<strong>Jern</strong>/Stålproduksjon <strong>av</strong> <strong>DRI</strong> / <strong>HBI</strong> i <strong>Norge</strong><br />

(<strong>The</strong> <strong>IRONMAN</strong> <strong>project</strong> )<br />

Stefan Gustafsson and Ulf Holmqvist<br />

Höganäs AB<br />

2012-11-16


Content<br />

• Steelmaking processes and CO2 emissions<br />

• <strong>DRI</strong> process and created value<br />

• EU market for <strong>DRI</strong> products<br />

• <strong>IRONMAN</strong> <strong>project</strong><br />

• DR plant lay-out<br />

• <strong>DRI</strong> Plant logistics and production numbers<br />

2012-11-16


<strong>DRI</strong>/<strong>HBI</strong> the clean way to make steel<br />

- Decreasing the dependency of coal in EU steelmaking<br />

- Differentiated raw material, contributing to cleaner steel<br />

- Securing expected shortage of steel scrap raw material<br />

2012-11-16<br />

Photo: Statoil


World Steel production<br />

– Approx. raw material balance 2009<br />

150 Mton/y of scrap<br />

2012-11-16


CO 2 emission for new <strong>DRI</strong> production in<br />

<strong>IRONMAN</strong> process<br />

2012-11-16


<strong>DRI</strong>/<strong>HBI</strong> production<br />

–<br />

Maximising the value contribution of natural gas<br />

<strong>The</strong> value created per kg of CO2 is doubled by using<br />

Natural Gas for <strong>DRI</strong>/<strong>HBI</strong> (NOK/kg compared CO2) to El. Power<br />

> 2 NOK/kg CO2<br />

<strong>DRI</strong> process<br />

500 kg CO2/ton<br />

Melting stock for<br />

steel production<br />

(value addition)<br />

1 100 NOK/ton<br />

Natural gas<br />

< 1 NOK/kg CO2<br />

2012-11-16<br />

Gas turbine<br />

400 kg CO2/MWh<br />

Electricity<br />

350 NOK/MWh


<strong>DRI</strong>/<strong>HBI</strong> enhance the EAF scrap charge<br />

▪ It is high Fe (91-94%), high Carbon (1-3%), Pellets (<strong>DRI</strong>) or<br />

Briquettes of <strong>DRI</strong> (<strong>HBI</strong>)<br />

▪ It is a low residual (Cu, Ni, Mo, Cr


Mton<br />

1 800<br />

1 600<br />

1 400<br />

1 200<br />

1 000<br />

Securing raw material supply for<br />

European steel industry<br />

800<br />

600<br />

2013<br />

400<br />

200<br />

0<br />

20 year gap<br />

1970 1975 1980 1985 1990 1995 2000 2005 2010 2015 2020<br />

Steel production<br />

Scrap <strong>av</strong>ailability<br />

2012-11-16


Potential EU customers<br />

Country No. of Steel producers Mton/year<br />

Spain 8 6,7<br />

Germany 10 10,0<br />

UK 2 4,0<br />

France 6 5,3<br />

BeNeLux 4 4,5<br />

Italy 10 6,7<br />

Poland 2 3,2<br />

Scandin<strong>av</strong>ia 4 2,7<br />

Total approx. 46 43,1<br />

25% <strong>DRI</strong>/<strong>HBI</strong> market > 10 Mt/yr<br />

2012-11-16


Norwegian coast is close to the market<br />

Freight cost for the customers will be 10-20 % lower<br />

compared with imported <strong>DRI</strong>/<strong>HBI</strong><br />

2012-11-16 | 10


Basic facts – <strong>The</strong> <strong>IRONMAN</strong> <strong>project</strong><br />

• A joint <strong>project</strong> between Höganäs, LKAB and Statoil<br />

• Unique mix of competences creates unique product<br />

• Evaluating a plant for <strong>DRI</strong>/<strong>HBI</strong> production at Statoils<br />

existing site at Tjeldbergodden in Norway<br />

• Höganäs initiator of the <strong>project</strong> and buyer of produced<br />

<strong>DRI</strong>/<strong>HBI</strong><br />

• Höganäs and LKAB main sales channels to be used<br />

• <strong>The</strong> pre-planning <strong>project</strong>, DG 2, was finished in Nov 2010<br />

2012-11-16 | 11


<strong>IRONMAN</strong> utilizing existing technology and<br />

infrastructure<br />

Transportation<br />

Photo: LKAB<br />

Photo: LKAB<br />

2012-11-16


...just adding know how<br />

...how to produce it<br />

environmentally<br />

…how to use it<br />

and market it<br />

2012-11-16


A Nordic Combination...<br />

Photo: Svein Harald Ledaal/ Statoil<br />

Photo: LKAB<br />

...that can’t be found any where else in Europe<br />

2012-11-16


Captured CO 2 for long term storage<br />

Discussions are held with Gassnova /Gassco regarding<br />

storage solutions for captured gas<br />

2012-11-16


2012-11-16<br />

Lay-out of <strong>IRONMAN</strong> 1.6 Mton/yr Natural Gas based<br />

<strong>DRI</strong>/<strong>HBI</strong> plant


Typical numbers of a 1.6 Mt/yr <strong>DRI</strong>/<strong>HBI</strong> module<br />

• <strong>DRI</strong>/<strong>HBI</strong> products 200 t/hr 1.6 Mt/yr<br />

• Iron Ore pellets 1.4 ton/t <strong>DRI</strong> 2.3 Mt/yr<br />

• Natural Gas 260 Nm3/t <strong>DRI</strong> 420 MNm3/yr<br />

• Oxygen 60 Nm3/t <strong>DRI</strong> 95 MNm3/yr<br />

• Nitrogen 70 Nm3/t <strong>DRI</strong> 112 MNm3/yr<br />

• Electric energy 140 kWh/t <strong>DRI</strong> 225 GWh/ yr<br />

200 t <strong>DRI</strong>/h 28 MW<br />

2012-11-16


Logistic advantages<br />

• Close to Iron Ore pellets transport facilities<br />

• Close to transport facilities for <strong>DRI</strong> products<br />

(30% less in weight compared to Iron Ore)<br />

• Stable Natural Gas supply<br />

• Access to gases like Oxygen and Nitrogen<br />

• Good access to Cooling water<br />

• Possibilities to use potable water, electricity…..<br />

• Good roads to the site for plant errection, spare parts and<br />

consumables supply<br />

2012-11-16