Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.

Special concrete<br />

The ZX delivery line in the lattice tower of the<br />

crane runs to the sliding formwork<br />

New platinum mine<br />

in South Africa:<br />

concrete placement on<br />

109 m high pit frame<br />

58<br />

60<br />

Platinum and its costly mining<br />

Platinum is currently almost twice as expensive<br />

as gold, and significantly harder.<br />

World-wide, only approximately 200 tons<br />

of this precious metal are mined each year,<br />

with 90 % of the production stemming<br />

from South African mines. Platinum is<br />

required, for example, for the production<br />

of catalytic converters in the automotive<br />

industry, in dental medicine, in space travel<br />

and for the production of jewellery. To<br />

acquire 15 grams of pure platinum, up to<br />

five tons of stone must be exploded, conveyed,<br />

pulverised and chemically treated.<br />

The metal is prepared above ground in<br />

high security areas. The platinum discovery<br />

sites around the Rustenburg region<br />

were mined in a strip of approximately<br />

400 km. Here, 27,000 miners work under<br />

the hardest of conditions at depths of<br />

approximately 2,000 m. With an air humidity<br />

of 90 %, there are temperatures at this<br />

depth of up to 50 °C. The platinum reserves<br />

were discovered in 1924 by the German<br />

geologist Hans Merensky. The land rights<br />

in Rustenburg belong to the Bafokeng<br />

clan, to which the IMPALA PLATINUM<br />

group assigns 5 % of its profit each year<br />

as payment for rights of use.<br />

In Rustenburg in South Africa, the<br />

IMPALA PLATINUM LTD mining company<br />

is investing significant sums of<br />

money in the mining of the precious metal<br />

platinum. In the meantime, work is being<br />

carried out on the completion of the 16th<br />

shaft. Already before commissioning,<br />

<strong>Putzmeister</strong> pumps were used here,<br />

although not for pumping residues from<br />

the ore dressing (tailings), but for highrise<br />

concrete pumping.<br />

In addition to constructing the shaft and<br />

connecting a new mining field to the existing<br />

mining fields, the tapping of a new<br />

mine also includes the installation of a pit<br />

frame. At its tip, the pit rope, to which the<br />

haulage skips for bringing up the mined<br />

material and the baskets for transporting<br />

the miners are attached, runs over a large<br />

pulley. In order to move the largest loads<br />

possible, or to achieve short circulation<br />

times, the pit frame must be of a certain<br />

height. At the 16th pit of IMPALA in<br />

Rustenburg, the tower is certainly not too<br />

small: with a base of 21 m x 20 m and a<br />

pulley at the record height of 109 m, the<br />

new pit is designed for extraordinary conveying<br />

capacities.<br />

A sliding formwork adapts to different<br />

wall thicknesses<br />

The work on the pit frame with several<br />

integrated concrete decks began with the<br />

pit brow at a depth of approximately 25 m.<br />

The main contractor assigned with the<br />

construction work is RENNIKS CON-<br />

STRUCTION. The project, costing around<br />

80 million rand (approximately EUR 10<br />

million), also includes the construction of<br />

the main ventilation shaft, several access<br />

tunnels, the foundation of the conveying<br />

system and various digging works.<br />

Completion is planned for May 2006.<br />

The walls of the pit frame, which are<br />

between 0.95 m and 0.55 m thick, were<br />

constructed using the sliding formwork<br />

procedure. Here, the formwork adapted<br />

22<br />

PM 3723 GB<br />

Truck mixers load the BSA 1408 E with a special type of concrete<br />

59<br />

In total, approximately 21,000 m 3 of concrete are processed<br />

at the pit frame<br />

62<br />

The PM gate valves are activated via a hydraulic circuit<br />

in the stationary pump<br />

61<br />

flexibly to the wall diameter which becomes<br />

thinner as you move upwards. The contract<br />

for concrete delivery was awarded to the<br />

specialists from MURRAY & ROBERTS<br />

CONSTRUCTION, who, incidentally, have<br />

been working with <strong>Putzmeister</strong> pumps for<br />

many years.<br />

In total, 7,000 m 3 of concrete was required<br />

to construct the carcass of the pit frame.<br />

The concrete used had a specially developed<br />

mixture breakdown. It contained,<br />

amongst other things, aggregate with a<br />

maximum particle size of 19 mm (of which<br />

50 % was slag), drift sand, stone dust and<br />

various concrete additives. The further<br />

details of the concrete composition are<br />

considered to be confidential. In other construction<br />

measures within the project, a<br />

further 14,000 m 3 of concrete was placed.<br />

The "chief operator" has full control of his <strong>Putzmeister</strong><br />

stationary pump. On the left you can see the cable<br />

remote control of the BSA 1408 E<br />

63<br />

BSA and rotary distributors<br />

work as a team<br />

The free-pumping material was delivered<br />

by MURRAY & ROBERTS with a<br />

<strong>Putzmeister</strong> BSA 1408 E via a ZX high<br />

pressure line, which was mounted on a<br />

tower crane. With a hydraulically activated<br />

gate valve, the concrete flow in the pipeline<br />

could be interrupted, for example for cleaning<br />

operations on the stationary pump.<br />

A second BSA was kept ready as a standby<br />

pump. The crane was set up about three<br />

metres from the carcass and mounted with<br />

cross-beams in the continuously rising<br />

structure. The upper end of the riser was<br />

connected with a flexible hose (DN 125),<br />

so that a connection to the RV 10 rotary<br />

distributor on the sliding formwork could<br />

be established at any time in the 90 ° delivery<br />

line bend. Incidentally, this too was a<br />

device manufactured by the <strong>Putzmeister</strong><br />

subsidiary in South Africa. In the interest<br />

of the most unrestricted slewing circle<br />

possible, the construction company elevated<br />

the four support legs of the deck distributor<br />

by approximately 5 m.<br />

Service technicians available at all times<br />

During the carcass construction phase,<br />

employees of <strong>Putzmeister</strong> South Africa<br />

were on site at least once a week. They<br />

trained the concrete pump operators, gave<br />

tips on cleaning and maintenance of the<br />

BSA and clarified any service questions.<br />

In addition, the PMSA emergency service<br />

was also available 24/7 via a hotline.<br />

A service technician could have been on<br />

site within 2 hours, if required.<br />

As the construction progressed, additional<br />

pipe sections were used between the riser<br />

and the delivery hose. On average, the pit<br />

frame grew by 4.5 m each day, with the<br />

best daily performance being 6 m. At<br />

109 m, the BSA 1408-E reached its highest<br />

pump height on the new IMPALA pit.<br />

23<br />

PM 3723 GB

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!