INDIA: Integrated Coastal Zone Management Project
INDIA: Integrated Coastal Zone Management Project
INDIA: Integrated Coastal Zone Management Project
Create successful ePaper yourself
Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.
<strong>INDIA</strong> <strong>Integrated</strong> <strong>Coastal</strong> <strong>Zone</strong> <strong>Management</strong> <strong>Project</strong> (P007985)<br />
Bhaskarachaya Insitute of Space Application and Geo-Informatics has been excellent. Among the pilot<br />
investments, progress is very good with respect to the sewerage system in Jamnagar city, where one<br />
minor work has been completed; a major work and the project management consultancy has been<br />
awarded. The remaining work related to the sewage treatment plant will be procured once the industry<br />
discussions on the issue of leveraging private sector investment is over and incorporated in bid<br />
documents. About 1,300ha of mangrove had been planted and verified; and community mobilization<br />
work is near complete in 80 villages. For livelihood improvement pilot investments, community<br />
mobilization is nearly completed in 70 villages, and progressing well in the remaining villages; and 42<br />
entry point activities, mostly small civil works, have been completed. However, the works related to the<br />
marine oceanarium and the central research facility of the Gujarat Ecology and Environment Research<br />
Foundation are delayed due to the need to integrate these with the proposed NCMB. The initial work<br />
related to development of appropriate models for coral reef regeneration is delayed, although some<br />
capacity building activities have been implemented. Ecotourism related works in the Marine national Park<br />
has not progressed at all. With respect to project management, the Gujarat SPMU is functioning well,<br />
and its communication cell has undertaken excellent initiatives. The SPMU website is under preparation,<br />
but all information is already hosted in a temporary webpage; an MIS has been prepared; and the<br />
grievance redress processes have all been set up and functioning.<br />
19. Component Three - Piloting ICZM Approaches in Odisha: This component, overall, has also<br />
progressed well, and the current achievements are good. Some consultations and one expert meeting for<br />
preparation of ICZM Plan(s) for the two stretches of Chilika-Gopalpur and Dhamra-Bhitarkanika have<br />
been initiated; but further discussion is dependent on the delineation of coastal sediment cell by the<br />
NCSCM. Given that preparation of such plan(s) will start only in Year 3 of the <strong>Project</strong>, and delineation of<br />
coastal sediment cell will probably be initiated this year by NCSCM, the current lack of full-scale<br />
consultation on the planning process is not yet a major concern. The capacity building activities of the<br />
Chilika Development Authority are progressing well, where substantial recruitment of staff and<br />
procurement of equipment, hardware and software have been completed; and there has been reasonable<br />
progress in the activities by the Odisha State Pollution Control Board. The SPMU has already taken a lot<br />
of initiative on the regional coastal process study, and subject to the outputs from the NCSCM related to<br />
delineation of coastal sediment cells, this activity is likely to be completed on schedule. Among the pilot<br />
investments, progress is very good with respect to the provision of cyclone shelters in the remote coastal<br />
villages by the Odisha State Disaster <strong>Management</strong> Authority, where bidding process for the work of 10<br />
cyclone shelters is nearly complete, and the work is expected to be awarded in August 2011. A small<br />
work and a consultancy have been procured related to the pilot work of shoreline protection at village<br />
Pentha, and the major work is being finalized to be procured as scheduled. Social and environmental<br />
analysis, community mobilization, and soil surveys have been completed for all 14 cyclone shelters. In<br />
most other cases of pilot investment, the planned consulting services, such as for design and supervision<br />
consultancy, had been procured, and the works are expected to be procured during the remainder of<br />
FY11-12. Pilot investments depending on community contracting have also progressed well, although<br />
more intensive work is required to conclude the community contracts, such as for the Wildlife<br />
Department, the Industries Department or the Fisheries Department. With respect to project<br />
management, the Odisha SPMU is functioning well, and its communication cell has undertaken excellent<br />
initiatives. The SPMU website is under preparation, but all information is already hosted in a temporary<br />
webpage; a regular schedule of progress review meetings has been agreed to and is being implemented;<br />
the technical unit is adequately engaged in coordination and monitoring; and the grievance redress<br />
processes have all been set up and functioning.<br />
20. Component Four - Piloting ICZM Approaches in West Bengal: This component, overall, has been<br />
experiencing delays and lack of adequate project management, and the current achievements are less than<br />
expected. A major reason for this was the inability to take decisions before the State Elections and during<br />
7