Republic of Indonesia<br />

Ministry of Public Works<br />

Directorate General of<br />

Highway<br />

T H E E A S T E R N I N D O N E S I A<br />

N A T I O N A L R O A D I M P R O V E M E N T<br />

P R O J E C T ( E I N R I P )<br />

AIP LOAN NO: AIPRD - L002<br />

ANNUAL PROGRESS REPORT<br />

2010<br />

PROJECT MANAGEMENT UNIT<br />

(PMU-EINRIP)


In accordance with Section III.A.3 (a) of Schedule 2 of the AIPRD-L002 loan agreement for<br />

Eastern Indonesia National Road Improvement Project (EINRIP), this report, prepared by<br />

Project Management Unit (PMU-EINRIP) is the 2010 Annual Progress Report.<br />

The report describes the progress achieved in various phases of project implementation during<br />

the year 2010; and presents a general plan for activities for the year 2011.<br />

Any <strong>com</strong>ments and feedback should be directed to:<br />

PMU EINRIP<br />

Direktorat Bina Program<br />

Direktorat Jenderal Bina Marga<br />

Jl. Pattimura No. 20, Kebayoran Baru<br />

Jakarta Selatan<br />

Email: pmu.einrip@yahoo.<strong>com</strong>


EINRIP 2010 Annual Progress Report<br />

1 TABLE OF CONTENTS<br />

Abbreviations<br />

EXECUTIVE SUMMARY ......................................................................................................... 1<br />

1. Introduction ....................................................................................................................... 5<br />

1.1. Background ............................................................................................................... 5<br />

1.2. EINRIP Loan AIPRD L-002 ....................................................................................... 5<br />

1.3. Loan categories ......................................................................................................... 6<br />

1.4. Project Planning, Administration and Management ................................................. 11<br />

1.5. Terminology for Annual Works Program (AWP) ...................................................... 13<br />

2. Project Preparation (Feasibility Studies, Investigations and Design) ......................... 14<br />

2.1. Project Preparation Consultants (PPC) ................................................................... 14<br />

2.2. Documentation <strong>com</strong>pletion under PPC .................................................................... 14<br />

3. Project Preparation (Environmental & Social Studies) ................................................ 16<br />

3.1. Extent of ESS Studies in EINRIP............................................................................. 16<br />

3.2. Summary Progress on ESS for 2010 ....................................................................... 17<br />

4. Procurement of Civil Works ........................................................................................... 23<br />

4.1. EINRIP Procurement Activities ................................................................................ 23<br />

4.2. Procurement Activities in 2010 ................................................................................ 24<br />

4.3. Procurement Plans .................................................................................................. 27<br />

5. Implementation of Civil Works (Construction) ............................................................. 29<br />

5.1. Summary of On-going Contracts ............................................................................. 30<br />

6. Procurement of Goods ................................................................................................... 31<br />

6.1. Contract Data for Goods Contract ESB-02 .............................................................. 31<br />

7. Financial Summary ......................................................................................................... 32<br />

7.1. Status of Loan Withdrawals, Payments and Disbursements .................................... 32<br />

7.2. Analysis of Planned Vs Actual Expenditure ............................................................. 34<br />

7.3. Foreign Exchange Rate Variation ............................................................................ 35<br />

7.4. Impact of Exchange Rate on Total Project Cost ...................................................... 35<br />

8. Implementation Support Consultants ........................................................................... 36<br />

8.1. Project Management Support Consultant (PMSC) .................................................. 36<br />

8.2. Regional Supervision Consultants (RSC) ................................................................ 37<br />

8.3. Project Advisory Services (PAS) Consultants .......................................................... 38<br />

9. Technical and Financial Audits in 2010 ......................................................................... 40<br />

9.1. Technical and Financial Audit Consultants .............................................................. 40<br />

9.2. Key issues identified in TFAC Audits ....................................................................... 40


EINRIP 2010 Annual Progress Report<br />

9.3. Re<strong>com</strong>mendations of TFAC Audits ......................................................................... 41<br />

9.4. Follow-up of TFAC Audit ......................................................................................... 41<br />

10. Project Administration and Management ................................................................ 43<br />

10.1. HIV/AIDS Campaign................................................................................................ 43<br />

10.2. Implementation of Anti Corruption Action Plan (ACAP) ........................................... 43<br />

10.3. Project Management Manual ................................................................................... 45<br />

10.4. Coordination Meetings in 2010 ................................................................................ 46<br />

10.5. Management Action Plan (MAP) ............................................................................. 48<br />

10.6. M & E Annual Surveys ............................................................................................ 48<br />

10.7. FIDIC Training and Workshops ............................................................................... 49<br />

11. Loan Extension ......................................................................................................... 51<br />

LIST OF APPENDICES<br />

APPENDIX 1 Summary of ESS Studies at December 2010<br />

APPENDIX 2 Procurement Plan Approved in 2010 – Version 5 and 6<br />

APPENDIX 3 Status of Procurement Plan at 31 December 2010<br />

APPENDIX 4<br />

Contract Data Sheets of Ongoing Civil Works<br />

(Status on 31 December 2010)<br />

APPENDIX 5<br />

APPENDIX 6<br />

Payment Monitoring Table for Loan Categories<br />

Performance Indicators for 2010 ACAP Audit<br />

APPENDIX 7 Minutes of Joint Management Meeting No. 6<br />

APPENDIX 8 Management Action Plan Approved in January 2010<br />

LIST OF FIGURES<br />

Figure 1-1 EINRIP Project Location Map ............................................................................. 8<br />

Figure 1-2 EINRIP – Implementation Arrangements .......................................................... 12<br />

Figure 7-1 Cumulative Monthly Expenditure to Dec 2010 .................................................. 34<br />

Figure 7-2 S-curve for Expenditure of Special Account ..................................................... 34<br />

Figure 7-3 Trend of Exchange Rates ................................................................................. 35<br />

Figure 7-4 Project Cost changes on Variable Exchange Rate ........................................... 35


EINRIP 2010 Annual Progress Report<br />

LIST OF TABLES<br />

Table 1-1 Loan Financing Table ......................................................................................... 6<br />

Table 1-2 List of EINRIP Packages .................................................................................... 7<br />

Table 4-1 Packages with Procurement Completed by end of 2010 .................................. 24<br />

Table 5-1 List of Projects Commenced by end of Dec 2009 ............................................. 29<br />

Table 5-2 List of projects awarded of NOL (Disbursement) .............................................. 30<br />

Table 7-1 Payments Processed in 2010 ........................................................................... 33<br />

Table 7-2 EINRIP Cumulative Payments up to 31 December 2010 .................................. 33<br />

Table 10-1 List of packages for 2010 ACAP Audit .............................................................. 45<br />

Table 10-2 Summary Evaluation of 2010 ACAP Audit ........................................................ 45<br />

Table 10-3 List of 2010 M&E Surveys ................................................................................ 49<br />

Table 11-1 Loan Amendment Changes .............................................................................. 52<br />

Table 11-2 Loan Amendment Changes .............................................................................. 52


EINRIP 2010 Annual Progress Report<br />

ABBREVIATIONS<br />

ACAP<br />

AIPRD<br />

AMDAL<br />

AusAID<br />

AWP<br />

Bina Marga<br />

Dit Bintek<br />

Dit Bipram<br />

EINRIP<br />

ESS<br />

FMR<br />

GOI<br />

IBRD, WB<br />

ICB<br />

LARAP<br />

MOF<br />

MPW<br />

NOL<br />

P2JJ<br />

PAS<br />

PC<br />

PMM<br />

PMSC<br />

PMU<br />

PPC<br />

RSC<br />

SLARAP<br />

SRIP<br />

TOR<br />

UKL<br />

UPL<br />

BLHD<br />

Anti-Corruption Action Plan<br />

Australia-Indonesia Partnership for Reconstruction and Development<br />

Analisa Mengenai Dampak Lingkungan – Environmental Impact Assessment<br />

Process<br />

Australian Agency for International Development which administers AIP, AIPRD<br />

Annual Work Programme<br />

Directorate General of Highways within the Ministry of Public Works (DGH)<br />

Directorate of Technical Affairs within DGH<br />

Directorate of Planning within DGH<br />

Eastern Indonesia National Roads Improvement Project<br />

Environmental and Social Safeguards<br />

Financial Monitoring Report – quarterly expenditure report and cash forecast for<br />

six months<br />

Government of Indonesia<br />

International Bank for Reconstruction and Development – World Bank<br />

International Competitive Bidding<br />

Land Acquisition and Resettlement Action Plan<br />

Ministry of Finance<br />

Ministry of Public Works<br />

No Objection Letter<br />

Perencanaan dan Pengawasan Jalan dan Jembatan – Road and Bridge Design<br />

and Supervision Unit<br />

Procurement Advisory Services<br />

Procurement Committee<br />

Project Management Manual<br />

Project Management Support Consultant<br />

Project Management Unit (to be qualified by Project name, e.g. PMU-EINRIP)<br />

Project Preparation Consultant<br />

EINRIP Regional Supervision Consultant<br />

Simplified LARAP<br />

Strategic Roads Infrastructure Project (World Bank funded)<br />

Terms of Reference<br />

Upaya Pengelolaan Lingkungan – site specific Environmental Mitigation Plan<br />

Upaya Pemantauan Lingkungan – site specific Environmental Monitoring Plan<br />

Balai Lingkungan Hidup Daerah


EINRIP 2010 Annual Progress Report<br />

EXECUTIVE SUMMARY<br />

The Government of Indonesia and the Government of Australia through the Australia-Indonesia<br />

Partnership for Reconstruction and Development (AIPRD) has <strong>com</strong>mitted loan funds of A$300<br />

million to the Eastern Indonesia National Road Improvement Project (EINRIP) for road and<br />

bridge improvement works across nine provinces in Eastern Indonesia. The Government of<br />

Indonesia has pledged the equivalent of A$33 million to the program.<br />

Loan Number : AIPRD L-002<br />

Loan Signing : 7 September 2007<br />

Loan Effectiveness : 4 March 2008<br />

Loan Closing date : 1 June 2011<br />

The main objective of EINRIP is to improve National links to an acceptable standard of service<br />

and accessibility. A major focus of EINRIP is the minor widening and improvement including<br />

limited capex (capacity expansion) of about 400 km of roads in Eastern Indonesia which have<br />

been reclassified as National roads. The program is also funding the replacement of a limited<br />

number of steel bridge superstructures.<br />

Mobilization of 3 Implementation Support Consultants<br />

The project preparation services of PPC Consultants concluded in April 2009.<br />

Procurement of implementation support consultants <strong>com</strong>menced in early 2008 and by the end<br />

of 2008, three consultants were awarded the contracts, as follows:<br />

1. Regional Supervision Consultants (RSC), contract signed on 26 November 2008, services<br />

for 39 months<br />

2. Procurement Advisory Services Consultants (PAS), contract signed on 28 October 2008,<br />

services for 18 months<br />

3. Project Management Support Consultants (PMSC), contract signed on 9 December 2008,<br />

services for 39 months<br />

In 2010, all three consultants continued on the project, except for PAS consultants who were<br />

demobilised on 30 November 2010.<br />

Number of Civil Works Packages<br />

24 packages were finally selected for EINRIP program in middle of 2008. In 2009, four<br />

packages in South Kalimantan province; EKS-03, EKS-04, EKS-05 and EKS-06 were removed<br />

from EINRIP program due to lack of funds for land acquisition and this was agreed in principle<br />

by DGH and AusAID.<br />

In 2010, 20 packages were considered under EINRIP.<br />

Detailed Design of Civil Works<br />

Design for all packages was finalized and <strong>com</strong>pleted before demobilization of PPC in April<br />

2009.<br />

Environmental and Social Studies of Civil Works<br />

By end of 2010, from the 20 packages under EINRIP:<br />

Environmental studies were not required for 6 packages (EBL-02, ESS-01, ESS-02, EKB-01,<br />

EKS-01 and EKS-02).<br />

Project Management Unit (PMU-EINRIP) Page 1


EINRIP 2010 Annual Progress Report<br />

Environmental studies (UKL/UPL) for 11 packages were <strong>com</strong>pleted in 2008 and 2009 (EBL-<br />

01, ESH-01, ESU-01, ENB-01AB, ENB-01C, ENB-02, ENB-03, ENT-01, ESR-01, ESR-02<br />

and ESS-03).<br />

For ESS-04, ESS-05, ESS-06 in South Sulawesi, ANDAL, RKL, RPL was approved by the<br />

AMDAL Commission and signed by South Sulawesi Governor on 1 October, 2010. The<br />

process is deemed <strong>com</strong>pleted, except for issue of NOL from AusAID, expected in January<br />

2011.<br />

Land Acquisition<br />

Of the 20 packages now listed under EINRIP:<br />

There was no land acquisition required for 2 packages.<br />

EBL- 01 EBL- 02<br />

Land acquisition for 7 packages was <strong>com</strong>plete by end of 2009.<br />

ESU- 01 EKB- 01 ENB- 01AB ENB- 01C ENB- 03<br />

ESR- 01 ESS- 02<br />

Land acquisition for another 7 packages was <strong>com</strong>plete by end of 2010.<br />

ENB-02 ESR-02 ESS-01 EKS- 01 EKS- 02<br />

ESH-01<br />

ENT-01<br />

For remaining 4 packages, land acquisition process is on-going.<br />

ESS- 03 ESS- 04 ESS- 05 ESS- 06<br />

Procurement of Civil Works<br />

In 2008 and 2009, 5 contracts were signed and construction <strong>com</strong>menced in 2009.<br />

Contracts were awarded and signed for 7 additional packages in December 2009 and<br />

another contract (ESH-01) was signed on 25 May, 2010 and construction <strong>com</strong>menced.<br />

Four contracts were awarded and signed in 2010 and the NOL for Contract and<br />

Disbursement was issued by the end of December 2010 for all of them.<br />

In summary, construction <strong>com</strong>menced on 13 packages by the end of 2010, while another 4<br />

packages will <strong>com</strong>mence construction in 2011.<br />

Bid for ESS-04 was called on 21 September, 2010 and was under evaluation at end of 2010.<br />

Bidding for 2 packages (ESS-05 and ESS-06) will <strong>com</strong>mence in 2011.<br />

Implementation of Civil Works<br />

Construction had <strong>com</strong>menced on 13 packages by the end of 2010. The summary of progress is<br />

as follows:<br />

Package<br />

EBL-01<br />

EBL-02<br />

EKB-01<br />

Location<br />

Bali<br />

Tohpati – Kusamba<br />

Bali<br />

Tohpati – Kusamba Stg 2<br />

West Kalimantan<br />

Pontianak - Tayan<br />

Commencement<br />

Date<br />

Physical Progress<br />

31-December-2010<br />

Planned Actual Deviation<br />

Financial<br />

Progress<br />

25 Feb 2009 96,35 % 74,26 % 22.09 % 62.2%<br />

1 Mar 2010 30.01 % 32.64 % + 2.63 % 36.6%<br />

24 Jul 2009 71.02 % 66.45 % - 4.56 % 62.5%<br />

Project Management Unit (PMU-EINRIP) Page 2


EINRIP 2010 Annual Progress Report<br />

Package<br />

ESU-01<br />

ENB-01AB<br />

ENB-01C<br />

ENB-02<br />

ENB-03<br />

ESR-01<br />

ESR-02<br />

ESS-01<br />

Location<br />

North Sulawesi<br />

Molibagu - Mamalia -<br />

Taludaa<br />

West Nusa Tenggara<br />

Sumbawa Besar Bypass<br />

West Nusa Tenggara<br />

Pal IV - Km 70<br />

West Nusa Tenggara<br />

Km 70 - Bts. Cadbin<br />

Dompu<br />

West Nusa Tenggara<br />

Bts. Cadbin Dompu -<br />

Banggo<br />

South East Sulawesi<br />

Tinanggea - Kasipute<br />

South East Sulawesi<br />

Bambaea - Sp. Kasipute<br />

South Sulawesi Sengkang<br />

- Impa Impa -<br />

Tarumpakkae<br />

ESS-02 South Sulawesi Bantaeng -<br />

Bulukumba<br />

ESH-01 Central Sulawesi Lakuan –<br />

Buol<br />

Commencement<br />

Date<br />

Physical Progress<br />

31-December-2010<br />

Planned Actual Deviation<br />

Financial<br />

Progress<br />

1 Mar 2010 29.50 % 8.63 % - 20.87 % 18.1%<br />

5 Jun 2009 81.30 % 54.03 % - 27.28 % 50.6%<br />

1 Mar 2010 27.70 % 8.53 % - 19.16 % 18.8%<br />

6 Apr 2010 41.63 % 5.22 % - 36.41 % 16.7%<br />

1 Mar 2010 15.84 % 6.50 % - 9.34 % 19.7%<br />

13 Jul 2009 73.74 % 26.86 % - 46.88 % 33.9%<br />

30 Apr 2010 21.14 % 14.07 % - 7.07 % 25.4%<br />

1 Mar 2010 21.11 % 11.51 % - 9.60 % 18.3%<br />

15 Oct 2009 57.50 % 17.20 % - 40.31 % 24.4%<br />

7 October 2010 3.19 % 3.38 % + 0.19 % 12.9%<br />

Project Financial Status (December 2010)<br />

Cumulative Advances to Special Account till 31 December 2010: A$ 91.27 million<br />

Balance on 31-Dec-2010 A$ 24.344 million<br />

Cumulative expenditure to Dec-09 from loan: A$ 66.924million<br />

Cumulative expenditure to Dec-09 from GOI: A$ 7.662 million<br />

EINRIP Loan Budget Plan and Actual (A$ million)<br />

350,00<br />

300,00<br />

286,37<br />

294,24 298,49<br />

300,66 302,32 302,61<br />

273,56<br />

250,00<br />

242,14<br />

200,00<br />

Proc. Plan<br />

Actual<br />

150,00<br />

100,00<br />

66,92<br />

50,00<br />

-<br />

HIV/AIDS awareness campaign<br />

During March/April 2010, it was decided the <strong>com</strong>ponent of HIV/AIDS Awareness Program will<br />

be added to the consultancy contract of Regional Supervision Consultants (RSC) through an<br />

addendum. BCEOM (RSC Consulting firm) invited proposals covering all 20 packages from the<br />

Project Management Unit (PMU-EINRIP) Page 3


EINRIP 2010 Annual Progress Report<br />

shortlisted firms/consultants provided by DGH and has <strong>com</strong>pleted the evaluation of proposals.<br />

The contract with the NGO (Yayasan Kusuma Buana) was signed on 8 November 2010. The<br />

first campaign will <strong>com</strong>mence in Bali on packages EBL-01/EBL-02 in January 2011.<br />

Technical and Financial Audits (TFAC)<br />

The independent Technical and Financial Audits, financed by AusAID, were conducted for five<br />

packages in 2010 and identified a number fop key areas that need improvement.<br />

Project Management Manual<br />

The revision of the PMM is well advanced with <strong>com</strong>ments from PMSC, PAS and RSC<br />

incorporated in the proposed revisions. The Draft revision is under review by DGH.<br />

Implementation of ACAP<br />

The 2010 ACAP audit was planned in September-November 2009 and prior to audit, BPKP<br />

coordinated with PMU and Inspectorate General of MPW to develop the performance indicators<br />

for evaluation of ACAP implementation.<br />

The audit was conducted as planned and report was published by BPKP in December 2010.<br />

Monitoring & Evaluation Surveys<br />

The 2010 M&E surveys were carried out under the supervision of PMSC between June - August<br />

2010 in the provinces of Bali, NTT, West Kalimantan, South Sulawesi and South Kalimantan.<br />

Coordination Meetings in 2010<br />

Six-monthly Joint Management Meeting No. 6 was held on 24 August 2010.<br />

The second 3-monthly Progress Coordination Meeting involving all Satkers/PPK for Civil<br />

Works and RSC was held on 18 February 2010.<br />

A total of eight Monthly Coordination Meetings were held in 2010.<br />

Management Action Plan (MAP)<br />

As part of extension to the EINRIP loan closing date, DGH prepared a Management Action Plan<br />

(MAP) to strengthen the existing institutional and procedural arrangements to expedite<br />

<strong>com</strong>pletion of ESS studies, procurement and early <strong>com</strong>mencement of construction contracts.<br />

The final version of MAP was formally approved by AusAID on 16-Feb-10 and the MAP<br />

reporting has been done regularly. A total of eleven (11) MAP Reports have been prepared by<br />

PMU since Feb 2010.<br />

Loan Extension<br />

During the 6th JMM held on 24 August 2010, it was agreed in principle by AusAID and GOI that<br />

the EINRIP Loan Closing date will be extended from 1 June 2011 to 31 March 2013. The loan<br />

extension explanatory note and supporting analysis for this was finalised in 2010 and will be<br />

submitted to Bappenas and Ministry of Finance (MOF) in early 2011.<br />

Formalisation is expected by March 2011.<br />

Project Management Unit (PMU-EINRIP) Page 4


EINRIP 2010 Annual Progress Report<br />

1. Introduction<br />

1.1. Background<br />

The Australian Indonesia Partnership for Reconstruction and Development (AIPRD) is<br />

administered by the Australian Agency for International Development (AusAID), on behalf of<br />

Government of Australia (GOA) in partnership with the Government of Indonesia (GOI).<br />

The primary objective of this partnership is to support Indonesia‟ s reconstruction and<br />

development efforts, with an emphasis on economic and social reform. As part of AIPRD, both<br />

governments have <strong>com</strong>mitted loan funds (A$300 million) to the Eastern Indonesia National<br />

Road Improvement Project (EINRIP).<br />

The project development objective is:<br />

“To support regional economic and social development in Eastern Indonesia by<br />

improving the condition of the national road network.”<br />

EINRIP will support a program of National road and bridge improvement projects, with major<br />

focus on roads recently upgraded to National roads from previously provincial or non-status<br />

roads. The main objective is to improve road links to an acceptable standard to ensure that the<br />

National road network provides acceptable standards of service and accessibility, and is<br />

capable of supporting local and regional economic development.<br />

Approximately 4,300 km of roads are affected, of which around 400 kilometers will be upgraded<br />

and rehabilitated under this project. The project also includes supply, fabrication and delivery of<br />

seven types of steel truss bridges, between 30-60 meters span, and covering a total length of<br />

895 meters.<br />

1.2. EINRIP Loan AIPRD L-002<br />

The salient features of the EINRIP loan are:<br />

a. Loan Number : AIPRD - L002<br />

b. ID Project : 21594001<br />

c. Total Project Value : AUD 330 million<br />

d. AusAID Loan portion : AUD 300 million<br />

e. GOI Loan portion : AUD 30 million (as sharing for the applicable tax<br />

payment under EINRIP project)<br />

f. Loan negotiation : 3 July 2007<br />

g. Loan Signing : 7 September 2007<br />

h. Loan Effectiveness : 4 March 2008<br />

i. Implementation Period : 2008 - 2012<br />

j. Loan Closing date : 1 June 2011 (Extension proposed - 31 March 2013)<br />

k. Executing Agency : Directorate General of Highways (DGH)<br />

Project Management Unit (PMU-EINRIP) Page 5


EINRIP 2010 Annual Progress Report<br />

l. Treatment Length : About 400 km roads and 3504 meters of bridges<br />

m. Treatment Type : Betterment of existing road with widening, road<br />

capacity expansion; and replacement and rehabilitation<br />

of bridges<br />

n. Provinces in project : Bali, West Kalimantan, South Kalimantan, South East<br />

Sulawesi, South Sulawesi, North Sulawesi, Central<br />

Sulawesi, NTB (Nusa Tenggara Barat) & NTT (Nusa<br />

Tenggara Timur)<br />

1.3. Loan categories<br />

The EINRIP loan categories and financing plan is shown in Table 1-1.<br />

Category<br />

GOA (A$m.) GOI (A$m.) Total<br />

Physical<br />

Share<br />

%<br />

Physical<br />

VAT<br />

Share<br />

%<br />

A$m.<br />

1. Civil Works<br />

National Roads 229.7 89% 28.6 2.9 11% 261.2<br />

Sub Total 229.7 28.6 2.9 261.2<br />

2. Goods<br />

Bridge Trusses 9.9 89% 1.2 0.1 11% 11.3<br />

Equipment 0.3 89% - - 11% 0.3<br />

Sub Total 10.2 1.3 0.1 11.6<br />

3. Incremental Operating Costs<br />

PMU 0.7 89% 0.1 0.01 11% 0.8<br />

Sub Total 0.7 - - 0.8<br />

4. Consultants’ services<br />

Project Management Support 6.3 100% - - 0% 6.3<br />

Regional Supervision 17.0 100% - - 0% 17.0<br />

Procurement Advisory Services 1.2 100% - - 0% 1.2<br />

Sub Total 24.5 - - 24.5<br />

5. Unallocated<br />

Physical Contingencies 11.5 100% - - 0% 11.5<br />

Price Contingencies 23.4 100% - - 0% 23.4<br />

Sub Total 34.9 - - 34.9<br />

TOTAL LOAN-RELATED COST 300.0 30.0 3.0 333.0<br />

Land Acquisition 0.0 0% 26.1 2.6 100% 28.7<br />

Training and Workshops 0.0 0% 1.0 0.1 100% 1.1<br />

TOTAL 100% GOI COST 0.0 27.1 2.7 29.8<br />

1.3.1. Civil Works<br />

Table 1-1<br />

Loan Financing Table<br />

The scope of the Civil Works includes the following <strong>com</strong>ponents:<br />

• Betterment treatments including minor widening on inter-urban roads;<br />

• Improvements to bridges on existing selected links;<br />

• A road dualisation project in Bali province; and<br />

Project Management Unit (PMU-EINRIP) Page 6


EINRIP 2010 Annual Progress Report<br />

• A steel truss bridge replacement program for existing deteriorated bridges in Eastern and<br />

Western Indonesia. (included under Goods Category)<br />

The roads have been selected after earlier feasibility studies conducted by Project Preparation<br />

Consultants (PPC), engaged by AusAID through the Grant funds.<br />

The packages <strong>com</strong>prise civil works contracts, with construction period varying between 18-24<br />

months and 12 months defects notification period.<br />

The list of packages is shown in Table 1-2; and location map is shown in Figure 1-1.<br />

CIVIL WORKS<br />

No. Name Province Length<br />

1 EBL- 01 Tohpati – Kusamba Bali 10.79 km<br />

2 EBL- 02 Tohpati – Kusamba Stage 2 Bali 8.21 km<br />

3 ESH- 01 Lakuan – Buol Central Sulawesi 16.23 km<br />

4 ESU- 01 Molibagu – Taludaa North Sulawesi 5 bridges (490 m)<br />

5 ENB- 01AB Sumbawa Bypass NTB (Sumbawa) 11.20 km<br />

6 ENB- 01C Sumbawa Pal IV – Km 70 NTB (Sumbawa) 31.79 km<br />

7 ENB- 02 Km 70- Bts. Cabdin Dompu NTB (Sumbawa) 14.09 km<br />

8 ENB- 03 Bts. Cabdin Dompu – Banggo NTB (Sumbawa) 23.62 km<br />

9 ENT- 01 Ende – Aegela NTT 15.60 km<br />

10 ESR- 01 Tinanggea – Kasipute South East<br />

Sulawesi<br />

11 ESR- 02 Kasipute – Bambaea South East<br />

Sulawesi<br />

12 ESS- 01 Sengkang – Impa Impa –<br />

Tarumpakkae<br />

South Sulawesi<br />

33.77 km<br />

23.93 km<br />

24.18 km<br />

13 ESS- 02 Bantaeng – Bulukumba South Sulawesi 26.88 km<br />

14 ESS- 03 Jeneponto – Bantaeng South Sulawesi 25.84 km<br />

15 ESS- 04 Bulukumba – Tondong South Sulawesi 20.74 km<br />

16 ESS- 05 Bulukumba – Tondong South Sulawesi 19.96 km<br />

17 ESS- 06 Bulukumba – Tondong – Sinjai South Sulawesi 24.52 km<br />

18 EKB- 01 Pontianak – Tayan West Kalimantan 31.50 km<br />

19 EKS- 01 Martapura – Ds. Tungkap South Kalimantan 18.89 km<br />

20 EKS- 02 Banjarmasin – Bts. Kalteng South Kalimantan 12.90 km<br />

21 EKS- 03 Jl AYani (Martapura – Ds.Tungkap)<br />

22 EKS- 04 Ds.Tungkap – Rantau<br />

23 EKS- 05 Barabai – Mantimin<br />

24 EKS- 06 Mantimin – Dahai<br />

GOODS<br />

In discussions between GOI and AusAID<br />

in latter half of 2009, it has been<br />

indicated that these four packages are<br />

likely to be dropped.<br />

1 ESB- 02 Prefabricated Steel Bridges Various 895 m<br />

Table 1-2<br />

List of EINRIP Packages<br />

Project Management Unit (PMU-EINRIP) Page 7


EINRIP 2010 Annual Progress Report<br />

Figure 1-1<br />

EINRIP Project Location Map<br />

Project Management Unit (PMU-EINRIP) Page 8


EINRIP 2010 Annual Progress Report<br />

1.3.2. Goods<br />

The Goods category <strong>com</strong>prises of two parts:<br />

i) Acquisition of pre-fabricated steel truss bridge material; and replacement program for<br />

selected deteriorated bridges in Eastern and Western Indonesia; and<br />

ii) Provision of <strong>com</strong>munications and office equipment for Project Management Unit (PMU).<br />

Procurement of Goods valued at A$300,000 or more is to be under International Competitive<br />

Bidding (ICB) and that under A$300,000 through National Competitive Bidding (NCB).<br />

1.3.3. Incremental Operating Costs (IOC)<br />

This loan category provides to fund the costs of incremental expenses incurred by the Central<br />

and Provincial level units and the PMU in the carrying out activities of the Project, including staff<br />

travel and per diem, <strong>com</strong>munications, consumables, web page operation and maintenance,<br />

advertisement of bidding, printing and publication of Project information etc. but excluding<br />

Government staff salaries, allowances and honoraria.<br />

1.3.4. Implementation Support<br />

Implementation support is provided to ensure efficiency in implementation and overall quality of<br />

the Civil Works. Amongst others, three separate consultancy services were identified. These are<br />

100% financed by the loan.<br />

a. Project Management Support Consultants (PMSC)<br />

The PMSC provides support to the PMU and DGH in management of the Project. PMSC is<br />

managed by the Directorate of Planning and directly works under Project Management Unit<br />

(PMU) under the Directorate. PMSC is based in Jakarta and functions include:<br />

Provide full support to the PMU in the exercise of all its functions.<br />

Establish and maintain the relevant financial monitoring systems.<br />

Develop a monthly Project Progress Report that satisfies the needs of all stakeholders,<br />

and ensure the timeliness and accuracy of all reports.<br />

Undertake an independent performance monitoring of the effectiveness of construction<br />

supervision, including monitoring the effectiveness of environmental management<br />

procedures, and <strong>com</strong>pliance with the ESS.<br />

Provide assistance as required with the establishment of anti-corruption measures<br />

necessary to support the project, and monitor and report their effectiveness.<br />

Monitor the general quality of procurement activities and make re<strong>com</strong>mendations on<br />

improvement of standards.<br />

Support Implementation of Environmental and Social Safeguards (ESS) and assist the<br />

PMU to ensure that all environmental and social safeguards required are properly<br />

applied, and report regularly on this activity.<br />

Provide administrative support for the conduct of post-implementation surveys of project<br />

performance, using previously-prepared guidelines and procedures.<br />

Support the implementation of the proposed DGH training program.<br />

Project Management Unit (PMU-EINRIP) Page 9


EINRIP 2010 Annual Progress Report<br />

Support the PMU‟ s reporting requirements and assist with the preparation of the<br />

Borrower‟ s Project Completion Report.<br />

b. Regional Supervision Consultant (RSC)<br />

Regional Supervision Consultant (RSC) is responsible for construction supervision of all<br />

Civil Works and designated the role of “Engineer” under the FIDIC-based contract.<br />

RSC is managed by DGH through the Directorate of Roads and Bridges, Eastern Region,<br />

including supervision of packages in Metropolitan areas. The team is based in Makassar,<br />

with all field supervision teams to be established at project locations. Major tasks of RSC<br />

include:<br />

Provide training for RSC staff focusing on contract administration and construction<br />

supervision tasks.<br />

Carry out an assessment of the training needs and develop a training plan that <strong>detail</strong>s<br />

training modules, target audience, implementation schedules etc.<br />

Prepare and maintain Quality Assurance Plan that will show clearly the procedures that<br />

will be used to ensure that consistently high standards of construction supervision are<br />

maintained across all contracts.<br />

Validate and Update Designs.<br />

Establishment of testing laboratory in Makassar that can be operated fully independently<br />

from the project site laboratories.<br />

Supervision of Civil Works.<br />

Monitoring and management of environmental and social safeguards, and ensure that<br />

the provisions of the Specification and the Contract are fully observed by contractors<br />

during works implementation.<br />

Support financial and progress reporting.<br />

c. Procurement Advisory Services (PAS)<br />

The Procurement Advisory Services Consultant (PAS) provide support to the civil works<br />

Procurement Committees established in the Provincial Satker for each contract package.<br />

The primary objective of the PAS is to help ensure that the procurement of civil works<br />

proceeds smoothly in accordance with all the applicable guidelines and regulations.<br />

The team is based in Jakarta and managed by DGH through the Directorate of Roads and<br />

Bridges, Eastern Region, including procurement of packages in Metropolitan areas.<br />

The functions of the PAS include:<br />

Review all arrangements made to support project procurement, including the “readiness”<br />

of the Procurement Committees, adequacy of facilities, equipment and materials;<br />

suitability and feasibility of the proposed Procurement Schedule for each contract, and<br />

all related matters.<br />

PAS will report to DGH and to AusAID on the readiness of the Committees and its<br />

supporting arrangements to initiate procurement.<br />

Provide procurement training for Procurement Committees to ensure familiarity with the<br />

procurement process required by all stipulated guidelines and regulations,<br />

Project Management Unit (PMU-EINRIP) Page 10


EINRIP 2010 Annual Progress Report<br />

Monitor the establishment and use of the “semi” e-procurement system for EINRIP‟<br />

Provide support for the publication on the official project website and posting elsewhere<br />

of all required information and documents,<br />

Develop measures/protocols to help detect and prevent collusive/fraudulent/ corrupt/<br />

coercive practices in the bidding process<br />

Provide support to the procurement <strong>com</strong>mittee for the evaluation of bids, including<br />

monitoring the validity of bid bonds, guarantees and other instruments,<br />

Monitor each PIU and Procurement Committee‟ s adherence to the Procurement<br />

Schedule,<br />

Support the PMU and Procurement Committees to ensure that the provisions of the<br />

ACAP are fully <strong>com</strong>plied with.<br />

1.3.5. Unallocated<br />

The unallocated amount in the Loan covers physical and price contingencies. Physical<br />

contingencies allow for increases in quantities to achieve Project objectives. Price contingencies<br />

allow for the effect of inflation on the cost of works contracted in later years. Unallocated<br />

amounts are not available for the project without specific allocation to a Loan category.<br />

1.4. Project Planning, Administration and Management<br />

The EINRIP project has put in place a number of initiatives and mechanisms for efficient<br />

management of the program. These are briefly described below:<br />

1.4.1. Establishment of Steering Committee and Project Management Unit (PMU)<br />

The Directorate General of Highways (DGH) within MPW is the Executing Agency (EA) for the<br />

Project. An inter-agency Steering Committee chaired by BAPPENAS‟ Deputy for Infrastructure<br />

and including representatives from the Ministry of Finance (MoF) and Ministry of Public Works<br />

(MPW) is responsible for policies relating to Project implementation.<br />

DGH has established a Project Management Unit (PMU-EINRIP) that is chaired by the Director<br />

of Planning in DGH. The PMU-EINRIP is responsible for coordination of all EINRIP activities.<br />

PMU monitors project status, prepares Financial Monitoring Reports, manages effective<br />

implementation of provisions specified in ACAP and monitors performance of RSC and PAS.<br />

PMSC is the consultant supporting PMU.<br />

DGH Directorate of Eastern Region (DJJWT) manages the RSC and PAS services.<br />

The implementation of Civil Works is carried out by the Contract Officer within Specific Work<br />

Units for Construction (Satker / SNVT Pembangunan Provinsi). They manage procurement and<br />

implementation of works and administer civil works contracts as the Employer.<br />

Figure 1-2 presents the organization structure for the project during implementation.<br />

Project Management Unit (PMU-EINRIP) Page 11


EINRIP 2010 Annual Progress Report<br />

DGH – Executing Agency<br />

AUSAID<br />

Directorate of Planning<br />

Head of PMU<br />

Directorate of Roads &<br />

Bridges<br />

Eastern Region<br />

(DJJWT)<br />

Directorate of Freeways<br />

& Urban Roads<br />

(DJBHJK)<br />

Bina Marga Regional<br />

Balai Offices/<br />

Metropolitan<br />

EMU<br />

Coordination<br />

PMU-EINRIP<br />

Officer-in-Charge<br />

Procurement<br />

Committee<br />

For Works<br />

Satker for the<br />

Works<br />

“Employer”<br />

Project Management<br />

Support Consultants<br />

PMSC<br />

Monitor<br />

Procurement<br />

Procurement Advisory<br />

Services<br />

PAS<br />

Regional Supervision<br />

Consultants<br />

RSC<br />

CONTRACT<br />

Monitor<br />

Supervision<br />

RSC Team Leader<br />

“The Engineer”<br />

Implementation Support Consultants<br />

“Contractor”<br />

Figure 1-2<br />

EINRIP – Implementation Arrangements<br />

1.4.2. Project Management Manual (PMM)<br />

The EINRIP loan agreement provided for <strong>com</strong>mitment by the GOI for adoption and<br />

implementation of project activities through a Project Management Manual. The Manual sets<br />

out:<br />

Project management information and reporting systems and procedures, including the<br />

financial management information system;<br />

Financial management plan, including budgeting, disbursements, accounting and<br />

reporting requirements of Project finances, and audit procedures;<br />

Procurement regulations, procedures and requirements;<br />

Provisions of the Environmental and Social Safeguards,<br />

Provisions of the Anti-Corruption Action Plan;<br />

Training programs and workshops; and<br />

Arrangements for Monitoring and evaluation.<br />

The first version of PMM was approved and released in September 2008.<br />

1.4.3. Improved Engineering Design and Bidding Documentation<br />

In EINRIP preparation, two significant changes were introduced i.e. <strong>detail</strong>ed engineering design<br />

process and use of FIDIC based bidding documents.<br />

The project uses World Bank‟ s Standard Bidding Documents including the Multilateral<br />

Development Bank Harmonised version of FIDIC. The Team Leader of the Regional<br />

Supervision Consultant has been designated as the “Engineer” with the responsibilities and<br />

authorities clearly defined with the aim to improve construction quality.<br />

During EINRIP preparation, appropriate field investigations have been carried out in addition to<br />

full topographic survey. This has enabled <strong>detail</strong>ed road and drainage design for both roads and<br />

bridges with special attention on drainage design. Integration of environmental impacts into<br />

<strong>detail</strong>ed design has been ensured.<br />

Project Management Unit (PMU-EINRIP) Page 12


EINRIP 2010 Annual Progress Report<br />

1.4.4. Anti Corruption Action Plan (ACAP)<br />

The Anti-Corruption Action Plan (ACAP) for EINRIP has been developed to ensure that the<br />

project‟ s goal of road improvement is not <strong>com</strong>promised by corruption and malpractice. The<br />

ACAP has been adopted by GOI as a legally binding <strong>com</strong>mitment, ensuring that anti-corruption<br />

measures are an integral part of the implementation of EINRIP. The key features of the EINRIP<br />

ACAP are:<br />

Key project documents and updated reports on financial and technical aspects of project<br />

implementation, <strong>com</strong>plaints handling mechanism and results, and audit results will be<br />

publicly available, including on the EINRIP website and dissemination by email and post,<br />

to allow for monitoring and oversight of the project by a broad range of stakeholders.<br />

Strengthened supervision and audit mechanismas have been put in place. This includes<br />

appoitinting RSC as the Engineer and financial and technical audits.<br />

Measures to increase the efficiency and accountability of procurement processes,<br />

including the use of a Procurement Agent for the selection of consultancy services and<br />

Procurement Advisory Services (PAS) for the selection of civil works contractors, and<br />

improvement of MPW‟ s existing e-procurement system.<br />

The PMU is responsible for ensuring the ACAP is properly implemented and for revising the<br />

Project Management Manual on an annual basis to incorporate necessary improvements to<br />

processes and procedures.<br />

1.5. Terminology for Annual Works Program (AWP)<br />

At the start of EINRIP project, separate batches of projects were prepared and implemented<br />

using the term “Annual Work Programs (AWPs)”. These were separate groups of projects that<br />

could be implemented in sequential manner, e.g. AWP1, Batch 1 included projects that were<br />

planned to be ready for implementation by mid-2007; AWP-2 implementation by mid 2008, etc.<br />

This term AWP was consistently followed in project preparation and reporting documentation.<br />

However, in early 2009, the use of „AWP‟ as reference was gradually reduced. At end of 2009,<br />

the projects in EINRIP program are 20 in total and as such the term AWP is no longer used.<br />

Project Management Unit (PMU-EINRIP) Page 13


EINRIP 2010 Annual Progress Report<br />

2. Project Preparation (Feasibility Studies, Investigations and<br />

Design)<br />

The preparation work for EINRIP has been more extensive than the earlier donor funded<br />

projects. AusAID directly procured the Project Preparation Consultants, and funded the<br />

resources to produce <strong>detail</strong>ed engineering design.<br />

The preparation work en<strong>com</strong>passed adequate levels of field and soils investigation and full<br />

topographic survey. Final Engineering Design provided for both roads and bridges with special<br />

attention on drainage design. Design Integration ensured that a range of environmental matters<br />

are included in the final approved design.<br />

2.1. Project Preparation Consultants (PPC)<br />

Project preparation for EINRIP, including all feasibility studies and final engineering design of<br />

identified works, was directly funded by Grant Funds from the AIPRD financing facility, and<br />

Project Preparation Consultants (PPC) were appointed in March 2006.<br />

The scope of services of PPC included: (Source: PPC Final Report March 2009)<br />

Review of background information to develop an understanding of the extent and<br />

location of road and bridge deficiencies.<br />

Develop a short list of road corridors to be examined for potential inclusion in the road<br />

and bridge program.<br />

Develop environmental and social guidelines to be used in the planning, design and<br />

implementation of the works.<br />

Carry out field investigations to identify road and bridge candidates and potential<br />

betterment works.<br />

Carry out feasibility assessment of the candidate projects<br />

Prepare final engineering designs of selected roads and bridges sub-projects,<br />

Prepare specifications and bidding documents for the works.<br />

Carry out environmental and social studies and provide monitoring and assistance<br />

during the land acquisition process.<br />

The PPC team <strong>com</strong>prised URS Australia supported by ARRB, Louis Berger, VicRoads, PT.<br />

Dacrea Mitrasaya and PT. Perentjana Djaja.<br />

The project preparation <strong>com</strong>menced in March 2006 and after the initial review of background<br />

information the initial planning <strong>com</strong>menced and was <strong>com</strong>pleted in early 2007.<br />

The <strong>detail</strong>ed design of all packages <strong>com</strong>menced in late 2006 and the design activity achieved<br />

full <strong>com</strong>pletion in April 2009. All engineering designs were legalized by BinTek (Directorate of<br />

Technical Affairs) and environmental integration into road design was also legalized by SubDit<br />

Environment in BinTek.<br />

2.2. Documentation <strong>com</strong>pletion under PPC<br />

With <strong>com</strong>pletion of design preparation activities, the following documents for all EINRIP<br />

packages were also available at end of April 2009:<br />

Design Specification<br />

Project Management Unit (PMU-EINRIP) Page 14


EINRIP 2010 Annual Progress Report<br />

Design Specification provided a consistent approach to the provision of the field<br />

investigation, design and documentation for roads and bridge works. The Design<br />

Specification Document was revised towards the end of the EINRIP project preparation and<br />

was edited to focus the document on the specific requirements for investigations and design<br />

of road betterment projects.<br />

Design Reports<br />

Each design report provided a summary of the project features, existing alignment and the<br />

<strong>detail</strong>s on the field investigations, topographic survey and design for both road and bridge<br />

improvement through rehabilitation. The works on new bridges were covered by a separate<br />

bridge design report.<br />

Legalisation of Design<br />

Full legalisation required the approvals for preliminary design; final highway and bridge<br />

design; Bill of Quantities; and legalisation of integration of environmental aspects in the<br />

<strong>detail</strong>ed design.<br />

Standard Drawings<br />

Costed Bill of Quantities<br />

The estimated cost report were prepared including the cost estimating process and reviewed<br />

with Bina Marga.<br />

Preparation of Bid Documents<br />

After legalisation and AusAID concurrence, <strong>com</strong>plete sets of documents were prepared,<br />

including:<br />

a) Highway Drawings<br />

b) Bridge Drawings<br />

c) Standard Drawings<br />

d) General Specification<br />

e) Special Specifications (if any)<br />

f) General and Particular Conditions<br />

g) Other bidding documents<br />

After demobilization of PPC, no further work on design was carried out, except for issue of<br />

standard drawings in the bidding documents and minor revisions to the BOQ and subsequent<br />

impact on Engineer‟ s and Owner‟ s Estimate.<br />

Project Management Unit (PMU-EINRIP) Page 15


EINRIP 2010 Annual Progress Report<br />

3. Project Preparation (Environmental & Social Studies)<br />

The environmental approach in EINRIP project preparation has been developed to ensure that<br />

environmental and social safeguards are covered <strong>com</strong>prehensively throughout the planning,<br />

design, implementation and monitoring activities.<br />

After close consultation between Bina Marga and AusAID, a Guideline for Implementation of<br />

Environmental and Social Safeguards (ESS) was prepared that evolved through a series of<br />

meetings and reviews of draft documents until final agreement was achieved jointly between<br />

AusAID and Bina Marga in mid 2007.<br />

All EINRIP sub-projects have been identified and prepared in full <strong>com</strong>pliance with the provisions<br />

of the ESS.<br />

Environmental Studies<br />

There are two levels of environmental studies required for road and bridge subprojects.<br />

The higher level is Environmental Impact Assessment, referred to as an AMDAL (Analisis<br />

Mengenai Dampak Lingkungan Hidup). The lower level is an Environmental Monitoring and<br />

Management Plan, UKL/UPL (Upaya Pengelolaan Lingkungan Hidup dan Upaya<br />

Pemantauan Lingkungan). Based on defined threshold, the environmental Screening<br />

process determines what triggers the need for an AMDAL or a UKL/UPL.<br />

Land Acquistion Studies<br />

Where land acquisition is required or where there is displacement of existing occupants or<br />

users of land, a Land Acquisition and Resettlement Action Plan (LARAP) is to be prepared.<br />

The LARAP could be full LARAP of a Simplified LARAP (SLARAP).<br />

3.1. Extent of ESS Studies in EINRIP<br />

Two packages (EBL-01 and EBL-02) did not require land acquisition.<br />

Land acquisition continued in 2009 and the process was <strong>com</strong>pleted for following packages by<br />

end of 2009.<br />

ESU- 01 ENB- 01AB ENB- 01C ENB- 03 ESR- 01<br />

EKB- 01 ESS- 02 EKS-01 (Simplified LARAP)<br />

At start of 2010, the remaining ESS studies covered following packages:<br />

Study Nos Packages<br />

AMDAL<br />

2 studies for<br />

5 packages<br />

ESS-04, 05, 06 (1 study)<br />

EKS-05, 06 (1 study)<br />

LARAP 10 ESH- 01 ENB- 02 ENT- 01 ESR- 02<br />

ESS- 01 ESS- 03 ESS- 04 ESS- 05<br />

ESS- 06 EKS- 02<br />

Project Management Unit (PMU-EINRIP) Page 16


EINRIP 2010 Annual Progress Report<br />

In 2010, it was generally agreed between Bina Marga and AusAID that the four packages in<br />

South Kalimantan will be removed from the EINRIP program, primarily due to funding shortfall<br />

for construction and no confirmed source of funding for land acquisition.<br />

3.2. Summary Progress on ESS for 2010<br />

The progress of ESS activities during 2009 is presented below.<br />

The status of environmental and Social Safeguards Studies is shown in Appendix 1.<br />

1. EBL-01: Tohpati - Kusamba, Bali Province<br />

UKL/UPL required for bridge <strong>com</strong>ponents was <strong>com</strong>pleted and approved by DGH and<br />

BLHD/Bapedalda by June 2008. However, the UKL/UPL was only for bridge <strong>com</strong>ponents<br />

based on Regulation of the Minister of Environment No. 14/2010 on activities that already<br />

have Business License but do not have Environment Document. This package should<br />

now have DPLH/EMD (Dokumen Pengelolaan Lingkungan Hidup/Environmental<br />

Management Document) which should be prepared by proponent with time limit of<br />

October 2011.<br />

Land acquisition: There was no land required for this package.<br />

2. EBL-02: Tohpati - Kusamba Section, Bali Province<br />

Initially, the project only required Standard Operation Procedure (SOP). However, based<br />

on Regulation of the Minister of Environment No. 14/2010 on activities that already have<br />

Business License but do not have Environment Document, this package should have<br />

DPLH/EMD (Dokumen Pengelolaan Lingkungan Hidup/Environmental Management<br />

Document) which should be prepared by proponent with time limit by October 2011.<br />

Land acquisition: There was no land required for this package.<br />

3. EKB-01: Pontianak - Tayan, West Kalimantan Province<br />

Initially, the project only required Standard Operation Procedure (SOP). However, based<br />

on Regulation of the Minister of Environment No. 14/2010 on Activities that already have<br />

Business License but do not have Environment Document, this package should have<br />

DPLH/EMD (Dokumen Pengelolaan Lingkungan Hidup/Environmental Management<br />

Document) which should be prepared by proponent by October 2011.<br />

Land acquisition: Process of land acquisition is <strong>com</strong>plete, and LARAP monitoring report<br />

<strong>com</strong>pleted and submitted. Land certification is under process by Local Government (for all<br />

land affected by project in Kabupaten Sanggau and Kubu Raya) and will be monitored in<br />

2011.<br />

4. ENB-01AB: Sumbawa Besar Bypass, NTB/West Nusa Tenggara Province<br />

UKL/UPL was required, has been <strong>com</strong>pleted and approved by DGH and BLHD/Bapedalda<br />

in August 2008.<br />

Land acquisition: Process is <strong>com</strong>plete, LARAP monitoring report <strong>com</strong>pleted and<br />

submitted. Land certification process is <strong>com</strong>plete by Local Government (only for land<br />

Project Management Unit (PMU-EINRIP) Page 17


EINRIP 2010 Annual Progress Report<br />

affected by project with certified right of ownership), but the data has not been received by<br />

PMU. Further investigation and <strong>com</strong>pletion will follow in 2011.<br />

5. ENB-01C: Pal IV - Km 70, NTB/West Nusa Tenggara Province<br />

UKL/UPL was required, has been <strong>com</strong>pleted and approved by DGH and BLHD/Bapedalda<br />

in December 2008.<br />

Land acquisition: process in now <strong>com</strong>plete and LARAP monitoring report <strong>com</strong>pleted and<br />

submitted in December 2009. Land certification is planned by Local Government (only for<br />

land affected by project with certified right of ownership) and will be monitored in 2011.<br />

6. ENB-02: Km 70 - Bts. Cabdin Dompu, West Nusa Tenggara Province (NTB)<br />

UKL/UPL was required, has been <strong>com</strong>pleted and approved by DGH and BLHD/Bapedalda<br />

in December 2008.<br />

Land acquisition: LARAP monitoring report was <strong>com</strong>pleted and submitted in December<br />

2009. All PAPs for this project have received <strong>com</strong>pensation. Three (3) PAPs have been<br />

<strong>com</strong>pensated on behalf of beneficiaries and four (4) PAPs were <strong>com</strong>pensated through<br />

village head in Ds. Penginapan Pindang. LARAP <strong>com</strong>pletion report is <strong>com</strong>plete. Land<br />

certification is planned by local government (only for land affected by project with certified<br />

right of ownership) and will be monitored in 2011.<br />

7. ENB-03: Bts. Cabdin Dompu - Banggo, West Nusa Tenggara Province (NTB)<br />

UKL/UPL was required, has been <strong>com</strong>pleted and approved by DGH and<br />

BLHD/Bapedalda.<br />

Land acquisition: Process of land acquisition is now <strong>com</strong>plete and LARAP monitoring<br />

report <strong>com</strong>pleted and submitted in December 2009. Land certification is planned in 2010<br />

by Local Government (only for land affected by project with certified right of ownership)<br />

and will be monitored in 2011.<br />

8. ESR-01: Tinanggea – Kasipute, South East Sulawesi Province<br />

UKL/UPL was required, has been <strong>com</strong>pleted and approved by DGH and BLHD in<br />

February 2009.<br />

Land acquisition: Process is <strong>com</strong>plete, LARAP monitoring report <strong>com</strong>pleted and<br />

submitted. Land certification is planned in 2010 by each Local Government (for all land<br />

affected by project in Kab Bombana and only for land affected by project with certified<br />

right of ownership in Kab Konawe Selatan) and will be monitored in 2011.<br />

9. ESR-02: Bambae - Kasipute, South East Sulawesi Province<br />

UKL/UPL was required, has been <strong>com</strong>pleted and approved by DGH and BLHD/Bapedalda<br />

in September 2008.<br />

Land acquisition: Final LARAP Monitoring Report of this package was <strong>com</strong>pleted in April<br />

2010; however evidence of land acquisition from 2 PAPs is still outstanding. It has been<br />

requested from the LG in early May 2010 and datasets for 10 PAP have been presented<br />

Project Management Unit (PMU-EINRIP) Page 18


EINRIP 2010 Annual Progress Report<br />

so far. The final evidence for the 2 remaining PAPs was collected from the Kabupaten by<br />

the PPK and provided for verification. Land certification is planned in 2011.<br />

10. ESU-01: Molibagu - Mamalia - Taludaa, North Sulawesi Province<br />

The project required only UKL/UPL, which was <strong>com</strong>pleted and approved by August 2008.<br />

Land acquisition: The acquisition <strong>com</strong>pensation of this project was only for trees and<br />

building, while for land is through donation. There are only 16 People affected by the<br />

Project. Hence this project required only a Simple LARAP (SLARAP). SLARAP process is<br />

<strong>com</strong>plete, and Simple LARAP Monitoring Report <strong>com</strong>pleted on December 2008. No<br />

program of certification for land affected by project.<br />

11. ENT-01: Ende - Aegela, East Nusa Tenggara Province<br />

The project required only UKL/UPL, which was <strong>com</strong>pleted and approved by March 2009.<br />

Land acquisition: LARAP and pleno meeting has finished. Evidence of payment is<br />

<strong>com</strong>plete and a Final Monitoring Report was submitted to PMU in June 2010, for further<br />

submission to AusAID. The report was accepted by AusAID on 20 July 2010.<br />

12. ESH-01: Lakuan - Buol, Central Sulawesi Province<br />

The project required only UKL/UPL, which was <strong>com</strong>pleted and approved by March 2008.<br />

Land acquisition: LARAP has finished. The Draft LARAP Monitoring Report was sent to<br />

PMU/EMU in June 2010 and this was formally sent to AusAID by DGH on 13 August<br />

2010. After the review, AusAID issued acceptance of the report for <strong>com</strong>pliance with the<br />

ESS guidelines on 25 August 2010 and NOL for Contract and Disbursement was issued<br />

on 25 August 2010 as well. Land certification is planned in 2010/2011 by local<br />

government for all land affected project and will be monitored in 2011.<br />

13. ESS-01: Sengkang - Impaimpa - Tarumpakke, South Sulawesi Province<br />

Initially, the project only required Standard Operation Procedure (SOP). However, based<br />

on Regulation of the Minister of Environment No. 14/2010 on Activities that already have<br />

Business License but do not have Environment Document, this package should now have<br />

DPLH/EMD (Dokumen Pengelolaan Lingkungan Hidup/Environmental Management<br />

Document) which should be prepared by proponent with time limit of October 2011.<br />

Land acquisition: LARAP is finished and payment process has finished. Comparison of<br />

<strong>com</strong>pensation payment evidence to PAP with the LARAP‟ s list of approved PAP shows<br />

that all PAPs have been paid <strong>com</strong>pensation expect for seven in land dispute cases, which<br />

is being proposed an appeal in court therefore no decision on land disputes in 2010.<br />

Further investigation and <strong>com</strong>pletion will follow in 2011. However, the parties involved in<br />

the dispute have indicated that they will not obstruct the road construction and that the<br />

winner of the dispute case will receive the <strong>com</strong>pensation. LA monitoring report was<br />

<strong>com</strong>pleted in December 2009. Land certification is planned in 2010 for all land affected<br />

project and will be monitored in 2011.<br />

Project Management Unit (PMU-EINRIP) Page 19


EINRIP 2010 Annual Progress Report<br />

14. ESS-02 : Bantaeng - Bulukumba, South Sulawesi Province<br />

Initially, the project only required Standard Operation Procedure (SOP). However, based<br />

on Regulation of the Minister of Environment No. 14/2010 on Activities that already have<br />

Business License but do not have Environment Document, this package should have<br />

DPLH/EMD (Dokumen Pengelolaan Lingkungan Hidup/Environmental Management<br />

Document) which should be prepared by proponent with by October 2011.<br />

Land acquisition: Process is <strong>com</strong>plete, LARAP monitoring report <strong>com</strong>pleted and<br />

submitted. Land certification is planned in 2010 by each Local government (for all land<br />

affected by project in kab Bulukumba and only for land affected by project with certified<br />

right of ownership in Kab Bantaeng) and will be monitored 2011.<br />

This package has <strong>com</strong>menced work since mid of October 2009, and still under<br />

construction work. Unfortunately there are no longitudinal drainage proposals, and<br />

proposed to discharge road drainage from outlet onto adjacent private land. Therefore it<br />

was thought by RSC that further land acquisition required, however they tried to develop<br />

an alternative that requires very little land or absolutely no land required.<br />

15. ESS-03: Janeponto - Bantaeng, South Sulawesi Province<br />

The project required only UKL/UPL, which was <strong>com</strong>pleted and approved by July 2009.<br />

Land acquisition: There are 1,187 people affected by project. LARAP and pleno meeting<br />

is finished. LG is in process of <strong>com</strong>pensation payment. In Bantaeng, all PAPs (124<br />

households) have been paid, and evidences have been submitted to Satker. In<br />

Jeneponto, <strong>com</strong>pensations have been paid for land and building. However, there are 16<br />

mosques and there is one PAP who has six lots of land, that has not been fully paid for<br />

land and building. The LG of Jeneponto has received additional funds from the Province<br />

of South Sulawesi around IDR 82 million to <strong>com</strong>plete the land acquisition process.<br />

Subsequently, <strong>com</strong>pletion LARAP monitoring report will be submitted by end of January<br />

2011 after data is <strong>com</strong>pleted.<br />

16. ESS-04, ESS-05 & ESS-06: Bulukumba – Tondong – Sinjai, South Sulawesi Province<br />

There is one AMDAL for three packages. Final Draft ANDAL-RKL-RPL documents have<br />

been submitted and formally <strong>com</strong>mented on by the AMDAL Commission at BLHD<br />

Makassar in May 2010. The AMDAL Consultant has revised ANDAL-RKL-RPL documents<br />

incorporating their <strong>com</strong>ments. The final documents have been sent on 27 September<br />

2010, and have been approved by the Governor. These documents have been submitted<br />

to Bintek and PMU on October 1st, 2010.<br />

Land acquisition: In Bulukumba Regency (ESS-04 and ESS-05), pleno meeting has<br />

finished (20 July 2010) and LARAP revised report was submitted by DGH to EMU –<br />

AusAID on 12 August 2010. Proposal for delivering payment to peoples affected project<br />

has submitted to Satker/SNVT, unfortunately <strong>com</strong>pensation fund from APBN-P 2010<br />

cannot be disbursed due to lack of data from LG of Bulukumba. Completion data is being<br />

prepared by LA Committee, and LARAP monitoring report will be submitted after data is<br />

<strong>com</strong>pleted.<br />

In Kab Sinjai (ESS-05 and ESS-06), a pleno meeting was held and finished on 29<br />

September 2010. LARAP revised report has been submitted to PMU and EMU. Local<br />

government has proposed data of peoples affected project who should receive payment of<br />

Project Management Unit (PMU-EINRIP) Page 20


EINRIP 2010 Annual Progress Report<br />

<strong>com</strong>pensation. Unfortunately, <strong>com</strong>pensation fund from APBN-P 2010 cannot be disbursed<br />

due to lack of data from LG Sinjai. Completion data is being prepared by LA Committee,<br />

and LARAP monitoring report will be submitted after data is <strong>com</strong>pleted.<br />

17. EKS-01: Martapura - Ds. Tungkap, South Kalimantan Province<br />

Initially, the project only required Standard Operation Procedure (SOP). However, based<br />

on Regulation of the Minister of Environment No. 13/2010 on Environmental Management<br />

Effort and Environmental Monitoring Effort, this package should have SPPL/SEMM (Surat<br />

Pernyataan Kesanggupan Pengelolaan dan Pemantauan Lingkungan Hidup/Statement<br />

letter of readiness on Environmental Management and Monitoring).<br />

Land acquisition: Data of evidence payment was <strong>com</strong>pleted in May 2010. LARAP<br />

monitoring report has been finished and submitted. There is no program of land<br />

certification for this package.<br />

18. EKS-02: Banjarmasin - Bts. Kalteng, South Kalimantan Province<br />

Initially, the project only required Standard Operation Procedure (SOP). However, based<br />

on Regulation of the Minister of Environment No. 13/2010 on Environmental Management<br />

Effort and Environmental Monitoring Effort, this package should have SPPL/SEMM (Surat<br />

Pernyataan Kesanggupan Pengelolaan dan Pemantauan Lingkungan Hidup/Statement<br />

letter of readiness on Environmental Management and Monitoring).<br />

Land acquisition: The Kabupaten LA team carried out appraisal of land, buildings, and<br />

trees. Land measurement and verification by BPN finished during August 2010. During<br />

survey by BPN, discrepancy was noted between PMSC measurements. To clarify this and<br />

to streamline the <strong>com</strong>pensation process, PMSC Environmental Specialist and Highway<br />

Engineer visited Kabupaten Barito Kuala and held coordination meeting with Land<br />

Acquisition Committee. There is now agreement on measurements, as the cause of<br />

discrepancy was different ROW widths and different perception of ROW maps scale.<br />

The LG has <strong>com</strong>pleted payment process by end of September 2010 for building. Payment<br />

evidence has been submitted to PMSC. Monitoring Report <strong>com</strong>pleted and submitted.<br />

Land certification is planned in 2011 for all land affected project by local government and<br />

will be monitored.<br />

19. EKS-03: Jl. A. Yani (Martapura - Ds. Tungkap), South Kalimantan Province<br />

UKL/UPL was required, has been <strong>com</strong>pleted and approved by DGH and BLHD in May<br />

2009.<br />

Land acquisition: The preparation of the LARAP documents was <strong>com</strong>pleted on April 2009.<br />

There is no process of <strong>com</strong>pensation payment, because no budget for land acquisition.<br />

This package has been removed from the EINRIP.<br />

20. EKS-04: Ds. Tungkap - Rantau, South Kalimantan Province<br />

UKL/UPL was required, has been <strong>com</strong>pleted and approved by DGH and BLHD in April<br />

2009.<br />

Project Management Unit (PMU-EINRIP) Page 21


EINRIP 2010 Annual Progress Report<br />

Land acquisition: LARAP documents and pre-plenum has been finished. There is no<br />

process of <strong>com</strong>pensation payment, because no budget for land acquisition. This package<br />

has been removed from the EINRIP.<br />

21. EKS-05 and EKS-06: Ds. Barabai - Mantimin - Dahai, South Kalimantan Province<br />

There are two packages (EKS-05 and EKS-06) that require Environmental Impact<br />

Assessment/AMDAL. TOR of EIA (KA-ANDAL) has been discussed with BLHD<br />

Kabupaten Tapin in November 2009 and waiting for approval.<br />

Land acquisition: There are 4,584 people affected by project, LARAP and Pre Pleno<br />

meeting was finished. Process of <strong>com</strong>pensation payment is not yet available, because<br />

there is no budget for land <strong>com</strong>pensation. This package has been removed from the<br />

EINRIP.<br />

Project Management Unit (PMU-EINRIP) Page 22


EINRIP 2010 Annual Progress Report<br />

4. Procurement of Civil Works<br />

The Procurement Advisory Services (PAS) consultancy was initially scheduled to start work in<br />

the middle of 2008. However, due to delays, the final contract was signed on December 2008.<br />

The PAS team then mobilised and was on board by start of 2009. In the interim, the PPC<br />

Consultants provided the interim procurement services for second half of 2008.<br />

4.1. EINRIP Procurement Activities<br />

The procurement for civil works for EINRIP is undertaken by DGH, through Procurement<br />

Committees (PC) which are appointed under the Provincial Work Unit for Road Construction<br />

(Satker Pembangunan Jalan) in each involved province.<br />

Broad responsibilities of PC include:<br />

Finalising the bidding documents<br />

Preparing the procurement schedule<br />

Advertising the tender<br />

Uploading essential information to the internet for E-procurement<br />

Opening and recording the tenders<br />

Evaluation and post qualification of the bids<br />

Preparing the bid evaluation report<br />

The role of PAS is to provide ongoing assistance at key points and if possible help speed up the<br />

process.<br />

Review all arrangements made to support project procurement, including the “readiness”<br />

of the procurement <strong>com</strong>mittee;<br />

Ensure that World Bank Guidelines are followed in the procurement;<br />

Provide procurement training and capacity building;<br />

Assist PC in responding to queries and clarification sought by bidders before bid opening<br />

date;<br />

Oversee implementation of measures/protocols to avoid fraud and collusion in bidding;<br />

Attend bid opening for all procurement exercises and certify the Minutes of Bid Opening<br />

and any clarification of bids; and<br />

Provide a report to DGH on each procurement exercise.<br />

The approval of the Minister of Public Works is required for award of contracts over Rp. 50<br />

billion.<br />

AusAID undertakes prior review and approval of all civil work procurement and issue No<br />

Objection Letters (NOLs) at three key stages of the procurement process:<br />

NOL to start Procurement;<br />

NOL for Contract Award (Bid Evaluation Report); and<br />

NOL for Contract and Disbursement.<br />

Project Management Unit (PMU-EINRIP) Page 23


EINRIP 2010 Annual Progress Report<br />

In addition, AusAID NOL is also required for:<br />

NOL for Addendum to Bidding Documents; and<br />

NOL for holding Pre-Bid Meeting.<br />

4.2. Procurement Activities in 2010<br />

Following on from the procurement activities in 2009, where a total of 12 contracts were<br />

awarded, in 2010, total five contracts were awarded and bidding process for one package ESS-<br />

04 was ongoing at end of 2010.<br />

Conditional NOL to start procurement was issued for packages ESS-05 and ESS-06 in<br />

December 2010.<br />

Summary of contracts awarded by end of 2010 is presented in the following Table 4-1, and the<br />

summary of procurement activities (for active packages for 2010) is also presented.<br />

No.<br />

Package No.<br />

NOL<br />

Procurement<br />

Invitation for<br />

Bids Date<br />

Bid Opening<br />

Date<br />

NOL Award<br />

Contract<br />

Signature<br />

Date<br />

NOL<br />

Disbursement<br />

Civil Works awarded in 2009<br />

1 EBL-01 4-Aug-08 6-Aug-08 19-Sep-08 20-Nov-08 5-Dec-08 11-Dec-08<br />

2 EKB-01 5-Sep-08 9-Sep-08 29-Oct-08 24-Mar-09 20-Apr-09 19-May-09<br />

3 ENB-01AB 2-Sep-08 4-Sep-08 3-Nov-08 10-Feb-09 16-Mar-09 1-Apr-09<br />

4 ENB-01C 30-Apr-09 12-Jun-09 4-Aug-09 5-Nov-09 9-Dec-09 11-Dec-09<br />

5 ESR-01 25-Aug-08 28-Aug-08 5-Nov-08 12-Feb-09 2-Apr-09 4-May-09<br />

6 ESS-01 23-Apr-09 1-May-09 11-Jun-09 9-Oct-09 10-Dec-09 14-Dec-09<br />

7 ESS-02 29-Aug-08 3-Sep-08 6-Nov-08 8-Apr-09 19-May-09 23-Jul-09<br />

8 ESU-01 20-Mar-09 31-Mar-09 4-Jun-09 11-Nov-09 2-Dec-09 9-Dec-09<br />

9 ENB-02 26-May-09 17-Jun-09 4-Aug-09 18-Nov-09 14-Dec-09 16-Dec-09<br />

10 ENB-03 10-Jun-09 22-Jun-09 25-Aug-09 2-Dec-09 10-Dec-09 14-Dec-09<br />

11 ESR-02 20-May-09 5-Jun-09 22-Jul-09 8-Oct-09 2-Dec-09 23-Dec-09<br />

12 EBL-02 10-Jun-09 23-Jun-09 26-Aug-09 5-Nov-09 10-Dec-09 14-Dec-09<br />

Civil Works awarded in 2010<br />

13 EKS-01 11-Feb-09 10-Mar-10 27-Apr-10 7-Oct-10 5-Nov-10 1-Dec-10<br />

14 EKS-02 17-Feb-09 10-Mar-10 27-Apr-10 20-Jul-10 6-Oct-10 22-Nov-10<br />

15 ESH-01 11-Sep-09 5-Oct-09 27-Jan-10 12-Apr-10 25-May-10 25-Aug-10<br />

16 ESS-03 21-Aug-09 27-Aug-09 6-Nov-09 11-Jan-10 19-Mar-10 15-Dec-10<br />

17 ENT-01 15-Jun-10 23-Jul-10 2-Sep-10 6-Dec-10 17-Dec-10 20-Dec-10<br />

18 ESS-04 28-Jul-10 10-Aug-10 21-Sep-10 23-Dec-10<br />

ICB for Goods<br />

1 ESB-02 22-Sep-08 25-Sep-08 6-Nov-08 2-Dec-08 15-Dec-08 15-Dec-08<br />

Table 4-1 Packages with Procurement Completed by end of 2010<br />

Project Management Unit (PMU-EINRIP) Page 24


EINRIP 2010 Annual Progress Report<br />

1. EBL- 02, Tohpati – Kusamba Stage 2<br />

The NOL for Award was issued by AusAID on 5 November 2009. After the approval of the<br />

Minister, the contract was signed on 10 December 2009. PAS also undertook additional<br />

reviews on the draft contract. The NOL for Contract and Disbursement was issued on 14<br />

December 2009. Procurement was <strong>com</strong>pleted in 2009.<br />

In January 2010, there was a claim by one of the bidders PT Yasa Patria Perkasa who<br />

were disqualified on basis of equipment. Their claim was evaluated by PAS and Minister‟ s<br />

office upheld the earlier evaluation decision of failure on equipment.<br />

The contract <strong>com</strong>menced construction on 1 March 2010.<br />

2. ESH- 01, Lakuan – Buol<br />

After <strong>com</strong>pletion of Procurement Committee training in May 2009, bid documents were<br />

prepared in June 2009. AusAID issued NOL to start procurement on 11 September 2009.<br />

The bids were advertised on 5 October 2009 and tentatively the bid opening was fixed at 27<br />

November 2009. However, due to discussions on revision of post-qualification criteria for<br />

bid evaluation, an Addendum was prepared and issued on 16 November 2009 and bid<br />

opening was revised to 17 December 2009. In first week of December 2009, further<br />

discussion continued on evaluation of personnel and equipment and it was decided that bid<br />

opening be deferred to 2010.<br />

Bid opening was finally fixed at 27 January 2010 and the bid opening was held in Palu. The<br />

bid evaluation continued between early February and April 2010 and the BER with PAS<br />

review was submitted to AusAID on 25 March 2010. On 12 April 2010, AusAID issued the<br />

NOL to Bid Evaluation Report.<br />

Minister‟ s approval on PC BER was issued on 5 May 2010 and the contract was signed on<br />

25 May 2010. The NOL for Contract and Disbursement was issued by AusAID on 25<br />

August 2010.<br />

The contract <strong>com</strong>menced construction on 7 October 2010<br />

3. EKS-01: Martapura – Ds. Tungkap, South Kalimantan Province<br />

After verification of the <strong>com</strong>pleteness and consistency of bid documents by PAS<br />

consultants, the NOL to start procurement was issued by AusAID on 11 February 2010.<br />

The bid opening of package EKS-01 was conducted on 27 April 2010 in Banjarmasin and<br />

eighteen (18) bidders submitted the bid proposal.<br />

During May 2010, preliminary bid evaluation continued and the BER with PAS review was<br />

submitted to AusAID in end of May 2010. AusAID responded on 27 May 2010 with<br />

significant reservations about the evaluation and re<strong>com</strong>mendations and requested that the<br />

BER be revised and re-submitted.<br />

After a series of meetings and correspondence, AusAID in their review on 20 July 2010,<br />

agreed to the disqualification of Conbloc and Sumber Sari Cipta Maga, Lampiri Djaya<br />

Abadi-Raden Panji Soeprapto JO, Agrabudi Karya Marga, Duta Graha Indah and Citra<br />

Gading, but did not consider that disqualification of Bumi Rejo was supported by the<br />

evaluation.<br />

On 7 September 2010, PAS submitted letter of review on addendum to BER prepared by<br />

the PC. On 21 September 2010, Directorate of Planning sent the revised Bid Evaluation<br />

Project Management Unit (PMU-EINRIP) Page 25


EINRIP 2010 Annual Progress Report<br />

Report. The revised BER proposed the first lowest winner candidate as PT. Adhi Karya,<br />

Persero and the second lowest winner candidate to be PT. Bumi.<br />

The NOL to BER was issued by AusAID on 7 October 2010 with re<strong>com</strong>mendation that<br />

performance security of 10% of Owner‟ s Estimate should be provided.<br />

After approval from Minister‟ s office, the contract as signed on 5 November 2010 and<br />

AusAID issued the NOL for Contract and Disbursement on 1 December 2010.<br />

Contract will <strong>com</strong>mence construction in January 2011.<br />

4. EKS-02: Banjarmasin – Bts. Kalteng, South Kalimantan Province<br />

After verification of the <strong>com</strong>pleteness and consistency of bid documents by PAS<br />

consultants, the NOL to start procurement was issued by AusAID on 17 February 2010.<br />

The bid opening of package EKS-01 was conducted on 27 April 2010 in Banjarmasin and<br />

eighteen (18) bidders submitted the bid proposal.<br />

During May and June 2010, preliminary bid evaluation continued and the BER with PAS<br />

review was submitted to AusAID on 7 July 2010. The NOL to BER was issued by AusAID<br />

on 20 July 2010 with re<strong>com</strong>mendation that performance security of 10% of Owner‟ s<br />

Estimate should be provided.<br />

After approval from Minister‟ s office for the BER on 25 August 2010, the contract was<br />

signed on 6 October 2010 and AusAID issued the NOL for Contract and Disbursement on<br />

22 November 2010.<br />

Contract will <strong>com</strong>mence construction in January 2011.<br />

5. ESS- 03, Jeneponto – Bantaeng<br />

The bidding documents were prepared by PC in June 2009 and review of bid documents<br />

was conducted by PAS in July 2009. AusAID issued NOL to start procurement on 21<br />

August 2009.<br />

Bids for ESS-03 were opened on 6 November 2009. The Bid Evaluation Report (BER) was<br />

reviewed by PAS and re<strong>com</strong>mendations provided to the PC and Directorate of Eastern<br />

Region. The BER was finalised in December 2009 and submitted to AusAID on 23<br />

December 2009.<br />

On 11 January 2010, AusAID issued the NOL to the Bid Evaluation Report on the condition<br />

that final NOL will not be issued until <strong>com</strong>pletion of LARAP process for land acquisition.<br />

While the process of land acquisition continued, the approval from Minister‟ s Office was<br />

issued in March 2010, and the contract with lowest bidder (PT Bumi Karsa and PT Nindya<br />

Karya) was signed on 19 March 2010.<br />

Major part of remaining months in 2010 was focussed on <strong>com</strong>pletion of land acquisition and<br />

it was still in<strong>com</strong>plete by the end of 2010. Outstanding land <strong>com</strong>pensation activities<br />

included evidence of land <strong>com</strong>pensation, in<strong>com</strong>plete payment for 16 mosques and 17 plots<br />

in Janeponto and verification of number of affected people.<br />

On 15 December 2010, AusAID issued the NOL to Contract and Disbursement on the<br />

condition that the LARAP monitoring report should be revised in January 2011.<br />

It is expected that construction can <strong>com</strong>mence in 2011 after <strong>com</strong>pletion of land acquisition<br />

process.<br />

Project Management Unit (PMU-EINRIP) Page 26


EINRIP 2010 Annual Progress Report<br />

6. ENT- 01, Ende – Aegela<br />

On 19 to 21 January 2010, PAS conducted the procurement training and assessment of the<br />

readiness of PC in Satker Office in Ende, Flores, NTT. The review of the documents was<br />

carried out and <strong>com</strong>pleted by early June 2010. Bid documents were submitted to AusAID<br />

on 9 June 2010 and on 15 June 2010, AusAID issued the NOL to start procurement.<br />

Upon a request from DGH on holding a pre-bid meeting on 23 July 2010, AusAID issued No<br />

objection letter on 26 July 2010 and agreed to holding of a pre-bid conference. The pre-bid<br />

meeting and site visit was held on 2-5 August 2010. The minutes of the pre-bid meeting<br />

were also issued and copied to AusAID.<br />

The Bid opening was held in Ende, Flores on 2 September 2010, there were 10 bids<br />

submitted, among them PT. Nindya-Bumi Karsa JO submitted the lowest bid price.<br />

Bid evaluation continued upto mid-November 2010 and the BER was submitted by DGH on<br />

26 November 2010. On 6 December 2010, AusAID issued the NOL to the Bid Evaluation<br />

Report with the re<strong>com</strong>mendation that performance security of 10% of Owner‟ s Estimate<br />

should be provided.<br />

After approval from Minister‟ s office for the BER, the contract was signed on 17 December<br />

2010 and AusAID issued the NOL for Contract and Disbursement on 20 December 2010.<br />

Contract will <strong>com</strong>mence construction in 2011.<br />

7. ESS- 04, Jeneponto – Bantaeng<br />

From 16-17 June 2010, PAS together with the PC carried out the review of the Bid<br />

Document and finalized for submission to AusAID. On 28 July 2010, AusAID issued NOL to<br />

start procurement with conditions to be <strong>com</strong>pleted before next NOL is issued. These related<br />

to <strong>com</strong>pletion of land acquisition and AMDAL process.<br />

The pre-bid meeting was held on 18-19 August 2010 with a site visit organised as well.<br />

The bid opening held in Makassar on 21 September 2010, with 14 bids submitted.<br />

Bid evaluation continued to the end of 2010 and will be finalised in 2011.<br />

8. ESS- 05 (Bulukumba – Tondong) & ESS-06 (Bulukumba – Tondong - Sinjai)<br />

For these two packages in South Sulawesi, the PAS consultants carried out the review of<br />

the bid documents with the PC during June 2010 and the final documents were submitted<br />

to AusAID on 16 July 2010. Although the status of land acquisition is still unclear and<br />

<strong>com</strong>pensation process has not been <strong>com</strong>pleted, AusAID issued the NOL to start<br />

procurement on 15 December 2010, on the conditions that:<br />

Procurement schedule to be revised;<br />

Pre-bid briefing is provided; and<br />

Procurement advisory support to be provided.<br />

The procurement will <strong>com</strong>mence in 2011.<br />

4.3. Procurement Plans<br />

The Project Procurement Plan is the guiding plan for procurement of works and it identifies the<br />

key milestone dates during the procurement process.<br />

Project Management Unit (PMU-EINRIP) Page 27


EINRIP 2010 Annual Progress Report<br />

Each procurement plan revision is to be submitted to AusAID for their NOL before procurement<br />

can <strong>com</strong>mence. Subsequent amendments to the Plan must also be submitted to AusAID for<br />

their NOL.<br />

In 2010, two plans were prepared and submitted to AusAID.<br />

Procurement Plan Version No. 5 was approved by AusAID on 8 January 2010.<br />

Procurement Plan Version No. 6 was approved by AusAID on 8 June 2010.<br />

Appendix 2 presents the Procurement Plan version 5 & 6 approved in 2010.<br />

Appendix 3 presents the status of Procurement Plan Version 6 at 31 December 2010.<br />

Project Management Unit (PMU-EINRIP) Page 28


EINRIP 2010 Annual Progress Report<br />

5. Implementation of Civil Works (Construction)<br />

Up to the end of 2009, Commencement Date has been issued for 5 packages.<br />

In 2010, Commencement Date was issued for 8 more packages, and NOL for Contract and<br />

Disbursement was awarded to another 4 packages (EKS-01, EKS-02, ESS-03 and ENT-01), for<br />

which construction is expected to <strong>com</strong>mence in 2011.<br />

Thus by end of 2010, total 13 packages out of 20 were under construction.<br />

List of Packages for which Commencement Date has been issued are shown in Table 5-1. The<br />

table also presents the summary of progress as at 31 December 2010.<br />

Package<br />

EBL-01<br />

EBL-02<br />

EKB-01<br />

ESU-01<br />

ENB-01AB<br />

ENB-01C<br />

ENB-02<br />

ENB-03<br />

ESR-01<br />

ESR-02<br />

ESS-01<br />

ESS-02<br />

ESH-01<br />

Location<br />

Bali<br />

Tohpati – Kusamba<br />

Bali<br />

Tohpati – Kusamba<br />

Stage 2<br />

West Kalimantan<br />

Pontianak - Tayan<br />

North Sulawesi<br />

Molibagu - Mamalia -<br />

Taludaa<br />

West Nusa Tenggara<br />

Sumbawa Besar<br />

Bypass<br />

West Nusa Tenggara<br />

Pal IV - Km 70<br />

West Nusa Tenggara<br />

Km 70 - Bts. Cadbin<br />

Dompu<br />

West Nusa Tenggara<br />

Bts. Cadbin Dompu -<br />

Banggo<br />

South East Sulawesi<br />

Tinanggea - Kasipute<br />

South East Sulawesi<br />

Bambaea - Sp.<br />

Kasipute<br />

South Sulawesi<br />

Sengkang - Impa Impa<br />

- Tarumpakkae<br />

South Sulawesi<br />

Bantaeng - Bulukumba<br />

Central Sulawesi<br />

Lakuan – Buol<br />

Commencement<br />

Date<br />

Physical Progress<br />

31-December-2010<br />

Planned Actual Deviation<br />

Financial<br />

Progress<br />

25 Feb 2009 96,35 % 74,26 % 22.09 % 62.2%<br />

1 Mar 2010 30.01 % 32.64 % + 2.63 % 36.6%<br />

24 Jul 2009 71.02 % 66.45 % - 4.56 % 62.5%<br />

1 Mar 2010 29.50 % 8.63 % - 20.87 % 18.1%<br />

5 Jun 2009 81.30 % 54.03 % - 27.28 % 50.6%<br />

1 Mar 2010 27.70 % 8.53 % - 19.16 % 18.8%<br />

6 Apr 2010 41.63 % 5.22 % - 36.41 % 16.7%<br />

1 Mar 2010 15.84 % 6.50 % - 9.34 % 19.7%<br />

13 Jul 2009 73.74 % 26.86 % - 46.88 % 33.9%<br />

30 Apr 2010 21.14 % 14.07 % - 7.07 % 25.4%<br />

1 Mar 2010 21.11 % 11.51 % - 9.60 % 18.3%<br />

15 Oct 2009 57.50 % 17.20 % - 40.31 % 24.4%<br />

7 October 2010 3.19 % 3.38 % + 0.19 % 12.9%<br />

Table 5-1 List of Projects Commenced by end of Dec 2009<br />

The projects that have been awarded NOL for Contract and Disbursement was issued and<br />

advance payment processed in December 2010 are shown in Table 5-2<br />

Project Management Unit (PMU-EINRIP) Page 29


EINRIP 2010 Annual Progress Report<br />

Contracts awarded but not <strong>com</strong>menced by December 2010<br />

No<br />

Package<br />

No<br />

Province<br />

Location<br />

Contract<br />

Signature<br />

NOL<br />

Disbursement<br />

1 EKS-01 South Kalimantan Martapura - Ds. Tungkap 5-Nov-10 1-Dec-10<br />

2 EKS-02 South Kalimantan Banjarmasin-Bts.Kalteng 6-Oct-10 22-Nov-10<br />

3 ESS-03 South Sulawesi Janeponto - Bantaeng 19-Mar-10 15-Dec-10<br />

4 ENT-01 NTT Ende - Aegela 17-Dec-10 20-Dec-10<br />

Table 5-2<br />

List of projects awarded of NOL (Disbursement)<br />

5.1. Summary of On-going Contracts<br />

The <strong>detail</strong>ed contract data for five contracts awarded and where construction work has<br />

<strong>com</strong>menced is shown in Appendix 4.<br />

Project Management Unit (PMU-EINRIP) Page 30


EINRIP 2010 Annual Progress Report<br />

6. Procurement of Goods<br />

Under the EINRIP loan, the Goods category <strong>com</strong>prises two parts:<br />

i) Acquisition of pre-fabricated steel truss bridge material for replacement program for selected<br />

deteriorated bridges in Eastern and Western Indonesia; and<br />

ii) Provision of <strong>com</strong>munications/ office equipment for Project Management Unit (PMU).<br />

The original contract for steel truss bridge material was procured in Oct-Nov 2007, however,<br />

due to delays in obtaining funding, and as the loan did not be<strong>com</strong>e effective until March 2008,<br />

and increases in the cost of steel, the contract was cancelled for convenience in May 2008.<br />

The revised contract (ESB-02) was subsequently re-bid during September - November 2008<br />

and the bid of PT Karunia Berca Indonesia in the amount of IDR 50,529,504,300 was accepted<br />

and a contract was subsequently signed on 15-December 2008.<br />

The second <strong>com</strong>ponent of the Goods category for IT equipment was also removed from the<br />

procurement activities through a decision by Bina Marga.<br />

6.1. Contract Data for Goods Contract ESB-02<br />

Contract : ESB-02 for Supply of Prefabricated Steel Bridges<br />

Contract No : 01-20/ESB-02/BT/L002/1208<br />

Supplier : PT. Karunia Berca Indonesia<br />

Contract cost : Rp. 50,529,504,300<br />

Contract signature : 15-Dec-08<br />

Contract duration : 210 days<br />

Target <strong>com</strong>pletion : 13-Jul-09 (<strong>com</strong>pleted on schedule and on the actual price)<br />

Warranty Period : 360 days<br />

Progress Summary:<br />

At the time of the award of the contract, there was no supervision consultant identified in<br />

the General Conditions of Contract. In order to ensure proper professional supervision of<br />

supply of materials, the consultancy services agreement with EGIS BCEOM as the<br />

“Regional Supervision Consultant (RSC)” for the EINRIP project was amended through a<br />

Contract Memorandum No. 1 between DGH and BCEOM, signed on 4-May-2009.<br />

Letter of Appointment of the Supervision Engineer was issued on 6-May-2009.<br />

RSC Team Leader appointed Mr. Alain Debuissy as the Engineer‟ s Assistant, supported by<br />

an Inspector.<br />

RSC supervised the supply, fabrication and delivery of the steel bridge material in the<br />

contract through five site visits to KBI workshop in Cilegon, Java and to the delivery site at<br />

the Gudang Bina Marga at Citeureup, Bogor between May and July 2009. The RSC<br />

supervision did not find any major deficiency in the supplied material.<br />

The contract was <strong>com</strong>pleted in July 2009 and Final Report issued in August 2009.<br />

Project Management Unit (PMU-EINRIP) Page 31


EINRIP 2010 Annual Progress Report<br />

7. Financial Summary<br />

The financial progress for cumulative disbursements during 2010 has been lower than planned<br />

due to delays in award of contracts and delays in <strong>com</strong>mencement of procurement due to land<br />

acquisition process being in<strong>com</strong>plete. By 31 December 2010, only 27% of planned<br />

disbursements could be realised. Another key factor is slow process for filed engineering and<br />

preparation of sound technical justification for variation orders. Due to this slow aspect, many<br />

contractors are no slowing the works pending approval of Employer.<br />

7.1. Status of Loan Withdrawals, Payments and Disbursements<br />

Three withdrawal applications (WA) were processed to end of 2009. Another 3 applications<br />

were approved in 2010.<br />

Total loan withdrawals as on 31 December 2010 is A$ 91.27 million consisting of:<br />

WA No. 1 (23 April 2009) : A$ 8,177,894.00<br />

WA No. 2 (23 March 2009) : A$ 19,049,965.00<br />

WA No. 3 (23 June 2009) : A$ 24,999,965.00<br />

WA No. 4 (15 January 2010) : A$ 3,599,965.00<br />

WA No. 5 (15 March 2010) : A$ 9,725,965.00<br />

WA No. 6 (15 June 2010) : A$ 25,714,365.00<br />

‣ Payments Processed in 2010<br />

Total payment processed in 2010 is A$ 40.559 million, consisting of GOA payments from<br />

Special Account of A$ 36.153 million and contribution from GOI of A$ 4.406 million. Payments<br />

processed in 2010 are showed in Table 7-1.<br />

Category<br />

GOA<br />

A$ Million<br />

GOI<br />

A$ Million<br />

IDR AUD IDR AUD<br />

1 Civil Works<br />

EBL-01 (MC No. 11-22) 41,153.46 5.007 5,595.02 0.681<br />

EBL-02 (MC No. 1-9) 40,692.21 4.892 5,532.31 0.665<br />

ENB-01AB (MC No. 8-19) 17,602.71 2.057 2,393.18 0.280<br />

ENB-01C (MC No. 1-10) 10,400.83 1.198 1,414.05 0.163<br />

ENB-02 (MC No. 1- 9) 3,708.66 0.429 504.21 0.058<br />

ENB-03 (MC No. 1-10) 7,961.70 0.948 1,082.43 0.129<br />

ESR-01 (MC No. 6-18) 19,454.95 2.267 2,645.00 0.308<br />

ESR-02 (MC No. 1-8) 11,922.96 1.381 1,620.99 0.188<br />

EKB-01 (IMC No. 4-17) 54,696.26 6.532 7,436.23 0.888<br />

ESS-01 (MC No. 1-10) 6,823.30 0.763 927.66 0.104<br />

ESS-02 (MC No. 1-15) 14,476.88 1.727 1,968.21 0.235<br />

ESU-01 (MC No. 1-7) 2,785.14 0.331 378.65 0.045<br />

ESH-01 (MC No. 1-3) 10,707.12 1.237 1,353.19 0.157<br />

Project Management Unit (PMU-EINRIP) Page 32


EINRIP 2010 Annual Progress Report<br />

Category<br />

GOA<br />

A$ Million<br />

GOI<br />

A$ Million<br />

IDR AUD IDR AUD<br />

ESS-03 (Adv. Payment) 8,066.67 0.887 1,096.70 0.121<br />

EKS-01 (Adv. Payment) 6,902.79 0.764 938.47 0.104<br />

EKS-02 (Adv. Payment) 7,200.10 0.797 978.89 0.108<br />

ENT-01 (Adv. Payment) 10,718.50 1.179 1,457.23 0.160<br />

2 Goods<br />

ESB-02 - - - -<br />

3 IOC<br />

IOC 877.39 0.102 111.39 0.013<br />

4 Implementation Support<br />

PMSC (Dec. 2009-Dec. 2010) 6,477.03 0.750 - -<br />

RSC (Dec. 2009-Nov.2010) 18,590.11 2.151 - -<br />

PAS (Nov. 2009-Nov. 2010) 6,298,44 0.755 - -<br />

Total 307,517.22 36.153 37,433.82 4.406<br />

Table 7-1 Payments Processed in 2010<br />

Total cumulative payments up to 31 December 2010 are shown in Table 7-2 below:<br />

No<br />

Category<br />

Payments GOA<br />

(Million)<br />

Payments GOI<br />

(Million)<br />

Total<br />

(Million)<br />

IDR AUD IDR AUD IDR AUD<br />

1 Civil Works 430,124.65 51.168 58,375.12 6.945 488,499.77 58.114<br />

2 Goods 40,882.96 5.006 5,558.25 0.677 46,441.21 5.684<br />

3 IOC 2,525.99 0.312 318.44 0.039 2,844.44 0.351<br />

4<br />

Implementation<br />

Support<br />

84,431.45 10.438 0.00 0.000 84,431.45 10.438<br />

Total 557,965.05 66.924 64,251.81 7.662 622,216.859 74.586<br />

Table 7-2 EINRIP Cumulative Payments up to 31 December 2010<br />

‣ Payments Monitoring<br />

Appendix 5 presents the monthly expenditure charged to each Civil Works contract and other<br />

loan categories, processed upto the end of December 2010.<br />

Figure 7-1 shows the monthly expenditure as accumulated upto December 2010.<br />

Project Management Unit (PMU-EINRIP) Page 33


Expenditure (A$ 000)<br />

EINRIP 2010 Annual Progress Report<br />

EINRIP Cumulative Expenditure up to 31 December 2010<br />

(A$ 000)<br />

80.000,00<br />

74.586,57<br />

70.000,00<br />

60.000,00<br />

55.398,18 56.157,09 60.326,90<br />

50.000,00<br />

46.317,91<br />

49.435,88<br />

40.000,00<br />

43.540,30<br />

39.889,10 41.262,41<br />

35.523,42 36.539,72<br />

34.027,59 34.027,59<br />

30.000,00<br />

20.000,00<br />

10.000,00<br />

20.914,66 22.248,64<br />

20.198,33<br />

17.516,77<br />

12.548,50<br />

11.841,93<br />

7.871,78 8.684,82 10.159,94<br />

-<br />

37,48 47,91 71,53<br />

Month<br />

Figure 7-1 Cumulative Monthly Expenditure to Dec 2010<br />

7.2. Analysis of Planned Vs Actual Expenditure<br />

The year 2009 <strong>com</strong>menced with Version 3 of the Procurement Plan that was approved on 26-<br />

Jan-2009. Based on this plan, a cash expenditure profile for only Special Account (SA) was<br />

drawn up to form the basis of <strong>com</strong>parison of planned disbursements from the Special Account<br />

and the actual expenditures incurred.<br />

Based on Procurement Plan Ver 3, the planned disbursement from loan funds up to 31<br />

December 2010 was estimated at A$ 242.14 million. The actual payment during the same<br />

period is A$ 66.92 million, about 27.64% of planned disbursement. The primary reasons for<br />

lower expenditure are delays in <strong>com</strong>pletion on environmental studies, especially land acquisition<br />

process which resulted in delays in procurement process and delays in award of contracts. The<br />

S-curve based on this plan is shown in Figure 7-2.<br />

EINRIP Loan Budget Plan and Actual (A$ million)<br />

350,00<br />

300,00<br />

286,37<br />

294,24 298,49<br />

300,66 302,32 302,61<br />

250,00<br />

242,14<br />

200,00<br />

150,00<br />

100,00<br />

66,92<br />

50,00<br />

-<br />

Proc. Plan<br />

Actual<br />

Figure 7-2<br />

S-curve for Expenditure of Special Account<br />

Project Management Unit (PMU-EINRIP) Page 34


Loan Allocation (mill)<br />

Rupiah<br />

Rupiah<br />

7.3. Foreign Exchange Rate Variation<br />

10.000<br />

EINRIP 2010 Annual Progress Report<br />

The exchange rate of AUD vs. IDR varied between highest rate of 9,142.50 (31-Dec 9.142,5 2010) to<br />

9.000<br />

lowest value of Rp. 7,555.0 (7 June 8.465 2010). 8.509<br />

8.727<br />

8.630,0 8.722,2<br />

The average AUD exchange rate to Rupiah was Rp.<br />

8.139<br />

8.291<br />

8.344,3 8.377,6<br />

7.949<br />

8.692<br />

8.049,6 8.079,1<br />

8.700,7<br />

8.342,4 (Figure<br />

7.7327-3).<br />

8.432<br />

8.000<br />

8.361,6 8.326,4<br />

7.000<br />

6.000<br />

7.556<br />

7.327<br />

7.792<br />

Trend of Australian Dollar (Middle Value)<br />

2009-2010<br />

8.204<br />

Trend of Australian Dollar (Middle Value)<br />

2009-2010<br />

7.789,7 7.730,1<br />

10.000<br />

5.000<br />

9.000<br />

4.000<br />

8.000<br />

3.000<br />

7.556<br />

7.732<br />

7.949<br />

8.139<br />

8.291<br />

8.204<br />

8.465 8.509<br />

8.727<br />

8.692<br />

8.432<br />

8.344,3 8.377,6<br />

8.361,6 8.326,4<br />

9.142,5<br />

8.630,0 8.722,2<br />

8.049,6 8.079,1<br />

8.700,7<br />

7.000<br />

2.000<br />

7.327<br />

7.792<br />

7.789,7 7.730,1<br />

6.000<br />

1.000<br />

5.000<br />

-<br />

4.000<br />

3.000<br />

Figure 7-3<br />

Trend of Exchange Rates<br />

2.000<br />

7.4. Impact of Exchange Rate on Total Project Cost<br />

1.000<br />

-<br />

Changes in exchange rate may have significant effect on loan project cost. For example, the<br />

impact of changes in exchange rate is showed in Figure 7-4, that shows if rupiah currency falls<br />

on Australian Dollar then the need of AUD currency will increase. Otherwise if rupiah currency<br />

increases then the need of AUD currency will decrease.<br />

Elasticity of Changes in Exchange Rate Between AUD and<br />

IDR to EINRIP Loan Allocation<br />

320,00<br />

310,00<br />

300,00<br />

290,00<br />

280,00<br />

270,00<br />

260,00<br />

250,00<br />

7500 8000 8500 9000<br />

Figure 7-4<br />

Project Cost changes on Variable Exchange Rate<br />

Project Management Unit (PMU-EINRIP) Page 35


EINRIP 2010 Annual Progress Report<br />

8. Implementation Support Consultants<br />

Procurement of implementation support consultants <strong>com</strong>menced in early 2008 and by the end<br />

of 2008, three consultants were awarded the contracts:<br />

1. Regional Supervision Consultants (RSC), contract signed on 26-Nov-2008, services for<br />

39 months<br />

2. Procurement Advisory Services Consultants (PAS), contract signed on 28-Oct-2008,<br />

services for 18 months<br />

3. Project Management Support Consultants (PMSC), contract signed on 09-Dec-2008,<br />

services for 39 months<br />

Thus, by January 2009, all three consultants had been mobilized. During 2010, following is<br />

summary of activities of the three consultants.<br />

8.1. Project Management Support Consultant (PMSC)<br />

The PMSC provides support to the PMU and DGH in management of the Project. Key<br />

milestones of PMSC services are:<br />

Staffing<br />

Team Leader of PMSC was replaced on 12 February 2010. The replacement TL was<br />

approved by AusAID on 12 April 2010. The international Senior Contracts/QA Specialist<br />

performed as Acting Team leader until 12 April and then as full TL in 2010.<br />

The replacement of international Senior Contracts/QA Specialist mobilized on 12 April<br />

2010, but resigned from the project on 28 July 2010. The replacement candidate has been<br />

approved by DGH, who will mobilize on 3 January 2011.<br />

Financial Management Specialist (Int) provided one 3-week input from 14 June 2010.<br />

The international Environmental Specialist provided three inputs between (22-March - 21<br />

April), (31 May – 15 July) and (18 Oct - 17 Dec).<br />

The Assistant Team Leader passed away in September 2010; his replacement has been<br />

submitted to DGH for approval and is expected to mobilize in January 2011.<br />

General Duties<br />

PMSC supported PMU-EINRIP in management of various EINRIP activities and provided<br />

coordination with AusAID, RSC and PAS Consultants, and other external agencies.<br />

PMSC took over the ESS activities including AMDAL for South Sulawesi packages and land<br />

acquisition of all packages from PPC in April 2009.<br />

Provided maintenance support to EINRIP website and uploading of bid documents and<br />

other notices.<br />

Provide assistance to PMU in preparation of all coordination meetings.<br />

Specific activities of PMSC in 2010<br />

Finalisation of Management Action Plan and preparation of Summary MAP Reports from<br />

February 2010.<br />

Project Management Unit (PMU-EINRIP) Page 36


EINRIP 2010 Annual Progress Report<br />

FMIS Version 2.0 was developed and first presentation made to PMU and EMU in January<br />

2010. After a number of iterations and trial runs, improvements have been incorporated and<br />

final version 2.0 was installed in Denpasar in Satker offices of EBL-01 and EBL-02 on 28<br />

June 2010.<br />

Installation of FMIS in all Satkers offices in West Nusa Tenggara in November 2010.<br />

Prepared the quarterly Financial Monitoring Report (FMR) No. 5, 6, 7 and 8 for Oct-Dec<br />

2009, Jan-Mar 2010, Apr-Jun 2010 and Jul-Sep 2010.<br />

Prepared the format for monthly Project Progress Report (PPR) which is prepared by PMU<br />

as per loan agreement and provided assistance in preparation of monthly PPRs.<br />

Attended the Pre-Construction Meetings for EBL-02 (21-22 January), ENB-01C, 02 & 03 (2-<br />

6 February), ESR-02 (3 February), ESS-01 (11 February), and ESH-01 (30 September).<br />

Conducted Quality Monitoring visits to EBL-01 (10-12 March), ESS-02 (8-11 March), ESR-<br />

01 (27-29 April), EKB-01 (17-18 May), ENB-01C and ENB-02 (2 June), EBL-01/02 (12-15<br />

July) and ESS-01 (19-21 July).<br />

PMSC developed an integrated environmental monitoring, response and reporting system<br />

incorporating different stakeholders in order to improve overall quality and relevance of the<br />

environmental <strong>com</strong>pliance monitoring process.<br />

Conducted ESS Monitoring visits to EBL-01 and EKB-01.<br />

TFAC Follow-up audits were conducted by PMSC in November and December 2010.<br />

Developed draft Management Practices for base camp, quarry sites and asphalt mixing<br />

plant for BinTek.<br />

Assisted PMU in coordination of development of proposal for HIV/AIDS awareness<br />

campaign.<br />

Provided input in revision of Annual Procurement Plans and monitoring its implementation.<br />

Provided support and monitored the to M&E surveys of 2010. The M&E teams conducted<br />

the surveys between June-August 2010.<br />

Updating of Project Management Manual (PMM) in March-April 2010.<br />

Support to development of performance indicators for ACAP and assisted PMU in<br />

preparation for 2010 ACAP audit.<br />

Carried out financial exercises and analyses of loan amount to propose loan category<br />

changes related to preparation of explanatory notes for Loan Closing date extension.<br />

Contract Amendments<br />

Addendum No. 1 was signed on 20 August 2010, covering the replacement of key<br />

personnel, adjustment in time for <strong>com</strong>pletion of services and adjustment in staffing<br />

schedule. Cost was reduced both for IDR and AUD.<br />

8.2. Regional Supervision Consultants (RSC)<br />

Regional Supervision Consultant (RSC), responsible for construction supervision of all Civil<br />

Works, are designated the role of “Engineer” under the FIDIC-based contract. RSC is managed<br />

by DGH through the Directorate of Roads and Bridges, Eastern Region, including supervision of<br />

Project Management Unit (PMU-EINRIP) Page 37


EINRIP 2010 Annual Progress Report<br />

packages in Metropolitan areas. The team is based in Makassar, with all field supervision teams<br />

are established at project locations.<br />

Staffing<br />

Team Leader mobilized on 1-Dec-08 and Deputy TL mobilized on 23-Dec-08.<br />

The Quality/Pavement/Materials Specialist mobilized on 11-Jan-09, but resigned and<br />

demobilized on 09-Apr-09. The replacement specialist mobilized on 14-Apr-09.<br />

International Chief Supervision Engineer CSE-A1 and CSE-A2 mobilised on 11-Feb-09 and<br />

1-Sep-09 respectively. CSE-A3 mobilised on 1 July 2010.<br />

National Chief Supervision Engineer CSE-B1 mobilised on 06-Jan-09.<br />

National Bridge Engineer mobilized on 1 February 2010.<br />

International Environmental Specialist provided two inputs in 2010.<br />

Field supervision teams (key professional staff) were mobilized for:<br />

- EBL-02: Jan-May, 2010<br />

- ENB-01C: Jan-March, 2010<br />

- ENB-02: Jan-March, 2010<br />

- ENB-03: Jan-March, 2010<br />

- ESR-02: Jan-May, 2010<br />

- ESS-01: Dec 2009 - March, 2010<br />

- ESU-01: Feb-Aug, 2010<br />

- ESH-01: September, 2010<br />

Specific activities of RSC in 2010<br />

Updated the Quality Assurance Plan (QAP) and RSC organized a 3-day Training Workshop<br />

on 26-19 September, 2010 in Makassar.<br />

The workshop was attended by field supervision staff of the five on-going contracts as well<br />

as Contractor‟ s key staff.<br />

Monitoring of environmental aspects in construction and preparation of specific<br />

Environmental Monitoring Reports.<br />

Contract Amendments<br />

Addendum No. 1 was signed in May 2009 to include the supervision of ESB-02,<br />

Prefabricated Steel Bridge Material contract.<br />

8.3. Project Advisory Services (PAS) Consultants<br />

The Procurement Advisory Services Consultant (PAS) provide support to the civil works<br />

Procurement Committees established in the Provincial Satker for each contract package. The<br />

team is based in Jakarta and managed by DGH through the Directorate of Roads and Bridges,<br />

Eastern Region, including procurement of packages in Metropolitan areas.<br />

Project Management Unit (PMU-EINRIP) Page 38


EINRIP 2010 Annual Progress Report<br />

Staffing<br />

Contract was signed on 28 October 2008.<br />

Team Leader mobilized on 17-Dec-2008 and Assistant Team Leader on 9-Jan-2009.<br />

3 of the 4 Procurement Advisors were mobilized in January 2009. The fourth Procurement<br />

Advisor was not mobilized.<br />

Training<br />

In 2010, PAS provided procurement training to the Procurement Committees for:<br />

- ENT-01 on 19-21 January 2010<br />

- ESS-04 on 6-8 April 2010<br />

- EL-02 on 28-30 April 2010<br />

- ENT-01 on 21-22 April 2010<br />

Procurement activities in 2010<br />

By end of November, 2010 PAS had <strong>com</strong>pleted procurement activities for 13 packages:<br />

Procurement ongoing at time of demobilization for 5 packages:<br />

EKS-01, EKS-02, ESH-01, ESS-03 and ESS-04<br />

Bidding did not <strong>com</strong>mence for ESS-05 and ESS-06<br />

Contract Amendments<br />

Memorandum No. 2 was signed in August 2009.<br />

Contract Addendum No. 1 was signed on 19 February 2010, for extension of PAS contract<br />

to 31 August 2010.<br />

Contract Addendum No. 2 was signed on 28 October 2010, for extension of PAS contract to<br />

30 November 2010.<br />

PAS consultants de-mobilised on 30 Novembre 2010.<br />

Project Management Unit (PMU-EINRIP) Page 39


EINRIP 2010 Annual Progress Report<br />

9. Technical and Financial Audits in 2010<br />

A requirement of the loan agreement for the EINRIP Project is that the individual projects will be<br />

independently audited by consultants appointed directly by AusAID. The objective is to conduct<br />

technical and financial audits during the implementation of civil works to assess <strong>com</strong>pliance with<br />

the design document requirements and that the required quality is achieved.<br />

9.1. Technical and Financial Audit Consultants<br />

In early 2010, AusAID engaged the services of Cardno Emerging Markets (Australia) Pty Ltd as<br />

the Technical and Financial Audit Consultants (TFAC). After their mobilization and initial<br />

inception meetings in March 2010, the TFAC team conducted its first full TFAC audit in Bali on<br />

EBL-01 in end of March 2010.<br />

A presentation of the Inception Report and findings of first audit of EBL-01 was presented in a<br />

workshop in Jakarta on 19 and 20 May, 2010. This was followed by full audits of 4 packages.<br />

The dates of initial full TFAC audits are:<br />

EBL- 01, Tohpati - Kusamba 29 - 31 March, 2010<br />

ENB- 01AB, Sumbawa Besar Bypass 25 May - 2 June, 2010<br />

EKB- 01, Pontianak - Tayan 14 - 21 June, 2010<br />

ESR- 01, Tinanggea - Kasipute 29 June - 8 July, 2010<br />

ESS- 02, Bantaeng - Bulukumba 16 - 23 July, 2010<br />

The TFAC audit reports were released by AusAID on 27 May, 2010, and reports for other four<br />

packages on 18-August, 2010.<br />

The findings of the first TFAC audit for EBL-01 was presented in a workshop in Jakarta on 20<br />

May, 2010.<br />

The findings of the next four TFAC audits (EKB-01, ENB-01AB, ESR-01, and ESS-02) were<br />

presented in a workshop in Jakarta on 5 October, 2010.<br />

9.2. Key issues identified in TFAC Audits<br />

a) There is lack of quality management both by the contractors and site supervision teams.<br />

The Quality Management procedures required by the Conditions of Contract and by the<br />

General Specification have not been applied in a satisfactory manner on any of the<br />

projects. Many Site Supervision staff are unaware of the required quality standards and<br />

are not enforcing Holding Points.<br />

b) Interim Certificate claims including payment for works that are non conforming have been<br />

processed in many cases.<br />

c) Most projects are proceeding at a rate that will not ensure <strong>com</strong>pletion within the Time for<br />

Completion. In some cases work is being delayed by uncertainty associated with the<br />

variation approval process.<br />

d) There are deficiencies in Contractor‟ s Equipment e.g. intermediate to small drum width<br />

rollers; deficiencies in blending plant design; Coal fired asphalt plants are without<br />

certification; <strong>com</strong>plying bitumen distributers for prime and tack coat; rotary power broom<br />

and use of oversized haulage trucks<br />

Project Management Unit (PMU-EINRIP) Page 40


EINRIP 2010 Annual Progress Report<br />

e) Works defect categories that are <strong>com</strong>mon to most projects include: traffic management;<br />

maintenance of the existing road and haul roads; staking out; drainage of works in<br />

progress; drainage of pavement structure (weep holes); drain level <strong>com</strong>pliance; grade<br />

preparation; benching, pavement sub layer width; private access; aggregate base<br />

segregation; aggregate base grading and concrete strength insitu (Schmidt Hammer).<br />

f) Several projects are suffering delay to works because of delay to <strong>com</strong>mence field<br />

engineering,finalization of field engineering report, process and finalization of Variation<br />

Order (at field level), mobilization of equipment, construction and slow progress in<br />

implementation of works, management and financial problems.<br />

9.3. Re<strong>com</strong>mendations of TFAC Audits<br />

a) All Supervision Team and QCM staff should be reminded of the Quality Management<br />

duties they are required to perform. Quality Control Manager actions necessary to <strong>com</strong>ply<br />

with General Conditions of Contract, General Specification and Quality Assurance Plan<br />

(QAP) requirements must be defined by the CWC Quality Control Plan.<br />

b) Some further personnel changes are needed both for CWC-QCMs and Supervision Team<br />

staff. Site staff should be provided more intensive on-the-job training.<br />

c) The Site Supervision Engineers should only approve conforming works for payment. Non<br />

conforming works including those already included in Monthly Certificates should be<br />

deleted from current and future Interim Payment until corrected or approved.<br />

d) The Engineer should apply GCC Part 1, Cl 8.6 requirements in relation to Rate of<br />

Progress to all projects.<br />

e) Certain works including widening and asphalt work, should not be permitted to proceed<br />

until all necessary equipment is available on site.<br />

9.4. Follow-up of TFAC Audit<br />

One of the conclusions of the 5 October TFAC workshop was the need for follow-up on the<br />

actions by the Contractors and RSC field supervision teams on the initial TFAC findings and an<br />

evaluation of the extent to which the TFAC findings have resulted in improvement of the general<br />

quality of works and review the actions to address individual non-conformities identified in the<br />

initial audit.<br />

After discussions with PMU and PMSC, it was decided that a general follow up will be<br />

conducted initially by PMSC and then by TFAC consultants during Nov-Dec, 2010.<br />

The follow-up review visits were undertaken at following dates:<br />

ENB- 01AB, Sumbawa Besar Bypass<br />

EKB- 01, Pontianak - Tayan<br />

ESR- 01, Tinanggea - Kasipute<br />

ESS- 02, Bantaeng - Bulukumba<br />

25 Nov, 2010 (TFAC &PMSC)<br />

10 Nov, 2010 (PMSC)<br />

30 Nov - 3 Dec, 2010 (TFAC &PMSC)<br />

4 - 5 Dec, 2010 (TFAC &PMSC)<br />

The results of the reviews were not encouraging. A number of non-conformities identified in<br />

initial TFAC audits were not addressed, and there was little effective response either from the<br />

Contractor or RSC field supervision team. This concern was conveyed by AusAID to DGH<br />

formally, as well as through formal meetings between senior management.<br />

At the end of follow-up visits by TFAC and PMSC, DGH was also concerned about lack of<br />

effective response from the Contractors and RSC on the initial TFAC findings.<br />

Project Management Unit (PMU-EINRIP) Page 41


EINRIP 2010 Annual Progress Report<br />

Subsequently, the Directors of Implementation Regions initiated a final follow-up of the TFAC<br />

findings in late December 2010.<br />

As part of this response, it was decided that:<br />

Satkers and PPK should make the RSC to take actions so that the audit findings from<br />

original and follow up TFAC audits are addressed immediately.<br />

The Contractor must be required to <strong>com</strong>plete the rectification and provide a report on<br />

response to the follow up to the SSE of RSC and copy to PPK<br />

RSC should inspect all rectification works and items and submit a confirmation report by<br />

15-Jan-2011 that the audit findings have been rectified.<br />

PMSC will then conduct verification/evaluation visits to all five packages and provide a<br />

final report to PMU and DGH.<br />

The follow-up process will be initiated in January 2011 and is expected that the DGH response<br />

to TFAC audit first round will be <strong>com</strong>pleted by February 2010.<br />

Project Management Unit (PMU-EINRIP) Page 42


EINRIP 2010 Annual Progress Report<br />

10. Project Administration and Management<br />

10.1. HIV/AIDS Campaign<br />

During 2009, a number of discussions were held between PMSC/PMU and AusAID HIV/AIDS<br />

advisor on the requirements of this campaign. Discussions were also held with SRIP project<br />

office in DGH and with Environment Sub directorate in DGH, who had earlier provided key input<br />

in the campaign for other projects.<br />

Meetings were also held with National Aids Commission, who provided information on the<br />

regional offices in the areas where project works will be carried out. At end of 2009, the draft<br />

TOR for the campaign was prepared and was under discussion.<br />

In January 2010, an informal presentation was given by IPPA Jakarta Chapter (PKBI DKI<br />

Jakarta) who provided useful information on the different HIV/AIDS campaigns and programs<br />

currently undertaken by them.<br />

The Terms of Reference (TOR) were discussed with Environment Sub directorate in end of<br />

March 2010, and an indicative Owner‟ s Estimate was also prepared. It was eventually decided<br />

that services will be ac<strong>com</strong>modated in the supervision consultancy contract through an<br />

addendum; and RSC will take the lead on calling for proposals and evaluation. The actual<br />

campaign will then be delivered by the selected service provider (NGO) under RSC supervision.<br />

After administrative approvals, during May 2010, BCEOM (RSC Consulting firm) invited<br />

proposals from shortlisted firms/consultants provided by DGH. The evaluation of the proposals<br />

was <strong>com</strong>pleted by end of September 2010.<br />

The contract with the NGO (Yayasan Kusuma Buana) was signed on 8-Nov-2010 and they<br />

indicated 15-Nov 2010 as the date for <strong>com</strong>mencement of services. An informal meeting was<br />

held with DGH in end of November to present the contract and draft program. A formal<br />

presentation was given by YKB on 20 Dec-2010 in which they presented the team structure and<br />

preliminary visit plan for conducting the campaign.<br />

The actual campaign will <strong>com</strong>mence in January 2011 from the two packages in Bali.<br />

10.2. Implementation of Anti Corruption Action Plan (ACAP)<br />

The EINRIP Anti Corruption Action Plan has been adopted by GOI and incorporated into the<br />

Loan Agreement. It is intended to ensure that anti corruption measures are an integral part of<br />

project implementation.<br />

The key features of the EINRIP ACAP are:<br />

Key project documents and updated reports on financial and technical aspects of project<br />

implementation, <strong>com</strong>plaints handling mechanism and results, and audit results will be<br />

publicly available, including on the EINRIP website<br />

Strengthened supervision and audit mechanismas have been put in place. This includes<br />

use of FIDIC based contracts and appoitinting RSC as the Engineer<br />

External technical and financial audits.<br />

Measures to increase the efficiency and accountability of procurement process, including<br />

the use of a Procurement Agent for the selection of consultancy services and<br />

Project Management Unit (PMU-EINRIP) Page 43


EINRIP 2010 Annual Progress Report<br />

Procurement Advisory Services (PAS) for the selection of civil works contractors, and<br />

improvement of MPW‟ s existing e-procurement system.<br />

During June 2010, a meeting was held with BPKP (Badan Pengawasan Keuangan Dan<br />

Penbanguan) to discuss the implementation of ACAP in EINRIP and other projects. It was<br />

advised that 2010 Audit of ACAP is planned for August-October 2010 and a number of EINRIP<br />

contracts will be visited. BPKP also discussed the revision of the performance indicators.<br />

In July 2010, a dissemination meeting was organised by BPKP for the Guidelines for ACAP<br />

2010 evaluation. The meeting, at Bogor (Java), spanned over the week of 26-30 July 2010.<br />

Along with EINRIP, other funded projects as EIRTP-2 and SRIP were also discussed. The<br />

participants of the meeting were BPKP officials from the 20 provinces of the funded projects.<br />

The Director of Planning from DGH attended the meeting with the PMU for EINRIP, SRIP and<br />

EIRTP.<br />

The 2010 ACAP audit was planned in August-October 2010 period and prior to audit, BPKP<br />

coordinated with PMU and Inspectorate General of MPW to revise the performance indicators<br />

for evaluation of ACAP implementation. These indicators were broadly based on the seven key<br />

areas of ACAP including:<br />

Establishment of Project Website (Pengelolaan Website)<br />

Bidding Preparation (Persiapan Lelang)<br />

Bidding Evaluation (Evaluasi lelang).<br />

Contract Implementation (Pelaksanaan kontrak)<br />

Complaints Handling Procedures (Penanganan Pengaduan)<br />

Financial (Finansial)<br />

Audit (Audit)<br />

Each of the above indicators was further classified into sub-indicators to <strong>com</strong>pletely en<strong>com</strong>pass<br />

the key considerations of ACAP.<br />

The revised performance indicators used for 2010 ACAP Implementation Audit are presented in<br />

Appendix 6.<br />

BPKP <strong>com</strong>pleted audit on EINRIP packages in October 2010. Total 14 packages in EINRIP<br />

were audited, as shown in Table 10-1.<br />

No. Package Name Province<br />

1 EBL- 01 Tohpati – Kusamba Bali Also in 2009 audit<br />

2 EBL- 02 Tohpati – Kusamba Stage 2 Bali<br />

3 ESH- 01 Lakuan – Buol Central Sulawesi<br />

4 ESU- 01 Molibagu – Taludaa North Sulawesi Also in 2009 audit<br />

5 ENB- 01AB Sumbawa Bypass NTB (Sumbawa) Also in 2009 audit<br />

6 ENB- 01C Sumbawa Pal IV – Km 70 NTB (Sumbawa) Also in 2009 audit<br />

7 ENB- 02 Km 70- Bts. Cabdin Dompu NTB (Sumbawa)<br />

8 ENB- 03 Bts. Cabdin Dompu –<br />

Banggo<br />

NTB (Sumbawa)<br />

9 ESR- 01 Tinanggea – Kasipute South East Sulawesi Also in 2009 audit<br />

Project Management Unit (PMU-EINRIP) Page 44


EINRIP 2010 Annual Progress Report<br />

No. Package Name Province<br />

10 ESR- 02 Kasipute – Bambaea South East Sulawesi<br />

11 ESS- 01 Sengkang – Impa Impa –<br />

Tarumpakkae<br />

South Sulawesi<br />

12 ESS- 03 Jeneponto – Bantaeng South Sulawesi<br />

13 EKB- 01 Pontianak – Tayan West Kalimantan Also in 2009 audit<br />

14 EKS- 02 Banjarmasin – Bts. Kalteng South Kalimantan<br />

Table 10-1<br />

List of packages for 2010 ACAP Audit<br />

In this second year of ACAP audit, 7 evaluators visited 14 packages and PMU and the summary<br />

of evaluation is shown in Table 10-2.<br />

Indicator Value (%) Compilation Value Of<br />

Package Performance (%)<br />

Value Of PMU<br />

Performance (%)<br />

Website Management 15 9.138 % 12, %<br />

Bid Preparation 20 22.945 % 20 %<br />

Bid Evaluation 20 23.227 % 20 %<br />

Contract Implementation 20 15.606 % 20 %<br />

Handling Complaints 5 3.804 % 5 %<br />

Finance 10 10.672 % 10 %<br />

Audit 10 6.495 % 10 %<br />

%Total 100 91.888 % 97 %<br />

Table 10-2<br />

Summary Evaluation of 2010 ACAP Audit<br />

Overall, the BPKP Report termed that ACAP EINRIP performance value of 91.89% on limited<br />

basis may be deemed to reflect the optimum success.<br />

10.3. Project Management Manual<br />

As a requirement of the EINRIP loan agreement, the Project Management Manual (PMM) is a<br />

condition for loan effectiveness which is to be used by all concerned parties as a key reference<br />

for project implementation in all activities including consultancy services, implementation and<br />

other matters contained in the loan agreement. The PMM was approved in 2008 and the current<br />

version at end of 2010 is the September 2008 version.<br />

After the initial months of the application of PMM by the various units within DGH and by the<br />

three consultants, the need for revision was felt by all users. Although the PMM was quite<br />

<strong>com</strong>prehensive, there were few regulations issued by the DGH that necessitated the updating of<br />

the PMM. In addition, the PMM itself re<strong>com</strong>mended that the PMM should be updated annually.<br />

The update process was a progressive one with initial discussions between PMSC and PMU.<br />

RSC and PAS, being directly involved in supervision and procurement, were requested to<br />

provide their feedback and <strong>com</strong>ments.<br />

The <strong>com</strong>ments received from RSC and PAS were discussed with PMU in Sep/Oct 2009 and a<br />

draft revision of the PMM was provided to EMU (AusAID) for <strong>com</strong>ments in Nov/Dec 2009.<br />

The key areas where revision has been discussed include:<br />

Project Management Unit (PMU-EINRIP) Page 45


EINRIP 2010 Annual Progress Report<br />

Changes in Complaints handling procedures<br />

Design updating and revision during procurement and in construction<br />

Changes to procurement procedures especially post qualification criteria for personnel<br />

and equipment<br />

Integrity Pact for awarded contracts<br />

Variations and contract amendments<br />

Measures to handle slow rate of progress in construction<br />

Changes in the FMR forms<br />

A number of meetings were organised by Head of SubDit Standards & Guidelines in BinTek in<br />

March 2010 to review the proposed changes to PMM. Three focus groups, <strong>com</strong>prising of senior<br />

staff from Directorate of Eastern Region, BinTek and consultants, were formed for reviewing the<br />

PMM sections on implementation, procurement, and financial management. The final<br />

re<strong>com</strong>mendations by the three focus groups and the formal suggested changes were<br />

incorporated into the new version of PMM. In a meeting held under Dir (Eastern Region) on 1-<br />

July-10, the flow chart of procurement was discussed and it was suggested that a separate flow<br />

chart for preparation of BER should be prepared. The flow chart was finalised in July 2010 and<br />

the draft revision along with Annexes was sent to AusAID on 23-Jul-10 for their concurrence.<br />

AusAID provided their final <strong>com</strong>ments on 22-Oct-2010 and meeting was held with them on the<br />

proposed minor revisions. The changes were also incorporated in the revised PMM.<br />

At end of 2010, the draft revision of PMM was <strong>com</strong>pleted and it is expected that the new version<br />

will be released after formal approval in early 2011.<br />

10.4. Coordination Meetings in 2010<br />

The loan agreement requires that the Republic of Indonesia shall, through MPW and the<br />

Ministry of Finance, meet with the Commonwealth, through AUSAID, every six months during<br />

Project implementation, to review measures taken in response to key audit report findings, and<br />

the adequacy of the Republic of Indonesia funds and the need for any adjustment of those<br />

funds. These were termed as the six-monthly Joint Management meetings.<br />

Two types of coordination meetings are held in EINRIP:<br />

Six-monthly Joint Management Meeting (JMM) between DGH, AusAID, BAPPENAS and<br />

MOF. (Every 2 nd JMM is also termed as Senior Representative meeting)<br />

Monthly Coordination Meeting – PMU, PMSC, PAS, RSC and EMU<br />

Summary of meetings held in 2010 is presented below.<br />

Six-monthly Joint Management Meeting<br />

The 6 th EINRIP Joint Management Meeting was held on 24 August 2010 at Directorate General<br />

of Highways, MPW, attended by senior officials from MoF, BAPPENAS and AusAID.<br />

Key issues discussed during the meeting included:<br />

Review of project progress for previous six months covering procurement and contracts<br />

ward progress. Concern was expressed on delays in procurement process and land<br />

acquisition;<br />

Process for contract variations and delays associated with the approval process;<br />

Project Management Unit (PMU-EINRIP) Page 46


EINRIP 2010 Annual Progress Report<br />

Unsatisfactory progress and delays on some packages and consideration of termination<br />

of contracts;<br />

Proposed Changes to Loan Sharing Arrangement (tabled by AusAID);<br />

Proposed Amendment to Loan Agreement to change the loan closing date to 31 March<br />

2013;<br />

Technical and Financial Audit Consultants first round of five audits and the results and<br />

findings; and<br />

Variations in Civil Works through design optimisation (balanced budget) - Tabled by<br />

DGH<br />

The minutes of JMM No. 6 are presented in Appendix 7.<br />

Monthly Coordination Meeting<br />

In the 4 th EINRIP Joint Management Meeting held on 12-Aug-09, AusAID raised the item of<br />

monthly coordination meetings. The project has 3 separate consultant teams working with PMU<br />

(PAS, PMSC, and RSC) and it was proposed that all parties agree to have a regular monthly<br />

meeting with PMU and AusAID/EMU. This initiative was agreed and the monthly coordination<br />

meeting has been regularly held since September 2009.<br />

In 2010, the meetings were held on:<br />

Monthly Coordination Meeting No 4 held on 12 January 2010 at EMU AusAID<br />

Monthly Coordination Meeting No 5 held on 26 March 2010 at EMU AusAID<br />

Monthly Coordination Meeting No 6 held on 26 April 2010 at Bina Marga<br />

Monthly Coordination Meeting No 7 held on 25 June, 2010 at Bina Marga<br />

Monthly Coordination Meeting No 8 held on 11 August, 2010 at EMU AusAID<br />

Monthly Coordination Meeting No 9 held on 23 September, 2010 at EMU AusAID<br />

Monthly Coordination Meeting No 10 held on 18 November, 2010 at EMU AusAID<br />

Monthly Coordination Meeting No 11 held on 21 December, 2010 at Bina Marga<br />

Generally, the agenda of these meetings covered:<br />

Progress on HIV/AIDS campaign for contracts<br />

Status of ESS studies including land acquisition<br />

Review the implementation progress on awarded contracts and statys of mobilization of<br />

RSC Field supervision teams<br />

Technical and Financial Audit Consultants (TFAC) first round of audits<br />

Status of Procurement of active packages<br />

Management Action Plan (MAP) Report<br />

Update of PMM<br />

2010 M&E Surveys<br />

Project Management Unit (PMU-EINRIP) Page 47


EINRIP 2010 Annual Progress Report<br />

10.5. Management Action Plan (MAP)<br />

In the 2 nd half of 2009, it was felt that the implementation of EINRIP program is experiencing<br />

delays and a number of projects that were planned to <strong>com</strong>mence in 2009 will be delayed.<br />

Primary reasons for delays was delays in land acquisition process and some delays in<br />

procurement where two packages were decided to be re-bid and a number of clarifications were<br />

being sought from bidders, thus delaying the award of contracts.<br />

Informal discussions were held for possible extension to the EINRIP loan, with original loan<br />

closing date at 1 June 2011. It was proposed to extend the loan to March 2013.<br />

In October 2009 it was advised that the loan extension is likely to be approved and for this<br />

purpose it has been sought by GoA that additional monitoring measures be adapted to fast<br />

track the ongoing land acquisition and procurement process.<br />

For this purpose, it was desired that a Management Action Plan (MAP) will be prepared by PMU<br />

to strengthen the existing institutional and procedural arrangements to expedite <strong>com</strong>pletion of<br />

ESS studies, procurement and early <strong>com</strong>mencement of construction contracts for sub-packages<br />

in EINRIP project.<br />

A Management Action Plan (MAP) was proposed by DGH and formally agreed with AusAID in<br />

Jan-Feb 2010. The broad MAP framework is:<br />

• Identify actions, <strong>com</strong>ponent tasks and agencies/units responsible in each phase;<br />

• Develop activity/task monitoring and reporting schedules;<br />

• Formulating time-based performance benchmarks for key activities;<br />

• Developing intervention modalities in case of delays and difficulties; and<br />

• Monitoring and reporting requirements<br />

The Management Action Plan approved in January 2010 is presented in Appendix 8.<br />

After the approval of MAP, monthly Summary MAP reports were prepared by PMU for<br />

submission to AusAID. In 2010, ten reports were produced.<br />

In the Summary MAP Reports, for land acquisition, the intervention sheets for packages with<br />

on-going land acquisition were updated each month. Status of procurement and progress on<br />

ongoing construction contracts was also updated each month.<br />

10.6. M & E Annual Surveys<br />

As part of the loan agreement, AusAID is funding a separate Monitoring and Evaluation (M&E)<br />

programme with the objective to establish the extent to which EINRIP program meets its<br />

objectives.<br />

An independent consultant for Monitoring & Evaluation has prepared a separate Monitoring and<br />

Evaluation programme, intended to establish the extent to which EINRIP meets its objectives.<br />

Key Performance Indicators (KPI) have been developed by the M&E consultant in consultation<br />

with DGH and AusAID. These include:<br />

Traffic Growth<br />

Road Condition as measured by International Roughness Index (IRI)<br />

Average speeds<br />

Project Management Unit (PMU-EINRIP) Page 48


EINRIP 2010 Annual Progress Report<br />

Accident Rates<br />

Vehicle Operating Costs<br />

Baseline surveys <strong>com</strong>menced in 2007, and further surveys will be carried out between 2008<br />

and 2013. Annual reports of the results of the survey programme will be prepared. A Final<br />

Project Review will be undertaken, to provide an overall evaluation of the project.<br />

In 2010, the M&E surveys were carried out under the supervision of PMSC. Initial discussions<br />

on TOR of M&E team, arrangements for office space and financing the surveys were held<br />

between PMSC and AusAID in May/June 2010. It was indicated that the survey will involve<br />

engagement of 3 teams of 2 staff each, over a period of 3 months.<br />

The M&E Consultant of AusAID also participated in the administrative arrangements during May<br />

and June 2010, and a series of meetings were held between AusAID and PMSC on finalising<br />

the modalities of the M&E survey program for 2010.<br />

Five batches of surveys were planned for 2010, and were <strong>com</strong>pleted by early August 2010. The<br />

list of surveys is presented in Table 10-3:<br />

Province Link No Name Dates for Survey<br />

South Sulawesi 54.034 Watampone - Pompanua 7 - 12 June, 2010<br />

54.043 Pangkajene Sidrap - Anabanua<br />

Bali 40.00.2 Negara – Cekik 21 - 26 June, 2010<br />

40.005 Tabanan – Antosari<br />

40.039 Sidan – Klungkung<br />

NTT (Flores) 44.006 Ende - Aegela<br />

27 June - 2 July,<br />

2010<br />

West Kalimantan 30.009.2 Sei Dui - Singkawang 19 - 24 July, 2010<br />

30.079.1 Tayan - Teraju<br />

30.079.2 Teraju - Bts.Balai Berkuak<br />

South Kalimantan 36.011.1 Sp. Liang Anggang - Ds. Liang Anggang 2 – 7 August, 2010<br />

36.034.2 Empat Harui - Batu Babi<br />

Table 10-3<br />

List of 2010 M&E Surveys<br />

10.7. FIDIC Training and Workshops<br />

During the initial months of <strong>com</strong>mencement of construction of EINRIP packages and as one of<br />

the key finding of the TFAC audits, it was generally felt by AusAID and DGH senior<br />

management that many DGH staff, RSC supervision teams and Contractors often lack clear<br />

understanding of the contracting environment under EINRIP which is FIDIC based “Conditions<br />

of Contract for Construction - Multilateral Development Bank Harmonised Edition March 2006”.<br />

During middle of 2010, EINRIP Monitoring Unit (EMU) under AusAID held discussions with DGH<br />

and prepared a training program on Contract Administration under FIDC based contract. The<br />

objective of training was to further educate and familiarize the key stakeholders DGH PPKs,<br />

RSC teams and Contractors in responsibilities of various parties under the contract and for<br />

efficient contract administration. The training material and presentations were fully financed by<br />

AusAID.<br />

The „Pilot‟ training in English was conducted in Jakarta on 29 September 2010, and in Bahasa<br />

on 7 October 2010. Based on positive feedback from the participants, AusAID extended the<br />

Project Management Unit (PMU-EINRIP) Page 49


EINRIP 2010 Annual Progress Report<br />

training program to EINRIP packages. Three more training workshops were organized in<br />

Makassar, Bali and in Jakarta during November and December 2010.<br />

The three regional workshops were conducted in Bahasa language and participants included<br />

staff from DGH, RSC supervision teams and Contractors.<br />

Project Management Unit (PMU-EINRIP) Page 50


EINRIP 2010 Annual Progress Report<br />

11. Loan Extension<br />

During the JMM No. 7 held in August 2010, and subsequent meetings, it was agreed in principle<br />

by AusAID and GOI that the EINRIP Loan Closing date may be extended from 1st June 2011 to<br />

31st March 2013, and it was desired that formal amendment should be prepared and finlaised.<br />

The amendment of the Loan Agreement will provide for the changed Loan Closing Date and<br />

other consequences of this; some changes to the allocation of the Loan to the Loan Categories<br />

originally proposed; and a number of minor changes that have arisen during implementation.<br />

During September and December 2010, works continued on the analysis and review of funding<br />

requirements and re-allocation within loan categories.<br />

Key changes to the loan agreement include:<br />

No change in loan amount or sharing arrangements.<br />

Extension to Loan Closing Date (LCD) to 31 March 2013.<br />

Funds transferred to Special Account prior to LCD may be utilised upto 30 June 2013.<br />

Re-allocation within loan categories.<br />

The proposed amendments are summarised in the Table 11-1 below.<br />

No<br />

Original<br />

Project Loan Agreement<br />

Proposal<br />

Amendment No. 1<br />

Project Loan Agreement<br />

1. Schedule 2, Section I.A.I.(f) , page 8<br />

(f)<br />

the five regional implementation agencies<br />

of national inter-urban roads in Eastern<br />

Indonesia under the DGH: (i) Balai Besar<br />

Pelaksanaan Jalan Nasional in<br />

Banjarmasin; (ii) Balai Besar Pelaksanaan<br />

Jalan Nasional in Makassar; (iii) Balai<br />

Pelaksanaan Jalan Nasional in Denpasar.;<br />

(iv) Balai Pelaksanaan Jalan Nasional in<br />

Ambon; and (v) Balai Pelaksanaan Jalan<br />

Nasional in Jayapura .<br />

(f)<br />

the regional implementation agencies<br />

of national inter-urban roads in<br />

Eastern Indonesia under Balai Besar<br />

/ Balai Pelaksanaan Jalan DGH.<br />

2. Schedule 2, Section I C.8, Page 11<br />

8. The Republic of Indonesia shall take all<br />

steps necessary to ensure that the<br />

Procurement Agent, the Financial Audit<br />

Consultant, the Technical Audit Consultant,<br />

and the Monitoring and Evaluation<br />

Consultants, as defined in the Appendix to<br />

this Agreement, are permitted to provide<br />

their services in accordance with their<br />

contractual terms of reference.<br />

8. The Republic of Indonesia shall take<br />

all steps necessary to ensure that the<br />

Procurement Agent, the Technical<br />

and Financial Audit Consultant, and<br />

the Monitoring and Evaluation<br />

Consultants, as defined in the<br />

Appendix to this Agreement, are<br />

permitted to provide their services in<br />

accordance with their contractual<br />

terms of reference.<br />

3. Schedule 2, Section III, A.3 (b) and (c), page 18<br />

(b) The Republic of Indonesia shall, when<br />

preparing the Annual Progress Reports: (i)<br />

take into account the results of the Project<br />

monitoring and evaluation for such year,<br />

carried out by the Monitoring and<br />

Evaluation Consultants, and (ii) prepare the<br />

Annual Progress Reports on the basis of<br />

(b) The Republic of Indonesia shall,<br />

when preparing the Annual Progress<br />

Reports: take into account the<br />

results of the Project monitoring and<br />

evaluation for such year.<br />

Project Management Unit (PMU-EINRIP) Page 51


EINRIP 2010 Annual Progress Report<br />

No<br />

Original<br />

Project Loan Agreement<br />

the performance indicators set forth in subparagraph<br />

(c) below.<br />

(c) The performance indicators referred to in<br />

sub-paragraph (b) above shall, except as<br />

otherwise agreed by the Commonwealth,<br />

consist of the following: (i) traffic growth; (ii)<br />

road condition as measured by<br />

International Roughness Index (IRI); (iii)<br />

average speeds; (iv) accident rates; and (v)<br />

vehicle operating costs.<br />

Proposal<br />

Amendment No. 1<br />

Project Loan Agreement<br />

4. Schedule 2, Section IV, A.4, page 20<br />

Loan Category<br />

Loan Category changed in:<br />

Item V. Proposed Re-allocation of Loan<br />

Category<br />

5. Schedule 2, Section IV, B.2, page 20<br />

1. The Closing Date is 1 June 2011 1. The Closing Date is 31st March<br />

2013.<br />

6. Schedule 2, Section IV, B.3, page 20<br />

3. Funds transferred to the designated<br />

account of the Republic of Indonesia prior<br />

to the Closing Date may continue to be<br />

utilised in accordance with this Agreement<br />

until 31 December 2012.<br />

3. Funds transferred to the designated<br />

account of the Republic of Indonesia<br />

prior to the Closing Date may<br />

continue to be utilised in accordance<br />

with this Agreement until 31 Juni<br />

2013.<br />

Table 11-1<br />

Loan Amendment Changes<br />

The proposed re-allocation of funds is summarised in the Table 11-2 below.<br />

Loan Category<br />

Original Allocation<br />

(AUD)<br />

Revised<br />

Allocation<br />

(AUD)<br />

1 Civil works<br />

(under Part 1 of the project)<br />

229,700,000 257,993,778<br />

2 Goods<br />

(i) Under Part 1 (iv) of the project<br />

(ii) Under Part 2 (iv) of the project<br />

9,900,000<br />

300,000<br />

5,006,222<br />

3 Incremental Operating Costs<br />

(under Part 2 (v) of the project)<br />

700,000 700,000<br />

4 Consultants‟ services<br />

(i) Under Part 2 (i) of the project<br />

(ii) Under Part 2 (ii) of the project<br />

(iii) Under Part 2 (iii) of the project<br />

6,300,000<br />

17,000,000<br />

1,200,000<br />

26,300,000<br />

5 Unallocated 34,900,000 -<br />

TOTAL (AUD) 300,000,000 300,000,000<br />

Table 11-2<br />

Loan Amendment Changes<br />

Project Management Unit (PMU-EINRIP) Page 52


EINRIP 2010 Annual Progress Report<br />

The loan extension explanatory note and supporting analysis was <strong>com</strong>pleted by DGH in end of<br />

December 2010 and will be submitted to Bappenas in January 2011. After endorsement of the<br />

loan amendment, the explanatory note will be sent to Ministry of Finance (MOF) and it is<br />

targeted to finalise the loan agreement by March 2011.<br />

Project Management Unit (PMU-EINRIP) Page 53


Appendices<br />

EINRIP 2010 Annual Progress Report<br />

APPENDICES<br />

Project Management Unit (PMU-EINRIP) Page 54


Appendices<br />

EINRIP 2010 Annual Progress Report<br />

Appendix 1<br />

Summary of ESS Studies at<br />

December 2010<br />

Project Management Unit (PMU-EINRIP) Page 55


Appendices<br />

EINRIP 2010 Annual Progress Report<br />

Appendix 2<br />

Procurement Plan Approved in 2010<br />

Version 5 & 6<br />

Project Management Unit (PMU-EINRIP) Page 56


Appendices<br />

EINRIP 2010 Annual Progress Report<br />

Appendix 3<br />

Status of Procurement Plan<br />

31 December 2010<br />

Project Management Unit (PMU-EINRIP) Page 57


Appendices<br />

EINRIP 2010 Annual Progress Report<br />

Appendix 4<br />

Contract Data Sheets of Ongoing Civil<br />

Works<br />

Project Management Unit (PMU-EINRIP) Page 58


Appendices<br />

EINRIP 2010 Annual Progress Report<br />

Name of Package<br />

Province<br />

EBL-01, TOHPATI – KUSAMBA<br />

Bali<br />

CONTRACT SUMMARY & PROGRESS DATA<br />

Contract No. KU.08.08-727-40/EBL-01/NR/ A/L002/1208 Contract Signed December 5, 2008<br />

Contractor<br />

JAYA KONSTRUKSI – DUTA GRAHA<br />

INDAH, JO<br />

Commencement Date February 25, 2009<br />

Contract Amount Rp. 180,819,429,297 (incl VAT) Time for Completion 730 days<br />

Project Scope<br />

PROGRESS REPORT<br />

Reporting Period December 2010<br />

Physical Progress<br />

Effective length : 10.79 kms<br />

Dual carriageway : (2x7x0.5) m and<br />

(0.5x7x2) m<br />

10 Bridges, 30 Culverts, 16 Syphons<br />

Scheduled<br />

Actual<br />

Deviation<br />

Disbursement/Payment Status (incl VAT)<br />

Advance Payment: Rp. 18,081,942,928<br />

IPC#1, 2, 3 Rp. 2,414,453,292<br />

IPC # 4, 5 Rp. 10,567,996,932<br />

IPC#6 Rp. 9,280,124,695<br />

IPC#7 Rp 4,111,037,332<br />

IPC#8 Rp 2,881,470,894<br />

IPC#9 Rp. 8,906,763,405<br />

IPC#10 Rp. 5,384,773,949<br />

:<br />

:<br />

:<br />

96,35 %<br />

74,26 %<br />

- 22.09 %<br />

Defects Notification Period<br />

Contract Time elapsed<br />

(days and %)<br />

365 days<br />

675 days<br />

92.50 %<br />

IPC#11 Rp. 4,906,154,028<br />

IPC#12 Rp. 14,893,015,993<br />

IPC#13 Rp. 3,341,640,804<br />

IPC#14-15 Rp 3,646,702,631<br />

IPC#16 Rp. 9,844,509,767<br />

IPC#17 Rp. 8,342,248,041<br />

IPC#18 Rp. 5,887,554,549<br />

Total: Rp. 112,492,389,237.04 (62.21 %)<br />

PROJECT ISSUES & ACTION<br />

Contractor was instructed to improve boring equipment for achieving 16m pile depth at Tukad Udang udang bridge in Jan<br />

2010. TFAC finding result suggested all work on Tukad Udang-udang bridge should be suspended, pending the out<strong>com</strong>e of<br />

<strong>detail</strong>ed technical review. The revised design for Tukad Udang-Udang bridge is under review by AusAID.<br />

Re-design for pier at Tukad Was bridge was <strong>com</strong>pleted in Feb 2010<br />

VO no 3 covering additional quantity and new pay item was in prepration but was not finalized till end of 2010. The draft was<br />

formally submitted to AusAID for NOL on 13 August 2010. AusAID did not issue NOL to the amendment due to in<strong>com</strong>plete<br />

technical justification and disagreement with a number of items.<br />

Rigid pavement between km 3+950 and 4+070 was removed <strong>com</strong>pletely.<br />

RSC terminated the SSE, Quality Engineer, surveyor and inspector on July 2010 due to poor performance<br />

As a follow up of the TFAC audit, RSC conducted additional investigations and at STA 4+020 found that the aggregate Class<br />

A did not meet specifications and the thickness of lean concrete was less than design thickness. SQPMS-RSC inspection<br />

showed clearly the materials for aggregate base fully natural and uncrushed below lean concrete. Base on this finding, TL-<br />

RSC suspects that the aggregate class A below of the lean concrete is not adequate with specification.<br />

For further analysis, RSC had initially instructed demolition of one slab in every kilometer. Later this instruction was revised to<br />

a lesser destructive testing method i.e. coring at every 250 m to a depth of 42 cms, for testing for thickness, mix and strength.<br />

Removal of Rigid pavement between STA 3+950 and 4+070 was ordered by the Engineer.<br />

With the exception of bridges works, the Engineer suspended the works effective on 27 September 2010 due to the lack of<br />

<strong>com</strong>petent management and as many Engineer’s instruction were not followed by the Contractor. The Tukad Udang Udang<br />

Bridge works were suspended on 22 September 2010.<br />

New road section at STA 3+600 failed, demolition of this section in progress<br />

Inadequate control of traffic diversion was seen on detours/ramps. Contractor instructed to maintain detours and provide lights<br />

at at night.<br />

Project Management Unit (PMU-EINRIP) Page 59


Appendices<br />

EINRIP 2010 Annual Progress Report<br />

Project Management Unit (PMU-EINRIP) Page 60


Appendices<br />

EINRIP 2010 Annual Progress Report<br />

CONTRACT SUMMARY & PROGRESS DATA<br />

Name of Package EBL- 02, TOHPATI – KUSAMBA Stage 2<br />

Province<br />

Bali<br />

Contract No. 02-40/EBL-02/NR/A/L002/1209 Contract Signed 10 December 2009<br />

Contractor<br />

PT. ADHI KARYA – PT.WASKITA KARYA<br />

(Persero), JO<br />

Commencement Date 1 March 2010<br />

Contract Amount Rp. 175,610,522,000 (incl 10%VAT) Time for Completion 730 Calendar Days<br />

Project Scope<br />

PROGRESS REPORT<br />

Reporting Period December 2010<br />

Physical Progress<br />

Effective length : 8.2 kms<br />

Dual carriageway, (2x7x0.5) m and<br />

(0.5x7x2)m 5 new bridges, 1 aqua duct,<br />

extension of 47 box culverts, and 18<br />

syphons<br />

Scheduled<br />

Actual<br />

Deviation<br />

:<br />

:<br />

:<br />

30.01 %<br />

32.64 %<br />

+ 2.634 %<br />

Defects Notification Period<br />

Contract Time elapsed<br />

(days and %)<br />

365 Calendar Days<br />

306 days<br />

41.90 %<br />

Disbursement/Payment Status (incl VAT)<br />

Advance Payment: Rp 14,048,841,760 (8%)<br />

IPC#1-2 Rp. 5,473,661,860<br />

IPC#3 Rp. 5,360,793,588<br />

IPC#4 Rp. 7,342,343,728<br />

IPC#5 Rp 5,522,485,734<br />

IPC#6 Rp 6,663,543,052<br />

IPC#7 Rp 1,565,158,787<br />

IPC#8 Rp 7,888,766,124<br />

IPC#9 Rp 10,476,994,653<br />

Total: Rp. 64,342,589,286 (36.64 %)<br />

PROJECT ISSUES & ACTION<br />

No Pay item for clearing and grubbing works (pay item 3.4.3)<br />

Dimension of box culverts extension do not match with the existing box dimension, and there have been <strong>com</strong>plaints from local<br />

farmer irrigation society (SUBAK).<br />

SSE has instructed the Contractor to prepare drawings for revised design for 5 syphons and 7 box culverts.<br />

Contractor Quality Control Plant has been submitted to the Engineer for approval.<br />

Variation Order No 1 for changed mobilization schedule has been submitted to Balai for approval.<br />

Activities going as planned on various items and project ahead of schedule.<br />

Variation Order No.2 is under revision of the Contractor.<br />

Project Management Unit (PMU-EINRIP) Page 61


Appendices<br />

EINRIP 2010 Annual Progress Report<br />

Name of<br />

Package<br />

Province<br />

EKB-01, PONTIANAK – TAYAN<br />

West Kalimantan<br />

CONTRACT SUMMARY & PROGRESS DATA<br />

Contract No. 03-30/EKB-01/NR/A/L002/0409 Contract Signed 20-Apr-09<br />

Contractor PT. WASKITA KARYA Commencement Date 24-Jul-09<br />

Contract<br />

Amount<br />

Project Scope<br />

PROGRESS REPORT<br />

Reporting<br />

Period<br />

Physical<br />

Progress<br />

Rp. 137,336,950,000 (incl VAT) Time for Completion 730 calendar days<br />

Effective length : 31.50 kms<br />

Carriageway : 6 m with 1.5 m shoulders 39<br />

Box Culvert/RCP, 67 Corrugated Pipe<br />

Culvert<br />

December 2010<br />

Scheduled<br />

Actual<br />

Deviation<br />

:<br />

:<br />

:<br />

71.02 %<br />

66.45 %<br />

- 4.56 %<br />

Defects Notification Period<br />

Contract Time elapsed<br />

(days and %)<br />

365 days<br />

526 days<br />

72.10 %<br />

Disbursement/Payment Status (incl VAT)<br />

Advance Payment: Rp. 13,733,695,000<br />

IPC#1,2,3 Rp. 4,448,123,185<br />

IPC#4,5,6 Rp. 11,397,441,697<br />

IPC#7, 8 Rp. 9,725,556,575<br />

IPC#9,10 Rp. 11,208,262,796<br />

IPC#11,12,13 Rp. 10,490,063,800<br />

IPC#14, 15 Rp. 11,833,217,641<br />

IPC#16, 17 Rp. 12,947,579,746<br />

Total: Rp. 85,783,940,437.66 (62.46%)<br />

PROJECT ISSUES & ACTION<br />

Laying of geo textile <strong>com</strong>menced on January 2010 for preloading.<br />

AMP and Aggregate blending Plant were calibrated and operational in March 2010.<br />

JMF for AC-BC and mobilization of Asphalt finisher and Asphalt distributor was <strong>com</strong>pleted in April.<br />

VO meeting was held on 1 April 2010 between Balai, Wilayah Timur, PPK, PMU, PMSC and RSC.<br />

Quality Control Plan by contractor was <strong>com</strong>pleted by May 2010.<br />

In the VO discussion held on 17 June 2010 agreed that there is no alternative selected for road formation width and it was decided<br />

to follow the original design.<br />

For alignment change shown in VO no.1 that have differences regarding centre line and elevation <strong>com</strong>pared to design drawing,<br />

possibly the survey for staking out design drawing is not correct.<br />

Related the VO No.1, Head of Sub Directorate of Road Technical on 26 August 2010 has decided to revert to original design 1.5-<br />

6-1.5 m and for differences of surveying, it was decided by Head of Sub Directorate of Road Technical to involve third party<br />

independent Surveyor for evaluate which survey is correct.<br />

TFAC Audit was done on July 2010 and found some non conformity. Special observation from TFAC is concerning coal fire /<br />

burning asphalt plant. Certificate from Balai related to the Asphalt Plan operation was received,<br />

In the Bawas Lestari Bridge at STA 15 + 300 is a 30 m single slab, steel girder and RCC slab bridge (not part of EKB-01 contract),<br />

one the abutment has started tilting towards approach and the bridge is unsafe for traffic. RSC has <strong>com</strong>pleted the preliminary<br />

investigations and report submitted to Client. In the interim, the construction of fill on the abutment has been stopped by RSC and<br />

existing material has been removed.<br />

VO No.1 is still under preparation.<br />

Project Management Unit (PMU-EINRIP) Page 62


Appendices<br />

EINRIP 2010 Annual Progress Report<br />

Project Management Unit (PMU-EINRIP) Page 63


Appendices<br />

EINRIP 2010 Annual Progress Report<br />

Name of Package<br />

Province<br />

Contract No.<br />

Contractor<br />

ONTRACT SUMMARY & PROGRESS DATA<br />

ESU-01, MOLIBAGU – MAMALIA - TALUDAA<br />

North Sulawesi<br />

KU.08.08-01-50/ESU-01/NR/A/AIPRD-<br />

L002/1209<br />

PT.NINDYA KARYA (Persero)– PT BUMI<br />

KARSA, JO<br />

Contract Signed 2 December 2009<br />

Commencement Date 1 March 2010<br />

Contract Amount Rp. 42,663,776,000 (incl VAT) Time for Completion 540 days<br />

Project Scope 5 Bridges replacement Defects Notification Period 365 days<br />

PROGRESS REPORT<br />

Reporting Period December 2010<br />

Physical Progress<br />

Scheduled<br />

Actual<br />

Deviation<br />

PROJECT ISSUES & ACTION<br />

:<br />

:<br />

:<br />

29.50 %<br />

8.63 %<br />

-20.87 %<br />

Contract Time elapsed<br />

(days and %)<br />

306 days<br />

56.70 %<br />

Disbursement/Payment Status (incl VAT)<br />

Advance Payment: Rp. 4,266,377,600 (10%)<br />

IPC#1,2,3 Rp 1,684,504,991<br />

IPC#4 - 7 Rp 1,757,805,661<br />

Total: Rp. 7,708,688,252 (18,07 %)<br />

Consultant’s Bridge Engineer has not been mobilized up to April 2010<br />

Slow mobilization of major equipment. The main equipment for bore pile for this work was not mobilized till November 2010<br />

Limited information from this package regarding <strong>com</strong>munication problem. No fixed telephone facility and mobile phone signal<br />

in this project area. Additional budget was proposed for fuel, satellite phone and operational cost satellite phone. Due to this<br />

problem late receipt of the weekly report submitted every week by SSE to PMU-EINRIP.<br />

CSE has instructed investigations for checking the strength of existing abutment and underlying foundation of Pilolahunga<br />

Bridge. Subject to results of investigations, the existing embankment may not be strong to resist seismic loading in which case<br />

new abutments and foundations has to be designed and design to be revised.<br />

A meeting to review progress was held on 14 October 2010<br />

Contractor has been instructed by Engineer to re-submit Traffic Management and Quality control plans.<br />

Project Management Unit (PMU-EINRIP) Page 64


Appendices<br />

EINRIP 2010 Annual Progress Report<br />

Name of Package<br />

Province<br />

CONTRACT SUMMARY & PROGRESS DATA<br />

ENB- 01AB, SUMBAWA BESAR BYPASS<br />

West Nusa Tenggara (NTB)<br />

Contract No. 01-23/ENB-01AB/NR/A/L002/0309 Contract Signed 16 March 2009<br />

Contractor<br />

PT. JAYA KONTRUKSI MANGGALA<br />

PRATAMA Tbk<br />

Contract Amount Original: Rp. 66,983,600,000<br />

Amendment 1 & 2 approved in Dec-09<br />

Revised: Rp 71,511,445,000 (incl VAT)<br />

Project Scope<br />

PROGRESS REPORT<br />

Reporting Period December 2010<br />

Physical Progress<br />

(based on revised<br />

program)<br />

Effective Length : 11.2 Kms<br />

(9.029 km @ 7.0 m; 2.171 km @ 6.0 m)<br />

Culverts: 10 new, 18 replacement, 19 syph<br />

Scheduled<br />

Actual<br />

Deviation<br />

PROJECT ISSUES & ACTION<br />

:<br />

:<br />

:<br />

81.30 %<br />

54.03 %<br />

- 27.28 %<br />

Commencement Date 5 June 2009<br />

Time for Completion<br />

Defects Notification Period<br />

Contract Time elapsed<br />

(days and %)<br />

540 days (original)<br />

640 days (revised)<br />

365 Calendar Days<br />

575 days<br />

89.80 %<br />

Disbursement/Payment Status (incl VAT)<br />

Advance Payment: Rp. 6,698,360,000<br />

IPC#1,2,3,4,5 Rp. 2,969,340,557<br />

IPC#6,7 Rp. 4,770,952,876<br />

IPC#8,9,10 Rp. 3,182,663,343<br />

IPC#11 Rp. 2,104,972,178<br />

IPC#12,13,14 Rp. 3,453,145,470<br />

IPC#15 Rp. 1,015,025,350<br />

IPC#16 Rp. 1,596,303,369<br />

IPC#17 Rp. 3,049,588,839<br />

IPC#18 Rp. 7,354,459,190<br />

Total: Rp. 36,194,810,872.91(50.61 %)<br />

Additional retaining walls need to be constructed at several locations to protect people houses form collapse due to excavation activity,<br />

PPC design integration did not ac<strong>com</strong>modate this structure in drawing<br />

There are problems with relocation of PLN electric poles within widening area. PLN specification need extra poles if relocated in<br />

residential area and need additional transformer. The quantity for related works is not sufficient and provided in the BOQ, as the BOQ<br />

covered relocation for PLN electric pole only – did not include material related to PLN electric pole (like transformer and cable). PLN<br />

advised that they have no budget for this activity, and additional budget was proposed.<br />

NOL to contract amendment for relocation of utilities has been issued by AusAID<br />

Variation Order for additional quantity and Technical Justification under process<br />

The first meeting for VO 3 at level Balai was held in Jakarta on 11 May 2010. Unfortunately as same like others Technical Justification<br />

prepared by RSC, this TJ was not endorsed by TL-RSC, only approved by SSE. Too much delay by RSC in preparing this TJ<br />

Amendment No. 3 (additional quantity) + Technical Justification to cover all problems above has been endorsed by TL-RSC and is<br />

under discussion.<br />

Project Management Unit (PMU-EINRIP) Page 65


Appendices<br />

EINRIP 2010 Annual Progress Report<br />

CONTRACT SUMMARY & PROGRESS DATA<br />

Name of Package ENB-01C, PAL IV – KM 70<br />

Province<br />

West Nusa Tenggara (NTB)<br />

Contract No. 02-23/ENB-01C/NR/A/L002/1209 Contract Signed 9 December 2009<br />

Contractor PT. JAYA KONSTRUKSI – DUTA GRAHA, JO Commencement Date 1 March 2010<br />

Contract Amount Rp. 145,604,273,000 (incl VAT) Time for Completion 730 calendar days<br />

Project Scope<br />

Effective length : 31.787 kms<br />

Carriageway : 6m wide 2x1.5m shoulders<br />

Culverts: 5 new<br />

Defects Notification Period<br />

365 days<br />

PROGRESS REPORT<br />

Reporting Period December 2010<br />

Physical Progress<br />

Scheduled<br />

Actual<br />

Deviation<br />

PROJECT ISSUES & ACTION<br />

:<br />

:<br />

:<br />

27.70 %<br />

8.53 %<br />

- 19.16 %<br />

Contract Time elapsed<br />

(days and %)<br />

306 days<br />

41.90 %<br />

Disbursement/Payment Status (incl VAT)<br />

Advance Payment: Rp 14,560,427,300<br />

IPC#1,2,3,4 Rp 2,118,530,188<br />

IPC#5,6 Rp 1,740,391,011<br />

IPC#7,8 Rp 1,619,420,618<br />

IPC#9 Rp 7,376,617,326<br />

Total: Rp. 27,415,386,442.72 (18.83 %)<br />

Slow mobilization and delay in obtaining permits for base camp and quarry activities<br />

Reported mobilization is still in progress. Penalty must be applied for this delay.<br />

3 bridges included in the contract were recently <strong>com</strong>pleted under APBN project; there will be reduction contract cost.<br />

RCTA applied in this project with depth 22 cm. The average existing asphalt thickness is 15 cm. The next layer is gravel with average<br />

thickness 5 cm . After that the layer is Telford foundation. Telford layer can not be milled by recycling machine. Due to RCTA elevation<br />

was defined in design drawing and RCA thickness is 22 cm, application RCTA for this condition difficult to be applied.<br />

Variation Order No 1 that includes relocation of PDAM utility pipes and PLN poles additional quantities for embankment and granuilar<br />

material has been endorsed by RSC TL on 27-Oct-2010 for approval process.<br />

Contractor has been instructed by Engineer to re-submit Traffic Management and Quality control plans<br />

Project Management Unit (PMU-EINRIP) Page 66


Appendices<br />

EINRIP 2010 Annual Progress Report<br />

Name of Package<br />

Province<br />

CONTRACT SUMMARY & PROGRESS DATA<br />

ENB-02, KM 70 – Bts. CABDIN DOMPU<br />

West Nusa Tenggara (NTB)<br />

Contract No. 04-23/ENB-02/NR/A/L002/1209 Contract Signed 14 December 2009<br />

Contractor PT. SUMBER SARI CIPTA MARGA Commencement Date 6 April 2010<br />

Contract Amount Rp. 68,261,116,000 (incl 10%VAT) Time for Completion 540 calendar days<br />

Project Scope<br />

PROGRESS REPORT<br />

Reporting Period December 2010<br />

Physical Progress<br />

Effective length : 12.77 kms<br />

Carriageway: 7 m with 2x2m shoulders<br />

Rehabilitation of 7 Bridges, 33 Culverts<br />

and 30 new culverts.<br />

Scheduled<br />

Actual<br />

Deviation<br />

:<br />

:<br />

:<br />

41.63 %<br />

5.22 %<br />

- 36.41 %<br />

Defects Notification Period<br />

Contract Time elapsed<br />

(days and %)<br />

365 calendar days<br />

270 days<br />

50.00 %<br />

Disbursement/Payment Status (incl VAT)<br />

Advance Payment: Rp 6,826,111,600 (10%)<br />

IPC#1,2,3,4,5 Rp 1,358,088,336<br />

IPC#6,7 Rp 2,.509,685,284<br />

IPC#8 Rp 715,959,429<br />

Total: Rp. 11,409,844,648.65 (16.71 %)<br />

PROJECT ISSUES & ACTION<br />

Commencement of work delay as PAP have not yet received the payment by March 2010<br />

Management and financial problems, contractor’s GS was absent from the project since 17 May 2010. New GS arrived on 12<br />

June 2010<br />

Variation Oder under preparation to cater for possible realignment, rock excavation, slope protection works.<br />

8 months elapse (per December 2010), field engineering reported still in process<br />

Lack of proper management, limited personnel to adequate the activity by Contractor and financial problems still not resolved<br />

Deviation by December 2010 was -36.41% (critical condition), SCM 2 was held on 24 November 2010<br />

Project Management Unit (PMU-EINRIP) Page 67


Appendices<br />

EINRIP 2010 Annual Progress Report<br />

Name of Package<br />

Province<br />

CONTRACT SUMMARY & PROGRESS DATA<br />

ENB 03, BTS CABDIN DOMPU - BANGGO<br />

West Nusa Tenggara (NTB)<br />

Contract No. 03-42/ENB-03/NR/A/L002/1209 Contract Signed 10 December 2009<br />

Contractor<br />

PT. ADHI KARYA – PT.WASKITA KARYA<br />

(Persero), JO<br />

Commencement Date 1 March 2010<br />

Contract Amount Rp. 101,927,591,000.00 (incl. 10%VAT) Time for Completion 540 Calendar Days<br />

Project Scope<br />

PROGRESS REPORT<br />

Effective length : 23.62 kms<br />

Single Carriageway 6m + 2x1.5m<br />

shoulders<br />

34 box culverts<br />

Reporting Period December 2010<br />

Physical Progress<br />

Scheduled<br />

Actual<br />

Deviation<br />

:<br />

:<br />

:<br />

15.84 %<br />

6.50 %<br />

- 9.34 %<br />

Defects Notification Period<br />

Contract Time elapsed<br />

(days and %)<br />

365 Calendar Days<br />

306 days<br />

56.70 %<br />

Disbursement/Payment Status (incl VAT)<br />

Advance Payment: Rp 10,192,759,100 (10%)<br />

IPC#1,2,3,4,5,6 Rp. 6,614,111,710<br />

IPC#7,8 Rp. 1,933,556,277<br />

PC#9 Rp. 1,292,635,510<br />

Total: Rp. 20,033,062,596.31 (19.65 %)<br />

PROJECT ISSUES & ACTION<br />

All consultant member have been mobilized on April 2010,<br />

Up to June 2010 Stone crusher has not been <strong>com</strong>plete erected.<br />

Mobilization is still in progress. Penalty must be applied for this delay of mobilization.<br />

Stationing and Field engineering survey are in progress<br />

The erection of stone crusher has not yet been finished. This delay will cause delays in production of crushed stone.<br />

Variation Order under preparation that covers rock excavation, improvement of expansive soils, possible realignment.<br />

Rock excavation works were not ac<strong>com</strong>modated in present design. Due to this additional works, this project proposed<br />

additional budget approximately Rp. 76 billion including rock excavation. This VO-01 is under review.<br />

Project Management Unit (PMU-EINRIP) Page 68


Appendices<br />

EINRIP 2010 Annual Progress Report<br />

Name of Package<br />

Province<br />

CONTRACT SUMMARY & PROGRESS DATA<br />

ESR-01, TINANGGEA – KASIPUTE<br />

South East Sulawesi<br />

Contract No. KU.08.08-55/ESR-01/056/NR/A/L002/0409 Contract Signed 02 April 2009<br />

Contractor<br />

PT. MULTI STRUCTURE – PT. TRIFA<br />

ABADI, JO<br />

Commencement Date 13 July 2009<br />

Contract Amount Rp. 115,730,355,000 (incl VAT) Time for Completion 730 calendar days<br />

Project Scope<br />

PROGRESS REPORT<br />

Reporting Period December 2010<br />

Physical Progress<br />

Effective length : 33.75 kms<br />

Carriageway : 6 m with 1.5 m shoulders<br />

5 Bridges, 21 Culverts<br />

Scheduled<br />

Actual<br />

Deviation<br />

:<br />

:<br />

:<br />

73.74 %<br />

26.86 %<br />

- 46.88 %<br />

Defects Notification Period<br />

Contract Time elapsed<br />

(days and %)<br />

365 calendar days<br />

537 days<br />

73.60 %<br />

Disbursement/Payment Status (incl VAT)<br />

Advance Payment: Rp. 11,573,035,500<br />

IPC#1,2,3 Rp. 1,512,088,272<br />

IPC#4,5 Rp. 2,074,596,120<br />

IPC#6,7 Rp. 2,162,700,557<br />

IPC#8 Rp. 2,752,818,052<br />

IPC#9 Rp. 1,593,111,739<br />

IPC#10 Rp. 960,337,644<br />

IPC#11, 12 Rp 1,833,615,065<br />

IPC#13 Rp 913,040,813<br />

IPC#14-15 Rp 1,166,605,053<br />

IPC#16 Rp 1,070,386,100<br />

IPC#17 Rp 11,592,833,928<br />

Total: Rp. 39,205,168,843.71 (33.88 %)<br />

PROJECT ISSUES & ACTION<br />

AMP and aggregate blending plan under construction, some equipment still not <strong>com</strong>plete per January 2010.<br />

SCM 1 was carried out on 04 Feb 2010.<br />

Cash flow problem, insufficient supply of stone for stone crusher regarding limited material resources.<br />

Aggregate Blending Plant operating start on April 2010 but poor supervision.<br />

SCM 2 held on 31 May 2010<br />

Pre-Show Cause Meeting (SCM 3) was held on July 13 in Jakarta. A one month test case was agreed for mobilization of<br />

additional equipment only. Contractor has agreed to mobilize additional equipment such as 1 unit motor grader, 1 unit<br />

aggregate blending machine, 1 unit stone crusher, 1 unit vibro <strong>com</strong>pactor, 2 unit excavator and 6 unit hydraulic breaker. All<br />

equipment reported by SSE-RSC status 31 July 2010 has departed from origin place to Tinanggea.<br />

Considering the difficulty to get permit for exploration Linea quarry, Contractor has proposed 3 locations for quarry (Batu<br />

Langkapa, Tompo Batu and Bumi Raya). The formal permit to exploration the quarry from Local Government fo Langkapa and<br />

Tompo Batu have been obtained, for Bumi Raya under process. With this condition, stone crusher installed in Linea to be<br />

dismantled and moved to Tatanggea (quarry Tompo Batu).<br />

MOU between Contractor and management of National Park for disposal areas reported still in process<br />

TFAC Audit carried out on July 2010 and a number of site instructions were conveyed to the Contractor.<br />

Currently Contractor has 3 stone crushers (all 3 crushers operating). The contractor has one aggregate blending plant with<br />

capacity 25 ton/hour and one aggregate blending plant with capacity 50 ton/jam, both are operating.<br />

VO No. 1 was approved by Engineer on 24 May 2010 for additional cost of Rp. 9,226,304,000. This VO was discussed in<br />

December 2010 and the draft VO has been sent back for revision and improvement by RSC.<br />

Project Management Unit (PMU-EINRIP) Page 69


Appendices<br />

EINRIP 2010 Annual Progress Report<br />

Project Management Unit (PMU-EINRIP) Page 70


Appendices<br />

EINRIP 2010 Annual Progress Report<br />

Name of Package<br />

Province<br />

CONTRACT SUMMARY & PROGRESS DATA<br />

ESR-02. BAMBAEA - SP. KASIPUTE<br />

South East Sulawesi<br />

Contract No. KU.08.08-530/ESR-02/056/NR/A/L002/1209 Contract Signed 02 December 2009<br />

Contractor PT. BUMI KARSA – PT.NINDYA KARYA, JO Commencement Date 30 April 2010<br />

Contract Amount Rp. 95,598,144,012.27 (incl 10%VAT) Time for Completion 540 calendar days<br />

Project Scope<br />

PROGRESS REPORT<br />

Reporting Period December 2010<br />

Physical Progress<br />

Effective length : 23.9 kms<br />

Carriageway: 6m with 2x1.5m shoulders<br />

1 new bridge, 10 bridges rehabilitation and<br />

13 new culverts<br />

Scheduled<br />

Actual<br />

Deviation<br />

:<br />

:<br />

:<br />

21.14 %<br />

14.07 %<br />

- 7.07 %<br />

Defects Notification Period<br />

Contract Time elapsed<br />

(days and %)<br />

365 calendar days<br />

246 days<br />

45.60 %<br />

Disbursement/Payment Status (incl VAT)<br />

Advance Payment: Rp 9,559,814,402 (10%)<br />

IPC#1,2 Rp. 1,322,936,420<br />

IPC#3 Rp. 1,161,627,749<br />

IPC#4 Rp. 1,922,175,644<br />

IPC#5 Rp. 1,500,300,007<br />

IPC#6 Rp. 2,010,405,098<br />

IPC#7 Rp. 6,818,794,143<br />

Total: Rp. 24,296,053,462.12 (25.41 %)<br />

PROJECT ISSUES & ACTION<br />

Only SSE and Quantity Engineer were mobilized in May 2010.<br />

Contractor must find a new location of quarry to anticipation of shortage of material from Lawaeya. This problem must be<br />

anticipated by Contractor. Contractor must find a new location of quarry in anticipation of this shortage.<br />

7 months (by December 2010) after <strong>com</strong>mencement, field engineering reported still in progress.<br />

The contractor claim for new pay item of delivery cost from Cituerup to the project location, bridge erection cost and rock<br />

excavation as they were not ac<strong>com</strong>modate in the Contract (BoQ).<br />

Boring equipment still not mobilized.<br />

Replacement Quality Control Manager accepted by Engineer on 17 December 2010.<br />

Design change may be required for Rau Rau brigde at Sta 0+133 as existing bridge is narrow.<br />

Project Management Unit (PMU-EINRIP) Page 71


Appendices<br />

EINRIP 2010 Annual Progress Report<br />

Name of Package<br />

Province<br />

CONTRACT SUMMARY & PROGRESS DATA<br />

ESS-01, SENGKANG – IMPA IMPA – TARUMPAKKAE<br />

South Sulawesi<br />

Contract No. 02-54/ESS-01/NR/A/L002/1209 Contract Signed 10 December 2009<br />

Contractor PT. MULTI STRUCTURE Commencement Date 1 March 2010<br />

Contract Amount<br />

Project Scope<br />

PROGRESS REPORT<br />

Reporting Period December 2010<br />

Physical Progress<br />

Original: Rp. 100,650,347,589.67<br />

Amendment 1 approved in Apr-10<br />

Revised: Rp 100,903,347,590 (incl VAT)<br />

Effective length : 24.175 kms<br />

Carriage way : 7m (3.25km), 6m<br />

(20.925km) and 2x1.5 shoulders<br />

Rehabilitation of 6 Bridges, Replacement<br />

of 1 bridge<br />

Scheduled<br />

Actual<br />

Deviation<br />

:<br />

:<br />

:<br />

21.11 %<br />

11.51 %<br />

- 9.60 %<br />

Time for Completion<br />

Defects Notification Period<br />

Contract Time elapsed<br />

(days and %)<br />

720 calendar days<br />

365 calendar days<br />

306 days<br />

42.50 %<br />

Disbursement/Payment Status (incl VAT)<br />

Advance Payment: Rp 10,065,034,759 (9.97 %)<br />

IPC#1-10 Rp. 8,433,289,017<br />

Total: Rp. 18,498,323,774.82 (18.33 %)<br />

PROJECT ISSUES & ACTION<br />

Routine maintenance for road and drainage has not been started by April.<br />

No activities carried out on June 2010 except for tree removal only.<br />

Construction of AMP, Stone crusher and Blending plant unit were <strong>com</strong>pleted on August 2010 except for electrical installation.<br />

Stone masonry retaining walls constructed are of poor quality, not accepted by the Engineer.<br />

Contractor’s Quality Control Plan (QCP) still in process by Engineer.<br />

Reported mobilization is still in progress / not yet <strong>com</strong>plete. Penalty must be applied for this delay as has been already 9<br />

months.<br />

Field Engineering is in progress and changes in the quantities under analysis.<br />

Contractor has been instructed by Engineer to re-submit Traffic Management and Quality control plans.<br />

VO No. 1 for changes in mobilization period for equipment has been endorsed by RSC TL. No impact on cost/time.<br />

Project Management Unit (PMU-EINRIP) Page 72


Appendices<br />

EINRIP 2010 Annual Progress Report<br />

Name of Package<br />

Province<br />

CONTRACT SUMMARY & PROGRESS DATA<br />

ESS-02, BANTAENG – BULUKUMBA<br />

South Sulawesi<br />

Contract No. 01-54/ESS-02/NR/A/L002/0509 Contract Signed 19-May-09<br />

Contractor<br />

PT. WASKITA KARYA - PT. BRANTAS<br />

ABIPRAYA JO<br />

Commencement Date<br />

15-Oct-09<br />

Contract Amount Rp. 124,600,055,000 (incl VAT) Time for Completion 730 calendar days<br />

Project Scope<br />

PROGRESS REPORT<br />

Reporting Period December 2010<br />

Physical Progress<br />

Effective length : 26.9<br />

0 kms<br />

Carriageway : 6 m with 1.5 m shoulders 7<br />

Bridges, 19 Culverts, 3 Syphons<br />

Scheduled<br />

Actual<br />

Deviation<br />

:<br />

:<br />

:<br />

57.50 %<br />

17.20 %<br />

- 40.31 %<br />

Defects Notification Period<br />

Contract Time elapsed<br />

(days and %)<br />

365 calendar days<br />

443 days<br />

60.70 %<br />

Disbursement/Payment Status (incl VAT)<br />

Advance Payment: Rp 12,460,005,500 (10%)<br />

IPC#1,2,3,4,5,6,7 Rp. 6,583,820,958<br />

IPC#8,9,10,11 Rp. 3,387,376,078<br />

IPC#12,13,14,15 Rp. 7,921,581,105<br />

Total: Rp. 30,352,783,641.09 (24.36 %)<br />

PROJECT ISSUES & ACTION<br />

Mobilization Period expired on 12 Jan 2010.<br />

Temporary bridge to be provided Contractor’s cost.<br />

Contractor’s Quality Control Plan has been approved by Engineer.<br />

SCM No 1 was held on 16 April 2010<br />

Variation order for reinstatement works in process.<br />

Aggregate blending Plant installation finished in July 2010. Spun piles and pre-stress beams, temporary bridge finished in July 2010<br />

TFAC Audit was carried out on July 2010 and found some non conformity. Special observation from TFAC is concerning coal fire /<br />

burning asphalt plant. This equipment is still without any certificate.<br />

RSC has instructed Contractor on 24-Aug-10 to replace Quality Control manager due to non-performance..<br />

Blending plant has been fully operating on September 2010.<br />

Show Cause Meeting No 3 has been requested by SSE to the PPK..<br />

VO 2 amounting to Rp. 8.54 million was endorsed by Engineer on 17 December 2010.<br />

Project Management Unit (PMU-EINRIP) Page 73


Appendices<br />

EINRIP 2010 Annual Progress Report<br />

Name of Package<br />

Province<br />

ESH-01, LAKUAN - BUOL<br />

Central Sulawesi<br />

CONTRACT SUMMARY & PROGRESS DATA<br />

Contract No. 01-52/ESH-01/NR/A/L002/0510 Contract Signed 25 May 2010<br />

Contractor PT. Brantas Abipraya Commencement Date 7 October 2010<br />

Contract Amount Rp. 128,448,797,000 (incl 10%VAT) Time for Completion 540 Calendar Days<br />

Project Scope<br />

PROGRESS REPORT<br />

Reporting Period December 2010<br />

Physical Progress<br />

Treatment of road is: 16.236 km.<br />

Replacement of 2 temporary single-lane<br />

bridges with new bridges having a total<br />

length of 425 metres.<br />

Bridge approach roads will <strong>com</strong>prise a<br />

total of approximately 2km of road with a<br />

width of 6 m with two 1.5 m shoulders<br />

built on embankment.<br />

Scheduled<br />

Actual<br />

Deviation<br />

PROJECT ISSUES & ACTION<br />

:<br />

:<br />

:<br />

3.19 %<br />

3.38 %<br />

+ 0.19 %<br />

Defects Notification Period<br />

Contract Time elapsed<br />

(days and %)<br />

365 Calendar Days<br />

86 days<br />

15.90 %<br />

Disbursement/Payment Status (incl VAT)<br />

Advance Payment: Rp 10,277,675,000 (10.03 %)<br />

IPC#1 Rp. 2,983,520,374<br />

Total : Rp. 13,261,195,374.18 (12.94 %)<br />

The General Superintendant and Quality Control Manager, included in the bid are to be replaced by the Contractor. No<br />

candidate submitted yet.<br />

CSE instructed for proper disposal of excavated material<br />

Project Management Unit (PMU-EINRIP) Page 74


Appendices<br />

EINRIP 2010 Annual Progress Report<br />

Appendix 5<br />

Payment Monitoring Table for Loan<br />

Categories<br />

Project Management Unit (PMU-EINRIP) Page 75


Appendices<br />

EINRIP 2010 Annual Progress Report<br />

Project Management Unit (PMU-EINRIP) Page 76


Appendices<br />

EINRIP 2010 Annual Progress Report<br />

Appendix 6<br />

Performance Indicators for 2010 ACAP<br />

Implementation Audit<br />

Project Management Unit (PMU-EINRIP) Page 77


Appendices<br />

EINRIP 2010 Annual Progress Report<br />

No INDIKATOR/SUB INDIKATOR PENJELASAN USUL REVISI<br />

I Pengelolaan Website (bobot 15%)/ Establishment of Website (Scoring 15%)<br />

1. Website sudah ada sejak awal proyek fisik, dan mudah diakses<br />

Project Website has been established before the Civil Works contract can <strong>com</strong>mence<br />

and easy to access<br />

2. Manual manajemen proyek telah di-upload pada website<br />

Project Management Manual has been uploaded on website<br />

3. Rencana pengadaan telah di-upload pada website<br />

Procurement Plan has already been uploaded on website<br />

4. Dokumen lelang telah di-upload pada website<br />

Tender documents has already been uploaded on website<br />

5. Dokumen lelang dapat di-download<br />

Tender documents can be downloaded<br />

6. Kontrak yang telah ditandatangani dengan menyajikan nama perusahaan, nilai kontrak, lingkup dan<br />

lokasi pekerjaan telah di-upload pada website<br />

(Penyajian harus lengkap)<br />

Signed Contract Documents <strong>com</strong>pleted with the name of Contractor, contract value,<br />

and sub-project location has already been uploaded on website<br />

(Information should be <strong>com</strong>plete)<br />

7. Ringkasan hasil audit (final) telah di-upload pada website<br />

Summary of the final audit results has already been uploaded on website<br />

8. Laporan Bulanan Progres Proyek untuk setiap sub proyek setiap bulan telah di-upload pada website<br />

(Laporan harus diupload paling lambat tanggal 20 bulan berikutnya)<br />

Monthly Project Progress Report for civil works on each sub-project has already been<br />

uploaded on website<br />

(The report should be uploaded at least at the 20 th of the next month)<br />

9. Laporan Triwulanan Monitoring Keuangan untuk masing-masing sub-proyek telah di-upload pada<br />

website<br />

(Laporan harus diupload paling lambat tanggal 20 setelah akhir triwulan)<br />

Quarterly Financial Monitoring Report for each sub-project has been uploaded on<br />

website<br />

(The report should be uploaded at least at the 20 th after the end of quarter)<br />

10. Informasi tentang Mekanisme Penanganan pengaduan EINRIP dan cara menghubunginya telah di-<br />

Seluruhnya (nomor I)<br />

dilaksanakan oleh Tim Evaluasi<br />

Pusat<br />

All (Point No 1) are<br />

conducted by the<br />

Central Evaluation<br />

Team<br />

harus diupload setiap bulan,<br />

paling lambat tanggal 20 bulan<br />

berikutnya<br />

Should be uploaded<br />

every month, at least<br />

at the 20th of the next<br />

month.<br />

Project Management Unit (PMU-EINRIP) Page 78


Appendices<br />

EINRIP 2010 Annual Progress Report<br />

No INDIKATOR/SUB INDIKATOR PENJELASAN USUL REVISI<br />

upload pada website<br />

Information on EINRIP Complaints Handling Mechanism including contact <strong>detail</strong>s<br />

has been uploaded on website<br />

11. Laporan triwulanan atas status pengaduan yang diterima dan ditangani telah di-upload pada website<br />

(Laporan harus diupload setiap triwulan)<br />

Quarterly report on status of <strong>com</strong>plaints handling has been uploaded on website<br />

(The report must be uploaded quarterly)<br />

12. Laporan triwulanan tentang sanksi yang dijatuhkan terhadap kontraktor atau konsultan sesuai seksi<br />

E ACAP telah di-upload pada website<br />

(Laporan harus diupload setiap triwulan)<br />

Quarterly report on sanction imposed to contractors or consultants under section E of<br />

this ACAP has been uploaded on website<br />

(The report must be uploaded quarterly)<br />

II Persiapan Lelang (bobot 20%)/ Bidding Preparation (Scoring 20%)<br />

1. Procurement Advisory Service (PAS) melakukan tindakan untuk membantu, mendeteksi dan<br />

mencegah praktek-praktek KKN dalam proses pelelangan dan membantu serta memonitor<br />

pelaksanaannya.<br />

PAS is taking action to support, detect and prevent Corruption, Collusion and<br />

Nepotism during the procurement process and monitorize the implementation<br />

(Dibuktikan dengan adanya dokumen yang turut ditanda tangani oleh PAS :<br />

(Proven with the documents also signed by PAS:<br />

Minute of Bid Submission and bid Opening<br />

Form 4 Bid Prices and Bid securities (ass read out)<br />

Form 4A List of Substantial Important Documents <strong>com</strong>prising the bid<br />

Laporan Wakil Masyarakat yang ditandatangani wakil yang bersangkutan/<br />

Report from Public Stakeholders signed by the representatives)<br />

Jika dokumen tersebut tidak ada/tidak lengkap maka dijawab dengan “Tidak”.<br />

If the document is not available/in<strong>com</strong>plete, please mark with “NO”<br />

2. PAS memantau ketaatan panitia pengadaan terhadap jadwal lelang dan untuk memastikan bahwa proses<br />

lelang dan penetapan pemenang dibuat berdasarkan kerangka waktu yang telah disetujui, dan kelambatan<br />

harus diupload setiap triwulan,<br />

paling lambat tanggal 20 bulan<br />

setelah akhir triwulan<br />

Should be uploaded<br />

every 3 months, at<br />

least at the 20th after<br />

the end of quarter.<br />

Sebagai bahan evaluasi pusat<br />

As central evaluation<br />

materials<br />

Project Management Unit (PMU-EINRIP) Page 79


Appendices<br />

EINRIP 2010 Annual Progress Report<br />

No INDIKATOR/SUB INDIKATOR PENJELASAN USUL REVISI<br />

serta risiko yang menyertai dapat dihindari.<br />

PAS to monitor the procurement <strong>com</strong>mittee <strong>com</strong>pliance to procurement plan and<br />

ensure that the procurement process and establishment of winner are based on the<br />

agreed time frame, and the delay or the ac<strong>com</strong>panying risk can be avoided.<br />

3. PAS telah memberikan bantuan atas pelaksanaan bertahap e-procurement untuk masing-masing<br />

provinsi<br />

PAS has provided assistance for the phasing execution of e-procurement process in<br />

each province.<br />

4. Kasatker/PPK telah menyerahkan konsep Harga Perkiraan Sendiri, Owner Estimate (OE) kepada<br />

PMU untuk di-review kecermatannya sekurang-kurangnya 14 hari sebelum dokumen lelang<br />

dikeluarkan.<br />

The Contract Officer for each contract has submitted the OE to the PMU for review of<br />

its accuracy at least 14 days before the bidding documents issued<br />

5. Pelelangan dilaksanakan oleh panitia lelang yang khusus dibentuk untuk paket pekerjaan yang<br />

dilelangkan<br />

Procurement exercised by procurement <strong>com</strong>mittee specifically established for<br />

individual package tendered<br />

6. PAS mengadakan pelatihan kepada panitia pengadaan tentang prosedur lelang untuk EINRIP<br />

PAS has provided procurement <strong>com</strong>mittees with a procurement training on bidding<br />

procedure for EINRIP<br />

7. Setiap Panitia lelang telah mengikuti pelatihan yang dilaksanakan oleh PAS tentang prosedur lelang<br />

untuk EINRIP<br />

Each member of Procurement <strong>com</strong>mittees have attended a procurement training on<br />

bidding procedure for EINRIP provided by PAS<br />

8. Kasatker/PPK dan setiap anggota Panitia Pengadaan telah menandatangani Pakta Integritas sesuai<br />

“Formulir 2‟ Bab V Keppres 80/2003 sebelum lelang diiklankan<br />

An integrity pact in the form of „FORM 2‟ Chapter V of Presidential Decree 80/2003<br />

has been signed by Kasatker/ PPK and each member of the procurement <strong>com</strong>mittee<br />

before the tender advertisement is placed<br />

9. Pengumuman Lelang telah diiklankan pada koran nasional yang beredar di provinsi dimana lelang<br />

tersebut diadakan<br />

Tender notification has already been advertised in national newspapers readily<br />

Project Management Unit (PMU-EINRIP) Page 80


Appendices<br />

EINRIP 2010 Annual Progress Report<br />

No INDIKATOR/SUB INDIKATOR PENJELASAN USUL REVISI<br />

available in the province in which procurement is being undertaken<br />

10. Pengumuman Lelang telah diiklankan pada sistem semi e-procurement Kementerian PU<br />

Tender notification has already been advertised on the MPW Semi e-Procurement<br />

system<br />

11. Pengumuman Lelang telah dimumkan pada website EINRIP<br />

Tender notification has already been announced on the EINRIP website<br />

12. Pengumuman Lelang telah dimumkan pada website DG market<br />

Tender notification has already been announced on DG market<br />

13. Tidak dilaksanakan Rapat penjelasan lelang (aanwijzing), kecuali dengan persetujuan tertulis<br />

sebelumnya dari AusAID<br />

No pre-bid conferences will be held, except with AusAID‟s prior written approval<br />

14. Peserta lelang dapat memperoleh dokumen lelang dengan cara download dari Semi e-Procurement<br />

atau soft copy/hard copy dokumen lelang sampai dalam waktu 24 jam sebelum batas akhir<br />

pemasukan lelang<br />

Bidders may obtain bidding documents by down-loading from semi e-procurement or<br />

soft copy/hard copy of bidding documents be available up to 24 hours prior to the<br />

deadline for submission<br />

15. Nilai OE diumumkan dalam dokumen lelang<br />

Total value of OE be provided in bidding documents<br />

III Evaluasi lelang (bobot 20%)/ Bidding Evaluation (Scoring 20%)<br />

1. Panitia lelang membuka penawaran di depan umum, di hadapan wakil-wakil peserta lelang, serta<br />

pada alamat, tanggal dan waktu yang disebutkan dalam data lelang<br />

Bids will be opened in public by procurement <strong>com</strong>mittee, in the presence of the<br />

bidder‟s representative at the address, date and time specified in bidding data<br />

2. Pembukaan penawaran disaksikan oleh wakil masyarakat yang diundang panitia lelang untuk hadir<br />

Bid opening must be witnessed by representative from relevant local civil society<br />

invited by the procurement <strong>com</strong>mittee<br />

3. Pembukaan penawaran disaksikan oleh Penasehat Pelelangan (PAS)<br />

(Jika jawaban “Ya” maka langsung ke nomor 5. Nomor 4 dijawab “N/A”)<br />

Bid opening must be witnessed by PAS<br />

(If the answer “YES”, then go directly to item 5. Item 4 marked with “N/A”)<br />

Project Management Unit (PMU-EINRIP) Page 81


Appendices<br />

EINRIP 2010 Annual Progress Report<br />

No INDIKATOR/SUB INDIKATOR PENJELASAN USUL REVISI<br />

4. PAS menunjuk Notaris Publik untuk melaksanakan fungsinya bila PAS tidak bisa menghadiri<br />

pembukaan penawaran<br />

PAS appoint a Public Notary to discharge his function if PAS is unable to attend a bid<br />

opening for any reason<br />

5. Penawaran yang diusulkan untuk menjadi pemenang lelang harus dilampiri Pakta Integritas dalam<br />

formulir sesuai „Formulir 2‟ Bab V Keppres 80/2003 atau formulir yang dilampirkan dalam<br />

dokumen lelang (yang ditandatangani oleh masing-masing Peserta Lelang dan diserahkan bersama<br />

dengan penawarannya)<br />

The bidder proposed to be the winner must attach an integrity pact in the form of<br />

“FORM 2” Chapter V of Presidential Decree 80/2003 or the form attached in bidding<br />

documents (signed by each bidder and submitted with their bids)<br />

6. Wakil-wakil dari organisasi kemasyarakatan setempat yang relevan diundang pada setiap<br />

pembukaan penawaran, sekurang-kurangnya 7 (tujuh) hari sebelumnya akan diberitahu tanggal dan<br />

tempat pembukaan penawaran<br />

Representative from relevant local civil society organisations be invited to each bid<br />

opening, at least seven days in advance will be given notification regarding the date<br />

and location of bid opening<br />

7. Batas waktu pemasukan penawaran tidak kurang dari 30 (tiga puluh) hari kerja atau 42 (empat<br />

puluh dua) hari kalender setelah Pengumuman Lelang<br />

Bid submission deadline is a minimum of 30 (thirty) working days or 42 (forty two)<br />

calendar days after the bidding announcement<br />

8. Setiap halaman dari Surat Penawaran dan Bill of Quantities diparaf oleh dua orang wakil Peserta<br />

Lelang yang hadir dan berasal dari perusahaan dan Joint Venture, Consortium or Association<br />

(JVCA) yang berbeda<br />

Each page of a bid proposal and Bill of Quantities must be signed by two<br />

representative bidders and they are from different <strong>com</strong>pany and JVCA<br />

9. Informasi yang berhubungan dengan evaluasi penawaran dan rekomendasi penetapan pemenang<br />

lelang tidak diberitahukan kepada peserta lelang atau orang yang tidak secara resmi berkepentingan<br />

dengan proses tersebut sampai penetapan pemenang lelang disampaikan kepada semua peserta<br />

lelang<br />

All information related to bid evaluation and re<strong>com</strong>mendation for the winner must not<br />

be informed to bidders or others which not correlated with the process up to the<br />

Project Management Unit (PMU-EINRIP) Page 82


Appendices<br />

EINRIP 2010 Annual Progress Report<br />

No INDIKATOR/SUB INDIKATOR PENJELASAN USUL REVISI<br />

proposed winner conveyed to all bidders<br />

10. Permintaan Panitia lelang untuk klarifikasi dan tanggapannya secara tertulis<br />

The bidding <strong>com</strong>mittee request for clarification and its response shall be in writing<br />

11. Hasil pembukaan penawaran diumumkan pada website selambat-lambatnya 24 jam setelah<br />

pembukaan lelang<br />

The results of the bidding shall be notified in the website within 24 hours after the bid<br />

opening<br />

12. Hasil Evaluasi Lelang disampaikan kepada seluruh peserta lelang disertai alasan mengapa<br />

penawarannya tidak ditetapkan sebagai pemenang kepada peserta lelang yang tidak ditunjuk<br />

sebagai pemenang<br />

The Procurement Committee shall write to all bidders with reasons to unsuccessful<br />

bidders why their bid was not selected<br />

13. Panitia lelang menyerahkan kepada AusAID sebagai bagian dari proses No Objection Letter (NOL)<br />

berupa Seluruh penawaran dan alasan-alasan suatu penawaran dinyatakan tidak responsif<br />

Procurement <strong>com</strong>mittee submit to AusAID as part of the NOL process include all bids<br />

received and reasons for any bid being declared as non-responsive<br />

14. PAS membantu Panitia lelang dengan pengendalian mutu sebelum dokumen pengadaan<br />

disampaikan kepada AusAID untuk NOL<br />

PAS will assist procurement <strong>com</strong>mittee with quality control before tender documents<br />

are submitted to AusAID for NOL<br />

IV Pelaksanaan kontrak (bobot 20%)/ Contract Implementation (Scoring 20%)<br />

1. MDF/FIDIC (Multi Donor Fund/Federation Internationale des Ingenieurs Conseils) Harmonised<br />

Contract digunakan untuk seluruh pekerjaan fisik, dengan peran Direksi Pekerjaan diisi oleh Team<br />

Leader Konsultan Regional Supervision Consultant (RSC)<br />

The MDF/FIDIC Harmonised Contract used for all civil works, with the role of<br />

Engineer being filled by the Team Leader of the RSC<br />

2. Pemilik Proyek memberikan rincian seluruh pengaturan berkaitan dengan pelimpahan wewenang<br />

kepada Direksi Pekerjaan (Letter of Appointment), tidak ada perubahan berikutnya yang dilakukan<br />

tanpa persetujuan tertulis sebelumnya dari AusAID<br />

The Employer provided <strong>detail</strong>s of all arrangements in relation to the delegation of the<br />

authority to FIDIC Engineer (Letter of Appointment), and no subsequent changes can<br />

Apakah perlu break-down untuk<br />

rincian pengaturan?<br />

Is it necessary to<br />

break-down the<br />

Project Management Unit (PMU-EINRIP) Page 83


Appendices<br />

EINRIP 2010 Annual Progress Report<br />

No INDIKATOR/SUB INDIKATOR PENJELASAN USUL REVISI<br />

be made to these arrangements without AusAID‟s prior written approval<br />

3. Direksi pekerjaan melimpahkan wewenang kepada Chief Supervision Engineer (CSE) dan Site<br />

Supervision Engineer (SSE), termasuk tanggung jawab untuk mengesahkan sertifikat pembayaran<br />

The Engineer delegated necessary authorities to each Chief Supervision Engineer and<br />

Site Supervision Engineer, including responsibility for authorizing payment<br />

certificates<br />

4. Pekerjaan belum dapat dimulai sampai RSC dimobilisasi dan CSE atau SSE diangkat<br />

Civil Works will not <strong>com</strong>mence until the RSC is mobilized and Chief Supervision<br />

Engineer or Site Supervision Engineer appointed<br />

5. Kasatker/PPK membuat dan memasang papan informasi (notice board) di luar kantor proyek<br />

sebelum proyek dilaksanakan, papan proyek tersebut sekurangnya menginformasikan:<br />

The Contract Officer must establish a notice board outside each Project Office before<br />

works <strong>com</strong>mencement date, at least containing the following information:<br />

- nama pekerjaan/ name of project,<br />

- nama pelaksana pekerjaan/ name of contractor,<br />

- nilai kontrak/ contract value<br />

- prosentase fisik dan keuangan yang selalu di-update setiap bulan/ percentage of <strong>com</strong>pletion<br />

and percentage of contract paid, upadated monthly<br />

- mekanisme penanganan pengaduan/ <strong>com</strong>plaints handling mechanism<br />

- alamat website/ website address<br />

6. Laporan bulanan progres proyek dapat diperoleh masyarakat dan media di tingkat provinsi dan<br />

kabupaten berdasarkan permintaan<br />

The monthly project progress reports are available to civil society and media at the<br />

provincial and kabupaten upon request<br />

7. Semua informasi pada website proyek tersebut dapat diperoleh perorangan/ organisasi yang<br />

berkepentingan berdasarkan permintaan<br />

All information on the project website will also be made available upon request to<br />

interested person/organisation<br />

8. Monthly Progress Report (RSC) diterima PPK, PMU dan PMSC tgl 14 bulan berikutnya, &<br />

dicatat/registrasi<br />

Monthly Progress Report (RSC) shall be received by PPK, PMU and PMSC on the<br />

regulation <strong>detail</strong>s?<br />

Usul butir tambahan :<br />

The proposed<br />

additional points:<br />

1.<br />

Project Management Unit (PMU-EINRIP) Page 84


Appendices<br />

EINRIP 2010 Annual Progress Report<br />

No INDIKATOR/SUB INDIKATOR PENJELASAN USUL REVISI<br />

date 14th of next month, and noted/registered.<br />

9. Monthly Project Report (dari SSE) harus dikirimkan ke team leader RSC paling lambat tgl 7 bulan<br />

berikutnya<br />

Monthly Project Report (from SSE) should be sent to the Team Leader RSC at the<br />

latest on date 7th of next month<br />

V Penanganan Pengaduan (bobot 5%)/ Complaint Handling Procedures (Scoring 5%)<br />

Pengaduan dan sanggahan dapat disampaikan melalui pos ke PO BOX 5100 JKTM, telepon, faksimili,<br />

e-mail dan website<br />

Complaints or objections may be submitted by post to PO BOX 5100 JKTM,<br />

telephone, facsimile, e-mail and website<br />

Jika terdapat sanggahan dalam pelelangan/ If there is objection during procurement<br />

(Jika tidak ada sanggahan, langsung ke nomor 3. Nomor 1 dan nomor 2 diisi dengan N/A)<br />

(If there is no objection, go directly to Item 3. Item 1 and item 2 marked with N/A)<br />

1. Sanggahan diteruskan oleh PMU kepada Satker/PPK atau atasan satker/PPK<br />

Objection is forwarded by PMU to the Contract Officer or the upper level official<br />

2. Sanggahan ditindaklanjuti oleh Satker/PPK atau atasan satker/PPK<br />

The Contract Officer or the upper level Official will take a follow up action and<br />

respond the objection<br />

Jika terdapat pengaduan dalam pelelangan/ If there is <strong>com</strong>plaint during procurement<br />

(Jika tidak ada pengaduan, langsung ke nomor 8. Nomor 3 s/d nomor 7 diisi dengan N/A)<br />

(If there is no <strong>com</strong>plaint, go directly to item 8. Item 3 to item 7 marked with N/A)<br />

3. Pengaduan diteruskan oleh Satker/PPK atau atasan satker/PPK kepada PMU/Itjen Kementerian PU<br />

atau pihak yang berwenang<br />

Complaint is forwarded by Contract Officer or the upper level Official to<br />

PMU/Inspectorate General of MPW or authorized party<br />

4. Pengaduan diteruskan oleh PMU kepada Inspektorat Jenderal Kementerian PU atau pihak yang<br />

berwenang<br />

Complaint is forwarded by PMU to Inspectorate General of MPW or authorized pary<br />

5. Pengaduan ditindaklanjuti oleh Inspektorat Jenderal Kementerian PU atau pihak yang berwenang<br />

Perlu pembicaraan dengan PMU<br />

:<br />

Need discussion with<br />

PMU regarding:<br />

- besarnya bobot/ value of<br />

scoring<br />

- bila tidak ada pengaduan,<br />

apakah karena proyek sudah<br />

baik atau karena masyarakat<br />

tdk peduli/tdk tahu/ if there<br />

is no <strong>com</strong>plaint, whether<br />

because the project is good<br />

or because public is<br />

ignorant/don‟t know<br />

- lebih ditekankan pada<br />

pengujian sistem<br />

penanganan pengaduan/<br />

more focused on testing the<br />

<strong>com</strong>plaint handling system<br />

Project Management Unit (PMU-EINRIP) Page 85


Appendices<br />

EINRIP 2010 Annual Progress Report<br />

No INDIKATOR/SUB INDIKATOR PENJELASAN USUL REVISI<br />

Complaint will be followed up by Inspectorate General of MPW or authorized party<br />

6. Pengaduan tanpa identitas ditindaklanjuti oleh PMU<br />

Anonymous <strong>com</strong>plaint will be followed up by PMU<br />

7. Seluruh pengaduan akan ditanggapi selambat-lambatnya 7 hari setelah diterima<br />

Complaint will be responded within 7 days of receipt<br />

8. Kementerian PU merahasiakan identitas pengadu dalam bentuk pernyataan yang dimuat dalam<br />

website atau media lainnya<br />

MPW keep the <strong>com</strong>plainant identity as secret in form of statement on website or other<br />

media<br />

9. Kementerian PU menerapkan prosedur untuk menjamin kerahasiaan identitas pengadu<br />

MPW implement the procedure to guarantee the <strong>com</strong>plainant identity<br />

10. Status seluruh pengaduan akan dicatat dan dikonsolidasikan dalam laporan bulanan oleh Itjen<br />

Kementerian PU, dan disampaikan kepada PMU dan AusAID<br />

Status of all <strong>com</strong>plaints will be noted and consolidated as monthly report by<br />

Inspectorate General of MPW and forwarded to PMU and AusAID<br />

11. Pengaduan yang berindikasi fraud, kolusi, dan korupsi diserahkan oleh Itjen PU kepada lembaga<br />

Pemerintah Indonesia yang terkait atau auditor independen yang ditunjuk untuk dilakukan<br />

investigasi dan penuntutan<br />

Complaint with indication of fraud, collusion and corruption will be forwarded by<br />

Inspectorate General of MPW to related government organization or appointed<br />

independent auditor for investigation and prosecution<br />

12. Kementerian PU menyusun pedoman tentang sanksi-sanksi yang diterapkan kepada<br />

konsultan/kontraktor/pegawai pemerintah yang terlibat dalam tindak korupsi<br />

MPW prepare guidelines on the sanctions imposed to consultant/contractor/<br />

government employee involved in corruption<br />

VI Keuangan (bobot 10%)/ Financial (Scoring 10%)<br />

1. Setiap PIU/Satker mempunyai seorang spesialis pelelangan yang memenuhi syarat, yaitu<br />

mempunyai sertifikat pengadaan barang dan jasa atau telah mengikuti pelatihan yang dilaksanakan<br />

oleh PAS tentang prosedur lelang untuk EINRIP<br />

Each Satker/ PIU has a qualified procurement specialist with certificate of expertise<br />

in procurement of works/good or he has involved in the EINRIP-procurement training<br />

Project Management Unit (PMU-EINRIP) Page 86


Appendices<br />

EINRIP 2010 Annual Progress Report<br />

No INDIKATOR/SUB INDIKATOR PENJELASAN USUL REVISI<br />

session provided by PAS<br />

2. Setiap PIU/Satker mempunyai pengelola keuangan minimal yang telah mengikuti diklat<br />

bendaharawan yang tugasnya akan termasuk menjamin pembukuan yang memadai untuk<br />

kepentingan audit<br />

Each PIU/Satker has a financial management specialist at least has attended a short<br />

course in treasurer whose duties will include ensuring adequate record keeping for<br />

audit purposes<br />

3. PIU/Satker mempunyai manual dari PMU atas rencana tindak manajemen keuangan, pengendalian<br />

intern dan prosedur penguatan validasi pembayaran, serta pengembangan pelatihan dalam<br />

manajemen keuangan EINRIP<br />

PIU/Satker has a manual from PMU about financial management action plan,<br />

internal controls and strengthen payment validation procedure as well as<br />

development training in EINRIP financial management<br />

4. Satker/PPK memastikan bahwa kontraktor membuka rekening terpisah yang hanya boleh dipakai<br />

untuk menampung dana-dana EINRIP dan dapat diaudit oleh auditor independen<br />

The Contract Officer make sure that contractors open a separate account that is only<br />

permitted to hold EINRIP funds and auditable by independent auditor<br />

5. Staf Satker telah mendapatkan pelatihan dari Ditjen Bina Marga tentang pelelangan dan manajemen<br />

keuangan termasuk persyaratan-persyaratan dari ACAP.<br />

Staff of Satker has received training from DGH on procurement and financial<br />

management including the requirements of ACAP<br />

VII Audit (bobot 10%)/ Audit (Scoring 10%)<br />

1. Satker/PPK telah diaudit keuangan oleh Auditor yang ditunjuk<br />

Satker/ PPK has financially audited by the appointed auditor<br />

2. Satker/PPK telah diaudit teknis oleh Inspektorat Jenderal Kementerian Pekerjaan Umum.<br />

Satker/ PPK has technically audited by Inspectorate General of MPW<br />

3. Satker/PPK telah menindaklanjuti temuan hasil audit keuangan dan audit teknis yang dilakukan<br />

oleh auditor independen selain yang ditunjuk oleh AusAID.<br />

Satker/PPK has followed-up the findings on financial and technical audit conducted<br />

by independent auditor other than those appointed by AusAID<br />

4. Technical & Financial Audit Consultant (TFAC) telah mengadakan pemeriksaan fisik pekerjaan<br />

Usul butir tambahan :<br />

The proposed<br />

additional points:<br />

Project Management Unit (PMU-EINRIP) Page 87


Appendices<br />

EINRIP 2010 Annual Progress Report<br />

No INDIKATOR/SUB INDIKATOR PENJELASAN USUL REVISI<br />

jalan termasuk pekerjaan drainase dan pekerjaan jembatan<br />

TFAC has conducted physical examination of road works including drainage and<br />

bridge<br />

5. TFAC telah mengadakan review terhadap metoda dan proses kerja kontraktor<br />

TFAC has reviewed the contractor‟s method and working process<br />

6. TFAC telah mengadakan audit terhadap sertifikasi dan pembayaran terhadap kontraktor sesuai<br />

dengan kontrak<br />

TFAC has conducted an audit to certification and payment of contractor according to<br />

contract<br />

7. TFAC telah mengadakan audit terhadap kualitas material yang digunakan, peralatan, dan fasilitas<br />

lainnya termasuk fasilitas bagi staf kontraktor.<br />

TFAC has conducted an audit to the quality of materials used, equipment and other<br />

facilities including facilities for contractor‟s staff<br />

8. Kementerian PU menjatuhkan sanksi bagi kontraktor berdasarkan hasil audit teknis<br />

MPW will impose sanction to contractor based on the findings of technical audit<br />

Penilaian/ Scoring:<br />

X adalah jumlah kumulatif dari seluruh indikator (dalam prosentase) = X1 + X2 + X3 + X4 + X5 + X6 + X7<br />

X is cummulative of all indicators (in percentage) = X1 + X2 + X3 + X4 + X5 + X6 + X7<br />

Xn diperoleh dengan cara : jumlah jawaban “ya” dibagi jumlah jawaban “ya” dan “tidak”, dikalikan bobot, dikalikan 100%<br />

Xn is obtained by: total answer of “yes” divided with total answer of “yes” and “no”, multiplied with scoring and 100%<br />

jumlah “ya” (total of “yes”)<br />

= ──────────────────────────── x % bobot (% scoring) x 100%<br />

juml. “ya” + juml “tidak” (tot “yes” + tot “no”)<br />

Project Management Unit (PMU-EINRIP) Page 88


Appendices<br />

EINRIP 2010 Annual Progress Report<br />

Appendix 7<br />

Minutes of the<br />

6 th EINRIP Joint Management Meeting<br />

Project Management Unit (PMU-EINRIP) Page 89


Appendices<br />

EINRIP 2010 Annual Progress Report<br />

DRAFT<br />

MINUTES of the<br />

6th EINRIP JOINT MANAGEMENT MEETING<br />

24 August 2010 - DGH Office<br />

List of Attendance:<br />

DGH: Bapak Harris H. Batubara, Bapak Muh. Iqbal Pane, Bapak Herman Darmansyah, Bapak<br />

Suharjanto, Bapak Budi Harimawan, Ibu Rien Marlia, Ibu Lyana Aryani T. Sihombing, Ibu<br />

Grace A., Bapak Arie Febriyanto, Bapak Hedy Rahadian, Ibu Rani Woro, Bapak Thomas<br />

Setiabudi Aden, Bapak KGS Syaiyful Anwar<br />

MoF: Bapak Maurin Sitorus<br />

Bappenas: Ibu Lusiana Murti, Bapak Aryawan Soetiarso<br />

AusAID: Sam Zappia, Ben Power, Patrick Dennis, Hugh Brown, Leslie Robertson, Bapak Sigit<br />

Pratignyo, Ms Widya Narsi<br />

PMSC: Abid Kazmi, Bapak Yuzerwan Sukiyo, Bapak Efrizal Effendi<br />

Agenda Item 1. Introduction by Chair<br />

The meeting was chaired by Pak Maurin Sitorus, Ministry of Finance, who opened the meeting<br />

at 3.30 pm.<br />

In his opening remarks, Pak Maurin stated that he was pleased to chair this Management<br />

Meeting to discuss the progress of a very important project for the Government of Indonesia. He<br />

stated that EINRIP had made progress but also faced ongoing challenges, including land<br />

acquisition for the remaining projects. This meeting provided the opportunity to examine those<br />

challenges and review the progress made.<br />

Agenda Item 2. Minutes of the Previous Meeting<br />

The meeting accepted the Minutes of Joint Management Meeting No.5 (also Senior Management<br />

Meeting No.2) as final. No <strong>com</strong>ments were received on the draft Minutes circulated by AusAID.<br />

Agenda Item 3. EINRIP Progress Report (Tabled by DGH)<br />

Pak Harris (Director of Planning, DGH) presented the summary report of EINRIP activities for<br />

the previous 6 month period. Project progress included 12 packages in construction stage, 2 more<br />

contracts have been awarded, 2 packages in final stage of procurement, 2 packages now<br />

advertised for bids, and bidding for the last 2 packages would likely <strong>com</strong>mence in September<br />

2010. Progress of expenditure was well under the Procurement Plan target with only 26.7%<br />

expended.<br />

Project Management Unit (PMU-EINRIP) Page 90


Appendices<br />

EINRIP 2010 Annual Progress Report<br />

Agenda Item 4. AusAID Response and Discussion<br />

Sam Zappia (Chief of Operations, AusAID Jakarta) wel<strong>com</strong>ed all to the meeting. He thanked<br />

Pak Maurin for his ongoing interest and <strong>com</strong>mitment to EINRIP to continue chairing the JMM<br />

meetings. Sam also acknowledged the contribution of Pak Taufik in so ably leading the EINRIP<br />

Program over many years as the Director Planning. He wel<strong>com</strong>ed Pak Harris in his new role and<br />

said that AusAID looks forward to working closely with him in future.<br />

Sam thanked Pak Harris for the DGH progress report and invited Ben Power to present<br />

AusAID‟s response.<br />

Comments on DGH Progress Report by Ben Power<br />

Ben Power said AusAID appreciated that some of the land acquisition issues that constrained<br />

procurement of projects last year had been over<strong>com</strong>e. However, AusAID is concerned about the<br />

level of cumulative disbursements so far. With 12 projects now under construction, the average<br />

disbursement is under $ 2 million per month, and a number of these projects were experiencing<br />

significant delays. AusAID is concerned that not all contracts will be <strong>com</strong>pleted by the new loan<br />

closing date of March 2013. There is clearly a need to expedite contracts so that progress is<br />

accelerated as negotiation of a further extension of the loan with the Government of Australia<br />

would prove very problematic.<br />

Pak Harris <strong>com</strong>mented that DGH will make every effort to expedite progress.<br />

Agenda Item 5. Management Issues Raised by AusAID<br />

Ben Power briefly re-stated the need for EINRIP to address key management issues such as<br />

disbursement rates, unsatisfactory physical progress and adherence to standard contract variation<br />

procedures.<br />

Contract Variations<br />

Leslie Robertson (EMU) stated that there were a number of contract variations in progress for<br />

which there had been no formal liaison with AusAID. He acknowledged that variations could<br />

take a long time to formalise and were quite significant in terms of cost and time for <strong>com</strong>pletion.<br />

He quoted the redesign of piles of Tukad Udang2 bridge in EBL-01, Bali, where the design issue<br />

has been known to all parties since September 2009, but to date AusAID has not received any<br />

technical justification for the proposed design change. Les reminded that any design changes<br />

require a No Objection Letter (NOL) from AusAID. There are other packages where variations<br />

have been reported but not consulted with AusAID, and for this reason AusAID is concerned<br />

that the agreed procedures for contract variations are not working properly. There is a need for<br />

increased understanding of the role of various parties under the FIDIC type contract.<br />

Leslie stated that to address this matter, it is AusAID‟s suggestion that resources should be made<br />

available to the RSC supervision team for assessment and evaluation of variations.<br />

Pak Harris stated that two contracts variations are in process; these are EBL-01 in Bali and EKB-<br />

01 in West Kalimantan.<br />

Project Management Unit (PMU-EINRIP) Page 91


Appendices<br />

EINRIP 2010 Annual Progress Report<br />

Bapak Thomas Aden (SubDit Metropolitan Implementation) explained that for EBL-01 some of<br />

the delays were avoidable and that DGH will make all efforts to ensure that they are not<br />

repeated. He also stated that all DGH staff are made aware of the need for an AusAID NOL<br />

before a contract amendment is formalised.<br />

For EKB-01, the Directorate of Planning was still waiting for the decision from Directorate of<br />

Region II to present the technical justification. Ibu Rien explained that there was some<br />

disagreement on alignment that may require a variation.<br />

Hugh Brown (EMU) stated that PMU and PMSC should review the process of variations and<br />

ensure that the information flow between various parties on the process is clear. He also stated<br />

that AusAID is providing training workshops on Contract Administration for FIDIC style<br />

contracts in September or early October. Pak Harris wel<strong>com</strong>ed the training opportunity. He<br />

confirmed DGH planned to remind staff of implementation requirements through internal<br />

meetings, and said that <strong>com</strong>munications between DGH implementation sections and PMU about<br />

contract variations should be more efficient.<br />

Ben Power stated that after these discussions and concerns of AusAID, he expected that there<br />

will be no more delays in preparation of variations and that all necessary documentation will be<br />

sent to AusAID in the next one or two months.<br />

Unsatisfactory Progress: ESR-01 in South East Sulawesi<br />

Leslie conveyed AusAID‟s concern about unsatisfactory progress of project ESR-01 (Tinanggea-<br />

Kasipute). After one year of a 2-year contract progress is only 13%, more than 30% behind<br />

schedule. There have been three (3) show cause meetings, and the Contractor has failed all 3<br />

„test cases‟. The TFAC audit also shows that their work quality is poor. It is AusAID‟s opinion<br />

that the Contract should be terminated as there is little expectation of improvement from the<br />

current contractor. Leslie acknowledged that termination may result in 12 months delay,<br />

however, even with this delay, it is expected that a good contractor could finish the contract<br />

within the extended loan period.<br />

Pak Suharjanto (Sub Directorate region III) stated that it is DGH opinion that the Contractor can<br />

still make up the lost progress by additional effort and that DGH will monitor the progress<br />

closely for another 2 months before taking decision for termination.<br />

Pak Harris stressed that there must be a firm time frame agreed for the evaluation.<br />

Agenda Item 6. Proposed Changes to Loan Sharing Arrangement (by AusAID)<br />

Hugh Brown explained that using the current sharing formula of 89% GoA:11% GoI for civil<br />

works may result in expenditure from loan of only about A$280 million, and contribution from<br />

GoI of A$40 million, which is more than their current <strong>com</strong>mitment of A$30 million. This<br />

situation is primarily due to cost escalation as a result of late starts on some of the contracts and<br />

slow progress of works.<br />

Hugh stated that a number of alternative loan sharing scenarios have been examined. These<br />

scenarios included changing the loan sharing portion to 100% from loan in 2011 and 2012; or<br />

variable sharing over next 3 years. He stressed that the intention was to ensure maximum use of<br />

loan funds before the loan expiry date.<br />

Project Management Unit (PMU-EINRIP) Page 92


Appendices<br />

EINRIP 2010 Annual Progress Report<br />

Ben Power invited DGH to <strong>com</strong>ment on the proposed arrangements. Pak Maurin stated the<br />

intention of GoI to withdraw the loan in full. MoF would discuss with DGH on how to best to<br />

respond to these options. Sam Zappia stated that GoA also intended that the full loan amount be<br />

utilised for the EINRIP program.<br />

Agenda Item 7. Proposed Amendment to Loan Agreement (by AusAID)<br />

Ben Power stated that it has been previously agreed in principle by AusAID and GoI that the<br />

EINRIP Loan Closing date be extended from 1 June 2011 to 31 March 2013, but as yet no<br />

formal amendment to the Loan Agreement has been <strong>com</strong>pleted. He stated that the expected steps<br />

were a letter requesting amendment from MOF to AusAID, then a letter in reply from AusAID<br />

<strong>detail</strong>ing the amendments to be made and counter-signed by MOF.<br />

Pak Maurin explained the general process within GoI and stated that the proposed letter for<br />

amendment will be prepared and sent by DGH to MoF and Bappenas. On re<strong>com</strong>mendation of<br />

Bappenas, MoF will send a formal request to AusAID for changes in the Loan Agreement. He<br />

stated that the process will be initiated soon.<br />

Agenda Item 8. Technical and Financial Audit Consultants: Audit Results<br />

Leslie described the TFAC Audit program and stated that after the initial Bali audit, four more<br />

audits have been <strong>com</strong>pleted for ENB-01 (Sumbawa), EKB-01 (West Kalimantan), ESR-01<br />

(South East Sulawesi) and ESS-02 (South Sulawesi). The Audit reports have been sent to DGH<br />

for onward distribution to DGH staff and RSC.<br />

The audits are intended to assess the basic quality of civil works and the processes being applied.<br />

Initial indications are that there are serious concerns emerging regarding both the processes<br />

being adopted and the quality of the works. The standard of supervision by the RSC as the<br />

Engineer has been unsatisfactory in some cases, and performance needs to be improved by all<br />

parties. He stated that there are no concerns arising from the financial findings. These audits<br />

provide a good opportunity to improve the noted deficiencies and should be seen in a positive<br />

and constructive context of maintaining project quality.<br />

Sam Zappia enquired whether it is possible for AusAID to share examples of good construction<br />

practices to DGH to address the audit findings. Hugh Brown stated that introduction of FIDIC<br />

type contracts is an example for good administration. He stated that changes have to <strong>com</strong>e from<br />

within DGH as some of the issues identified are <strong>com</strong>mon to other projects across Indonesia. The<br />

change is gradual and may face challenges, both internally and externally.<br />

AusAID would be willing to discuss future directions with DGH, but some of the steps that<br />

could be taken immediately are rejection of unsatisfactory work, suspension of work until<br />

standards are improved, strengthening of supervision teams and greater understanding of<br />

contractual requirements of the Engineer and Employer. AusAID will be facilitating several<br />

workshops on the audit findings to focus attention on the key issues, and is prepared to consider<br />

providing further support to DGH to improve the quality aspect.<br />

Pak Harris acknowledged the usefulness of the TFAC audits and the additional support of<br />

AusAID, especially for the holding of practical workshops.<br />

Project Management Unit (PMU-EINRIP) Page 93


Appendices<br />

EINRIP 2010 Annual Progress Report<br />

Agenda Item 9. Variations in Civil Works through design optimisation (balanced budget) -<br />

Tabled by DGH<br />

Ibu Rien presented the background of the balanced budget approach, basing the case on limited<br />

funding available to address all variations in Civil Works contracts. She stated that the maximum<br />

amount available under the loan and GOI contribution is about A$299 million, which will be<br />

insufficient if there are significant variations in the contracts. The approach of DGH is therefore<br />

to consider where the contract variations can be addressed by adjustments in design and scope of<br />

projects, without changing the cost of contract.<br />

In response, Hugh Brown stated that the initial allocation for works were tentative, subject to<br />

adjustment as projects progressed. During the loan discussions it was generally agreed that<br />

additional allocations for <strong>com</strong>pleting the works was not considered to be an impediment by GOI.<br />

As the program for EINRIP has been developed based on DGH‟s accepted standards, AusAID<br />

cannot accept <strong>com</strong>promise or reduction in design standard or in scope. As a general principle, all<br />

changes that do not <strong>com</strong>promise the original agreed standard of roads could be examined on<br />

individual cases-by-case basis, but a general policy of reducing the scope or standard to suit<br />

available funding breaches the Loan Agreement and is not acceptable to GoA.<br />

Agenda Item 10. Other Business<br />

No matter was raised by any participant.<br />

Agenda Item 11. Date of Next Meeting<br />

The meeting agreed that the next 6 Monthly Management Meeting (Senior Level) should be<br />

conducted in middle to late January 2011, with final date to be agreed later.<br />

The meeting closed at 5.10 pm.<br />

Project Management Unit (PMU-EINRIP) Page 94


Appendices<br />

EINRIP 2010 Annual Progress Report<br />

Appendix 8<br />

Management Action Plan Approved in<br />

January 2010<br />

Project Management Unit (PMU-EINRIP) Page 95


Republic of Indonesia<br />

Ministry of Public Works<br />

Directorate General of Highways<br />

Eastern Indonesia National Road Improvement Project<br />

(EINRIP)<br />

AIPRD Loan L002<br />

EINRIP<br />

MANAGEMENT ACTION PLAN<br />

(MAP)<br />

January 2010<br />

PMU - EINRIP<br />

Directorate General of Highways<br />

PMU – EINRIP, Directorate of Planning, DGH


EINRIP, MANAGEMENT ACTION PLAN (MAP)<br />

1. Introduction<br />

The preparation and implementation of EINRIP has been active since 2006 (the loan<br />

effectiveness date was 4-Mar-08). The <strong>detail</strong>ed designs for all approved road improvement<br />

packages and most of environmental studies were <strong>com</strong>pleted before demobilisation of Project<br />

Preparation Consultants (PPC) in April 2009. However, the land acquisition process was still ongoing<br />

and not <strong>com</strong>plete for all packages. PPC also acted as interim procurement consultants for<br />

initial procurement process.<br />

The three implementation support consultants PMSC (for PMU support), PAS (for procurement)<br />

and RSC (construction supervision) were engaged in late 2008 and the consultants are now fully<br />

operational.<br />

Under EINRIP, a total of 24 packages in nine eastern provinces were proposed for construction<br />

in 2008-2012. Preparation of the packages <strong>com</strong>menced in 2007 after initial feasibility studies and<br />

these packages have progressed to varying degree of preparation and implementation.<br />

A brief summary of current status of all EINRIP packages (as at 15-Dec-09) is as follows:<br />

Preparation (design)<br />

Detailed design for all packages is <strong>com</strong>plete.<br />

Environmental and Social Studies<br />

Environmental studies for 19 packages were either not required or have been <strong>com</strong>pleted.<br />

AMDAL process for 3 packages in South Sulawesi, and 2 in South Kalimantan is ongoing.<br />

There was no land acquisition for 2 packages. Land acquisition process for 7 packages has<br />

been <strong>com</strong>pleted.<br />

Of the remaining 15 packages, land acquisition is in progress, but there are insufficient<br />

funds for 4 packages in South Kalimantan.<br />

Procurement of Civil Works<br />

2 packages are under bidding<br />

6 packages are being prepared for bidding to <strong>com</strong>mence in early 2010<br />

Implementation (Construction) of Civil Works<br />

7 additional contracts have been signed in December 2009, and NOL (disbursement)<br />

issued for all. Construction is expected to <strong>com</strong>mence in February 2010.<br />

5 Contracts <strong>com</strong>menced in 2009 and construction is on-going.<br />

2. Rationale of MAP<br />

The <strong>com</strong>parison of planned implementation schedule at start of procurement process in second<br />

half of 2008 and the actual achievement of target schedule has been behind plan, with only five<br />

packages awarded up to November 2009. Land acquisition issues on some packages has<br />

prevented <strong>com</strong>pletion of procurement and award of contract. Primary causes are attributed to:<br />

Delay in early <strong>com</strong>pletion of <strong>detail</strong>ed design of AWP-2 and AWP-3 packages<br />

Delays in <strong>com</strong>pletion of environmental studies (5 still on-going)<br />

PMU – EINRIP, Directorate of Planning, DGH


Increased land acquisition costs <strong>com</strong>pared with initial estimates<br />

Shortage or non-confirmation of available funds with Local Government<br />

Delays in procurement process especially bid evaluation<br />

The packages awarded in late 2009 and those targeted to <strong>com</strong>mence in first half of 2010 will be<br />

in<strong>com</strong>plete by the Loan Closing Date (LCD) originally agreed of 1-June-2011. There is therefore<br />

a need to extend the LCD to cover expenditures of construction beyond the original LCD.<br />

A number of formal and informal discussions have been held between DGH and AusAID on the<br />

possible extension of LCD. AusAID have generally agreed to the extension of LCD on the<br />

assurance that DGH employ additional management measures to monitor any further delays and<br />

apply proactive management interventions to address a particular issue and ensure achievement<br />

of target dates for key stages in implementation.<br />

DGH has assured AusAID that increased monitoring will be undertaken for all packages and this<br />

document, Management Action Plan (MAP) presents the intent and modalities of this assurance.<br />

The purpose of MAP is to demonstrate the additional management control that DGH will<br />

exercise in ensuring of <strong>com</strong>pletion of all phases without further delays.<br />

3. Management Action Plan (MAP)<br />

Due to varying stages of progress for different packages, there is need for developing a realistic<br />

action plan for closer monitoring of various activities. For some sub-packages, land acquisition<br />

and procurement can proceed in parallel, however, the contracts cannot be awarded until all land<br />

acquisition has been <strong>com</strong>pleted and verified.<br />

In appreciating the distinct and overlapping concurrently running activities, three key broad<br />

streams of activities have been identified:<br />

Land acquisition<br />

Procurement<br />

Implementation (Construction)<br />

Due to this overlap in main phases, the MAP identifies key activities and <strong>com</strong>ponent tasks in<br />

each of three phases and focuses on increased and enhanced monitoring.<br />

The MAP en<strong>com</strong>passes following framework:<br />

Identify actions, <strong>com</strong>ponent tasks and agencies/units responsible in each phase;<br />

Develop activity/task monitoring and reporting schedules;<br />

Formulating time-based performance benchmarks for key activities;<br />

Developing intervention modalities in case of delays and difficulties; and<br />

Monitoring and reporting requirements<br />

This monitoring and intervention plan is underpinned by the key performance benchmarks for<br />

each <strong>com</strong>ponent of project implementation i.e. land acquisition, procurement and<br />

implementation.<br />

4. Activity Monitoring Schedules<br />

The MAP <strong>com</strong>prises of first identifying and listing key activities and the tasks that constitute<br />

each key phase. It then lists the main agencies responsible for each activity and the line position<br />

responsible for <strong>com</strong>pletion or approval of each task within the activity.<br />

PMU – EINRIP, Directorate of Planning, DGH


A target date for <strong>com</strong>pletion of each task is identified and the schedule is monitored for task<br />

<strong>com</strong>pletion within the planned time.<br />

The Activity Schedule for Land acquisition, Procurement and Implementation are presented in<br />

Appendix (## not listed in 2010 Annual Report), respectively.<br />

5. Time-based performance benchmarks<br />

A key feature of MAP will be establishing time-based performance benchmarks which will a)<br />

mark the key stages within each mainstream activity; and b) provide a monitoring tool for senior<br />

management about the progress of each activity.<br />

The benchmarks predominantly relate to either production of key document/letter that marks the<br />

<strong>com</strong>pletion of certain phase; or is linked with achieving a target progress within planned time.<br />

The key considerations in developing these benchmarks are that these are tangible (through issue<br />

of NOL, for example) or are linked to achieving a planned activity (increments of 10% physical<br />

progress on civil works is another example).<br />

The proposed performance benchmarks are given below:<br />

Land Acquisition<br />

L-1 Land acquisition budget confirmed by end March 2010 for all packages<br />

L-2 Assurance that land acquisition can be fully <strong>com</strong>pleted before Contract Award, as a<br />

condition for issuance of NOL Procurement<br />

L-3 Examination of <strong>com</strong>pensation payment evidence and submission and acceptance of<br />

LARAP monitoring report before NOL Disbursement can be issued<br />

(The target time frame for NOL for Procurement and NOL for Disbursement are presented<br />

on the most current Procurement Plan and <strong>com</strong>pleted for each package)<br />

Procurement of Civil Works<br />

P-1 Target date for NOL to start Procurement (based on most current Procurement Plan)<br />

P-2 Target date for Bid opening (49 days from NOL-procurement)<br />

P-3 Target date for submission of Bid Evaluation Report (BER) to AusAID and issue of<br />

NOL Award (42 days from bid opening date) - this could be delayed depending on the<br />

clarity of bids received and any clarifications sought from bidders.<br />

P-4 Target date for Contract Signature (14 days from issue of NOL Award)<br />

P-5 Target date for NOL Disbursement (21 days from NOL Award)<br />

Civil Works Implementation (Construction)<br />

C-1 Target date for preconstruction formalities and issue of Commencement Date<br />

(maximum 60 days from Contract signing)<br />

C-2 Monitoring of physical progress achieved for each contract (at 10% increments on<br />

actual achieved progress <strong>com</strong>pared with planned progress)<br />

6. Intervention<br />

The regular monitoring of tasks in the Activity Schedule will highlight those tasks that are<br />

delayed or there are problems with <strong>com</strong>pletion of the task. The time-based performance<br />

benchmarks will be the basis for triggering an intervention by management or by allocating<br />

additional resources by the agency/unit responsible for <strong>com</strong>pletion of that task.<br />

The Activity Schedules will be updated for each package on a monthly basis and the <strong>com</strong>pletion<br />

of tasks identified on the schedule, which will also be used as summary of activity schedules.<br />

Any task which has been delayed will be <strong>com</strong>plemented by filling out a form titled Intervention<br />

Monitoring Report. This report will be <strong>com</strong>pleted for one task at a time – only for those tasks<br />

that fall behind the target <strong>com</strong>pletion date. This report will also identify the causes for delays and<br />

PMU – EINRIP, Directorate of Planning, DGH


modalities for intervention i.e. what intervention is needed, who is responsible for managing<br />

intervention and setting up a revised date for <strong>com</strong>pletion of that task.<br />

This intervention could also be repetitive in nature whether second or additional monitoring is<br />

required and this will also be recorded on the same sheet where 1st intervention was recorded.<br />

The template of Intervention Monitoring Report is attached at Appendix (## not listed in 2010<br />

Annual Report).<br />

7. Monitoring and reporting<br />

It is proposed to prepare the Summary MAP Monitoring Report every month that will report on<br />

the <strong>com</strong>pletion and progress of activities for each package in the preceding month.<br />

The responsibility of MAP monitoring report lies with PMU-EINRIP and supported by PMSC.<br />

Key input from PAS and RSC consultants will also be required.<br />

8. Management Coordination Meetings<br />

The Summary MAP Monitoring Report prepared each month will provide an indication of those<br />

key performance benchmarks that are not met. Such slippages need to be addressed promptly to<br />

avoid further delays. Coordination meeting will be organised by PMU involving key staff from<br />

Directorate of Planning and Director Eastern region.<br />

These coordination meeting will focus on those projects where target benchmarks have not been<br />

achieved. Problem areas will be identified and proactive remedy to remove the particular issue<br />

will be agreed by the two divisions. Monitoring of additional measures adopted to over<strong>com</strong>e the<br />

delays in benchmarks will be conducted and reported in monthly reports.<br />

These meetings will be minuted and distributed to all involved, including a copy to AusAID.<br />

9. Summary Status of ESS & Land Acquisition Studies as at Jan 2010<br />

The summary of ESS activities and land acquisition status is shown at Appendix (## not listed in<br />

2010 Annual Report). The summary also shows the estimated land acquisition costs for each<br />

package.<br />

DGH will ensure that budget availability for land acquisition is confirmed by March 2010 and<br />

that all necessary steps will be taken to provide any shortfall in land acquisition budgets from<br />

APBN.<br />

10. Procurement Plan updated for Jan 2010<br />

The updated Procurement Plan Version 5, as approved in January 2010 attached in Appendix (##<br />

not listed in 2010 Annual Report). The Plan shows the key target dates for procurement and award<br />

of contract. The implementation schedule is shown as a bar chart in Appendix (## not listed in<br />

2010 Annual Report).<br />

11. Appendices<br />

(Note: Appendices are not attached in this Annual Report 2010)<br />

PMU – EINRIP, Directorate of Planning, DGH