if required, or if required, or if asked by the Engineer-in-Charge water release test shall be<br />
carried out. The hydraulic test shall be maintained <strong>for</strong> a period of not less than 10 minutes<br />
to reveal any defect in the pipes, joints and anchorages.<br />
If the test is not satisfactory, the fault shall be found and rectified. In case fault cannot be<br />
identified easily, the section under test shall be sub-divided and each part tested separately.<br />
In case the leakage is greater than the allowable value determined through the above <strong>for</strong>mula the contractor<br />
shall identify all defective leaky joints, repair them until the leakage is <strong>with</strong>in allowable limit and these<br />
rectification works no extra payment shall be admissible.<br />
9.0 Cleaning out after Testing:<br />
After the completed pipeline is tested, approved back filling and the Contractor has removed all temporary<br />
work and has reconnected any parts temporarily removed from the pipeline. The contractor shall finally clean<br />
out the whole pipeline and flush it through <strong>with</strong> water.<br />