3.25<br />
alleviating drainage congestion. The reasons for drainage problems of this system may be<br />
summarized as follows:<br />
• Drainage lockage while High Tide <strong>and</strong> rising of low water level due to rise of river<br />
bed governing the outfall efficiency in an adverse way.<br />
• The old channel section has nearly remained unchanged n spite of big changes<br />
in drainage load.<br />
• Increase of population density resulting in additional loads.<br />
• Huge change in l<strong>and</strong>-use-pattern<br />
• Drastic reduction in spill areas.<br />
The drainage discharge mainly of the following Boroughs is being served by the SWF channel at<br />
present. Part of Borough IV, Part of Borough V, Part of Borough VI, Part of Borough VII, Part of<br />
Borough VIII, Part of Borough X, Part of Borough XI <strong>and</strong> Borough XII. During heavy rainfall,<br />
substantial area under the above Boroughs gets waterlogged <strong>and</strong> duration of inundation lasts for a<br />
long period due to inadequate capacity of the existing drainage system outfalling in SWF channel.<br />
To overcome the severe drainage problem, KEIP has taken up sewage <strong>and</strong> drainage project mainly<br />
for the added areas of Kolkata to address the drainage inadequacies of the area- specially falling<br />
under Borough VII, XI, <strong>and</strong> XII by construction of new pumping stations <strong>and</strong> also by augmentation of<br />
the existing pumping stations. This will result in additional discharge in SWF channel.The 3rd<br />
additional pump house at Chowbhaga <strong>and</strong> the new pumping station at Borough VII will increase the<br />
present drainage load of SWF channel at Chowbhaga point by 25.51 + 70% of 13.00 (since the<br />
discharge of the ail the pumping stations will not synchronize at the same time) = 34.61 m3/sec. The<br />
resulting afflux will surely affect the Full Drainage Level of the upstream channel, too. The Full<br />
Drainage Level (FDL) of crucial Topsia point 'A' will thus be increased from the already strained<br />
inconvenient level during tidal lockage. Due to increase in FDL, more areas will be waterlogged for<br />
longer duration.<br />
The design discharge of SWF channel before reaching additional pump house complex of<br />
Chowbhaga is 46.44 m3/sec. <strong>and</strong> the proposed pumped discharge from Borough VII is about 9.1<br />
m3/sec. The total discharge comes to about 46.44 + 9.1 = 55.54 m3/sec. The peak discharge<br />
capacity of SWF channel required before reaching the proposed 3rd additional pump house outfall at<br />
Chowbhaga is 55.54 + 8.45 + 11.34 + 11.34+ 25.51 m3/sec. = 112.18 m3/sec. (the capacity of the<br />
Old Pump House, if. Additional P.S., 2nd. Additional P.H <strong>and</strong> proposed 3rd.Additional P.M. are 8.45<br />
+ 11.34 + 11.34+ 25.51 m3/sec respectively). The objective of setting up the proposed dumping<br />
stations is to provide relief to its catchment area from water-logging upto the design year 2035. This