7.2<br />
resulted in large scale waterlogging. Water receded slowly, the inadequate drainage capacities of the<br />
channels being one of the main hindrances.<br />
The important locations where waterlogging takes place are shown in the annexed figures. The cross<br />
sections of some of the drainage channels are also shown.<br />
7.2. Past proposals for improvement of drainage of Kolkata<br />
A scheme, titled "Development of Comprehensive Drainage System in Kolkata Metropolitan Areas on<br />
the eastern bank of river Hooghly" was accordingly prepared following the recommendations of a<br />
High Powered Committee under the chairmanship of Dr. P.N. Roy constituted by Govt. of West<br />
Bengal in 1999 following an acute drainage congestion faced during the year. The work is under the<br />
aegeis of Housing Urban Development Corporation (HUDCO) loan assistance procured through<br />
West Bengal Infrastructure Development Finance Corporation (WBIDFC) Ltd. The scheme aims at<br />
better efficiency towards restoring the drainage system in <strong>and</strong> around Kolkata Metropolis <strong>and</strong> its<br />
environs as per original design stipulation <strong>and</strong> to remove the inherent impasse as far as possible.<br />
The scheme includes excavation of DWF, THC - SHC - SWF System, Bagjola Khal, Circular<br />
Beliaghata Khal, Kestopur-Bhangarkata Khal, <strong>and</strong> Pump House at outfall point at Kulti etc.<br />
7.3. Recommendations for further drainage improvement<br />
The following schemes need to be implemented for proper storm water disposal for the city of<br />
Kolkata <strong>and</strong> surrounding urbanised areas like Bidhan Nagar <strong>and</strong> adjacent upcoming new<br />
township of Rajarhat. These schemes have been decided jointly by the Kolkata Municipal<br />
Corporation <strong>and</strong> the Irrigation <strong>and</strong> Waterways Department, Government of West Bengal.<br />
1. Construction of additional pumping station at Maniktala within the existing with a force<br />
main delivery leading to the circular canal. Estimated cost: Rs. 6,00,00,000.<br />
2. Construction of lifting station on the bank of Kestopur canal to remove waterlogging at<br />
Maniktala area. . Estimated cost: Rs. 10,00,00,000.<br />
3. Construction of lifting station on the bank of Beliaghata canal to remove waterlogging<br />
near Eastern metropolitan Bye Pass. . Estimated cost: Rs. 4,00,00,000.<br />
4. Construction of a pumping station at the junction of K K tagore street <strong>and</strong> Str<strong>and</strong> Bank<br />
Road / Jackson Ghat. Estimated cost: Rs. 5,00,00,000.