Revised Final Environmental Study Report (24 MB) - Gold Canyon ...

Revised Final Environmental Study Report (24 MB) - Gold Canyon ... Revised Final Environmental Study Report (24 MB) - Gold Canyon ...

goldcanyon.ca
from goldcanyon.ca More from this publisher
06.05.2015 Views

Project Description for Submission to Transport Canada Under the NWPA Birch River Bridge, Springpole Road, East of Red Lake, District of Kenora, ON Project History Gold Canyon Resources Inc. is a mining exploration company with an active drilling program on properties it holds near the west end of Springpole Lake. The drilling program is supported by a sixty person tent camp with cookhouse, sewage treatment plant, domestic water supply, core shacks, storage, dock, heli-pad and ancillary lay down areas. Access to the Springpole Camp is currently by helicopter, float plane and a seasonal ice road across Birch Lake to the north of the camp. It is projected that increased drilling activity and mine development will occur over the next few years and it is necessary to improve access to the Springpole Camp. An existing forest access road is located south of the camp (Wenasaga Road 82-6). It is proposed to build a forestry winter operational road from the existing road to the camp, a distance of about 40 km. At 18.2 km along this route is the Birch River, a large river crossing. It is proposed to build the Birch River Bridge to primary road standard in order to provide better protection of environment and to facilitate future upgrades to the road without impacting the river. For simplicity, the trail and future forest access road, will be referred to as Springpole Road. A proposed road to Birch River is approved in the current Forest Management Plan (2009-2019) prepared by Domtar for their Trout Lake Forest. The corridor location for this section was approved by the Ministry of Natural Resources (MNR), following Ontario’s forest management planning process, including public and First Nation consultations. Beyond Birch River, to Springpole Camp, the proposed trail follows the route of a largely pre-existing mineral exploration trail. The route crosses Crown land and mining claims held by Gold Canyon Resources. No other private properties are crossed. The road crosses Birch River near the outlet from Springpole Lake, at the east end of the lake. The location is N51 o 19.959’ W92 o 03.618’ (15U 565465 5687236). It is shown on the 1:50,000 scale topographic map Birch Lake (52 N/8). It is proposed to build a permanent bridge on the short-term trail, so it needs no further upgrading when the all-weather forest access road is constructed. It is proposed to cross Birch River with a clear span structure 120 feet long. A site visit was made on October 6, 2012, when flows were lower than average. From records at a downstream flow gauge station it was determined the flow at the time was 15 m 3 /sec, compared to the mean October flow of 20 m 3 /sec. During the visit a field survey was undertaken to provide data for bridge design. Adamson Consulting is an engineering consultant to Gold Canyon Resources Inc., assisting with design and approvals for water crossings along the route. Project Design An hydrology analysis was completed following the MNR method. Another analysis was done using the Single Station Frequency Analysis Method, as set out in the MTO Drainage Management Manual, 1997. Within the same watershed, downstream of the bridge site, is the Water Survey of Birch River Bridge Adamson Consulting Page 1 of 6 Springpole Trail October 21, 2012

Canada flow gauge on the Cat River, below Wesleyan Lake (04GA002). Drainage area at the bridge site is 1366 km 2 and it is 5390 km 2 at the gauge. Forty-three years of record are available. The latter method resulted in a higher flood flow, so this is used for design. The proposed bridge is 36.58m (120’) long to clear span the channel. The bridge will be high enough to meet minimum vertical clearance requirements for floods and navigation. The proposed superstructure will be a modular truss bridge design. The bridge abutments will be treated timber cribs, similar to most bridges on forest access roads in Ontario. The design drawings for the project are: Drawing 1 of 2, General Arrangement Drawing, Adamson Consulting, Rev. 1, Oct 18/12 Drawing 2 of 2, Bridge Abutment Construction Drawing, Adamson Consulting, Oct 15/12 Construction Strategy At present, it is proposed to construct the Birch River Bridge in February or March of 2013. This is the open fisheries timing window when the risk to fish is lower. Access for construction will be along the new trail construction route. The bridge abutments will be located back from the water’s edge, therefore no permanent instream excavation or in-stream fill will be necessary. February and March are the months with the lowest flows and water levels during the year. Bridge construction will be carried out by a competent and experienced bridge contractor and Gold Canyon Resources will arrange to monitor construction and do a final inspection to confirm the bridge is built properly. Any significant problems or deviations from the drawings will be brought to the attention of the design engineer for advice. On the bedrock river banks rock excavation will be necessary to achieve satisfactory road grades and to found the crib abutments on level ground. The material removed will provide rock rip rap for erosion protection in bridge and culvert construction. Although the contractor has not been selected yet, in general terms the expected strategy is: 1. Mobilize equipment and materials (incl. timber, steel superstructure, hardware, crib fill, ramp fill and rock rip rap materials) to the site by winter ice road over Springpole Lake from the camp to the outlet of Birch River from the lake. 2. At present, the planned winter ice road would allow access to both sides of Birch River by trails from Springpole Lake. If all goes as planned, it shouldn’t be necessary to ford the river for construction. However, the fall-back plan in case of schedule delay or unseasonably warm weather, would be a one time ford (across and back) by the backhoe to the far shore, as permitted by DFO’s Operational Statement for Clear Span Bridges. Due to the steep approaches, the ford crossing may have to be at Site #1, approximately 200m upstream of the proposed bridge site. 3. At each abutment location, the foundation area will be prepared by bedrock excavation and the crib abutment will be constructed to the bearing level. Birch River Bridge Adamson Consulting Page 2 of 6 Springpole Trail October 21, 2012

Canada flow gauge on the Cat River, below Wesleyan Lake (04GA002). Drainage area at the<br />

bridge site is 1366 km 2 and it is 5390 km 2 at the gauge. Forty-three years of record are available.<br />

The latter method resulted in a higher flood flow, so this is used for design.<br />

The proposed bridge is 36.58m (120’) long to clear span the channel. The bridge will be high<br />

enough to meet minimum vertical clearance requirements for floods and navigation. The proposed<br />

superstructure will be a modular truss bridge design. The bridge abutments will be treated timber<br />

cribs, similar to most bridges on forest access roads in Ontario. The design drawings for the<br />

project are:<br />

Drawing 1 of 2, General Arrangement Drawing, Adamson Consulting, Rev. 1, Oct 18/12<br />

Drawing 2 of 2, Bridge Abutment Construction Drawing, Adamson Consulting, Oct 15/12<br />

Construction Strategy<br />

At present, it is proposed to construct the Birch River Bridge in February or March of 2013. This is<br />

the open fisheries timing window when the risk to fish is lower. Access for construction will be<br />

along the new trail construction route.<br />

The bridge abutments will be located back from the water’s edge, therefore no permanent instream<br />

excavation or in-stream fill will be necessary. February and March are the months with the<br />

lowest flows and water levels during the year.<br />

Bridge construction will be carried out by a competent and experienced bridge contractor and <strong>Gold</strong><br />

<strong>Canyon</strong> Resources will arrange to monitor construction and do a final inspection to confirm the<br />

bridge is built properly. Any significant problems or deviations from the drawings will be brought to<br />

the attention of the design engineer for advice.<br />

On the bedrock river banks rock excavation will be necessary to achieve satisfactory road grades<br />

and to found the crib abutments on level ground. The material removed will provide rock rip rap for<br />

erosion protection in bridge and culvert construction.<br />

Although the contractor has not been selected yet, in general terms the expected strategy is:<br />

1. Mobilize equipment and materials (incl. timber, steel superstructure, hardware, crib fill, ramp fill<br />

and rock rip rap materials) to the site by winter ice road over Springpole Lake from the camp to<br />

the outlet of Birch River from the lake.<br />

2. At present, the planned winter ice road would allow access to both sides of Birch River by trails<br />

from Springpole Lake. If all goes as planned, it shouldn’t be necessary to ford the river for<br />

construction. However, the fall-back plan in case of schedule delay or unseasonably warm<br />

weather, would be a one time ford (across and back) by the backhoe to the far shore, as<br />

permitted by DFO’s Operational Statement for Clear Span Bridges. Due to the steep<br />

approaches, the ford crossing may have to be at Site #1, approximately 200m upstream of the<br />

proposed bridge site.<br />

3. At each abutment location, the foundation area will be prepared by bedrock excavation and the<br />

crib abutment will be constructed to the bearing level.<br />

Birch River Bridge Adamson Consulting Page 2 of 6<br />

Springpole Trail October 21, 2012

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!