First Implementation Support Mission, June 2011<br />
Staffing<br />
13. SICOM: A Chartered Accountant has been appointed as the finance manager who heads the accounts and<br />
finance wing at SPMU and is supported by accounts assistant (who is a commerce graduate). NPMU has<br />
hired PFMC from December 2010. In case of SOI dedicated staff for maintaining the Tally accounts has<br />
been appointed.<br />
14. Gujarat: At SPMU, a Chartered Accountant has been appointed as the finance manager who heads the<br />
accounts and finance wing at SPMU. The finance manager is supported by accounts officer (who has<br />
been shifted out to procurement and this post is vacant) and accounts assistant (who is a commerce<br />
graduate). The PEAs have appointed dedicated staff for maintaining the Tally accounts. SPMU is in the<br />
process of finalizing the PFMC contract, which would be completed before 31 July 2011. PFMC would<br />
visit PEAs and ensure that their accounts are maintained timely and correctly. The project has already<br />
imparted one round of training to the PEAs. Similar refresher training needs to be conducted by the<br />
SPMU before 31 August 2011.<br />
15. Odisha: Staffing at SPMU level is adequate, as the State has nominated two staff and has appointed one<br />
Chartered accountant (CA). PFMC has been appointed at the SPMU level that would also visit and ensure<br />
that PEA accounts are maintained timely and correctly. The staffing at the PEA level is a concern as 7<br />
PEAs are yet to appoint/nominate dedicated accounts staff for the project. This action is required to be<br />
completed at the earliest before 30 September 2011. In the interim period, the SPMU with the help of<br />
PFMC staff would ensure that the accounts of PEAs are maintained up to date. In case of some PEAs if<br />
the recruitment process of accountants gets delayed, then SPMU will initiate the process, appoint the staff<br />
for such PEAs and these staff would be paid by the respective PEAs. The mission interacted with all the<br />
PEAs at SPMU office. While majority of the accounts staff were well informed about the project, there<br />
would be requirement for constant training on accounts and Tally for the next six months. The project has<br />
already imparted training in February 2011, which was attended by 15 participants. Similar training needs<br />
to be conducted by the SPMU before 31 August 2011.<br />
16. West Bengal: Staffing at SPMU level is not yet as per the agreed staffing pattern. The State has<br />
nominated one staff and the SPMU has appointed two commerce graduates. The accounts officer who<br />
would be a professional accountant is yet to be appointed and it is expected that the person would be<br />
appointed by 31 July 2011. For PFMC, the consultant has been selected and the contract is expected to be<br />
issued before July 2011 end. The staffing at the PEA level is a concern as 4 PEAs are yet to<br />
appoint/nominate dedicated accounts staff for the project. This action is required to be completed at the<br />
earliest and not later than September 2011. In the interim period, the SPMU with the help of PFMC staff<br />
would ensure that the accounts of PEAs are maintained up to date. In case of some of the PEAs, if the<br />
recruitment process of accountants gets delayed, then the SPMU will initiate the process; appoint the staff<br />
for such PEAs; and these staff would be paid by the respective PEAs. The mission had interaction with<br />
most of the PEAs at SPMU office. While some of the accounts staff was well informed about the project,<br />
there would be requirement for constant training on accounts and Tally for the next six months.<br />
Internal audit<br />
17. SICOM: The internal auditor has been appointed and the contract has been signed for FY11-13 in the<br />
month of March 2011. The auditor has been requested to audit 2010-11 for the project covering both<br />
NPMU and all states. The audit is in progress and the report is expected to be submitted to the World<br />
Bank by end July 2011.<br />
18. Gujarat: The internal auditor has been appointed and the contract has been signed for FY11-13 in the<br />
month of April 2011. The auditor is expected to start the work from July 2011. The first quarter report is<br />