First Implementation Support Mission, June 2011<br />
Activity Current Progress Agreed Next Steps & World Bank Recommendations<br />
[4C-B5]<br />
Distribution of<br />
Grid Electricity<br />
in Sagar Island<br />
by West Bengal<br />
State Electricity<br />
Distribution<br />
Company<br />
Limited<br />
(WBSEDCL)<br />
[4C-C1]<br />
Support to CBO<br />
Coordinated<br />
Livelihood<br />
Improvement<br />
Program at<br />
Sagar Island<br />
(through<br />
SPMU)<br />
[4C-C2]<br />
Support to<br />
Community<br />
6. No progress yet on the issue of certification and/or accreditation to be<br />
able to meet international standards.<br />
1. The WBSEDCL has signed MOU with the SPMU, nominated a senior<br />
officer as the nodal officer for the activities to be undertaken; has<br />
opened the required bank account; delegated technical and financial<br />
powers to the nodal officer; and has installed the financial<br />
management and accounting software.<br />
2. The WBSEDCL has dedicated staff resources available to undertake<br />
and deliver this activity.<br />
3. The work on the transmission line across the 4km wide river is nearing<br />
completion. Purchase order for the sub-station was placed in July<br />
2010, and installation is expected to be completed in August 2011. It is<br />
expected that grid electricity will reach Sagar Island in August 2011.<br />
4. For the distribution system, the required soil testing work has been<br />
completed. Bids have been invited, and it is expected that the award<br />
will be in early September 2011. Albeit a little delayed, this activity is<br />
progressing very well.<br />
1. This activity was originally proposed to be coordinated by the<br />
Sundarban Development Corporation. Looking at the lack of capacity,<br />
and the lack of need to have the Sundarban Development Corporation<br />
to coordinate CBOs, it was recommended by the World Bank that<br />
SPMU is better placed to coordinate this activity. Implementation will<br />
remain to be delivered by a group of CBOs.<br />
2. Consultation meetings have been organized with a few CBOs;<br />
however no actual progress has been made. The CBOs have, in turn,<br />
undertaken several informal consultations in the villages of Sagar<br />
Island.<br />
3. Three prominent CBOs will take lead to prepare a joint action plan.<br />
SPMU will lend support to these CBOs to prepare the action plan.<br />
1. The SAD has not yet signed MOU with the SPMU, nor did they<br />
nominate a senior officer as the nodal officer for the activities to be<br />
undertaken. SAD has not opened the required bank account.<br />
the auction center will not work.<br />
5. EDC shall obtain all clearances that is needed by September 2011.<br />
6. EDC will prepare a plan of actions to achieve the required certification<br />
and accreditation, and share such plan with the World Bank by<br />
October 2011.<br />
1. Nil.<br />
2. Nil.<br />
3. The WBSEDCL is encouraged organize a celebration event at Sagar<br />
Island in August 2011, when grid electricity will reach the Island, and<br />
will connect a few establishment such as hospitals.<br />
4. Nil.<br />
1. SPMU will nominate a staff of the SPMU to lead and coordinate the<br />
activities by the CBOs. If required, the SPMU will recruit or contract<br />
specialists for this work as soon as possible, and not later than by<br />
March 2012.<br />
2. The SPMU will ensure that a clear set of agreements emerge by<br />
September 2011.<br />
3. The SPMU will take all necessary actions (including if required<br />
modification in the choice of CBOs) such that CBO contracts are<br />
signed by SPMU in October 2011, and actual work by the CBOs starts<br />
by November 2011.<br />
1. The SPMU and the SAD should finalize the agreements related to (i)<br />
the project’s required processes, and (ii) the concept of eco-tourism<br />
including that clean-up of the Sagar Mela ground is essential before<br />
any new tourist facilities are added in Sagar. Unless such agreements<br />
52