Large construction site<br />

46<br />

Up to 1,500 workers are employed on the<br />

vast site. In peak times, 60 cranes lift the<br />

various loads to the different sections. In a<br />

separate production facility, prefabricated<br />

steel parts are supplied, and the necessary<br />

welding and anticorrosion work is carried<br />

out on site.<br />

Two concrete pump centres ensure<br />

smooth placement of 270,000 m 3 of<br />

concrete<br />

In order to guarantee self-supply with concrete,<br />

two mixers have been set up on the<br />

premises. A MAX BÖGL owned system<br />

delivers the Rohbau consortium with<br />

approximately 250,000 m 3 of concrete,<br />

while the concrete produced by the other<br />

mixer is required for the construction of<br />

the multi-storey car park (approximately<br />

20,000 m 3 ) and also covers the peaks in<br />

demand from the Rohbau consortium. The<br />

mixers also produce self-compressing concretes,<br />

in addition to standard concrete with<br />

strength class C40/50.<br />

construction of the interior, the exposed<br />

concrete, with its natural surface structure,<br />

plays an important role and must be pumped<br />

without interruption. To do this, BRM uses<br />

all sizes of truck-mounted concrete pumps<br />

– from a refurbishing mobile through to a<br />

large boom pump. TB Göppingen or BP<br />

Schwaben's machines are also scheduled.<br />

For the concrete work around the multistorey<br />

car park, pump service provider<br />

SAUSSELE (Besigheim), which belongs to<br />

CEMEX, controls the use of concrete<br />

pumps. Here too, it is usually the maintained<br />

machines from their own fleet that are<br />

set up on both sides of the motorway. With<br />

increasing completion of the interior of the<br />

car park levels, the flexible "low building<br />

masters" with 24 m booms with four folds<br />

are most in demand. Other concrete pump<br />

service providers, such as UNION-BETON<br />

(Ludwigsburg) and GODEL-BETON<br />

(Stuttgart) also provide their machines as<br />

required.<br />

A PM M 36 truck-mounted concrete pump filling<br />

a wall formwork<br />

48<br />

According to information from project<br />

manager Dipl.Ing. Michael Frey, the coordination<br />

with the central pump scheduling takes<br />

place fairly smoothly, taking into consideration<br />

the large concrete volumes and the<br />

number of contract sections. He considers<br />

the fact that his consortium only has to coordinate<br />

with one concrete pump schedule as<br />

a great advantage: "Of our ten foremen, each<br />

one works with his people on a separate construction<br />

section.<br />

Often they all need concrete in the afternoon.<br />

Central scheduling is therefore very helpful<br />

if our concrete mixer is constantly fully<br />

loaded and we want to use the pumps with<br />

the required boom reach at the same time at<br />

the individual sections."<br />

Project manager Dipl.Ing. Michael Frey<br />

49<br />

The concrete pump scheduling for the<br />

MAX BÖGL and LEONHARD WEISS<br />

construction sections is carried out by<br />

Betonpumpendienst Rhein-Main (BRM),<br />

Lorsch. The range of concrete work is considerable:<br />

long strip foundations, powerful<br />

bottom plates, floors, girders and circular<br />

supports, external walls and internal<br />

partitions, etc. Above all, in the<br />

47<br />

This M 36 used by the concrete pump service provider<br />

BRM is today encountered on several sections of the<br />

vast trade fair construction site<br />

50<br />

BRM operator<br />

Werner Mann. He<br />

has been operating<br />

51<br />

concrete pumps for<br />

13 years<br />

Our picture shows one of BP Schwaben's BSF 52.16 H<br />

pumps on field 2 during the placement of 280 m 3 of<br />

concrete. As soon as the bottom plate is completely concreted,<br />

the machine is moved by a few hundred metres,<br />

in order to pump 400 m 3 of concrete into a ceiling formwork.<br />

18<br />

PM 3723 GB<br />

A BSF 28.16 H with refurbishment equipment<br />

19<br />

PM 3723 GB

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!