INDIA: Integrated Coastal Zone Management Project
INDIA: Integrated Coastal Zone Management Project
INDIA: Integrated Coastal Zone Management Project
You also want an ePaper? Increase the reach of your titles
YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.
<strong>INDIA</strong> <strong>Integrated</strong> <strong>Coastal</strong> <strong>Zone</strong> <strong>Management</strong> <strong>Project</strong> (P007985)<br />
First Implementation Support Mission, June 2011<br />
COMPONENT FOUR: PILOTING I.C.Z.M. APPROACHES IN WEST BENGAL<br />
Activity Current Progress Agreed Next Steps & World Bank Recommendations<br />
[4A]<br />
ICZM plan for<br />
West Bengal<br />
[4B-1]<br />
Capacity<br />
building of the<br />
Environment<br />
Department<br />
(West Bengal<br />
SCZMA)<br />
[4B-2]<br />
Capacity<br />
building of<br />
Calcutta<br />
University for<br />
Research on<br />
Microbial<br />
Diversity in the<br />
<strong>Coastal</strong> Areas<br />
[4B-3]<br />
1. The project has initiated a number of communication activities to<br />
gradually build awareness about integrated management plan.<br />
2. The SPMU has a multi-stakeholder state level workshop to create<br />
awareness about objectives of ICZM and the CRZ Notification 2011.<br />
3. The RFP for ICZM Plan is not expected until mid-2011. SPMU is<br />
collecting all information and stakeholder views which should be<br />
useful in formulating the ToR.<br />
4. The SPMU/IESWM has started preparing base map for the entire<br />
coastal zone of the state.<br />
1. No specific progress has been made on the issue of capacity building<br />
of the Forest and Environment Department.<br />
1. Calcutta University has signed MOU with the SPMU, nominated a<br />
professor as the nodal officer for the activities to be undertaken; has<br />
opened the required bank account; delegated technical and financial<br />
powers to the nodal officer; and has installed the financial<br />
management and accounting software.<br />
2. Recruitment of the first batch Research personnel completed.<br />
3. Procurement of the first set of research equipment (through an ICB) is<br />
under progress, and bid evaluation is nearing completion.<br />
4. Microbial samples collected at 2 stations in the Sundarban; analysis of<br />
data and experimentation is progressing well. Research teams have<br />
already published 4 papers in international refereed journals.<br />
1. IESWM is itself housing the SPMU, nominated a senior officer as the<br />
nodal officer for the activities to be undertaken; has opened the<br />
1. Support the Gujarat SPMU to establish forum to coordinate discussion<br />
on the ToR for preparation of ICZM Plan.<br />
2. Nil.<br />
3. By January 2012, a formal process for finalizing ToR for ICZM plan<br />
should start; and all inputs from the progress of preparation of the<br />
regional coastal process study and the proposed shoreline management<br />
plan should be provided by Odisha SPMU.<br />
4. Nil.<br />
1. A<br />
2. SPMU should prepare a brief estimate of the workload related to the<br />
work as the secretariat to the SCZMA, and if required ask to additional<br />
resources, particularly for supporting decision-making by SCZMA and<br />
for dissemination of the SCZMA decisions. Such a plan for additional<br />
resources should be finalized by March 2012; and if required should be<br />
included in the next year’s annual action plan.<br />
3. A detailed proposal for capacity building of the Forest and<br />
Environment Department should be shared with SICOM and World<br />
Bank by December 2011. The SPMU is requested to coordinate with<br />
Odisha SPMU in this regard.<br />
1. Nil.<br />
2. It will be important to expand the scale of laboratory and field work.<br />
For this purpose, additional research scholars may be employed (or<br />
graduate students be involved at a part-time basis).<br />
3. It is important to award the contracts as soon as possible; and<br />
thereafter install the equipment also as soon as possible. Before or at<br />
the time of delivery at laboratories, CU should get qualified experts to<br />
inspect the equipment and ascertain that these equipment meets the<br />
standards and technical specifications in all aspects.<br />
1. Nil.<br />
2. It is important to distinguish between the staff of IESWM and that of<br />
48