First Implementation Support Mission, June 2011<br />
Activity Current Progress Agreed Next Steps & World Bank Recommendations<br />
the MNP<br />
[2D]<br />
<strong>Project</strong><br />
management<br />
1. Nearly all SPMU staff appointed including staff of the operations unit,<br />
communication unit, finance and procurement unit. The State Steering<br />
Committee has met and approved annual action plan.<br />
2. SPMU office was established; office space refurbished and repaired,<br />
the minimum office infrastructure has been created.<br />
3. The <strong>Project</strong> was launched at Dandi in presence of the Union Minister<br />
for Environment and Forests.<br />
4. The Procurement and Financial management cell is now fully<br />
operational– with recruitment of consultants for (i) procurement and<br />
financial management support; (ii) internal audit; (iii) development of<br />
an integrated management information system; and, (iv) preparation of<br />
a dedicated website for SPMU. Financial management reports<br />
(including interim unaudited financial reports) for two quarters, viz.,<br />
September-December 2010 and January-March 2011 has been<br />
submitted and approved by the Bank. Tally accounting software has<br />
been installed and training completed at SPMU and at PEAs. Statutory<br />
audit report for 2010-11 has been prepared and is under review of<br />
SICOM.<br />
5. The Communication Unit has started working full steam. The Cell led<br />
publication of a monthly newsletter (“Sagarika”), 3 such monthly<br />
issues have been published until now. The website for SPMU is under<br />
development, and is expected to run as a full-fledged website by end-<br />
July 2011. Currently, all documents are available in a <strong>Project</strong>-specific<br />
webpage in the GEC website. A toll-free telephone line is operational<br />
to record grievances.<br />
6. All PEAs have opened bank accounts, nominated nodal officers, signed<br />
MoU with SPMU, put in place computerized accounting system;<br />
recruited staff. Additionally, all audit backlog of JMC has been<br />
updated, and the entity audit is now up to date.<br />
7. SPMU has organized several workshops: (i) a two day workshop for<br />
district judges and judges of the High Court on CRZ Notification 2011,<br />
ICZM <strong>Project</strong> and the proposed grievance redress procedures in the<br />
<strong>Project</strong>; (ii) a two day National ICZM workshop, (ii) a three day PRA<br />
training workshop; (iii) an orientation workshop with MNPS; (iv) a<br />
procurement workshop; (v) a communications workshop, and (vi) a<br />
1. The State <strong>Project</strong> Director has recently retired. The Government of<br />
Gujarat is in the process of selection of a new State <strong>Project</strong> Director to<br />
be chosen from among the senior officials of the State. Until such new<br />
State <strong>Project</strong> Director is nominated by the State, the Principal<br />
Secretary, Forest and environment department will act as the State<br />
<strong>Project</strong> Director.<br />
2. Nil.<br />
3. Nil.<br />
4. SPMU will finalize the format for Quarterly Progress report, and the<br />
QPR for the period of April-June 2011 will be submitted using this<br />
finalized format.<br />
5. Nil.<br />
6. Nil.<br />
7. Nil.<br />
8. See Annex 5 for a detailed discussion on State share of Financing.<br />
IMPORTANT: Please note the specific agreements related to the<br />
improvements required in the Procurement and the Financial<br />
<strong>Management</strong> Systems – described in detail in Annex 5 and Annex 6.<br />