FINAL SAMPLING AND ANALYSIS PLAN - Documents for Moffett Field
FINAL SAMPLING AND ANALYSIS PLAN - Documents for Moffett Field
FINAL SAMPLING AND ANALYSIS PLAN - Documents for Moffett Field
You also want an ePaper? Increase the reach of your titles
YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.
<strong>FINAL</strong><br />
<strong>SAMPLING</strong> <strong>AND</strong> <strong>ANALYSIS</strong> <strong>PLAN</strong><br />
(FIELD <strong>SAMPLING</strong> <strong>AND</strong> QUALITY ASSURANCE PROJECT <strong>PLAN</strong>) FOR<br />
NON-TIME-CRITICAL REMOVAL ACTION FOR PCB CONTAMINATION<br />
AT INSTALLATION RESTORATION SITE 29, HANGAR 1<br />
Former Naval Air Station <strong>Moffett</strong> <strong>Field</strong>,<br />
<strong>Moffett</strong> <strong>Field</strong>, Cali<strong>for</strong>nia<br />
PERMAC Contract Number N62473-08-D-8816<br />
Contract Task Order 0005<br />
Document Control Number AMEC-8816-0005-0039<br />
April 2010<br />
Submitted to:<br />
U.S. Department of the Navy<br />
Base Realignment and Closure<br />
Program Management Office West<br />
1455 Frazee Road, Suite 900<br />
San Diego, Cali<strong>for</strong>nia 92108-4310<br />
Submitted by:<br />
AMEC Earth & Environmental, Inc.<br />
9210 Sky Park Court, Suite 200<br />
San Diego, Cali<strong>for</strong>nia 92123<br />
(858) 300-4300
This page left intentionally blank.
EXECUTIVE SUMMARY<br />
AMEC Earth & Environmental, Inc., (AMEC) has been contracted by Naval Facilities<br />
Engineering Command Southwest (NAVFAC SW) under Contract Task Order (CTO) 0005<br />
to manage and per<strong>for</strong>m the removal action <strong>for</strong> Hangar 1 at Former Naval Air Station <strong>Moffett</strong><br />
<strong>Field</strong> (<strong>Moffett</strong> <strong>Field</strong>), located in <strong>Moffett</strong> <strong>Field</strong>, Cali<strong>for</strong>nia. This document presents the<br />
Sampling and Analysis Plan (<strong>Field</strong> Sampling Plan and Quality Assurance Project Plan;<br />
hereafter referred to as the SAP) <strong>for</strong> the Hangar 1 removal action and was prepared in<br />
concurrence with the Draft Non-Time-Critical Removal Action Work Plan (Work Plan).<br />
This SAP meets the updated Uni<strong>for</strong>m Federal Policy <strong>for</strong> Quality Assurance Project Plans<br />
(UFP-QAPP) (U.S. Environmental Protection Agency [EPA] 2005) and EPA Guidance <strong>for</strong><br />
Quality Assurance Project Plans, EPA Quality Assurance (QA)/G-5, Quality Assurance<br />
Manual (QAM) (U.S. EPA 2002) requirements.<br />
<strong>Moffett</strong> Hangar 1 was constructed in 1932 to house airships as part of the Navy’s Lighterthan-Air<br />
program. Construction materials used included Robertson Protected Metal siding,<br />
now known to contain polychlorinated biphenyls (PCBs) and asbestos. Hangar 1 was coated<br />
with a lead-based paint that contains PCBs. PCBs are a probable human carcinogen and<br />
ecological contaminant that bioaccumulates in the environment. Hangar 1 was also used <strong>for</strong><br />
aircraft maintenance, training facilities, and office space. Control of property management<br />
of Hangar 1 was transferred to National Aeronautics and Space Administration (NASA)<br />
under the Base Realignment and Closure (BRAC) program in 1994. During this time, the<br />
facility was used <strong>for</strong> air shows, open houses, a field museum, and various other public and<br />
commercial activities. In 1997, routine cleaning and sampling activities of a settling basin<br />
located approximately 2,000 feet northwest of Hangar 1 indicated the presence of a<br />
relatively uncommon PCB, Aroclor 1268. Hangar 1 was suspected as the source of the PCBs<br />
in the sediment samples. Subsequent investigations included sampling of the Hangar 1<br />
exterior construction materials, the interior paint, and ambient air outside and inside Hangar<br />
1, as well as stormwater and stormwater sediment. Data gathered from the investigations<br />
confirmed Hangar 1 as the PCB source.<br />
In July 2003, the Regional Water Quality Control Board (Water Board) was notified by<br />
NASA of the presence of Aroclor 1260 and Aroclor 1268 in the stormwater collection<br />
trench. Due to health and safety concerns, Hangar 1 was closed in 2003 to all access except<br />
<strong>for</strong> essential maintenance, abatement, or environmental cleanup. In September of 2003<br />
NASA conducted a Time-Critical Removal Action (TCRA) which involved cleaning out and<br />
characterizing sediment residue in the stormwater collection trench surrounding Hangar 1.<br />
In October of 2003 the Navy conducted a TCRA which involved pressure washing the<br />
exterior surface and the surrounding area of the hangar, coating the corrugated siding with<br />
an asphalt emulsion, and installing a security fence.<br />
Final Sampling and Analysis Plan<br />
Installation Restoration Site 29, Hangar 1<br />
Former Naval Air Station, <strong>Moffett</strong> <strong>Field</strong>, <strong>Moffett</strong> <strong>Field</strong>, Cali<strong>for</strong>nia<br />
DCN: AMEC-8816-0005-0039<br />
April 2010<br />
Page i
The Engineering Evaluation/Cost Analysis (EE/CA), finalized in July 2008, identified PCBs<br />
as the chemicals of concern and stated that the release of the PCBs needed to be controlled.<br />
In December 2008, the Action Memorandum <strong>for</strong> the Non-Time-Critical Removal Action<br />
(NTCRA) <strong>for</strong> the PCB Contamination at Hangar 1 was completed. The Action<br />
Memorandum selected Alternative 10, the removal of the Hangar 1 siding and application of<br />
a coating to the exposed surfaces, as the preferred removal action. Although PCBs are the<br />
regulatory driver <strong>for</strong> this NTCRA, the presence of lead and asbestos in the exterior and<br />
interior building materials of Hangar 1 will require abatement and disposal compliance, as<br />
well as additional health and safety precautions.<br />
To verify that the removal is executed without the release of PCBs into the environment as a<br />
result of the removal action, soil and sediment samples will be collected to establish baseline<br />
concentrations of PCBs, lead, and asbestos. Baseline/pre-construction samples will be<br />
collected from the soil areas immediately adjacent to Hangar 1 and from any sediment that<br />
may be present in the stormwater trench/conveyance system. The baseline/pre-construction<br />
soil samples will also indicate if soil excavation will be necessary to remove soil where the<br />
PCB concentrations exceed project action limits of 1000 micrograms per kilogram (µg/kg).<br />
Following the removal activities, samples will be collected from the previously sampled soil<br />
areas adjacent to Hangar 1 and from locations on the interior concrete floor of Hangar 1.<br />
Soil samples will be analyzed <strong>for</strong> PCBs, lead, and asbestos. Post-construction confirmation<br />
soil sample concentrations will be compared with the baseline/pre-construction soil sample<br />
concentrations to verify that contaminants were not released into the environment as a result<br />
of the removal action, and to ensure PCBs are below 1000 µg/kg. Concrete wipe samples<br />
will be collected from the interior concrete floor and analyzed <strong>for</strong> PCBs and lead to confirm<br />
that concentrations are below the regulatory limits. Sediment will be removed (washed)<br />
from the stormwater trench/conveyance system as part of the removal action, there<strong>for</strong>e; it is<br />
anticipated that there will not be sediment to sample during the confirmation sampling<br />
event.<br />
Waste streams generated during the removal action will be characterized and sent to the<br />
proper disposal facility. Spent water generated and collected during the removal action will<br />
be treated on site. Pending analytical results and verification that analytical results are below<br />
discharge criteria, the treated spent wash water will be discharged to the Sunnyvale Publicly<br />
Owned Treatment Works (POTW) via the NASA/Ames Sanitary Sewer system.<br />
Final Sampling and Analysis Plan<br />
Installation Restoration Site 29, Hangar 1<br />
Former Naval Air Station, <strong>Moffett</strong> <strong>Field</strong>, <strong>Moffett</strong> <strong>Field</strong>, Cali<strong>for</strong>nia<br />
DCN: AMEC-8816-0005-0039<br />
April 2010<br />
Page ii
All laboratories will be evaluated by the Naval Facilities Engineering Services Center<br />
(NFESC) or will hold the Department of Defense (DoD) Environmental Laboratory<br />
Accreditation Program (ELAP) certification, and the Cali<strong>for</strong>nia Department of Public Health<br />
ELAP certification (<strong>for</strong> methods certified by Cali<strong>for</strong>nia). For removal actions at installation<br />
restoration (IR) sites, data will be validated at 80 percent (%) Level III and 20% Level IV as<br />
described in the NAVFAC SW Environmental Work Instruction #1 (SWDIV 2001) by a<br />
third party <strong>for</strong> all samples except Investigation-Derived (IDW), air quality monitoring, and<br />
process sampling. AMEC chemists will evaluate the data against Data Quality Objectives<br />
(DQOs) specified in this SAP.<br />
This SAP consists of 37 worksheets organized according to the Uni<strong>for</strong>m Federal Policy <strong>for</strong><br />
Quality Assurance Project Plans (UFP-QAPP) (EPA 2005). The UFP-QAPP is the resulting<br />
product of the Intergovernmental Data Quality Task Force (IDQTF). It is the companion to<br />
the Uni<strong>for</strong>m Federal Policy <strong>for</strong> Implementing Environmental Quality Systems (UFP-QS).<br />
The UFP-QS was developed to consistently implement the quality system requirements of<br />
(American National Standards Institute/American Society <strong>for</strong> Quality) ANSI/ASQ E4-2004<br />
Quality Systems <strong>for</strong> Environmental Data and Technology Programs (ANSI 2004). A list of<br />
the worksheets is provided in the Table of Contents.<br />
Final Sampling and Analysis Plan<br />
Installation Restoration Site 29, Hangar 1<br />
Former Naval Air Station, <strong>Moffett</strong> <strong>Field</strong>, <strong>Moffett</strong> <strong>Field</strong>, Cali<strong>for</strong>nia<br />
DCN: AMEC-8816-0005-0039<br />
April 2010<br />
Page iii
This page left intentionally blank.<br />
Final Sampling and Analysis Plan<br />
Installation Restoration Site 29, Hangar 1<br />
Former Naval Air Station, <strong>Moffett</strong> <strong>Field</strong>, <strong>Moffett</strong> <strong>Field</strong>, Cali<strong>for</strong>nia<br />
DCN: AMEC-8816-0005-0039<br />
April 2010<br />
Page iv
TABLE OF CONTENTS<br />
Page<br />
WORKSHEET #1: TITLE <strong>AND</strong> APPROVAL PAGE ............................................................. 1<br />
WORKSHEET #2: SAP IDENTIFYING INFORMATION ................................................ 2-1<br />
WORKSHEET #3: DISTRIBUTION LIST ........................................................................... 3-1<br />
WORKSHEET #4: PROJECT PERSONNEL SIGN-OFF SHEET .................................... 4-1<br />
WORKSHEET #5: PROJECT ORGANIZATIONAL CHART .......................................... 5-1<br />
WORKSHEET #6: COMMUNICATION PATHWAYS ..................................................... 6-1<br />
WORKSHEET #7: PERSONNEL RESPONSIBILITIES <strong>AND</strong> QUALIFICATIONS .... 7-1<br />
WORKSHEET #8: SPECIAL PERSONNEL TRAINING REQUIREMENTS ............... 8-1<br />
WORKSHEET #9: PROJECT SCOPING SESSION PARTICIPANTS SHEET ............. 9-1<br />
WORKSHEET #10: PROBLEM DEFINITION .................................................................... 10-1<br />
WORKSHEET #11: PROJECT QUALITY OBJECTIVES/SYSTEMATIC <strong>PLAN</strong>NING<br />
PROCESS STATEMENTS .................................................................. 11-1<br />
11.1 Introduction and Problem Statements ................................. 11-1<br />
11.2 DQOs <strong>for</strong> Removal Action <strong>for</strong> Hangar 1 ............................ 11-1<br />
WORKSHEET #12: MEASUREMENT PERFORMANCE CRITERIA TABLES ......... 12-1<br />
WORKSHEET #13: SECONDARY DATA CRITERIA <strong>AND</strong> LIMITATIONS .............. 13-1<br />
WORKSHEET #14: SUMMARY OF PROJECT TASKS ................................................... 14-1<br />
14.1 Site Preparation, Sampling, and Analysis Tasks .................. 14-1<br />
14.2 Sampling Procedures ................................................................ 14-3<br />
14.2.1 Pre-construction/Baseline Soil Sampling<br />
Procedure ................................................................... 14-3<br />
14.2.2 Pre-construction/Baseline Sediment Sampling<br />
Procedure ................................................................... 14-4<br />
14.2.3 Confirmation Soil Sampling Procedure ..................... 14-4<br />
14.2.4 Wipe Sampling Procedure.......................................... 14-5<br />
14.2.5 Import Soil Sampling Procedure ................................ 14-6<br />
14.3 Analytical Tasks ........................................................................ 14-6<br />
14.4 Quality Control Tasks .............................................................. 14-6<br />
14.5 <strong>Field</strong> Documentation and Data Correcting Tasks ................. 14-7<br />
14.6 Computerized and Manual Data Management Tasks <strong>for</strong><br />
Analysis, Reporting, Storage and Archiving ......................... 14-7<br />
14.7 Data Tracking, Storage, Archiving, Retrieval, and<br />
Security ....................................................................................... 14-8<br />
14.7.1 Electronic Data: ........................................................ 14-8<br />
14.7.2 Documentation and Records: .................................. 14-8<br />
14.7.3 Assessment/Audit Tasks: ......................................... 14-8<br />
14.7.4 Laboratory Analytical Data Review Tasks: .......... 14-9<br />
14.7.5 Laboratory Analytical Data: .................................. 14-10<br />
14.7.6 Independent Data Validation: ............................... 14-13<br />
14.7.7 Data Usability Assessment: ................................... 14-14<br />
Final Sampling and Analysis Plan<br />
Installation Restoration Site 29, Hangar 1<br />
Former Naval Air Station, <strong>Moffett</strong> <strong>Field</strong>, <strong>Moffett</strong> <strong>Field</strong>, Cali<strong>for</strong>nia<br />
DCN: AMEC-8816-0005-0039<br />
April 2010<br />
Page v
TABLE OF CONTENTS (Cont.)<br />
Page<br />
WORKSHEET #15: REFERENCE LIMITS <strong>AND</strong> EVALUATION TABLE ................... 15-1<br />
WORKSHEET #16: PROJECT SCHEDULE ........................................................................ 16-1<br />
WORKSHEET #17: <strong>SAMPLING</strong> DESIGN <strong>AND</strong> RATIONALE ...................................... 17-1<br />
WORKSHEET #18: <strong>SAMPLING</strong> LOCATIONS <strong>AND</strong> METHODS/SOP<br />
REQUIREMENTS TABLE ................................................................. 18-1<br />
WORKSHEET #19: ANALYTICAL SOP REQUIREMENTS TABLE ........................... 19-1<br />
WORKSHEET #20: FIELD QUALITY CONTROL SAMPLE SUMMARY .................. 20-1<br />
WORKSHEET #21: PROJECT <strong>SAMPLING</strong> SOP REFERENCES TABLE .................... 21-1<br />
WORKSHEET #22: FIELD EQUIPMENT CALIBRATION, MAINTENANCE,<br />
TESTING, <strong>AND</strong> INSPECTION TABLE ........................................... 22-1<br />
WORKSHEET #23: ANALYTICAL SOP REFERENCES TABLE .................................. 23-1<br />
WORKSHEET #24: ANALYTICAL INSTRUMENT CALIBRATION TABLE ........... 24-1<br />
WORKSHEET #25: ANALYTICAL INSTRUMENT <strong>AND</strong> EQUIPMENT<br />
MAINTENANCE, TESTING, <strong>AND</strong> INSPECTION TABLE ......... 25-1<br />
WORKSHEET #26: SAMPLE H<strong>AND</strong>LING SYSTEM ....................................................... 26-1<br />
WORKSHEET #27: SAMPLE CUSTODY REQUIREMENTS ......................................... 27-1<br />
27.1 Sample Name Assignment ....................................................... 27-1<br />
27.2 <strong>Field</strong> Sample Collection ........................................................... 27-1<br />
27.3 <strong>Field</strong> Sample Container Custody ............................................ 27-1<br />
27.4 <strong>Field</strong> Sample Identification Procedures ................................. 27-1<br />
27.5 Chain-of-Custody Forms ......................................................... 27-2<br />
27.6 <strong>Field</strong> Sample Packaging ........................................................... 27-2<br />
27.7 Laboratory Sample Custody Procedures ................................ 27-2<br />
27.8 <strong>Field</strong> Sample Custody, Shipment, and Laboratory<br />
Receipt ........................................................................................ 27-3<br />
WORKSHEET #28: LABORATORY QC SAMPLES TABLE.......................................... 28-1<br />
WORKSHEET #29: PROJECT DOCUMENTS <strong>AND</strong> RECORDS TABLE ..................... 29-1<br />
WORKSHEET #30: ANALYTICAL SERVICES TABLE ................................................. 30-1<br />
WORKSHEET #31: <strong>PLAN</strong>NED PROJECT ASSESSMENTS TABLE ............................ 31-1<br />
WORKSHEET #32: ASSESSMENT FINDINGS <strong>AND</strong> CORRECTIVE ACTION<br />
RESPONSES .......................................................................................... 32-1<br />
WORKSHEET #33: QUALITY ASSURANCE MANAGEMENT REPORTS ............... 33-1<br />
WORKSHEET #34: VERIFICATION (STEP 1) PROCESS TABLE ............................... 34-1<br />
WORKSHEET #35: VALIDATION (STEPS IIA <strong>AND</strong> IIB) PROCESS TABLE ........... 35-1<br />
WORKSHEET #36: ANALYTICAL DATA VALIDATION (STEPS IIA <strong>AND</strong> IIB)<br />
SUMMARY TABLE............................................................................. 36-1<br />
WORKSHEET #37: USABILITY ASSESSMENT ......................................................... 37-1<br />
Final Sampling and Analysis Plan<br />
Installation Restoration Site 29, Hangar 1<br />
Former Naval Air Station, <strong>Moffett</strong> <strong>Field</strong>, <strong>Moffett</strong> <strong>Field</strong>, Cali<strong>for</strong>nia<br />
DCN: AMEC-8816-0005-0039<br />
April 2010<br />
Page vi
TABLE OF CONTENTS (Cont.)<br />
Page<br />
LIST OF TABLES<br />
Table 3-1. Document Distribution List ..................................................................................... 3-1<br />
Table 4-1. Project Personnel Sign-off Sheet ............................................................................. 4-1<br />
Table 6-1. Communication Matrix ............................................................................................ 6-1<br />
Table 7-1. Key Personnel Project Responsibilities ................................................................... 7-1<br />
Table 11-1. Data Quality Objectives Summary Pre-Construction and Confirmation<br />
Sampling ................................................................................................................ 11-1<br />
Table 11-2. Data Quality Objectives Summary Treated Water Sampling ................................ 11-4<br />
Table 12-1. Concrete Wipe ....................................................................................................... 12-1<br />
Table 12-2. Soil ......................................................................................................................... 12-1<br />
Table 12-3. Sediment ................................................................................................................ 12-2<br />
Table 15-1. Reference Limits and Evaluation <strong>for</strong> PCBs in Pre-construction Samples ............. 15-1<br />
Table 15-2. Reference Limits and Evaluation <strong>for</strong> PCB in Wipe Samples ................................ 15-2<br />
Table 15-3. Reference Limits and Evaluation <strong>for</strong> PCBs in Treated Water Samples ................ 15-3<br />
Table 15-4. Reference Limits and Evaluation <strong>for</strong> Metals in Import Soil .................................. 15-4<br />
Table 15-5. Reference Limits and Evaluation <strong>for</strong> PAHs in Import Soil ................................... 15-6<br />
Table 15-6. Reference Limits and Evaluation <strong>for</strong> Semi-volatile Organics in Import<br />
Soil ......................................................................................................................... 15-7<br />
Table 15-7. Reference Limits and Evaluation <strong>for</strong> TPHs in Import Soil ................................... 15-9<br />
Table 15-8. Reference Limits and Evaluation <strong>for</strong> Lead in Wipe Samples ................................ 15-9<br />
Table 15-9. Reference Limits and Evaluation <strong>for</strong> pH in Treated Water ................................. 15-10<br />
Table 15-10. Reference Limits and Evaluation <strong>for</strong> Asbestos in Soil/Sediment Samples ......... 15-10<br />
Table 15-11. Reference Limits and Evaluation <strong>for</strong> Metals in Treated Water Samples ............. 15-10<br />
Table 19-1. Analytical SOP Requirements ............................................................................... 19-1<br />
Table 20-1. <strong>Field</strong> Quality Control Sample Summary ............................................................... 20-1<br />
Table 21-1. Project Sampling SOP References ......................................................................... 21-1<br />
Table 22-1. <strong>Field</strong> Equipment Calibration, Maintenance, Testing, and Inspection .................... 22-1<br />
Table 23-1. Analytical SOP Reference Table ........................................................................... 23-1<br />
Table 24-1. Analytical Instrument Calibration ......................................................................... 24-1<br />
Table 25-1. Analytical Instrument and Equipment Maintenance, Testing, and<br />
Inspection............................................................................................................... 25-1<br />
Table 28-1. Laboratory Quality Control Samples – Soil/EPA Method 8082 ........................... 28-1<br />
Table 28-2. Laboratory Quality Control Samples – Wipe/EPA Method 8082 ......................... 28-2<br />
Table 28-3. Laboratory Quality Control Samples – Water/EPA Method 6010B ..................... 28-3<br />
Table 28-4. Laboratory Quality Control Samples – Wipe/Soil/ EPA Method 6010B .............. 28-4<br />
Table 29-1. Project <strong>Documents</strong> and Records ............................................................................ 29-1<br />
Table 30-1. Analytical Services Matrix .................................................................................... 30-1<br />
Table 31-1. Planned Project Assessments Matrix ..................................................................... 31-1<br />
Table 32-1. Assessment Findings and Corrective Action Response ......................................... 32-1<br />
Final Sampling and Analysis Plan<br />
Installation Restoration Site 29, Hangar 1<br />
Former Naval Air Station, <strong>Moffett</strong> <strong>Field</strong>, <strong>Moffett</strong> <strong>Field</strong>, Cali<strong>for</strong>nia<br />
DCN: AMEC-8816-0005-0039<br />
April 2010<br />
Page vii
TABLE OF CONTENTS (Cont.)<br />
Page<br />
LIST OF TABLES (Cont.)<br />
Table 33-1. Quality Assurance Management Reports .............................................................. 33-1<br />
Table 34-1. Verification Process ............................................................................................... 34-1<br />
Table 35-1. Validation Process ................................................................................................. 35-1<br />
Table 36-1. Analytical Data Validation Summary .................................................................... 36-2<br />
Table 37-1. Usability Assessment Activities ............................................................................ 37-2<br />
LIST OF FIGURES<br />
Figure 11-1. Soil Sample Location Map .................................................................................... 11-5<br />
Figure 11-2. Wipe Sample Location Map .................................................................................. 11-7<br />
Figure 17-1. Decision Tree <strong>for</strong> Soil Samples ............................................................................. 17-4<br />
Figure 17-2. Decision Tree <strong>for</strong> Sediment Samples .................................................................... 17-5<br />
LIST OF APPENDICES<br />
APPENDIX A<br />
APPENDIX B<br />
APPENDIX C<br />
AMEC ST<strong>AND</strong>ARD OPERATING PROCEDURES<br />
FIELD FORMS<br />
RESPONSES TO COMMENTS<br />
Final Sampling and Analysis Plan<br />
Installation Restoration Site 29, Hangar 1<br />
Former Naval Air Station, <strong>Moffett</strong> <strong>Field</strong>, <strong>Moffett</strong> <strong>Field</strong>, Cali<strong>for</strong>nia<br />
DCN: AMEC-8816-0005-0039<br />
April 2010<br />
Page viii
ACRONYMS <strong>AND</strong> ABBREVIATIONS<br />
% percent<br />
µg/ft 2<br />
micrograms per square foot<br />
µg/kg<br />
micrograms per kilogram<br />
AMEC<br />
APP<br />
BC Labs<br />
BHAP<br />
BMP<br />
BRAC<br />
Cali<strong>for</strong>nia EPA<br />
CARB<br />
CAS<br />
CCAL<br />
CCB<br />
CCR<br />
CCV<br />
CERCLA<br />
CFR<br />
CLP<br />
cm 2<br />
COD<br />
CTO<br />
DCC<br />
DoD<br />
DoN<br />
DQI<br />
DQO<br />
DTSC<br />
EDD<br />
EE/CA<br />
ELAP<br />
EPA<br />
EWI<br />
ft 2<br />
FAA<br />
AMEC Earth & Environmental, Inc.<br />
Accident Prevention Plan<br />
BC Laboratories, Inc.<br />
Biological Hazards Abatement Plan<br />
Best Management Practice<br />
Base Realignment and Closure<br />
Cali<strong>for</strong>nia Environmental Protection Agency<br />
Cali<strong>for</strong>nia Air Resource Board<br />
Chemical Abstract Service<br />
continuing calibration<br />
continuing calibration blank<br />
Cali<strong>for</strong>nia Code of Regulations<br />
continuing calibration verification<br />
Comprehensive Environmental Response, Compensation, and Liability Act<br />
Code of Federal Regulations<br />
Contract Laboratory Program<br />
square centimeter<br />
coefficient of determination<br />
Contract Task Order<br />
daily calibration check<br />
Department of Defense<br />
Department of Navy<br />
data quality indicator<br />
data quality objective<br />
Department of Toxic Substances Control<br />
electronic data deliverable<br />
Engineering Evaluation/Cost Analysis<br />
Environmental Laboratory Accreditation Program<br />
United States Environmental Protection Agency<br />
Environmental Work Instruction<br />
Square feet<br />
Federal Aviation Administration<br />
Final Sampling and Analysis Plan<br />
Installation Restoration Site 29, Hangar 1<br />
Former Naval Air Station, <strong>Moffett</strong> <strong>Field</strong>, <strong>Moffett</strong> <strong>Field</strong>, Cali<strong>for</strong>nia<br />
DCN: AMEC-8816-0005-0039<br />
April 2010<br />
Page ix
ACRONYMS <strong>AND</strong> ABBREVIATIONS (Cont.)<br />
GC<br />
GPS<br />
ICAL<br />
ICB<br />
ICP<br />
ICS<br />
ICV<br />
ID<br />
IDL<br />
IDW<br />
IR<br />
LCS<br />
LIMS<br />
mg/kg<br />
<strong>Moffett</strong><br />
MPC<br />
MS/MSD<br />
NA<br />
NAS<br />
NASA<br />
NAVFAC SW<br />
Navy<br />
NCR<br />
NEDD<br />
NFESC<br />
NIRIS<br />
NTCRA<br />
PAH<br />
PAL<br />
PCB<br />
PERMAC<br />
POTW<br />
PQO<br />
PT<br />
QA<br />
QAO<br />
QC<br />
gas chromatography<br />
global positioning system<br />
initial calibration<br />
initial calibration blank<br />
Inductively Coupled Plasma<br />
interference check solution<br />
initial calibration verification<br />
identification<br />
instrument detection limit<br />
investigation-derived wastes<br />
Installation Restoration<br />
laboratory control sample<br />
laboratory in<strong>for</strong>mation management system<br />
milligrams per kilogram<br />
Former Naval Air Station <strong>Moffett</strong> <strong>Field</strong><br />
measurement per<strong>for</strong>mance criteria<br />
matrix spike/matrix spike duplicate<br />
not applicable<br />
Naval Air Station<br />
National Aeronautics and Space Administration<br />
Naval Facilities Engineering Command Southwest (<strong>for</strong>merly SWDIV)<br />
U.S. Department of the Navy<br />
non-con<strong>for</strong>mance report<br />
Naval Electronic Data Deliverable<br />
Naval Facilities Engineering Services Center<br />
Naval Installation Restoration In<strong>for</strong>mation Solution<br />
Non-Time-Critical Removal Action<br />
polyaromatic hydrocarbon<br />
project action limit<br />
Polychlorinated Biphenyl<br />
Per<strong>for</strong>mance-Based Environmental Multiple Award Contract<br />
Publicly Owned Treatment Works<br />
project quality objective<br />
proficiency testing<br />
quality assurance<br />
Quality Assurance Officer<br />
quality control<br />
Final Sampling and Analysis Plan<br />
Installation Restoration Site 29, Hangar 1<br />
Former Naval Air Station, <strong>Moffett</strong> <strong>Field</strong>, <strong>Moffett</strong> <strong>Field</strong>, Cali<strong>for</strong>nia<br />
DCN: AMEC-8816-0005-0039<br />
April 2010<br />
Page x
ACRONYMS <strong>AND</strong> ABBREVIATIONS (Cont.)<br />
QCM<br />
QL<br />
QSM<br />
ROICC<br />
RPD<br />
RPM<br />
RSD<br />
RSL<br />
RT<br />
Water Board<br />
SAP<br />
SDG<br />
SHSP<br />
SOP<br />
SQL<br />
SVOC<br />
SWPPP<br />
TBD<br />
TCRA<br />
TPH<br />
TSA<br />
TSCA<br />
UFP-QAPP<br />
Work Plan<br />
yd 3<br />
Quality Control Manager<br />
quantitation limit<br />
Quality System Manual<br />
Resident Officer in Charge of Construction<br />
relative percent difference<br />
Remedial Project Manager<br />
relative standard deviation<br />
Regional Screening Levels<br />
retention time<br />
San Francisco Bay Regional Water Quality Control Board<br />
Sampling and Analysis Plan<br />
sample delivery group<br />
Site Health and Safety Plan<br />
standard operating procedure<br />
structured query language<br />
semi-volatile organic compound<br />
Storm Water Pollution Prevention Plan<br />
to be determined<br />
Time-Critical Removal Action<br />
total petroleum hydrocarbon<br />
technical systems audit<br />
Toxic Substance Control Act<br />
Uni<strong>for</strong>m Federal Policies <strong>for</strong> Quality Assurance Project Plan<br />
Non-Time-Critical Removal Action Work Plan<br />
cubic yards<br />
Final Sampling and Analysis Plan<br />
Installation Restoration Site 29, Hangar 1<br />
Former Naval Air Station, <strong>Moffett</strong> <strong>Field</strong>, <strong>Moffett</strong> <strong>Field</strong>, Cali<strong>for</strong>nia<br />
DCN: AMEC-8816-0005-0039<br />
April 2010<br />
Page xi
This page left intentionally blank.<br />
Final Sampling and Analysis Plan<br />
Installation Restoration Site 29, Hangar 1<br />
Former Naval Air Station, <strong>Moffett</strong> <strong>Field</strong>, <strong>Moffett</strong> <strong>Field</strong>, Cali<strong>for</strong>nia<br />
DCN: AMEC-8816-0005-0039<br />
April 2010<br />
Page xii
WORKSHEET #2:<br />
SAP IDENTIFYING INFORMATION<br />
Site Name: Installation Restoration (IR) Site 29, Hangar 1<br />
Operable Unit:<br />
Not Applicable (NA)<br />
Contractor Name:<br />
AMEC Earth & Environmental, Inc. (AMEC)<br />
Contract Number:<br />
N62473-08-D-8816<br />
Contract Title:<br />
Per<strong>for</strong>mance-Based Environmental Multiple Award<br />
Contract (PERMAC)<br />
Work Assignment Number (optional): Contract Task Order (CTO) 0005<br />
1. This Sampling and Analysis Plan (SAP) was prepared in accordance with the<br />
requirements of the Uni<strong>for</strong>m Federal Policy <strong>for</strong> Quality Assurance Project Plans<br />
(UFP-QAPP) (Intergovernmental Data Quality Task Force [IDQTF] 2005a,b) and<br />
United States Environmental Protection Agency (EPA) Guidance <strong>for</strong> Quality<br />
Assurance Project Plans, EPA Quality Assurance (QA)/G-5, Quality Assurance<br />
Manual (EPA 2002), and supplemental Naval Facilities Engineering Command<br />
Southwest (NAVFAC SW) guidance documents.<br />
2. Identify regulatory program: Comprehensive Environmental Response,<br />
Compensation, and Liability Act (CERCLA)<br />
3. This SAP is a project-specific sampling and analysis plan.<br />
4. List dates of scoping sessions that were held:<br />
Project kick-off meeting with the Remedial Project Manager (RPM), stakeholders,<br />
and Resident Officer in Charge of Construction (ROICC) on 27 October, 2009.<br />
5. List dates and titles of any SAP documents written <strong>for</strong> previous site work that are<br />
relevant to the current investigation:<br />
• Benchmark Environmental Engineering. Polychlorinated Biphenyl, Lead, and<br />
Asbestos Sampling Report. Hangar 1, <strong>Moffett</strong> <strong>Field</strong>, Mountain View,<br />
Cali<strong>for</strong>nia. January 2003.<br />
• Harding Environmental Science and Engineering. Ambient Air Sampling and<br />
Analysis Report, <strong>Moffett</strong> <strong>Field</strong>, Hangar 1. <strong>Moffett</strong> <strong>Field</strong>, Cali<strong>for</strong>nia. December<br />
2002.<br />
• Professional Analysis, Incorporated. Report of Investigation <strong>for</strong> Source of<br />
Aroclor1268 in Soil and Stormwater, National Aeronautics and Space<br />
Administration (NASA) Ames Research Center. October 2002.<br />
Final Sampling and Analysis Plan<br />
Installation Restoration Site 29, Hangar 1<br />
Former Naval Air Station, <strong>Moffett</strong> <strong>Field</strong>, <strong>Moffett</strong> <strong>Field</strong>, Cali<strong>for</strong>nia<br />
DCN: AMEC-8816-0005-0039<br />
April 2010<br />
Page 2-1
6. List organizational partners (stakeholders) and connection with lead organization:<br />
• San Francisco Bay Regional Water Quality Board (Water Board)<br />
• EPA Region IX.<br />
7. The NAFVAC SW is the lead organization.<br />
8. All required SAP elements and in<strong>for</strong>mation are included and applicable to this<br />
project except as noted below:<br />
Worksheet 13 – Secondary data criteria and limitations is not applicable to this<br />
project because secondary data was not evaluated <strong>for</strong> the decision making process.<br />
Final Sampling and Analysis Plan<br />
Installation Restoration Site 29, Hangar 1<br />
Former Naval Air Station, <strong>Moffett</strong> <strong>Field</strong>, <strong>Moffett</strong> <strong>Field</strong>, Cali<strong>for</strong>nia<br />
DCN: AMEC-8816-0005-0039<br />
April 2010<br />
Page 2-2
WORKSHEET #3:<br />
DISTRIBUTION LIST<br />
This worksheet identifies all personnel/entities who receive copies of the SAP, subsequent<br />
SAP revisions, addenda, and amendments. All submittals will be electronic except to Base<br />
Realignment and Closure (BRAC), NAVFAC SW and regulatory agencies.<br />
Name of SAP<br />
Recipients<br />
Narciso Ancog<br />
Title/Role<br />
Quality Assurance<br />
Officer (QAO)<br />
Table 3-1. Document Distribution List<br />
Organization<br />
Telephone<br />
Number<br />
(Optional)<br />
NAVFAC SW 619-532-3046<br />
Angela Lind RPM BRAC 619-532-0922<br />
Gary Munekawa ROICC NAVFAC SW 650-603-9834<br />
David Smith ROICC NAVFAC SW 650-603-9836<br />
Sarah Kloss EPA RPM EPA Region IX 415-972-3156<br />
Kathryn Stewart<br />
Elizabeth Wells<br />
BRAC<br />
Environmental<br />
Coordinator<br />
Water Board<br />
Project Manager<br />
BRAC 415-743-4715<br />
Water Board 510-622-2440<br />
E-mail Address or Mailing Address<br />
narciso.ancog@navy.mil<br />
1220 Pacific Hwy.<br />
San Diego, CA 92132<br />
angela.lind@navy.mil<br />
1455 Frazee Rd, Ste 900<br />
San Diego, CA 92108-4310<br />
gary.munekawa@navy.mil<br />
ROICC SFBA (<strong>Moffett</strong> <strong>Field</strong> Site Office)<br />
Bldg 107 (Corner of Wescoat Rd &<br />
McCord Ave)<br />
<strong>Moffett</strong> <strong>Field</strong>, CA 94035-0068<br />
david.r.smith2@navy.mil<br />
ROICC SFBA (<strong>Moffett</strong> <strong>Field</strong> Site Office)<br />
Bldg 107 (Corner of Wescoat Rd &<br />
McCord Ave)<br />
<strong>Moffett</strong> <strong>Field</strong>, CA 94035-0068<br />
kloss.sarah@epa.gov<br />
U.S. EPA Region 9<br />
75 Hawthorne Street<br />
San Francisco, CA, 94105<br />
Kathryn.Stewart@navy.mil<br />
1 Avenue of the Palms, Suite 161<br />
Treasure Island<br />
San Francisco, CA 94130-1807<br />
ewells@waterboards.ca.gov<br />
1515 Clay St, Suite 1400<br />
Oakland, CA 94612<br />
Mike Schulz Project Manager AMEC 505-796-7290 mike.schulz@amec.com<br />
Ann Bernhardt<br />
Program<br />
Quality Control AMEC 503-639-3400 ann.bernhardt@amec.com<br />
Manager (QCM)<br />
Mark Maniaci<br />
Construction<br />
Manager<br />
AMEC 618-401-3758 mark.maniaci@amec.com<br />
Mary Schneider<br />
Project<br />
QCM<br />
AMEC 909-569-7805 mary.schneider@amec.com<br />
Danille Jorgensen Project Chemist AMEC 503-639-3400 danille.jorgensen@amec.com<br />
Dan Higgins Data Manager AMEC 503-639-3400 dan.higgins@amec.com<br />
Jeanne Peterson Project Manager<br />
Analytical<br />
Quality<br />
Associates, Inc.<br />
702-3683513 jpeterson@aqainc.net<br />
(AQA)<br />
Tina Green Project Manager<br />
BC<br />
Laboratories,<br />
Inc. (BC Labs)<br />
661-327-4911 tina@bclabs.com<br />
Final Sampling and Analysis Plan<br />
Installation Restoration Site 29, Hangar 1<br />
Former Naval Air Station, <strong>Moffett</strong> <strong>Field</strong>, <strong>Moffett</strong> <strong>Field</strong>, Cali<strong>for</strong>nia<br />
DCN: AMEC-8816-0005-0039<br />
April 2010<br />
Page 3-1
This page left intentionally blank.<br />
Final Sampling and Analysis Plan<br />
Installation Restoration Site 29, Hangar 1<br />
Former Naval Air Station, <strong>Moffett</strong> <strong>Field</strong>, <strong>Moffett</strong> <strong>Field</strong>, Cali<strong>for</strong>nia<br />
DCN: AMEC-8816-0005-0039<br />
April 2010<br />
Page 3-2
WORKSHEET #4:<br />
PROJECT PERSONNEL SIGN-OFF SHEET<br />
The Final version of this SAP will be delivered to all project personnel involved with implementing any portion of the SAP.<br />
They will all be given sufficient time to read and ask questions about the content be<strong>for</strong>e the field activities commences.<br />
I have had the opportunity to read and ask questions about this SAP. My signature certifies that I understand the procedures,<br />
equipment, and restrictions of this plan and agree to abide by them.<br />
Table 4-1. Project Personnel Sign-off Sheet<br />
Name<br />
Organization/Title/Role<br />
Telephone Number<br />
Signature/<br />
(optional)<br />
E-mail receipt<br />
Mike Schulz AMEC/Project Manager 505-796-7290<br />
Mark Maniaci AMEC/Construction Manager 618-401-3758<br />
Mary Schneider AMEC/Project QCM 909-569-7805<br />
Danille Jorgensen AMEC/Project Chemist 503-639-3400<br />
Dan Higgins AMEC/Data Manager 503-639-3400<br />
To be determined (TBD) AMEC/<strong>Field</strong> Staff<br />
Jeanne Peterson AQA/ Project Manager 702-368-3513<br />
Tina Green BC Labs/Project Manager 661-327-4911<br />
Notes:<br />
TBD - Specific field staff will be designated based on staff experience and availability be<strong>for</strong>e field work commences.<br />
SAP Section<br />
Reviewed<br />
Date SAP Read<br />
Final Sampling and Analysis Plan<br />
Installation Restoration Site 29, Hangar 1<br />
Former Naval Air Station, <strong>Moffett</strong> <strong>Field</strong>, <strong>Moffett</strong> <strong>Field</strong>, Cali<strong>for</strong>nia<br />
DCN: AMEC-8816-0005-0039<br />
April 2010<br />
Page 4-1
This page left intentionally blank.<br />
Final Sampling and Analysis Plan<br />
Installation Restoration Site 29, Hangar 1<br />
Former Naval Air Station, <strong>Moffett</strong> <strong>Field</strong>, <strong>Moffett</strong> <strong>Field</strong>, Cali<strong>for</strong>nia<br />
DCN: AMEC-8816-0005-0039<br />
April 2010<br />
Page 4-2
WORKSHEET #5:<br />
PROJECT ORGANIZATIONAL CHART<br />
Final Sampling and Analysis Plan<br />
Installation Restoration Site 29, Hangar 1<br />
Former Naval Air Station, <strong>Moffett</strong> <strong>Field</strong>, <strong>Moffett</strong> <strong>Field</strong>,<br />
Cali<strong>for</strong>nia<br />
DCN: AMEC-8816-0005-0039<br />
April 2010<br />
Page 5-1
This page left intentionally blank.<br />
Final Sampling and Analysis Plan<br />
Installation Restoration Site 29, Hangar 1<br />
Former Naval Air Station, <strong>Moffett</strong> <strong>Field</strong>, <strong>Moffett</strong> <strong>Field</strong>,<br />
Cali<strong>for</strong>nia<br />
DCN: AMEC-8816-0005-0039<br />
April 2010<br />
Page 5-2
WORKSHEET #6:<br />
COMMUNICATION PATHWAYS<br />
This worksheet describes the communication pathways and modes of communication that<br />
will be used during the project. This worksheet is intended to promote an understanding of<br />
which project team members including the Department of the Navy (Navy) personnel are<br />
exchanging key in<strong>for</strong>mation, and describes the procedures <strong>for</strong> soliciting and/or obtaining<br />
approval between project personnel, between different contractors, and between samplers<br />
and laboratory staff. Also described in this worksheet are the procedures that will be<br />
followed when any project activity requires real-time modification to achieve project goals,<br />
or when a SAP amendment is required. Procedures and personnel responsible <strong>for</strong> stopping<br />
work are also defined herein.<br />
Communication<br />
Drivers<br />
Point of Contact<br />
with Regulators<br />
Navy Quality<br />
Assurance<br />
Manage All<br />
Project Phases<br />
Manage All <strong>Field</strong><br />
Tasks<br />
<strong>Field</strong> Quality<br />
Assurance<br />
Daily <strong>Field</strong><br />
Progress Reports<br />
Responsible<br />
Affiliation<br />
Navy RPM<br />
Navy QAO<br />
AMEC<br />
Project<br />
Manager<br />
AMEC<br />
Construction<br />
Manager<br />
Navy ROICC<br />
AMEC<br />
Construction<br />
Manager<br />
Table 6-1. Communication Matrix<br />
Name<br />
Angela Lind<br />
Narciso<br />
Ancog<br />
Mike Schulz<br />
Mark Maniaci<br />
Gary<br />
Munekawa<br />
David Smith<br />
Mark Maniaci<br />
Phone Number<br />
and/or e-mail<br />
619-532-0922<br />
angela.lind@navy.mil<br />
619-532-3046<br />
narciso.ancog@navy.mil<br />
505-821-1801<br />
mike.schulz@amec.com<br />
618-401-3758 (mobile)<br />
mark.maniaci@amec.com<br />
650-603-9834<br />
gary.munekawa@navy.mil<br />
650-603-9836<br />
david.r.smith2@navy.mil<br />
618-401-3758 (mobile)<br />
mark.maniaci@amec.com<br />
Procedure<br />
(timing, pathway to<br />
& from, etc.)<br />
All project documentation will be<br />
<strong>for</strong>warded by the Navy RPM to<br />
the regulators.<br />
RPM will notify BRAC Cleanup<br />
Team members including the<br />
EPA within 7 days of significant<br />
changes to the SAP.<br />
The QAO will coordinate with the<br />
Navy RPM and AMEC Program<br />
QCM.<br />
The AMEC Project Manager will<br />
direct and approve of all<br />
communication to the Navy<br />
RPM. The AMEC Project<br />
Manager will notify the Navy<br />
RPM of field changes or<br />
modifications by email within 24<br />
hours of first occurrence.<br />
Acts as alternate point of contact<br />
at AMEC in the absence of the<br />
Project Manager. Responsible<br />
<strong>for</strong> direct oversight of field<br />
sampling activities and<br />
en<strong>for</strong>cement of SAP Accident<br />
Prevention Plan (APP) and Site<br />
Health and Safety Plan (SHSP).<br />
Per<strong>for</strong>m QA that all field work is<br />
completed in accordance with<br />
contract and project<br />
requirements.<br />
The AMEC Construction<br />
Manager will send field progress<br />
reports to the AMEC Project<br />
Manager daily via email.<br />
Final Sampling and Analysis Plan<br />
Installation Restoration Site 29, Hangar 1<br />
Former Naval Air Station, <strong>Moffett</strong> <strong>Field</strong>, <strong>Moffett</strong> <strong>Field</strong>,<br />
Cali<strong>for</strong>nia<br />
DCN: AMEC-8816-0005-0039<br />
April 2010<br />
Page 6-1
Table 6-1. Communication Matrix<br />
Communication<br />
Drivers<br />
SAP Review<br />
SAP Changes in<br />
the <strong>Field</strong><br />
<strong>Field</strong> and<br />
Analytical<br />
Corrective<br />
Actions<br />
Release of<br />
Analytical Data<br />
Reporting Lab<br />
Data Quality<br />
Issues<br />
Responsible<br />
Affiliation<br />
AMEC<br />
Program QCM<br />
AMEC<br />
Construction<br />
Manager<br />
AMEC Project<br />
QCM<br />
AMEC Data<br />
Manager<br />
Laboratory<br />
Project<br />
Manager<br />
Name<br />
Ann Bernhardt<br />
Mark Maniaci<br />
Mary<br />
Schneider<br />
Dan Higgins<br />
Tina Green<br />
Phone Number<br />
and/or e-mail<br />
503-639-3400<br />
ann.bernhardt@amec.com<br />
618-401-3758 (mobile)<br />
mark.maniaci@amec.com<br />
909-569-7805<br />
mary.schneider@amec.com<br />
503-639-3400<br />
dan.higgins@amec.com<br />
661-327-4911<br />
tina@bclabs.com<br />
Procedure<br />
(timing, pathway to<br />
& from, etc.)<br />
The Program QCM assures the<br />
SAP is compliant with Navy<br />
requirements and applicable<br />
regulatory requirements.<br />
The AMEC Construction<br />
Manager or designee will notify<br />
the AMEC Project Manager, the<br />
Project QCM, and the Program<br />
QCM of proposed changes to the<br />
SAP and justifications by phone<br />
within 24 hours of first<br />
occurrence. The Navy QAO will<br />
be contacted <strong>for</strong> approval of any<br />
revisions or amendments of this<br />
SAP. SAP changes requiring<br />
Navy QAO approval include<br />
changes in: analytical methods,<br />
sampling methods, contaminants<br />
of concern, sampling locations,<br />
investigation scope changes,<br />
organizational changes, or any<br />
change in site characterization<br />
that alters the DQOs (see<br />
Environmental Work Instruction<br />
[EWI] #2).<br />
The need <strong>for</strong> corrective action <strong>for</strong><br />
field and analytical issues will be<br />
determined by the AMEC Project<br />
QCM.<br />
No analytical data can be<br />
released until validation is<br />
completed and AMEC’s Data<br />
Manager has approved the<br />
release.<br />
All QA/QC issues with project<br />
field samples will be reported by<br />
the subcontract laboratory<br />
Project Manager to the AMEC<br />
Project Chemist or Project QCM<br />
within two business days.<br />
Final Sampling and Analysis Plan<br />
Installation Restoration Site 29, Hangar 1<br />
Former Naval Air Station, <strong>Moffett</strong> <strong>Field</strong>, <strong>Moffett</strong> <strong>Field</strong>,<br />
Cali<strong>for</strong>nia<br />
DCN: AMEC-8816-0005-0039<br />
April 2010<br />
Page 6-2
WORKSHEET #7:<br />
PERSONNEL RESPONSIBILITIES <strong>AND</strong><br />
QUALIFICATIONS<br />
This worksheet identifies key project personnel associated with each organization,<br />
contractor, and subcontractor participating in responsible roles. Specific personnel roles<br />
and responsibilities are described in this worksheet.<br />
Name<br />
Table 7-1. Key Personnel Project Responsibilities<br />
Title/Role<br />
Organizational<br />
Affiliation<br />
Angela Lind Navy RPM Navy, BRAC<br />
Narciso Ancog<br />
Gary Munekawa<br />
David Smith<br />
Sarah Kloss<br />
Elizabeth Wells<br />
Mike Schulz<br />
Ann Bernhardt<br />
Navy QAO<br />
Navy ROICC<br />
Navy ROICC<br />
EPA RPM<br />
Water Board<br />
Project<br />
Manager<br />
Project<br />
Manager<br />
Program<br />
QCM<br />
Navy,<br />
NAVFAC SW<br />
Navy, NAVFAC<br />
SW<br />
Navy, NAVFAC<br />
SW<br />
EPA,<br />
Region IX<br />
San Francisco<br />
Water Board<br />
AMEC<br />
AMEC<br />
Mary Schneider Project QCM AMEC<br />
Mark Maniaci<br />
Chris Miele<br />
Construction<br />
Manager<br />
Site Safety &<br />
Health<br />
Supervisor<br />
AMEC<br />
AMEC<br />
Responsibilities<br />
RPM is the Navy manager directly responsible <strong>for</strong><br />
project execution and coordination with base<br />
representatives, regulatory agencies and the<br />
NAVFAC SW management team.<br />
Provides government oversight of the QA program,<br />
including review and sign-off on SAPs. The QAO has<br />
the authority to suspend affected projects activities if<br />
NAVFAC SW-approved quality requirements are not<br />
maintained.<br />
Provides site access and en<strong>for</strong>cement of SAP, APP<br />
and SHSP.<br />
Provides site access and en<strong>for</strong>cement of SAP, APP<br />
and SHSP.<br />
Manages the oversight of the project <strong>for</strong> EPA,<br />
Region IX.<br />
Manages the oversight of the project <strong>for</strong> the San<br />
Francisco Water Board.<br />
Supervises and coordinates all work per<strong>for</strong>med on<br />
the project. These responsibilities include project<br />
planning and execution, scheduling, staffing, data<br />
evaluation, report preparation, subcontracts, and<br />
managing deliverables.<br />
Assures the SAP is compliant with Navy and<br />
applicable regulatory requirements.<br />
Oversees and directs QA reviews <strong>for</strong> this project,<br />
including periodic reports, analytical program<br />
requirements, and schedules be<strong>for</strong>e submittal to the<br />
Navy <strong>for</strong> review and comment.<br />
Manages all field tasks.<br />
Responsible <strong>for</strong> development and implementation of<br />
the APP and SHSP.<br />
Final Sampling and Analysis Plan<br />
Installation Restoration Site 29, Hangar 1<br />
Former Naval Air Station, <strong>Moffett</strong> <strong>Field</strong>, <strong>Moffett</strong> <strong>Field</strong>,<br />
Cali<strong>for</strong>nia<br />
DCN: AMEC-8816-0005-0039<br />
April 2010<br />
Page 7-1
Name<br />
Dan Higgins<br />
Danille<br />
Jorgensen<br />
Table 7-1. Key Personnel Project Responsibilities<br />
Title/Role<br />
Data<br />
Manager<br />
Project<br />
Chemist<br />
Organizational<br />
Affiliation<br />
AMEC<br />
AMEC<br />
Responsibilities<br />
Responsible <strong>for</strong> inputting all the field data and the<br />
maintenance of the database. Submitting Naval<br />
Electronic Data Deliverable (NEDD) to the Navy in<br />
accordance with the requirements set <strong>for</strong>th in<br />
Environmental Work Instruction (EWI) EVR.6,<br />
Environmental Data Management and Required<br />
Electronic Delivery Standards (Naval Facilities<br />
Engineering Command-Southwest, 2005.)<br />
Oversees and reviews all laboratory procedures and<br />
actions. Reviews data and coordinates data<br />
validation. Has oversight responsibility <strong>for</strong><br />
management and integrity of the data.<br />
Final Sampling and Analysis Plan<br />
Installation Restoration Site 29, Hangar 1<br />
Former Naval Air Station, <strong>Moffett</strong> <strong>Field</strong>, <strong>Moffett</strong> <strong>Field</strong>,<br />
Cali<strong>for</strong>nia<br />
DCN: AMEC-8816-0005-0039<br />
April 2010<br />
Page 7-2
WORKSHEET #8:<br />
SPECIAL PERSONNEL TRAINING REQUIREMENTS<br />
Project<br />
Function<br />
Wipe Sampling<br />
Specialized Training<br />
By Title or Description<br />
of Course<br />
Wipe sampling<br />
procedure<br />
Training<br />
Provider<br />
Project Chemist<br />
Training<br />
Date<br />
Prior to<br />
sample<br />
collection<br />
Personnel/Groups<br />
Receiving<br />
Training<br />
Personnel<br />
Titles/<br />
Organizational<br />
Affiliation<br />
Location of Training<br />
Records / Certificates<br />
<strong>Field</strong> sampler AMEC Project field office<br />
Final Sampling and Analysis Plan<br />
Installation Restoration Site 29, Hangar 1<br />
Former Naval Air Station, <strong>Moffett</strong> <strong>Field</strong>, <strong>Moffett</strong> <strong>Field</strong>, Cali<strong>for</strong>nia<br />
DCN: AMEC-8816-0005-0039<br />
April 2010<br />
Page 8-1
This page left intentionally blank.<br />
Final Sampling and Analysis Plan<br />
Installation Restoration Site 29, Hangar 1<br />
Former Naval Air Station, <strong>Moffett</strong> <strong>Field</strong>, <strong>Moffett</strong> <strong>Field</strong>, Cali<strong>for</strong>nia<br />
DCN: AMEC-8816-0005-0039<br />
April 2010<br />
Page 8-2
WORKSHEET #9:<br />
PROJECT SCOPING SESSION PARTICIPANTS SHEET<br />
Project Name: Non-Time Critical Removal Action (NCTRA)<br />
<strong>for</strong> Polychlorinated Biphenyl (PCB)<br />
Contamination<br />
Projected Date(s) of Sampling: April 2010 through April<br />
2011<br />
Site Name: IR Site 29<br />
Site Location: Former Naval Air Station (NAS)<br />
<strong>Moffett</strong> <strong>Field</strong><br />
Project Manager: Mike Schulz<br />
Date of Session: 10/27/2009<br />
Scoping Session Purpose: Project Kickoff Meeting<br />
Name Title Affiliation<br />
Phone<br />
Number<br />
E-Mail Address<br />
Project<br />
Role<br />
Angela Lind RPM BRAC 619-532-0922 angela.lind@navy.mil RPM<br />
Kathy Stewart<br />
Gary<br />
Munekawa<br />
BRAC<br />
Environmental<br />
Coordinator<br />
BRAC 415-743-4715 Kathryn.stewart@navy.mil<br />
BRAC<br />
Environmental<br />
Coordinator<br />
ROICC NAVFAC SW 650-603-9834 Gary.munekawa@navy.mil ROICC<br />
David Smith ROICC NAVFAC SW 650-603-9836 David.r.smith2@navy.mil ROICC<br />
Mike Schulz<br />
Project<br />
Manager<br />
AMEC 505-796-7290 mike.schulz@amec.com<br />
Ann Bernhardt QCM AMEC 503-639-3400 Ann.bernhardt@amec.com<br />
Elizabeth Wells<br />
Water Board<br />
Project Manager<br />
Water Board 510-622-2440 ewells@waterboards.ca.gov<br />
Project<br />
Manager<br />
Program<br />
QCM<br />
Project<br />
Manager<br />
Sarah Kloss RPM EPA 415-972-3156 Kloss.sarah@epa.gov RPM<br />
Comments/Decisions: Present remedial action approach including sampling strategy<br />
consistent with technical proposal submitted to the Navy.<br />
Action Items: Prepare and submit Work Plan, SAP and other appendices.<br />
Consensus Decisions: Project team to coordinate in advance on approach to minimize<br />
rounds of edits and comments and expedite plan approval.<br />
Final Sampling and Analysis Plan<br />
Installation Restoration Site 29, Hangar 1<br />
Former Naval Air Station, <strong>Moffett</strong> <strong>Field</strong>, <strong>Moffett</strong> <strong>Field</strong>,<br />
Cali<strong>for</strong>nia<br />
DCN: AMEC-8816-0005-0039<br />
April 2010<br />
Page 9-1
This page left intentionally blank.<br />
Final Sampling and Analysis Plan<br />
Installation Restoration Site 29, Hangar 1<br />
Former Naval Air Station, <strong>Moffett</strong> <strong>Field</strong>, <strong>Moffett</strong> <strong>Field</strong>,<br />
Cali<strong>for</strong>nia<br />
DCN: AMEC-8816-0005-0039<br />
April 2010<br />
Page 9-2
WORKSHEET #10: PROBLEM DEFINITION<br />
Hangar 1 is located at <strong>Moffett</strong> <strong>Field</strong>, a joint civil-military airport located near the south end<br />
of San Francisco Bay, in Sunnyvale, Cali<strong>for</strong>nia. The facility is located 30 miles southeast<br />
of San Francisco and 10 northwest of San Jose. <strong>Moffett</strong> <strong>Field</strong>, which was <strong>for</strong>merly a<br />
United States Naval Air Station, is owned and operated by the NASA Ames Research<br />
Center. NASA operates several aircraft from <strong>Moffett</strong> <strong>Field</strong>.<br />
IR Site 29 (Hangar 1) is located west of the flight line between Sayre Avenue and<br />
Cummins Avenue at the Former NAS <strong>Moffett</strong> <strong>Field</strong>. Hangar 1 was built in 1932 to house<br />
U.S.S. Macon and other Navy Lighter-than-Air program airships. The building is<br />
constructed of a structural steel frame with corrugated siding and measure 1,133 feet long,<br />
308 feet wide, and 198 feet high. The interior floor of the hangar is of concrete<br />
construction. Hangar 1 is primarily surrounded by pavement, with several small grassy<br />
areas adjacent to the building. Water run-off from the building and surrounding areas is<br />
collected in a storm water conveyance system around the perimeter of the building. The<br />
corrugated siding panels of the hangar are constructed of a composite material known as<br />
Robertson Protected Metals, which contains PCBs and asbestos. Lead-paint is also present<br />
on the hangar.<br />
Hangar 1 is located within an industrial land use area adjacent to an active air field. Hangar<br />
1 and the surrounding area is part of an ecological community known as the Upland Areas.<br />
The Upland Areas include disturbed complexes that are characterized by human activity<br />
and corresponding physical disturbance resulting in the introduction of exotic plant<br />
species. Upland Areas surrounding Hangar 1 are paved or minimally landscaped and do<br />
not provide valuable habitat <strong>for</strong> wildlife species (Navy, 2001).<br />
During routine storm water management system cleanout and sampling activities<br />
conducted in 1997, PCBs were detected in sediment samples collected from a storm water<br />
settling basin located approximately 2,000 feet northwest of Hangar 1. In 1999, PCBs were<br />
detected in a storm water sample collected from a manhole “downstream” of Hangar 1.<br />
Based on the detection of PCBs in rainwater running off the hangar siding and out of the<br />
hangar downspout, an investigation was undertaken in 2002 to test the building materials<br />
in Hangar 1 <strong>for</strong> PCBs and other potential contaminants, specifically lead and asbestos.<br />
Samples were collected from siding panels, window putty, and roofing material. The<br />
analytical results of samples collected from siding material indicate that Aroclor-1268 is<br />
present in paint on the siding panels at concentrations that exceed 6,000 mg/kg.<br />
Concentrations Aroclor-1268 is present in the interior layers of the siding panels at<br />
concentrations up to 188,000 milligrams per kilogram (mg/kg) (18.8 percent by weight).<br />
Aroclor-1260 is present in interior layers of the siding up to a maximum concentration of<br />
5,500 mg/kg. PCBs were also detected in lead-based paint used to coat the steel support<br />
Final Sampling and Analysis Plan<br />
Installation Restoration Site 29, Hangar 1<br />
Former Naval Air Station, <strong>Moffett</strong> <strong>Field</strong>, <strong>Moffett</strong> <strong>Field</strong>,<br />
Cali<strong>for</strong>nia<br />
DCN: AMEC-8816-0005-0039<br />
April 2010<br />
Page 10-1
structure. Aroclor-1260 was detected in the structural steel paint coating at concentrations<br />
up to 120 mg/kg, and Aroclor-1268 was detected at concentrations up to 94 mg/kg. Total<br />
PCBs were detected in the paint at concentrations ranging from 65 to 214 mg/kg. Paint<br />
coatings of similar appearance that appear to be present on redwood ceiling and catwalk<br />
planks were not analyzed but are assumed to contain similar concentrations of PCBs.<br />
In addition to PCBs, lead was detected in paint that currently covers the hangar siding,<br />
doors and steel support structure, at maximum detected concentrations of 200,000 mg/kg<br />
(20%). Asbestos was also detected in building materials, including siding panels, roofing,<br />
and other surface materials. The PCB-containing building materials are considered the<br />
most likely source of the PCBs reported in sediment in the storm water collection trench<br />
around the perimeter of Hangar 1.<br />
NASA and the Navy completed Time-Critical Removal Actions (TCRAs) at Hangar 1 as<br />
interim measures to address potential threats to human health and the environment<br />
associated with elevated concentrations of PCBs in Hangar 1 building materials and the<br />
adjacent storm water management system.<br />
In 2008, an Engineering Evaluation/Cost Analysis (EE/CA) was prepared to evaluate PCB<br />
removal alternatives. Alternative 10, removal siding and coating of exposed surfaces, was<br />
selected as the preferred approach as documented in the Action Memorandum (Navy<br />
2008).<br />
This removal action will be conducted to address human health and environmental<br />
concerns associated with potential exposure pathways, including the surface water runoff<br />
pathway to storm water management system, through controlling the migration of PCBs<br />
from Hangar 1 to the environment. The Removal Action Objective is to control the release<br />
of contaminants at Hangar 1, thereby reducing the potential risks to human health and the<br />
environment while minimizing future operation and maintenance activities at the site.<br />
It should also be noted that this removal action is not addressing 1) potential releases to<br />
groundwater, because data previously collected indicates there have been no impacts to<br />
groundwater from PCBs, lead or asbestos; 2) contamination in or below the concrete<br />
foundation, because the foundation will be left in place and there are no indications that it<br />
is contaminated; or 3) institutional controls, because they are outside the scope of this<br />
NTCRA.<br />
To verify that the removal is executed without the release of PCBs into the environment as<br />
a result of the removal action, soil samples from areas adjacent to Hangar 1, sediment<br />
samples from storm drain system, and wipe sample from the concrete floor inside the<br />
hangar will be collected as pre- and post-removal samples.<br />
Final Sampling and Analysis Plan<br />
Installation Restoration Site 29, Hangar 1<br />
Former Naval Air Station, <strong>Moffett</strong> <strong>Field</strong>, <strong>Moffett</strong> <strong>Field</strong>,<br />
Cali<strong>for</strong>nia<br />
DCN: AMEC-8816-0005-0039<br />
April 2010<br />
Page 10-2
WORKSHEET #11: PROJECT QUALITY OBJECTIVES/SYSTEMATIC<br />
<strong>PLAN</strong>NING PROCESS STATEMENTS<br />
11.1 Introduction and Problem Statements<br />
The DQO problem statements are presented in Table 11-1. DQOs <strong>for</strong> the removal action<br />
<strong>for</strong> Hangar 1 are presented in Section 11.2.<br />
11.2 DQOs <strong>for</strong> Removal Action <strong>for</strong> Hangar 1<br />
The DQO process consists of seven steps that are presented in the Tables 11-1 and 11-2.<br />
Process<br />
Step 1<br />
State the<br />
problem.<br />
Step 2<br />
Identify the goals<br />
of the study<br />
Table 11-1. Data Quality Objectives Summary<br />
Pre-Construction and Confirmation Sampling<br />
Response<br />
The results of the various sampling and analysis investigations conducted at and<br />
adjacent to Hangar 1 confirmed that building materials used in the original construction<br />
were the source of the PCBs that were originally detected in the settling basin in 1997.<br />
PCBs. Specifically Aroclor-1260 and Aroclor-1268, were found in the building materials,<br />
with the highest concentrations detected in paint and interior layers of the siding panels.<br />
PCBs were also detected in window putty, roofing material and roof sealant, paint coating<br />
of the steel support structure and floor wipe samples. In addition, lead and asbestos<br />
detected in various building material.<br />
The PCB-containing building materials are considered the most likely source of the PCBs<br />
reported in sediment in the storm water collection trench around the perimeter of<br />
Hangar 1.<br />
The removal action will be conducted to address human health and environmental<br />
concerns associated with potential exposure pathways, including the surface water runoff<br />
pathway to storm water management system, through controlling the migration of PCBs<br />
from Hangar 1 to the environment. Asbestos and lead data will be collected to support<br />
the removal action health and safety program, and to verify that lead and asbestos were<br />
not released as a result of the removal action.<br />
After the removal action is completed, soil areas adjacent to Hangar 1, storm drain<br />
system, and interior concrete floor will be tested to verify that PCBs are not present<br />
above the established cleanup levels and that PCBs, lead and asbestos were not<br />
released into the environment as a result of the removal action.<br />
Data collected during the baseline/pre-construction and confirmation sampling events will<br />
be used <strong>for</strong> the following:<br />
1. Does the concentration of PCBs in baseline/pre-construction samples exceed<br />
regulatory limit listed in Worksheet 15 and require excavation or removal?<br />
2. Do the concentrations of PCBs,lead and asbestos in post-construction<br />
confirmation samples indicate that contaminants were released to the<br />
environment from the removal action of Hangar 1?<br />
3. Do the concentrations of PCBs and lead in the wipe samples collected from the<br />
floor of Hangar 1 demonstrate successful decontamination of the floor?<br />
4. Are concentrations of PCBs, lead and asbestos in storm drain sediment (if<br />
present after pressure washing) less than concentrations from baseline/pre-<br />
Final Sampling and Analysis Plan<br />
Installation Restoration Site 29, Hangar 1<br />
Former Naval Air Station, <strong>Moffett</strong> <strong>Field</strong>, <strong>Moffett</strong> <strong>Field</strong>,<br />
Cali<strong>for</strong>nia<br />
DCN: AMEC-8816-0005-0039<br />
April 2010<br />
Page 11-1
Process<br />
Step 3<br />
Identify<br />
in<strong>for</strong>mation<br />
inputs<br />
Step 4<br />
Define the study<br />
boundaries<br />
Table 11-1. Data Quality Objectives Summary<br />
Pre-Construction and Confirmation Sampling<br />
Response<br />
construction samples to verify that contaminants were not released to the<br />
environment?<br />
5. Are the results of PCBs, metals, semi-volatile organic compounds (SVOCs),<br />
polyaromatic hydrocarbons (PAHs), total petroleum hydrocarbons (TPHs),<br />
asbestos and pH in imported soil (clean fill) samples within the regulatory limits<br />
listed in Worksheet 15?<br />
Baseline/pre-construction concentrations of PCBs, lead, and asbestos will be established<br />
from pre-construction samples collected from the soil areas adjacent to Hangar 1 and the<br />
sediment in the stormwater trench/conveyance system surrounding the building.<br />
Samples will be collected from the soil after the removal action and analyzed <strong>for</strong> PCBs,<br />
lead, and asbestos. If sediment is present in the stormwater trench/conveyance system,<br />
post-removal samples will be collected and analyzed <strong>for</strong> PCBs, lead, and asbestos.<br />
Concrete wipe samples will be collected from the floor of Hangar 1 and analyzed <strong>for</strong><br />
PCBs and lead. Soil to be imported to use as backfill, if excavation is necessary, will be<br />
sampled and analyzed <strong>for</strong> TPHs, PAHs, SVOCs, PCBs, asbestos, metals and pH.<br />
The proposed soil sample locations are presented in Figure 11-1 and the interior<br />
concrete floor samples are presented in Figure 11-2. Soil samples will be collected from<br />
the soil areas immediately adjacent to Hangar 1. Concrete wipe samples will be collected<br />
from the floor of Hangar 1, within its interior boundaries.<br />
Sediment samples will be collected from the sediment inside the stormwater<br />
trench/conveyance system. Sample locations will be determined based on where there is<br />
a sufficient amount of sediment present <strong>for</strong> sample collection.<br />
<strong>Field</strong> activities are anticipated to begin in June 2010 and end in August 2011. Preconstruction<br />
samples will be collected be<strong>for</strong>e removal activities begin. Confirmation<br />
samples will be collected after removal and decontamination activities have been<br />
completed.<br />
1. If the concentrations of PCBs in baseline/pre-construction soil sample exceeds<br />
the regulatory limit listed in Worksheet 15, then the surrounding contaminated<br />
soil will be removed half way to the next clean sample location, and confirmation<br />
samples will be collected from the bottom center and on all four sides of the<br />
excavation until the result of the confirmation sample indicates that the<br />
concentration of total PCB in soil is below 1000 µg/kg. The Navy will consult<br />
with the EPA and Water Board <strong>for</strong> concurrence on areas requiring soil removal..<br />
Step 5<br />
Develop the<br />
analytic approach<br />
If the concentration of PCBs in baseline/pre-construction or confirmation<br />
samples are below the regulatory limit listed in Worksheet 15, then soil removal<br />
will not be required.<br />
2. If the concentrations of lead and asbestos in post-construction confirmation soil<br />
samples are at or below the levels reported in baseline/pre-construction sample,<br />
then contaminants were not released to the environment from the removal<br />
action of Hangar 1 and no soil removal is required.<br />
If concentrations of lead and asbestos in post-construction confirmation samples<br />
are greater than baseline samples, results will be provided to EPA and Water<br />
Board <strong>for</strong> consultation to determine the appropriate response action.<br />
Final Sampling and Analysis Plan<br />
Installation Restoration Site 29, Hangar 1<br />
Former Naval Air Station, <strong>Moffett</strong> <strong>Field</strong>, <strong>Moffett</strong> <strong>Field</strong>,<br />
Cali<strong>for</strong>nia<br />
DCN: AMEC-8816-0005-0039<br />
April 2010<br />
Page 11-2
Process<br />
Table 11-1. Data Quality Objectives Summary<br />
Pre-Construction and Confirmation Sampling<br />
Response<br />
3. If the PCBs and lead concentrations in the post-construction confirmation<br />
concrete wipe samples exceed the regulatory limits listed in Worksheet 15, then<br />
the concrete floor will be decontaminated and re-sampled.<br />
If the PCB and lead concentrations in the post-construction confirmation<br />
concrete wipe samples are within the regulatory limits listed in Worksheet 15,<br />
then no further action is required.<br />
4. If the concentrations of PCBs, lead and asbestos in post-construction<br />
confirmation sediment samples (if sediment is present after pressure washing)<br />
are above the concentrations found in baseline/pre-construction samples,<br />
sediment will be removed and the stormwater trench will be rewashed.<br />
If the concentrations of PCBs, lead and asbestos in post-construction<br />
confirmation sediment samples (if sediment is present after pressure washing)<br />
are within the concentrations found in baseline/pre-construction samples, no<br />
further action is required.<br />
5. If the results of PCBs, TPHs, SVOCs, PAHs, asbestos, metals and pH in import<br />
soil samples are within the regulatory limits listed in Worksheet 15, then the soil<br />
is considered clean and will be imported to the site.<br />
If the results of PCBs, TPHs, SVOCs, PAHs, asbestos, metals or pH in import<br />
soil samples are above the regulatory limits listed in WS 15, then another import<br />
soil source will be identified and soil samples will be collected and analyzed.<br />
Regulatory limits <strong>for</strong> PCB, lead, and asbestos concentrations are presented in<br />
Worksheet 15.<br />
Step 6<br />
Specify<br />
per<strong>for</strong>mance or<br />
acceptance<br />
criteria<br />
Step 7<br />
Develop the plan<br />
<strong>for</strong> obtaining the<br />
data<br />
Laboratory data will be developed using EPA protocols, and the reported data will be<br />
evaluated using AMEC QA and quality control (QC) procedures.<br />
To minimize error samplers will be trained and samples will be collected in accordance<br />
with procedures described in this SAP.<br />
The laboratories will be evaluated by the Naval Facilities Engineering Services Center<br />
(NFESC) or will hold the Department of Defense (DoD) Environmental Laboratory<br />
Accreditation Program (ELAP) certification, and the Cali<strong>for</strong>nia Department of Public<br />
Health ELAP certification (<strong>for</strong> methods certified by Cali<strong>for</strong>nia). Laboratory standard<br />
operating procedures (SOPs) will comply with DoD Quality System Manual (QSM)<br />
version 4.1.<br />
The sampling design is presented in Worksheet 17.<br />
Final Sampling and Analysis Plan<br />
Installation Restoration Site 29, Hangar 1<br />
Former Naval Air Station, <strong>Moffett</strong> <strong>Field</strong>, <strong>Moffett</strong> <strong>Field</strong>,<br />
Cali<strong>for</strong>nia<br />
DCN: AMEC-8816-0005-0039<br />
April 2010<br />
Page 11-3
Table 11-2. Data Quality Objectives Summary<br />
Treated Water Sampling<br />
Process<br />
Step 1<br />
State the<br />
problem.<br />
Step 2<br />
Identify the goals<br />
of the study<br />
Step 3<br />
Identify<br />
in<strong>for</strong>mation<br />
inputs<br />
Step 4<br />
Define the study<br />
boundaries<br />
Response<br />
Spent wash water generated from the washing activities will be treated and then<br />
discharged if treated water meets the Sunnyvale Publicly Owned Treatment Works<br />
(POTW) discharge requirement.<br />
Are the treated spent wash water concentrations less than or equal to the Sunnyvale<br />
POTW limits (see Worksheet 15)?<br />
Water samples will be collected and analyzed in accordance with the Sunnyvale POTW<br />
discharge requirements.<br />
This project is anticipated to begin field work in June 2010 and the estimated date of<br />
completion is August 2011.<br />
Step 5<br />
Develop the<br />
analytic approach<br />
If treated spent wash water is above the Sunnyvale POTW limits, then it will be retreated<br />
until it meets the discharge limits.<br />
If treated spent wash water is below the Sunnyvale POTW limits, then it will be<br />
discharged to the Sunnyvale treatment plant.<br />
Step 6<br />
Specify<br />
per<strong>for</strong>mance or<br />
acceptance<br />
criteria<br />
Step 7<br />
Develop the plan<br />
<strong>for</strong> obtaining the<br />
data<br />
Sunnyvale POTW limits are presented in Worksheet 15. Limits <strong>for</strong> additional disposal<br />
facilities will be included upon procurement.<br />
Laboratory data will be developed using EPA protocols, and the reported data will be<br />
evaluated.<br />
To minimize error, samplers will be trained and samples will be collected in accordance<br />
with field sampling procedures describes in this SAP.<br />
The laboratories will be evaluated by the NFESC or will hold the DoD ELAP certification,<br />
and the Cali<strong>for</strong>nia Department of Public Health ELAP certification (<strong>for</strong> methods certified<br />
by Cali<strong>for</strong>nia). Laboratory SOPs will comply with the DoD QSM version 4.1.<br />
A waste water sample will be collected per every 120,000 gallons of treated spent wash<br />
water.<br />
Final Sampling and Analysis Plan<br />
Installation Restoration Site 29, Hangar 1<br />
Former Naval Air Station, <strong>Moffett</strong> <strong>Field</strong>, <strong>Moffett</strong> <strong>Field</strong>,<br />
Cali<strong>for</strong>nia<br />
DCN: AMEC-8816-0005-0039<br />
April 2010<br />
Page 11-4
This page left intentionally blank.<br />
Final Sampling and Analysis Plan<br />
Installation Restoration Site 29, Hangar 1<br />
Former Naval Air Station, <strong>Moffett</strong> <strong>Field</strong>, <strong>Moffett</strong> <strong>Field</strong>,<br />
Cali<strong>for</strong>nia<br />
DCN: AMEC-8816-0005-0039<br />
April 2010<br />
Page 11-6
This page left intentionally blank.<br />
Final Sampling and Analysis Plan<br />
Installation Restoration Site 29, Hangar 1<br />
Former Naval Air Station, <strong>Moffett</strong> <strong>Field</strong>, <strong>Moffett</strong> <strong>Field</strong>,<br />
Cali<strong>for</strong>nia<br />
DCN: AMEC-8816-0005-0039<br />
April 2010<br />
Page 11-8
WORKSHEET #12: MEASUREMENT PERFORMANCE CRITERIA TABLES<br />
The following table identifies the data quality indicators (DQIs), measurement<br />
per<strong>for</strong>mance criteria (MPC), and QC sample and/or activity used to assess the<br />
measurement per<strong>for</strong>mance <strong>for</strong> both the sampling and analytical measurement systems.<br />
QC Sample<br />
Analytical<br />
Groups<br />
Table 12-1. Concrete Wipe<br />
Frequency<br />
Data Quality<br />
Indicators<br />
(DQIs)<br />
Measurement<br />
Per<strong>for</strong>mance Criteria<br />
QC Sample<br />
Assesses Error<br />
<strong>for</strong> Sampling (S),<br />
Analytical (A) or<br />
both (S&A)<br />
<strong>Field</strong> Duplicate NA 1 NA NA NA NA<br />
Equipment Blank NA 2 NA NA NA NA<br />
Source Blank NA 2 NA NA NA NA<br />
<strong>Field</strong> Blank PCBs, Lead 5% Accuracy<br />
No Analyte ><br />
Quantitation Limit<br />
S<br />
(QL)<br />
Trip Blank NA 3 NA NA NA NA<br />
Matrix Spike<br />
(MS)/Matrix<br />
Spike Duplicate<br />
NA NA NA NA NA<br />
(MSD)<br />
Notes:<br />
1 <strong>Field</strong> duplicates will not be collected <strong>for</strong> wipe sample because it is impractical to collect a duplicate from a<br />
wipe location.<br />
2 Decontamination of equipment will not be necessary. There<strong>for</strong>e, equipment blank will be not collected.<br />
3 Trip blank samples are not applicable <strong>for</strong> wipe samples since samples will not be analyzed <strong>for</strong> volatile organic<br />
compounds.<br />
QC Sample<br />
Analytical<br />
Groups<br />
Frequency<br />
Table 12-2. Soil<br />
Data Quality<br />
Indicators<br />
(DQIs)<br />
Measurement<br />
Per<strong>for</strong>mance Criteria<br />
QC Sample<br />
Assesses Error<br />
<strong>for</strong> Sampling (S),<br />
Analytical (A) or<br />
both (S&A)<br />
<strong>Field</strong> Duplicate<br />
PCBs, Lead,<br />
Asbestos<br />
10% Precision RPD < 30% S<br />
Equipment Blank NA 1 NA NA NA NA<br />
Source Blank NA 1 NA NA NA NA<br />
Trip Blank NA 2 NA NA NA NA<br />
MS/MSD PCBs, Lead 5%<br />
Precision and Criteria Listed in<br />
Accuracy Worksheet 28<br />
A<br />
Notes:<br />
1 Equipment blanks and source blanks are not applicable because soil samples will be collected using a<br />
disposable scoop and decontamination of equipment will not be necessary.<br />
2 Trip blank samples are not applicable since samples will not be analyzed <strong>for</strong> volatile organic compounds.<br />
Final Sampling and Analysis Plan<br />
Installation Restoration Site 29, Hangar 1<br />
Former Naval Air Station, <strong>Moffett</strong> <strong>Field</strong>, <strong>Moffett</strong> <strong>Field</strong>,<br />
Cali<strong>for</strong>nia<br />
DCN: AMEC-8816-0005-0039<br />
April 2010<br />
Page 12-1
QC Sample<br />
Analytical<br />
Groups<br />
Table 12-3. Sediment<br />
Frequency<br />
Data Quality<br />
Indicators<br />
(DQIs)<br />
Measurement<br />
Per<strong>for</strong>mance Criteria<br />
QC Sample<br />
Assesses Error<br />
<strong>for</strong> Sampling (S),<br />
Analytical (A) or<br />
both (S&A)<br />
<strong>Field</strong> Duplicate<br />
PCBs, Lead,<br />
Asbestos<br />
10% Precision RPD < 30% S<br />
Equipment Blank NA 1 NA NA NA NA<br />
Source Blank NA 1 NA NA NA NA<br />
Trip Blank NA 2 NA NA NA NA<br />
MS/MSD PCBs, Lead 5%<br />
Precision and Criteria Listed in<br />
Accuracy Worksheet 28<br />
A<br />
Notes:<br />
2<br />
Equipment rinsates and sources blanks are not applicable because sediment samples will be collected<br />
using a disposable scoop and decontamination of equipment will not be necessary.<br />
3<br />
Trip blank samples are not applicable since samples will not be analyzed <strong>for</strong> volatile organic compounds.<br />
Final Sampling and Analysis Plan<br />
Installation Restoration Site 29, Hangar 1<br />
Former Naval Air Station, <strong>Moffett</strong> <strong>Field</strong>, <strong>Moffett</strong> <strong>Field</strong>,<br />
Cali<strong>for</strong>nia<br />
DCN: AMEC-8816-0005-0039<br />
April 2010<br />
Page 12-2
WORKSHEET #13: SECONDARY DATA CRITERIA <strong>AND</strong> LIMITATIONS<br />
This worksheet identifies the source of secondary data and in<strong>for</strong>mation pertinent to this<br />
investigation. Secondary data is not applicable to this project.<br />
Final Sampling and Analysis Plan<br />
Installation Restoration Site 29, Hangar 1<br />
Former Naval Air Station, <strong>Moffett</strong> <strong>Field</strong>, <strong>Moffett</strong> <strong>Field</strong>,<br />
Cali<strong>for</strong>nia<br />
DCN: AMEC-8816-0005-0039<br />
April 2010<br />
Page 13-1
This page left intentionally blank.<br />
Final Sampling and Analysis Plan<br />
Installation Restoration Site 29, Hangar 1<br />
Former Naval Air Station, <strong>Moffett</strong> <strong>Field</strong>, <strong>Moffett</strong> <strong>Field</strong>,<br />
Cali<strong>for</strong>nia<br />
DCN: AMEC-8816-0005-0039<br />
April 2010<br />
Page 13-2
WORKSHEET #14: SUMMARY OF PROJECT TASKS<br />
This worksheet summarizes the major tasks <strong>for</strong> this project.<br />
14.1 Site Preparation, Sampling, and Analysis Tasks<br />
• Coordinate site access through the ROICC and NASA to minimize disruption to<br />
ongoing activities.<br />
• Mobilization, Utility Clearance, and Implementation of Stormwater Best<br />
Management Practices (BMP), and Storm Water Pollution Prevention Plan<br />
(SWPPP).<br />
• Biological Survey: Prior to beginning site activities, AMEC will conduct a<br />
biological survey to check <strong>for</strong> the presence of bird and mammals residing in<br />
Hangar 1. AMEC will work with a biologist from NASA to mitigate biological<br />
hazards in the hangar.<br />
• Dust/Air Emission Control: A perimeter air monitoring program will be<br />
implemented so that workers, NASA tenants, and the public are protected against<br />
dust emissions that could be generated during demolition. Baseline sampling will<br />
be conducted prior to the start of work and continuous, real-time perimeter dust<br />
monitoring will be provided during working hours. Air monitoring is discussed in<br />
detail in the Air Emission Control and Monitoring Plan, which is included in the<br />
Work Plan.<br />
• Asbestos Abatement: Asbestos abatement will comply with the Cali<strong>for</strong>nia Code of<br />
Regulations (CCR), Title 8, and section 1529. Asbestos abatement is discussed in<br />
detail in the Work Plan.<br />
• Baseline/Pre-Construction Sampling: Samples will be collected from the soil area<br />
immediately adjacent to Hangar 1 and from the sediment in the stormwater<br />
trench/conveyance system around the perimeter of Hangar 1. Sampling strategy <strong>for</strong><br />
soil and sediments are discussed in Worksheet 17.<br />
• Removal of Equipment and Furniture, Capping Utilities, and Demolition of Interior<br />
Buildings: The utilities in Hagar 1 will be capped in accordance with national and<br />
local codes, and Navy/NASA requirements prior to interior demolition. Greater<br />
detail is provided in the Work Plan.<br />
Final Sampling and Analysis Plan<br />
Installation Restoration Site 29, Hangar 1<br />
Former Naval Air Station, <strong>Moffett</strong> <strong>Field</strong>, <strong>Moffett</strong> <strong>Field</strong>,<br />
Cali<strong>for</strong>nia<br />
DCN: AMEC-8816-0005-0039<br />
April 2010<br />
Page 14-1
• Removal of Lighting, Power, and Communication Systems: All lighting, power,<br />
distribution, and communication systems will be removed from the interior of the<br />
hangar with the exception of power to the North Clamshell doors, the Federal<br />
Aviation Administration (FAA) Obstruction Lights and Airfield Beacon, the sump<br />
pump, and star, and surrounding buildings that receive their power from Hangar 1<br />
electric vault. Greater detail is provided in the Work Plan.<br />
• Pressure Washing and Removal of Siding: Once interior demolition is complete,<br />
AMEC will pressure wash and coat all accessible steel in the hangar while the<br />
exterior siding is still in place. AMEC will then remove the siding systematically<br />
from south to north, dividing the area into zones. Greater detail is provided in the<br />
Work Plan.<br />
• Replacement of Structural Steel Members: An AMEC structural engineer licensed<br />
in Cali<strong>for</strong>nia will per<strong>for</strong>m an inspection of the structure after interior demolition is<br />
complete. At that time, specifications and drawings will be prepared to define the<br />
location and type of repairs needed. Repairs will be made by a qualified steel<br />
erector and inspected by an AMEC engineer.<br />
• Segregation, Classification, and Disposal of Waste: Waste streams generated<br />
during the demolition activities will be characterized and disposed at the selected<br />
disposal facility. Spent wash water generated during the wash-down of the hangar<br />
interior, hangar concrete floor, and stormwater trench/conveyance system will be<br />
treated onsite and discharged to the Sunnyvale POTW. All waste will be handled<br />
per the Waste Transportation and Disposal Plan included in the Work Plan.<br />
• Coating Remaining Structure: The remaining structure will be coated with an<br />
epoxy coating system. Greater detail is provided in the Work Plan.<br />
• Implementation of Measures to Abate Bird Strike and Animal Hazards: AMEC will<br />
implement the recommended abatement measures during construction and will<br />
make recommendations <strong>for</strong> changes to <strong>Moffett</strong> <strong>Field</strong>’s Biological Hazards<br />
Abatement Plan (BHAP) plan based upon the final configuration of Hangar 1.<br />
Greater detail will be provided in the Biological Hazard Abatement Plan.<br />
• Post-construction confirmation samples will be collected after the removal<br />
activities are complete: Soil samples will be collected from the same sample<br />
locations as the baseline/pre-construction samples and analyzed <strong>for</strong> PCBs, lead, and<br />
asbestos at areas where PCB contaminated soil (above 1000 µg/kg) removal is not<br />
required. Results will be compared to the baseline/pre-construction soil samples or<br />
regulatory limit of 1,000 µg/kg <strong>for</strong> PCBs to verify that contaminants were not<br />
released into the environment as a result of the removal action. If the results of<br />
PCBs exceed the criteria the Navy will verify exact areas <strong>for</strong> excavation with the<br />
EPA and Water Board prior to removal of contaminated soil.<br />
Final Sampling and Analysis Plan<br />
Installation Restoration Site 29, Hangar 1<br />
Former Naval Air Station, <strong>Moffett</strong> <strong>Field</strong>, <strong>Moffett</strong> <strong>Field</strong>,<br />
Cali<strong>for</strong>nia<br />
DCN: AMEC-8816-0005-0039<br />
April 2010<br />
Page 14-2
• Excavation and Disposal of Contaminated Soil: Upon Navy approval, the PCB<br />
contaminated soil will be removed with a loader and place it in roll-off bins <strong>for</strong><br />
transportation to the selected disposal facility. Confirmation samples will be<br />
collected after the excavation until the concentrations <strong>for</strong> total PCB in soil is below<br />
1000 µg/kg. For areas where concentrations of total PCB in baseline/preconstruction<br />
samples exceed 1000 µg/kg, post-construction confirmation samples<br />
<strong>for</strong> asbestos and lead will be collected after PCB contaminated soil has been<br />
removed. The excavation will be backfilled with imported clean fill and compacted.<br />
The clean fill will be analyzed <strong>for</strong> PCBs, SVOCs, TPHs, PAHs, metals, asbestos,<br />
and pH.<br />
• The stormwater trench/conveyance system will be cleaned out and pressure washed<br />
as part of the scope of work, there<strong>for</strong>e; it is unlikely that sediment will be present to<br />
sample <strong>for</strong> comparison purposes with pre-construction samples. Thirty-seven wipe<br />
samples will be collected from the concrete floor of Hangar 1 and analyzed <strong>for</strong><br />
PCBs and lead. If the PCB and lead concentrations are within the regulatory limits<br />
of 10 µg/100 square centimeter (cm 2 ), and 40 micrograms per square foot (µg/ft 2 ),<br />
respectively, then cleanup will be deemed complete in this area. If either PCB or<br />
lead concentrations are not within the regulatory limits then additional pressure<br />
washing will be conducted, followed by additional wipe sampling until complete<br />
cleanup is demonstrated.<br />
• Airfield Beacon and Obstruction Lights, Decontamination, Site Cleanup, and<br />
Demobilization: AMEC will comply with FAA requirements <strong>for</strong> maintenance and<br />
final placement of the beacon and obstruction lights on top of the hangar.<br />
• Waste water generated during the NTCRA will be stored and treated on site prior to<br />
disposal or re-use. Treated water will be sampled every 120,000 gallons analyzed<br />
<strong>for</strong> PCBs, chromium, zinc, lead, asbestos, and pH, as required by the Sunnyvale<br />
POTW discharge permit. Treated water will be re-used <strong>for</strong> construction purposes<br />
when analyses indicate that water does not contain contaminants above federal,<br />
state and local concentration limits.<br />
14.2 Sampling Procedures<br />
14.2.1 Pre-construction/Baseline Soil Sampling Procedure<br />
The following is the soil sampling procedure <strong>for</strong> pre-construction samples:<br />
1. Don a new pair of nitrile gloves.<br />
Final Sampling and Analysis Plan<br />
Installation Restoration Site 29, Hangar 1<br />
Former Naval Air Station, <strong>Moffett</strong> <strong>Field</strong>, <strong>Moffett</strong> <strong>Field</strong>,<br />
Cali<strong>for</strong>nia<br />
DCN: AMEC-8816-0005-0039<br />
April 2010<br />
Page 14-3
2. Place the auger bit in the selected location and turn the auger until the 0.5 foot (6-<br />
inch) depth is obtained. Remove auger and collect sample from bit into a clean 8-<br />
ounce glass sample jar. Close the jar, label and place in cooler.<br />
2. Replace the auger bit into the original hole and continue augering until the 1 foot<br />
depth is reached. Remove auger and collect sample as above. Place excess soil back<br />
to the hole. Label a wooden stake with the sample number to mark the location <strong>for</strong><br />
confirmation sampling.<br />
3. Complete chain-of-custody record be<strong>for</strong>e taking the next sample.<br />
4. Place sample containers in an insulated cooler with ice.<br />
5. Samples will be packaged and shipped in accordance with SOP FP-F-7, Sample<br />
Handling, Storage, and Shipping (Appendix A).<br />
14.2.2 Pre-construction/Baseline Sediment Sampling Procedure<br />
Sediment samples will be collected from a shallow trench with disposable scoops. A new<br />
pair of nitrile gloves will be worn prior to sample collection. Nitrile gloves will be<br />
disposed of after each sample is collected, and a new pair will be worn be<strong>for</strong>e the next<br />
sample is collected to avoid possible cross-contamination.<br />
Using a new, individually packaged, disposable plastic scoop or equivalent, place sediment<br />
into an 8-ounce glass jar. Affix a completed sample label to the sample container. Wrap<br />
glass jar in bubble-wrap packaging material, place into resealable bags, and place sample<br />
containers into a cooler containing ice. Record sample number, time and date, and<br />
requested analysis on chain-of-custody <strong>for</strong>m. Samples will be packaged and shipped in<br />
accordance with SOP FP-F-7, Sample Handling, Storage, and Shipping procedure<br />
provided in Appendix A.<br />
14.2.3 Post-Construction Confirmation Soil Sampling Procedure<br />
The following is the soil sampling procedure <strong>for</strong> post-construction confirmation<br />
samples:<br />
1. Don a new pair of nitrile gloves.<br />
2. Place the auger bit in the selected location and turn the auger until 6-inch depth<br />
below surface is obtained. Remove auger and place soil in a stainless steel mixing<br />
bowl and homogenized. Then, place mixed soil into a clean 8-ounce glass sample<br />
jar. Close the jar, label and place in cooler.<br />
3. Label a wooden stake with the sample number to mark the location <strong>for</strong><br />
confirmation sampling.<br />
Final Sampling and Analysis Plan<br />
Installation Restoration Site 29, Hangar 1<br />
Former Naval Air Station, <strong>Moffett</strong> <strong>Field</strong>, <strong>Moffett</strong> <strong>Field</strong>,<br />
Cali<strong>for</strong>nia<br />
DCN: AMEC-8816-0005-0039<br />
April 2010<br />
Page 14-4
4. Complete chain-of-custody record be<strong>for</strong>e taking the next sample.<br />
5. Place sample containers in an insulated cooler with ice.<br />
6. Samples will be packaged and shipped in accordance with SOP FP-F-7, Sample<br />
Handling, Storage, and Shipping (Appendix A).<br />
14.2.4 Wipe Sampling Procedure<br />
Wipe samples will be collected from the floor of Hangar 1 following the procedure below:<br />
• Prepare a 100 cm 2 template by cutting 10 cm x 10 cm square area (<strong>for</strong> PCBs) or a 1<br />
ft 2 template by cutting 1 foot x 1 foot square area (<strong>for</strong> lead) from plastic sheet or<br />
cardboard.<br />
• Place the 100 cm 2 template over the area to be sampled <strong>for</strong> PCBs, and secure it so<br />
that the template will not move during sampling.<br />
• Don a new pair of disposable nitrile gloves.<br />
• Remove pre-moistened gauze soaked with appropriate solvent <strong>for</strong> PCB from the<br />
container provided by the laboratory. Avoid excess solvent on the gauze as it may<br />
cause drips and running on the surface thus diluting the sample.<br />
• Wipe the surface with firm pressure, using S-strokes (edge to edge direction,<br />
covering the entire surface. Fold the exposed side of the gauze inward (i.e. fold in<br />
half), and wipe the same area with S-strokes at right angles to the first wipe. Fold<br />
the exposed side of the gauze in (twice-folded), and wipe with S-strokes in the<br />
original direction. Then, fold the exposed side of the gauze in, and place it back in<br />
the container.<br />
• Cap the sample container, place in a double plastic bag and attach the label and<br />
custody seal. Record all pertinent data in the field logbook.<br />
• Place the 1 ft 2 template near where 100 cm 2 template was placed.<br />
• Remove pre-weighed ashless quantitative gauze paper soaked with appropriate<br />
solvent <strong>for</strong> lead from the container provided by the laboratory. Repeat step 5 and<br />
step 6.<br />
• Complete chain-of-custody record be<strong>for</strong>e taking the next sample.<br />
• Place sample containers in an insulated cooler with ice.<br />
• Samples will be packaged and shipped in accordance with SOP FP-F-7, Sample<br />
Handling, Storage, and Shipping procedure provided in Appendix A.<br />
Final Sampling and Analysis Plan<br />
Installation Restoration Site 29, Hangar 1<br />
Former Naval Air Station, <strong>Moffett</strong> <strong>Field</strong>, <strong>Moffett</strong> <strong>Field</strong>,<br />
Cali<strong>for</strong>nia<br />
DCN: AMEC-8816-0005-0039<br />
April 2010<br />
Page 14-5
14.2.5 Import Soil Sampling Procedure<br />
Soil to be used <strong>for</strong> import soil will be collected and analyzed <strong>for</strong> PCBs, metals, asbestos<br />
and pH prior to transporting to the site. It is anticipated that the material to be used will be<br />
from land near rock quarry. Based on the In<strong>for</strong>mation Advisory Clean Imported Fill<br />
Material fact sheet developed by the Department of Toxic Substance Control (DTSC)<br />
(DTSC 2001), five soil samples will be collected using following procedure:<br />
• The soil area will be divided into the number of sections equivalent to 500 cubic<br />
yards per sample.<br />
• The sample locations will be determined by generating random numbers.<br />
• Sampling personnel will don a new pair of disposable nitrile gloves immediately<br />
be<strong>for</strong>e collecting samples at each location.<br />
• A hand auger, or similar device, will be used to access each x, y, and z coordinate.<br />
Due to limitations in accessing deep depths in a large soil area, z-coordinates may be<br />
limited to 10 feet.<br />
• Once the sample location has been accessed, grab samples will be collected by<br />
inverting the hand auger with the material and dislodging the material into an 8-<br />
ounce glass jar.<br />
• Place sample containers in an insulated cooler with ice.<br />
• Samples will be packaged and shipped in accordance with SOP FP-F-7, Sample<br />
Handling, Storage, and Shipping (Appendix A).<br />
14.3 Analytical Tasks<br />
Baseline/pre-construction and confirmation soil and sediment samples will be analyzed <strong>for</strong><br />
PCBs, lead and asbestos. If import soil is required, soil samples will be tested <strong>for</strong> PCBs,<br />
asbestos, metals and pH. Wipe samples from concrete floor of Hangar 1 will be analyzed<br />
<strong>for</strong> PCBs, and lead. Samples will be analyzed <strong>for</strong> PCBs including Aroclor-1268 by EPA<br />
method 8082, lead and metals by EPA method 6010B, pH by EPA method 150.1, and<br />
asbestos by Cali<strong>for</strong>nia Air Resource Board (CARB) 435 method. Samples will be sent to<br />
an off-site laboratory evaluated by NFESC or will hold the DoD ELAP certification, and<br />
the Cali<strong>for</strong>nia Department of Public Health ELAP certification (<strong>for</strong> methods certified by<br />
Cali<strong>for</strong>nia).<br />
14.4 Quality Control Tasks<br />
Soil samples will be collected using procedures presented above. <strong>Field</strong> QC samples to be<br />
collected are presented in WS #12. Sample collection activities will be documented in<br />
Final Sampling and Analysis Plan<br />
Installation Restoration Site 29, Hangar 1<br />
Former Naval Air Station, <strong>Moffett</strong> <strong>Field</strong>, <strong>Moffett</strong> <strong>Field</strong>,<br />
Cali<strong>for</strong>nia<br />
DCN: AMEC-8816-0005-0039<br />
April 2010<br />
Page 14-6
accordance with procedures described in WS #27. In addition, sample handling, packaging<br />
and shipping procedure is described in SOP FP-F-7, Sample Handling, Storage, and<br />
Shipping (Appendix A).<br />
14.5 <strong>Field</strong> Documentation and Data Correcting Tasks<br />
<strong>Field</strong> measurements will be made by qualified field geologists, engineers, environmental<br />
scientists, and/or technicians. All field data will be recorded in ink on the <strong>for</strong>ms listed<br />
below. Review of field data and records will be per<strong>for</strong>med by the Project QCM or<br />
designee. All instrument selections and use, including calibration and standardization, field<br />
deviations, and sampling limitations, will be recorded on the daily field log. <strong>Field</strong> records<br />
will be initialed by the reviewer prior to their incorporation into reports or use in program<br />
decisions. Any changes or corrections to field <strong>for</strong>m entries will be completed by striking<br />
out the incorrect entry with a single line and inserting the correct entry next to the stricken<br />
entry. The corrector’s initials will be placed next to the correction.<br />
Examples of the field <strong>for</strong>ms listed below are provided in Appendix B:<br />
• Daily <strong>Field</strong> Log<br />
• Daily Report Form<br />
• Sample Collection Log<br />
• Chain-of-Custody<br />
14.6 Computerized and Manual Data Management Tasks <strong>for</strong> Analysis,<br />
Reporting, Storage and Archiving<br />
During sample collection, field-collected data including field observations and field<br />
screening data measurements will be hand-entered by field staff onto the appropriate field<br />
data recording <strong>for</strong>ms (See Appendix B). These data will be transcribed by data specialists<br />
to electronic data deliverables (EDDs) and loaded into an EQuIS 5 database. In addition,<br />
the data specialists will load: (1) field sample data (sample dates and time, sample depth,<br />
etc.); (2) requested analytical methods; and (3) electronic laboratory sample receipt data<br />
and planned test tables within the EQuIS database. Then the sample names and laboratorylogged<br />
analytical methods will be compared against the records in the sample and planned<br />
test tables in the database to make sure the laboratory logged in the correct sample names<br />
and requested analytical methods.<br />
Following laboratory analysis of the project samples, their analytical results will be<br />
supplied to AMEC by the laboratory in the standard EQuIS four-file <strong>for</strong>mat using Naval<br />
Installation Restoration In<strong>for</strong>mation Solution (NIRIS) valid-values and loaded into the project<br />
EQuIS database. These records will be flagged as unvalidated pending validation by a third-party<br />
Final Sampling and Analysis Plan<br />
Installation Restoration Site 29, Hangar 1<br />
Former Naval Air Station, <strong>Moffett</strong> <strong>Field</strong>, <strong>Moffett</strong> <strong>Field</strong>,<br />
Cali<strong>for</strong>nia<br />
DCN: AMEC-8816-0005-0039<br />
April 2010<br />
Page 14-7
firm. These draft records will be compared to the planned test and sample receipt records to insure<br />
completeness of the data deliverables. Data will be reported with 80 percent (%) Level III and 20%<br />
Level IV data package. AMEC will supply the data validator with a data validation EDD to<br />
populate with data qualifiers and reason codes. Following validation, AMEC will load this<br />
validation EDD into the project database, update the records with any applied qualifiers and reason<br />
codes, and flag all validated results as validated.<br />
Once the data validation records are updated in the database, AMEC will per<strong>for</strong>m a 20% check of<br />
analytical records from the database to hard copy analytical reports, and a 100% check of handentered<br />
field data, by comparing the field data sheets to field data in the database. If any systemic<br />
errors are identified in the analytical records, then a full 100% check will be per<strong>for</strong>med on the<br />
relevant data deliverables.<br />
Finally, the Data Manager will export validated and quality checked data from the database as<br />
EDDs con<strong>for</strong>ming to the Naval Electronic Data Deliverable (NEDD) <strong>for</strong>mat, checked with the<br />
NIRIS data checker, and loaded into the NIRIS database.<br />
14.7 Data Tracking, Storage, Archiving, Retrieval, and Security<br />
14.7.1 Electronic Data:<br />
The data tracking process is described above. The electronic data will be stored on a<br />
structure query language (SQL)-Server database using the Earthsoft EQuIS 5 data<br />
management system. Daily backups will be per<strong>for</strong>med by the SQL-Server system and<br />
archived on a separate file server. In addition, AMEC’s in<strong>for</strong>mation technology staff will<br />
per<strong>for</strong>m daily backups of both servers to a tape drive.<br />
Only a limited subset of AMEC database users is allowed access to the physical server. In<br />
addition, this project’s database will further limit access only to users who work directly on<br />
the project. Individual user rights will vary depending on their project role.<br />
14.7.2 Documentation and Records:<br />
<strong>Field</strong> logs, field <strong>for</strong>ms, chains-of-custody, correspondence, and project reports will be<br />
maintained in electronic <strong>for</strong>mat at the AMEC San Diego office at completion of the<br />
project. Hard copies of field <strong>for</strong>ms and chains-of-custody will be retained on-site in the<br />
project files until demobilization of the project.<br />
14.7.3 Assessment/Audit Tasks:<br />
Audits of field staff compliance with project SOPs will be per<strong>for</strong>med on a periodic basis as<br />
determined by the Project QCM, consistent with AMEC SOP FP-F-5. At least one audit<br />
will be per<strong>for</strong>med during each sampling task, as defined in this Worksheet. Audits of<br />
Final Sampling and Analysis Plan<br />
Installation Restoration Site 29, Hangar 1<br />
Former Naval Air Station, <strong>Moffett</strong> <strong>Field</strong>, <strong>Moffett</strong> <strong>Field</strong>,<br />
Cali<strong>for</strong>nia<br />
DCN: AMEC-8816-0005-0039<br />
April 2010<br />
Page 14-8
laboratory compliance will be handled by the Navy or AMEC if requested by the Navy.<br />
AMEC will use laboratories previously audited by the Navy or through the DoD ELAP.<br />
14.7.4 Laboratory Analytical Data Review Tasks:<br />
Prior to submitting analytical data to AMEC, the laboratory must verify compliance with<br />
the method requirements. The laboratory will follow their QA manual, SOPs, and this SAP<br />
<strong>for</strong> all sample analyses. The laboratory will also be responsible <strong>for</strong> the oversight of the data<br />
quality <strong>for</strong> all analyses. Any sample integrity issues, discrepancies with the chain-ofcustody,<br />
or concerns with the analysis will be addressed and resolved through the<br />
laboratory QA Manager.<br />
All analytical data shall be reviewed by the laboratory and shall include a minimum of<br />
three levels of documented review. An additional level of review shall be per<strong>for</strong>med by the<br />
laboratory on 5% of data to ensure system compliance. For each level, the review process<br />
shall be documented, signed, and dated by the reviewer. Each step of this review process<br />
shall include the evaluation of data quality based on both the results of the QC data and the<br />
professional judgment of those conducting the review.<br />
The first level of review, by the analyst, shall include QC review, method compliance, and<br />
documentation accuracy. For data that are manually processed, all steps in the computation<br />
shall be provided, including equations used and the source of input parameters such as<br />
response factors, dilution factors, and calibration constants, and shall be initialed and dated<br />
by the analyst and attached to the data sheets. For data entered into the computer, the<br />
analyst shall verify the sample-specific and project-specific in<strong>for</strong>mation (i.e. project<br />
numbers, sample numbers, units, and dilution factors).<br />
The second level of review shall be per<strong>for</strong>med by a supervisor, another analyst, or data<br />
review specialist. The function of this review is to provide an independent, complete peer<br />
review of the analytical data. This review shall include the review of QC per<strong>for</strong>mance,<br />
method compliance, documentation, calibrations, and identifications (IDs).<br />
A third level of review is per<strong>for</strong>med by the laboratory Program Manager, Quality<br />
Assurance Officer (QAO), or designee. This review shall provide a total overview of the<br />
data package to ensure its compliance with project requirements.<br />
Non-con<strong>for</strong>mance reports (NCRs) will be required <strong>for</strong> any errors noted. In all cases, an<br />
NCR shall be issued with the name of the individual reporting the issue, a description of<br />
the noncompliance issue, the corrective action taken, the date the issue was discovered, and<br />
the affected project samples. All employees are responsible <strong>for</strong> reporting the<br />
Final Sampling and Analysis Plan<br />
Installation Restoration Site 29, Hangar 1<br />
Former Naval Air Station, <strong>Moffett</strong> <strong>Field</strong>, <strong>Moffett</strong> <strong>Field</strong>,<br />
Cali<strong>for</strong>nia<br />
DCN: AMEC-8816-0005-0039<br />
April 2010<br />
Page 14-9
noncon<strong>for</strong>mance. The appropriate supervisor is responsible <strong>for</strong> assuring that the corrective<br />
actions are taken.<br />
14.7.5 Laboratory Analytical Data:<br />
The laboratory will prepare summary data packages and provide them to AMEC. The<br />
summary data package will consist of a case narrative, copies of all associated<br />
Contaminant of Concern (COC) <strong>for</strong>ms, sample results, and QA/QC summaries. The case<br />
narrative will identify the following in<strong>for</strong>mation:<br />
• Subcontractor name, project name, contract task order (CTO) number, sample<br />
delivery group (SDG) number, and a table that cross-reference client and laboratory<br />
sample ID numbers.<br />
• Detailed documentation of all sample shipping and receiving, preparation,<br />
analytical, and quality deficiencies.<br />
• Thorough explanation of all instances and manual integration.<br />
• Copies of all associated noncon<strong>for</strong>mance and corrective action <strong>for</strong>ms that will<br />
describe the nature of the deficiency and the corrective action taken.<br />
• Copies of all associated sample receipt notices.<br />
When a full data package is required, the laboratory will prepare data package that will<br />
contain all of the in<strong>for</strong>mation from the summary data package and all associated raw data.<br />
The laboratory will provide two copies of the summary package within 15 days after they<br />
receive the last sample in the SDG.<br />
Summary Data package requirements (Level III packages) are as follows:<br />
Organic Analysis<br />
• Cover page (with laboratory name, address, phone number, contact person, and<br />
SDG number)<br />
• Case narrative<br />
• Copies of noncon<strong>for</strong>mance and corrective action <strong>for</strong>ms<br />
• COC <strong>for</strong>ms<br />
• Copies of sample receipts notices<br />
• Analytical results including dilutions, re-analysis and confirmation of positive<br />
results <strong>for</strong> PCBs<br />
• System monitoring compound and surrogate recoveries<br />
Final Sampling and Analysis Plan<br />
Installation Restoration Site 29, Hangar 1<br />
Former Naval Air Station, <strong>Moffett</strong> <strong>Field</strong>, <strong>Moffett</strong> <strong>Field</strong>,<br />
Cali<strong>for</strong>nia<br />
DCN: AMEC-8816-0005-0039<br />
April 2010<br />
Page 14-10
• Matrix spike (MS) and matrix spike duplicate (MSD) recoveries and relative<br />
percent differences (RPDs)<br />
• Blank spike or laboratory control sample (LCS) recoveries<br />
• Method Blanks<br />
• Per<strong>for</strong>mance check<br />
• Initial calibration (ICAL) with retention time in<strong>for</strong>mation (When manual<br />
integration is per<strong>for</strong>med, raw data records shall include a complete audit trail <strong>for</strong><br />
those manipulations, raw data output showing the results of the manual integration,<br />
and notation of rationale, date and initials of person per<strong>for</strong>ming manual integration)<br />
• Continuing calibration (CCAL) with retention time in<strong>for</strong>mation<br />
• Internal standard areas and retention times<br />
• Analytical sequence<br />
Inorganic Analysis<br />
• Cover page (with laboratory name, address, phone number, contact person, and<br />
SDG number)<br />
• Case narrative<br />
• Copies of noncon<strong>for</strong>mance and corrective action <strong>for</strong>ms<br />
• COC <strong>for</strong>ms<br />
• Copies of sample receipts notices<br />
• Analytical results, including dilutions and re-analysis<br />
• Initial and continuing calibration verification (CCV)<br />
• Detection limit standard<br />
• Method blanks, CCAL blanks, and preparation blanks<br />
• Inductively coupled plasma (ICP) interference-check samples<br />
• MS and post-digestion spikes<br />
• Sample duplicates<br />
• LCSs<br />
• Method of standard additions<br />
• ICP serial dilution<br />
• Instrument detection limit<br />
Final Sampling and Analysis Plan<br />
Installation Restoration Site 29, Hangar 1<br />
Former Naval Air Station, <strong>Moffett</strong> <strong>Field</strong>, <strong>Moffett</strong> <strong>Field</strong>,<br />
Cali<strong>for</strong>nia<br />
DCN: AMEC-8816-0005-0039<br />
April 2010<br />
Page 14-11
• ICP interelement correction factors<br />
• ICP linear working range<br />
Full data package requirements (Level IV) are as follows:<br />
Organic Analysis<br />
• Cover page (with laboratory name, address, phone number, contact person, and<br />
SDG number)<br />
• Case narrative<br />
• Copies of noncon<strong>for</strong>mance and corrective action <strong>for</strong>ms<br />
• COC <strong>for</strong>ms<br />
• Copies of sample receipts notices<br />
• Analytical results (including dilutions, re-analysis and confirmation of positive<br />
results <strong>for</strong> PCBs) plus raw data<br />
• System monitoring compound and surrogate recoveries<br />
• MS and MSD recoveries and RPDs <strong>for</strong>m plus raw data<br />
• Blank spike or LCS recoveries <strong>for</strong>m plus raw data<br />
• Method Blanks <strong>for</strong>m plus raw data<br />
• Per<strong>for</strong>mance check<br />
• ICAL with retention time <strong>for</strong>m plus raw data (When manual integration is<br />
per<strong>for</strong>med, raw data records shall include a complete audit trail <strong>for</strong> those<br />
manipulations, raw data output showing the results of the manual integration, and<br />
notation of rationale, date and initials of person per<strong>for</strong>ming manual integration)<br />
• CCAL with retention time <strong>for</strong>m plus raw data<br />
• Internal standard areas and retention times plus raw data<br />
• Analytical sequence<br />
• Instrument analysis log<br />
Inorganic Analysis<br />
• Cover page (with laboratory name, address, phone number, contact person, and<br />
SDG number)<br />
• Case narrative<br />
Final Sampling and Analysis Plan<br />
Installation Restoration Site 29, Hangar 1<br />
Former Naval Air Station, <strong>Moffett</strong> <strong>Field</strong>, <strong>Moffett</strong> <strong>Field</strong>,<br />
Cali<strong>for</strong>nia<br />
DCN: AMEC-8816-0005-0039<br />
April 2010<br />
Page 14-12
• Copies of noncon<strong>for</strong>mance and corrective action <strong>for</strong>ms<br />
• COC <strong>for</strong>ms<br />
• Copies of sample receipts notices<br />
• Analytical results, including dilutions and re-analysis<br />
• Initial and CCV<br />
• Detection limit standard<br />
• Method blanks, CCAL blanks, and preparation blanks<br />
• ICP interference-check samples<br />
• MS and post-digestion spikes<br />
• Sample duplicates<br />
• LCSs<br />
• Method of standard additions<br />
• ICP serial dilution<br />
• Instrument detection limit<br />
• ICP interelement correction factors<br />
• ICP linear working range<br />
• % moisture <strong>for</strong> soil samples<br />
• Sample digestion, distillation, and preparation logs, as necessary<br />
• Instrument analysis log <strong>for</strong> each instrument used<br />
• Standard preparation logs, including initial and final concentrations <strong>for</strong> each<br />
standard used.<br />
• Formula and a sample calculation <strong>for</strong> the ICAL<br />
• Formula and a sample calculation <strong>for</strong> soil sample results<br />
14.7.6 Independent Data Validation:<br />
All analytical data will be independently validated by a subcontract validation. For<br />
investigation on IR projects <strong>for</strong> National Priorities List (NPL) sites, data will be randomly<br />
selected and validated at 80 percent level III and 20 percent level IV as described in<br />
NAVFAC SW Environmental Work Instruction #1 (SWDIV 2001). In this process,<br />
Final Sampling and Analysis Plan<br />
Installation Restoration Site 29, Hangar 1<br />
Former Naval Air Station, <strong>Moffett</strong> <strong>Field</strong>, <strong>Moffett</strong> <strong>Field</strong>,<br />
Cali<strong>for</strong>nia<br />
DCN: AMEC-8816-0005-0039<br />
April 2010<br />
Page 14-13
laboratory data are subjected to a comprehensive technically oriented evaluation by<br />
personnel experienced in the analysis and review of data from environmental matrices.<br />
For a Level III data validation ef<strong>for</strong>t, the data values <strong>for</strong> routine and QC samples are<br />
generally assumed to be correctly reported by the laboratory. Data quality is assessed by<br />
comparing QC parameters to the appropriate limits. In addition to per<strong>for</strong>ming data quality<br />
assessment <strong>for</strong> Level III, calculations of analytical values <strong>for</strong> routine and QC data are<br />
verified <strong>for</strong> Level IV data validation.<br />
14.7.7 Data Usability Assessment:<br />
Data will be evaluated by the AMEC Project Chemist <strong>for</strong> its use based on review of the<br />
data validation report, qualifications to the data, per<strong>for</strong>mance criteria, and any deviations<br />
from planned activities.<br />
Final Sampling and Analysis Plan<br />
Installation Restoration Site 29, Hangar 1<br />
Former Naval Air Station, <strong>Moffett</strong> <strong>Field</strong>, <strong>Moffett</strong> <strong>Field</strong>,<br />
Cali<strong>for</strong>nia<br />
DCN: AMEC-8816-0005-0039<br />
April 2010<br />
Page 14-14
WORKSHEET #15: REFERENCE LIMITS <strong>AND</strong> EVALUATION TABLE<br />
This worksheet identifies the project-required action limits and quantitation goals. Project<br />
Action Limits (PALs) are defined below in Tables 15-1 through 15-4.<br />
Table 15-1. Reference Limits and Evaluation <strong>for</strong> PCBs in Pre-construction<br />
Samples<br />
Matrix: Soil<br />
Analytical Group: PAHs<br />
Analyte<br />
Chemical<br />
Abstract<br />
Service<br />
(CAS)<br />
Number<br />
Project<br />
Action Limit<br />
(µg/kg)<br />
Project Action<br />
Limit<br />
Reference<br />
Project<br />
Quantitation<br />
Limit Goal 1<br />
(µg/kg)<br />
Laboratory-specific<br />
(ug/kg)<br />
QLs 1<br />
(µg/kg)<br />
Method<br />
Detection<br />
Limit 1<br />
(MDLs)<br />
(µg/kg)<br />
Aroclor 1016 12674-11-2 NE 40 CFR 761.61 2 50 10 2.7<br />
Aroclor 1221 11104-28-2 NE 40 CFR 761.61 2 50 10 5<br />
Aroclor 1232 11141-16-5 NE 40 CFR 761.61 2 50 10 1.2<br />
Aroclor 1242 53469-21-9 NE 40 CFR 761.61 2 50 10 1.6<br />
Aroclor 1248 12672-29-6 NE 40 CFR 761.61 2 50 10 1.2<br />
Aroclor 1254 11097-69-1 NE 40 CFR 761.61 2 50 10 0.78<br />
Aroclor 1260 11096-82-5 NE 40 CFR 761.61 2 50 10 2.2<br />
Aroclor 1268 11100-14-4 NE 40 CFR 761.61 2 50 10 5<br />
Total Aroclor -65 3 1,000 4 40 CFR 761.61 2 350 10 5<br />
Notes:<br />
1 Limits based on dry weight.<br />
2<br />
CFR 761.61 – self-implementing cleanup of PCB contaminated waste <strong>for</strong> high-occupancy area.<br />
3<br />
Total PCB is not registered in the CAS system. There<strong>for</strong>e, the Department of Navy assigned a number with the “-”<br />
prefix to be used <strong>for</strong> the NEDD.<br />
4 Total Arocolor will be determined by adding individual Aroclor concentrations. The laboratory will report detected<br />
concentration between MDL and QL as estimated. If an Aroclor is not detected, the MDL value will be used to<br />
determine total Arocolor concentration.<br />
Final Sampling and Analysis Plan<br />
Installation Restoration Site 29, Hangar 1<br />
Former Naval Air Station, <strong>Moffett</strong> <strong>Field</strong>, <strong>Moffett</strong> <strong>Field</strong>,<br />
Cali<strong>for</strong>nia<br />
DCN: AMEC-8816-0005-0039<br />
April 2010<br />
Page 15-1
Table 15-2. Reference Limits and Evaluation <strong>for</strong> PCB in Wipe Samples<br />
Matrix: Wipe<br />
Analytical Group: PCBs<br />
Analyte<br />
CAS<br />
Number<br />
Project Action<br />
Limit<br />
(µg/100cm 2 )<br />
Project Action<br />
Limit<br />
Reference<br />
Project<br />
Quantitation<br />
Limit Goal<br />
(µg/100cm 2 )<br />
Laboratory-specific<br />
(ug/kg)<br />
QLs<br />
(µg/100cm 2 )<br />
MDLs<br />
(µg/100cm 2 )<br />
Aroclor 1016 12674-11-2 NE 40 CFR 761.30 0.5 0.3 0.09<br />
Aroclor 1221 11104-28-2 NE 40 CFR 761.30 0.5 0.3 0.17<br />
Aroclor 1232 11141-16-5 NE 40 CFR 761.30 0.5 0.3 0.04<br />
Aroclor 1242 53469-21-9 NE 40 CFR 761.30 0.5 0.3 0.053<br />
Aroclor 1248 12672-29-6 NE 40 CFR 761.30 0.5 0.3 0.04<br />
Aroclor 1254 11097-69-1 NE 40 CFR 761.30 0.5 0.3 0.026<br />
Aroclor 1260 11096-82-5 NE 40 CFR 761.30 0.5 0.3 0.073<br />
Aroclor 1268 11100-14-4 NE 40 CFR 761.30 0.5 0.3 0.17<br />
Total Aroclor -65 1 10 2 40 CFR 761.30 3.5 0.3 0.17<br />
Notes:<br />
1<br />
Total PCB is not registered in the CAS system. There<strong>for</strong>e, the Navy assigned a number with the<br />
“- prefix to be used <strong>for</strong> the NEDD.<br />
2 Total Arocolor will be determined by adding individual Aroclor concentrations. The laboratory will report detected<br />
concentration between MDL and QL as estimated. If an Aroclor is not detected, the MDL value will be used to<br />
determine total Arocolor concentration.<br />
Final Sampling and Analysis Plan<br />
Installation Restoration Site 29, Hangar 1<br />
Former Naval Air Station, <strong>Moffett</strong> <strong>Field</strong>, <strong>Moffett</strong> <strong>Field</strong>,<br />
Cali<strong>for</strong>nia<br />
DCN: AMEC-8816-0005-0039<br />
April 2010<br />
Page 15-2
Table 15-3. Reference Limits and Evaluation <strong>for</strong> PCBs in Treated Water<br />
Samples<br />
Matrix: Water<br />
Analytical Group: PCBs<br />
Analyte<br />
CAS<br />
Number<br />
Project<br />
Action Limit<br />
(mg/L)<br />
Project Action<br />
Limit Reference<br />
Project<br />
Quantitation<br />
Limit Goal<br />
(mg/L)<br />
Laboratory-specific<br />
(ug/kg)<br />
QLs<br />
(mg/L)<br />
MDLs<br />
(mg/L)<br />
Aroclor 1016 12674-11-2 NE Sunnyvale POTW 0.04<br />
0.0004 0.0001<br />
Aroclor 1221 11104-28-2 NE Sunnyvale POTW 0.04<br />
0.0004 0.0001<br />
Aroclor 1232 11141-16-5 NE Sunnyvale POTW 0.04<br />
0.0004 0.0001<br />
Aroclor 1242 53469-21-9 NE Sunnyvale POTW 0.04<br />
0.0004 0.0001<br />
Aroclor 1248 12672-29-6 NE Sunnyvale POTW 0.04<br />
0.0004 0.0001<br />
Aroclor 1254 11097-69-1 NE Sunnyvale POTW 0.04<br />
0.0004 0.0001<br />
Aroclor 1260 11096-82-5 NE Sunnyvale POTW 0.04<br />
0.0004 0.0001<br />
Aroclor 1268 11100-14-4 NE Sunnyvale POTW 0.04<br />
0.0004 0.0001<br />
Total Aroclor -65 1 1.0 2 Sunnyvale POTW 0.3<br />
0.0004 0.0001<br />
Notes:<br />
1<br />
Total PCB is not registered in the CAS system. There<strong>for</strong>e, the Navy assigned a number with the<br />
“-” prefix to be used <strong>for</strong> the NEDD.<br />
2 Total Arocolor will be determined by adding individual Aroclor concentrations. The laboratory will report detected<br />
concentration between MDL and QL as estimated. If an Aroclor is not detected, the MDL value will be used to<br />
determine total Arocolor concentration.<br />
Final Sampling and Analysis Plan<br />
Installation Restoration Site 29, Hangar 1<br />
Former Naval Air Station, <strong>Moffett</strong> <strong>Field</strong>, <strong>Moffett</strong> <strong>Field</strong>,<br />
Cali<strong>for</strong>nia<br />
DCN: AMEC-8816-0005-0039<br />
April 2010<br />
Page 15-3
Table 15-4. Reference Limits and Evaluation <strong>for</strong> Metals in Import Soil<br />
Matrix: Soil<br />
Analytical Group: Metals<br />
Analyte<br />
CAS<br />
Number<br />
Project<br />
Action<br />
Limit<br />
(mg/kg)<br />
Antimony 7440.36-0 380<br />
Project Action<br />
Limit Reference<br />
Industrial<br />
Cali<strong>for</strong>nia Human<br />
Health Screening<br />
Levels (CHHSLs)<br />
Project<br />
Quantitation<br />
Limit Goal 1<br />
(mg/kg)<br />
Laboratory-specific<br />
(ug/kg)<br />
QLs 1<br />
(mg/kg)<br />
MDLs 1<br />
(mg/kg)<br />
140 0.5 0.033<br />
Arsenic 7440-38-2 0.24 2 Industrial CHHSL 0.5 0.5 0.12<br />
Barium 7440-39-3 190000<br />
Industrial Regional<br />
Screening Level<br />
(RSL)<br />
64000 0.25 0.095<br />
Beryllium 7440-41-7 1700 Industrial CHHSL 650 0.25 0.064<br />
Cadmium 7440-43-9 7.5 Industrial CHHSL 250 0.25 0.033<br />
Chromium 7440-47-3 1400 Industrial RSL 450 0.75 0.21<br />
Cobalt 7440-48-4 300 Industrial RSL 100 0.25 0.016<br />
Copper 7440-50-8 38000 Industrial CHHSL 13500 0.5 0.17<br />
Lead 7439-92-1 320 Industrial CHHSL 100 0.25 0.038<br />
Mercury 7439-97-6 180 Industrial CHHSL 1700 0.48 0.014<br />
Molybdenum 7439-98-7 310 Industrial RSL 100 0.25 0.033<br />
Nickel 7440-02-0 16000 Industrial CHHSL 6500 0.5 0.037<br />
Final Sampling and Analysis Plan<br />
Installation Restoration Site 29, Hangar 1<br />
Former Naval Air Station, <strong>Moffett</strong> <strong>Field</strong>, <strong>Moffett</strong> <strong>Field</strong>,<br />
Cali<strong>for</strong>nia<br />
DCN: AMEC-8816-0005-0039<br />
April 2010<br />
Page 15-4
Analyte<br />
CAS<br />
Number<br />
Project<br />
Action<br />
Limit<br />
(mg/kg)<br />
Project Action<br />
Limit Reference<br />
Project<br />
Quantitation<br />
Limit Goal 1<br />
(mg/kg)<br />
Laboratory-specific<br />
(ug/kg)<br />
QLs 1<br />
(mg/kg)<br />
MDLs 1<br />
(mg/kg)<br />
Selenium 7782-49-2 4800 Industrial CHHSL 1700 0.5 0.065<br />
Silver 7440-22-4 4800 Industrial CHHSL 1700 0.25 0.032<br />
Thallium 7440-28-0 63 Industrial CHHSL 35 0.25 0.037<br />
Vanadium 7440-62-2 6700 Industrial CHHSL 2400 0.75 0.28<br />
Zinc 7440-66-6 100000 Industrial CHHSL 103000 1.3 0.46<br />
Notes:<br />
1<br />
Limits based on dry weight.<br />
2<br />
The laboratory will report detected concentration above the MDL with a qualifier.<br />
Final Sampling and Analysis Plan<br />
Installation Restoration Site 29, Hangar 1<br />
Former Naval Air Station, <strong>Moffett</strong> <strong>Field</strong>, <strong>Moffett</strong> <strong>Field</strong>,<br />
Cali<strong>for</strong>nia<br />
DCN: AMEC-8816-0005-0039<br />
April 2010<br />
Page 15-5
Table 15-5. Reference Limits and Evaluation <strong>for</strong> PAHs in Import Soil<br />
Matrix: Soil<br />
Analytical Group: PAHs<br />
Analyte<br />
CAS<br />
Number<br />
Project<br />
Action Limit<br />
(ug/kg)<br />
Project Action<br />
Limit Reference<br />
Project<br />
Quantitation<br />
Limit Goal<br />
(ug/kg)<br />
Laboratory-specific<br />
(ug/kg)<br />
QLs 1 MDLs 1<br />
Acenaphthene 83-32-9 33,000,000 Industrial RSL 10,000,000 200 60<br />
Anthracene 120-12-7 170,000,000 Industrial RSL 60,000,000 200 60<br />
Benz(a)anthracene 56-55-3 2,100 Industrial RSL 700 200 60<br />
Benzo(a)pyrene 50-32-8 130 2 CHHSL 130 200 60<br />
Benzo(b)fluoranthene 205-99-2 2,100 Industrial RSL 700 200 60<br />
Benzo(k)fluoranthene 207-08-9 21,000 Industrial RSL 7000 200 60<br />
Chrysene 218-01-9 210,000 Industrial RSL 70,000 200 60<br />
Dibenz(a,h)anthracene 53-70-3 210 Industrial RSL 150 200 60<br />
Fluoranthene 206-44-0 22,000,000 Industrial RSL 7,000,000 200 60<br />
Fluorene 86-73-7 22,000,000 Industrial RSL 7,000,000 200 60<br />
Indeno(1,2,3-cd)pyrene 193-39-5 2,100 Industrial RSL 700 200 60<br />
Naphthalene 91-20-3 18,000 Industrial RSL 6,000 200 60<br />
Pyrene 129-00-0 17,000,000 Industrial RSL 5,000,000 200 60<br />
Notes:<br />
1 Limits based on dry weight.<br />
2 The aboratory will report detected concentration above the MDL with a qualifier.<br />
Final Sampling and Analysis Plan<br />
Installation Restoration Site 29, Hangar 1<br />
Former Naval Air Station, <strong>Moffett</strong> <strong>Field</strong>, <strong>Moffett</strong> <strong>Field</strong>,<br />
Cali<strong>for</strong>nia<br />
DCN: AMEC-8816-0005-0039<br />
April 2010<br />
Page 15-6
Table 15-6. Reference Limits and Evaluation <strong>for</strong> Semi-volatile Organics in<br />
Import Soil<br />
Matrix: Soil<br />
Analytical Group: SVOCs<br />
Analyte<br />
CAS<br />
Number<br />
Project Action<br />
Limit<br />
(mg/kg)<br />
Project Action<br />
Limit<br />
Reference1<br />
Project<br />
Quantitation<br />
Limit Goal<br />
(mg/kg)<br />
Laboratoryspecific<br />
QLs 1<br />
(mg/kg)<br />
MDLs 1<br />
(mg/kg)<br />
1,2,4-Trichlorobenzene 120-82-1 99 Industrial PRG 33 0.20 0.060<br />
1,2-Dichlorobenzene 95-50-1 9,800 Industrial PRG 330 0.20 0.060<br />
1,4-Dichlorobenzene 106-46-7 12 Industrial PRG 4.0 0.20 0.060<br />
2,4,5-Trichlorophenol 95-95-4 62,000 Industrial PRG 20,000 0.40 0.10<br />
2,4,6-Trichlorophenol 88-06-2 160 Industrial PRG 50 0.40 0.020<br />
2,4-Dichlorophenol 120-83-2 1,800 Industrial PRG 600 0.20 0.060<br />
2,4-Dimethylphenol 105-67-9 12,000 Industrial PRG 4,000 0.20 0.060<br />
2,4-Dinitrophenol 51-28-5 1,200 Industrial PRG 400 1.0 0.30<br />
2,4-Dinitrotoluene 121-14-2 5.5 Industrial PRG 1.8 0.20 0.060<br />
2,6-Dinitrotoluene 606-20-2 620 Industrial PRG 200 0.20 0.060<br />
2-Chloronaphthalene 91-58-7 82,000 Industrial PRG 27,000 0.20 0.060<br />
2-Chlorophenol 95-57-8 5,100 Industrial PRG 1,700 0.20 0.060<br />
2-Methylphenol 95-48-7 31,000 Industrial PRG 10,000 0.20 0.060<br />
2-Nitroaniline 88-74-4 6,000 Industrial PRG 2000 0.20 0.060<br />
3,3’-Dichlorobenzidine 91-94-1 3.8 Industrial PRG 1.0 0.40 0.10<br />
4,6-Dinitro-2-methylphenol 534-52-1 62 Industrial PRG 20 1.0 0.30<br />
4-Chloroaniline 106-47-8 8.6 Industrial PRG 3.0 0.40 0.10<br />
3-&4-Methylphenol<br />
108-39-4<br />
/106-44-5<br />
3,100 Industrial PRG 1,000 0.40 0.10<br />
4-Nitroaniline 100-01-6 86 Industrial PRG 28 0.40 0.10<br />
bis(2-Chloroethyl)Ether 111-44-4 1 Industrial PRG 0.5 0.20 0.060<br />
Final Sampling and Analysis Plan<br />
Installation Restoration Site 29, Hangar 1<br />
Former Naval Air Station, <strong>Moffett</strong> <strong>Field</strong>, <strong>Moffett</strong> <strong>Field</strong>,<br />
Cali<strong>for</strong>nia<br />
DCN: AMEC-8816-0005-0039<br />
April 2010<br />
Page 15-7
Analyte<br />
CAS<br />
Number<br />
Project Action<br />
Limit<br />
(mg/kg)<br />
Project Action<br />
Limit<br />
Reference1<br />
Project<br />
Quantitation<br />
Limit Goal<br />
(mg/kg)<br />
Laboratoryspecific<br />
QLs 1<br />
(mg/kg)<br />
MDLs 1<br />
(mg/kg)<br />
bis(2-Ethylhexyl) phthalate 117-81-7 120 Industrial PRG 40 0.40 0.10<br />
Butylbenzylphthalate 85-68-7 910 Industrial PRG 300 0.20 0.060<br />
Diethylphthalate 84-66-2 490,000 Industrial PRG 163,000 0.20 0.060<br />
Di-n-butylphthalate 84-74-2 62,000 Industrial PRG 20,000 0.20 0.060<br />
Hexachlorobenzene 118-74-1 1.1 Industrial PRG 1.0 0.20 0.060<br />
Hexachlorobutadiene 87-68-3 22 Industrial PRG 7 0.20 0.060<br />
Hexachlorocyclopentadiene 77-47-4 3,700 Industrial PRG 1200 0.20 0.060<br />
Hexachloroethane 67-72-1 120 Industrial PRG 40 0.20 0.060<br />
Isophorone 78-59-1 1,800 Industrial PRG 600 0.20 0.060<br />
Nitrobenzene 98-95-3 24 Industrial PRG 8.0 0.20 0.060<br />
N-nitrosodi-N-propylamine 621-64-7 0.25 Industrial PRG 0.2 0.20 0.060<br />
N-nitrosodiphenylamine 86-30-6 350 Industrial PRG 110 0.20 0.060<br />
Pentachlorophenol 87-86-5 9 Industrial PRG 3 0.40 0.020<br />
Phenol 108-95-2 180,000 Industrial PRG 60,000 0.20 0.060<br />
Notes:<br />
1<br />
Limits based on dry weight.<br />
Final Sampling and Analysis Plan<br />
Installation Restoration Site 29, Hangar 1<br />
Former Naval Air Station, <strong>Moffett</strong> <strong>Field</strong>, <strong>Moffett</strong> <strong>Field</strong>,<br />
Cali<strong>for</strong>nia<br />
DCN: AMEC-8816-0005-0039<br />
April 2010<br />
Page 15-8
Table 15-7. Reference Limits and Evaluation <strong>for</strong> TPHs in Import Soil<br />
Matrix: Soil<br />
Analytical Group: TPHs<br />
Analyte<br />
CAS<br />
Number<br />
Project<br />
Action<br />
Limit<br />
(mg/kg)<br />
Project Action<br />
Limit Reference<br />
Project<br />
Quantitation<br />
Limit Goal 1<br />
(mg/kg)<br />
Laboratory-specific<br />
QLs 1<br />
(mg/kg)<br />
MDLs 1<br />
(mg/kg)<br />
Gasoline -3534 2 180 ESL 3 2 20 5.0<br />
Diesel<br />
(C 10 to C 24 )<br />
-3527 2 180 ESL 3 15 10 1.2<br />
Notes:<br />
1 Limits based on dry weight.<br />
2<br />
TPH is a multi-component chemical substance and not registered in the Chemical Abstract Service system. There<strong>for</strong>e,<br />
the Navy assigned a number with the “-“ prefix to be used <strong>for</strong> the NEDD.<br />
3<br />
Environmental Screening Levels <strong>for</strong> Shallow Soils where Groundwater is Not a Current or Potential Source of<br />
Drinking Water (RWQCB 2008)<br />
Table 15-8. Reference Limits and Evaluation <strong>for</strong> Lead in Wipe Samples<br />
Matrix: Wipe<br />
Analytical Group: Lead<br />
Analyte<br />
CAS<br />
Number<br />
Project Action<br />
Limit<br />
(µg/ft 2 )<br />
Project Action<br />
Limit<br />
Reference<br />
Project<br />
Quantitation Limit<br />
Goal<br />
(µg/ft 2 )<br />
Laboratory-specific<br />
QLs<br />
(µg/ft 2 )<br />
MDLs<br />
(µg/ft 2 )<br />
Lead 7439-92-1 40 TSCA 403 13 0.75 0.114<br />
Final Sampling and Analysis Plan<br />
Installation Restoration Site 29, Hangar 1<br />
Former Naval Air Station, <strong>Moffett</strong> <strong>Field</strong>, <strong>Moffett</strong> <strong>Field</strong>,<br />
Cali<strong>for</strong>nia<br />
DCN: AMEC-8816-0005-0039<br />
April 2010<br />
Page 15-9
Table 15-9. Reference Limits and Evaluation <strong>for</strong> pH in Treated Water<br />
Matrix: Water<br />
Analytical Group: pH<br />
Analyte<br />
CAS<br />
Number<br />
Project Action<br />
Limit<br />
(pH units)<br />
Project Action<br />
Limit<br />
Reference<br />
Project<br />
Quantitation<br />
Limit Goal<br />
(pH units)<br />
Laboratory-specific<br />
QLs<br />
(pH units)<br />
MDLs<br />
(pH units)<br />
pH -9 6.0-10.5<br />
Sunnyvale<br />
POTW<br />
2.0-13.0 NA NA<br />
Table 15-10. Reference Limits and Evaluation <strong>for</strong> Asbestos in Soil/Sediment<br />
Samples<br />
Matrix: Soil/Sediment<br />
Analytical Group: Asbestos<br />
Analyte<br />
CAS<br />
Number<br />
Project Action<br />
Limit<br />
(percent)<br />
Project Action<br />
Limit<br />
Reference<br />
Project<br />
Quantitation<br />
Limit Goal<br />
(percent)<br />
Laboratory-specific<br />
QLs<br />
(percent)<br />
MDLs<br />
(percent)<br />
Asbestos 1332-21-4 0.25<br />
Recommended<br />
by EPA<br />
NA 0.25 NA<br />
Table 15-11. Reference Limits and Evaluation <strong>for</strong> Metals in Treated Water<br />
Samples<br />
Matrix: Water<br />
Analytical Group: Metals<br />
Analyte<br />
CAS<br />
Number<br />
Project Action<br />
Limit<br />
(mg/L)<br />
Project Action<br />
Limit<br />
Reference<br />
Project<br />
Quantitation<br />
Limit Goal<br />
(mg/L)<br />
Laboratory-specific<br />
QLs<br />
(mg/L)<br />
MDLs<br />
(mg/L)<br />
Lead 7439-92-1 0.5<br />
Chromium 7440-47-3 1.7<br />
Zinc 7440-66-6 1.48<br />
Sunnyvale<br />
POTW<br />
Sunnyvale<br />
POTW<br />
Sunnyvale<br />
POTW<br />
0.15 0.001 0.00019<br />
0.5 0.003 0.00064<br />
0.5 0.01 0.0032<br />
Final Sampling and Analysis Plan<br />
Installation Restoration Site 29, Hangar 1<br />
Former Naval Air Station, <strong>Moffett</strong> <strong>Field</strong>, <strong>Moffett</strong> <strong>Field</strong>,<br />
Cali<strong>for</strong>nia<br />
DCN: AMEC-8816-0005-0039<br />
April 2010<br />
Page 15-10
WORKSHEET #16: PROJECT SCHEDULE<br />
Project schedule <strong>for</strong> <strong>Moffett</strong> Hangar 1 demolition activities has been developed and is presented<br />
as Figure 3.<br />
Final Sampling and Analysis Plan<br />
Installation Restoration Site 29, Hangar 1<br />
Former Naval Air Station, <strong>Moffett</strong> <strong>Field</strong>, <strong>Moffett</strong> <strong>Field</strong>,<br />
Cali<strong>for</strong>nia<br />
DCN: AMEC-8816-0005-0039<br />
April 2010<br />
Page 16-1
This page left intentionally blank.<br />
Final Sampling and Analysis Plan<br />
Installation Restoration Site 29, Hangar 1<br />
Former Naval Air Station, <strong>Moffett</strong> <strong>Field</strong>, <strong>Moffett</strong> <strong>Field</strong>,<br />
Cali<strong>for</strong>nia<br />
DCN: AMEC-8816-0005-0039<br />
April 2010<br />
Page 16-2
WORKSHEET #17: <strong>SAMPLING</strong> DESIGN <strong>AND</strong> RATIONALE<br />
Samples collected during this project will include baseline soil/sediment samples collected<br />
prior to construction and confirmation soil, wipe, and sediment samples collected once the<br />
removal action is completed. Details on the sampling design and rationale are presented<br />
below.<br />
Baseline/Pre-Construction Samples:<br />
Pre-construction samples will be collected from soil areas immediately adjacent to Hangar<br />
1 and from the sediment in the stormwater trench/conveyance system around the perimeter<br />
of Hangar 1. The purpose of the pre-construction soil and sediment samples is to establish<br />
baseline concentrations of PCBs, lead, and asbestos. Baseline/pre-construction<br />
concentrations will be compared to confirmation soil samples to verify that contaminants<br />
were not released into the environment as the result of the removal action.<br />
The scope of the soil sampling ef<strong>for</strong>t is restricted to the area of the soil immediately<br />
adjacent to (east of) Hangar 1. This area is approximately 21,000 ft 2 . The rationale <strong>for</strong><br />
limiting the soil sampling ef<strong>for</strong>t to this area is based on the following:<br />
• This is the only unpaved area within the project site.<br />
• Hangar 1 is surrounded by a perimeter storm water collection trench which<br />
prevents surface water from leaving the project site.<br />
• The nearest unpaved area is 300 feet North of Hangar 1.<br />
• Hangar 1 is in an industrial land use area and there are no sensitive habitats nearby<br />
(see Worksheet 10).<br />
Soil samples will be collected from 51 locations from soil areas on the east side of the<br />
Hangar. Sample locations are shown in Figure 11-1. At each location, soil samples will be<br />
collected from 0-6 inches (surface) and 6-12 inches below ground surface (bgs). Surface<br />
samples will be analyzed <strong>for</strong> PCBs, lead, and asbestos. If the concentration of PCBs in the<br />
surface sample is above 1000 ug/kg, then the 6-12 inch sample will be analyzed <strong>for</strong> PCBs<br />
to determine the vertical extent of the PCB contamination. Additional samples will be<br />
collected at 6-inch intervals to determine the depth of PCB contamination. Results of<br />
baseline/pre-construction samples will be provided to EPA and Water Board <strong>for</strong><br />
consultation and concurrence on areas requiring soil removal if PCB concentrations exceed<br />
1000 ug/kg.<br />
Four baseline/pre-construction sediment samples will also be collected from the<br />
stormwater trench/conveyance system. Locations will be selected based on where there is a<br />
sufficient amount of sediment present <strong>for</strong> sample collection. Soil and sediment samples<br />
will be collected using the procedure described in Worsheet 14.<br />
Final Sampling and Analysis Plan<br />
Installation Restoration Site 29, Hangar 1<br />
Former Naval Air Station, <strong>Moffett</strong> <strong>Field</strong>, <strong>Moffett</strong> <strong>Field</strong>,<br />
Cali<strong>for</strong>nia<br />
DCN: AMEC-8816-0005-0039<br />
April 2010<br />
Page 17-1
The action level <strong>for</strong> baseline/pre-construction sampling is PCB concentrations above 1000<br />
ug/kg, which is selected based on the EPA self-implementing, on-site, cleanup requirement<br />
<strong>for</strong> high occupancy areas. Soil that exceeds the PCB action level will be removed and<br />
disposed off site. For each sample location that exceeds the PCB action level, the<br />
surrounding soil will be removed half way to the next clean location, in each direction.<br />
Excavation depth will be determined based on baseline/pre-construction sampling results.<br />
Laterally, soil will be removed half way to the next clean location. Following soil removal,<br />
confirmation samples will be collected from the bottom of the excavation, at the center and<br />
on all four sides of the excavation. If the concentration of PCBs in a confirmation sample<br />
is above 1000 ug/kg, then an additional 6-inches of soil will be removed from the bottom<br />
of the excavation. This step will be repeated until the result of the confirmation sample<br />
indicates that the concentration of PCBs in soil is below 1000 ug/kg. Soil samples will be<br />
collected using the procedure described in Worksheet 14.<br />
Post-Construction Confirmation Samples:<br />
Upon completion of the Hangar 1 removal action, post-construction confirmation samples<br />
will be collected from the soil areas to demonstrate that the removal action has not released<br />
contaminants at the site.<br />
For soil areas that do not require removal of PCB contaminated soil based on<br />
baseline/preconstruction sample results, post-construction confirmation samples will be<br />
collected where baseline/preconstruction samples were taken previously, and analyzed <strong>for</strong><br />
PCBs, lead and asbestos.<br />
For areas where PCB contaminated soil were removed, one sample from the bottom of the<br />
excavation will be collected and analyzed <strong>for</strong> lead and asbestos. If results indicate that<br />
post-construction confirmation results exceed pre-construction (in addition to the PCB<br />
confirmation samples analyzed during the soil removal) concentrations, the Navy will<br />
consult with EPA and the Water Board to determine the appropriate response action (see<br />
Figure 4, Decision Tree <strong>for</strong> Soil Sample).<br />
The scope of work <strong>for</strong> the Hangar 1 removal action includes the removal of sediment from<br />
the stormwater trench/conveyance system and the subsequent pressure washing of the<br />
trenches, there<strong>for</strong>e; it is highly unlikely that sediment will be present <strong>for</strong> post-construction<br />
confirmation sampling (See Figure 5, Decision Tree <strong>for</strong> Sediment Samples).<br />
Post-construction/confirmation samples will also be collected from the floor of Hangar 1<br />
once the removal action has been completed. Thirty-seven concrete wipe samples will be<br />
collected from the floor of Hangar 1. The purpose of the concrete wipe samples is to<br />
confirm that the PCB and lead concentrations of the floor are within the regulatory limits<br />
of 10 µg/100cm 2 <strong>for</strong> PCBs and 40 µg/ft 2 <strong>for</strong> lead. If the concrete wipe samples exceed the<br />
Final Sampling and Analysis Plan<br />
Installation Restoration Site 29, Hangar 1<br />
Former Naval Air Station, <strong>Moffett</strong> <strong>Field</strong>, <strong>Moffett</strong> <strong>Field</strong>,<br />
Cali<strong>for</strong>nia<br />
DCN: AMEC-8816-0005-0039<br />
April 2010<br />
Page 17-2
PCBs and/or lead regulatory limits, the concrete floor will be re-washed and resampled<br />
(See Figure 6, Decision Tree <strong>for</strong> Wipe Samples). Concrete wipe samples will be collected<br />
using the procedure described in Worksheet 14. Figure 11-2 presents the Concrete Wipe<br />
Sample Locations.<br />
Treated Water Samples:<br />
Waste water generated by the Hangar 1 removal action will be treated onsite. Waste water<br />
will be sampled every 120,000 gallons, which is estimated to take 4 to 6 weeks to generate.<br />
The sample will be analyzed <strong>for</strong> PCBs, chromium, zinc, lead, asbestos, and pH, as required<br />
by the Sunnyvale POTW discharge permit. Once the waste water has been treated to<br />
Sunnyvale limits, it will be discharged to the POTW.<br />
Import Soil:<br />
After contaminated soil has been removed, the excavation will be backfilled with clean soil<br />
obtained from a suitable source. Prior to being used as backfill, the clean soil will be<br />
sampled and analyzed <strong>for</strong> PCBs, metals, total petroleum hydrocarbons, semi-volatile<br />
organic compounds, and polyaromatic hydrocarbons, asbestos, and pH. One sample will be<br />
collected from the clean soil per 250 yd 3 , as recommended by the DTSC In<strong>for</strong>mation<br />
Advisory Clean Imported Fill Material. It is anticipated that approximately 400 cubic yards<br />
(yd 3 ) of clean soil would be used as backfill if the entire volume of soil were removed.<br />
Final Sampling and Analysis Plan<br />
Installation Restoration Site 29, Hangar 1<br />
Former Naval Air Station, <strong>Moffett</strong> <strong>Field</strong>, <strong>Moffett</strong> <strong>Field</strong>,<br />
Cali<strong>for</strong>nia<br />
DCN: AMEC-8816-0005-0039<br />
April 2010<br />
Page 17-3
Figure 17-1. Decision Tree <strong>for</strong> Soil Samples<br />
Final Sampling and Analysis Plan<br />
Installation Restoration Site 29, Hangar 1<br />
Former Naval Air Station, <strong>Moffett</strong> <strong>Field</strong>, <strong>Moffett</strong> <strong>Field</strong>,<br />
Cali<strong>for</strong>nia<br />
DCN: AMEC-8816-0005-0039<br />
April 2010<br />
Page 17-4
Figure 17-2. Decision Tree <strong>for</strong> Sediment Samples<br />
Final Sampling and Analysis Plan<br />
Installation Restoration Site 29, Hangar 1<br />
Former Naval Air Station, <strong>Moffett</strong> <strong>Field</strong>, <strong>Moffett</strong> <strong>Field</strong>,<br />
Cali<strong>for</strong>nia<br />
DCN: AMEC-8816-0005-0039<br />
April 2010<br />
Page 17-5
Figure 17-3. Decision Tree <strong>for</strong> Wipe Samples<br />
Final Sampling and Analysis Plan<br />
Installation Restoration Site 29, Hangar 1<br />
Former Naval Air Station, <strong>Moffett</strong> <strong>Field</strong>, <strong>Moffett</strong> <strong>Field</strong>,<br />
Cali<strong>for</strong>nia<br />
DCN: AMEC-8816-0005-0039<br />
April 2010<br />
Page 17-6
WORKSHEET #18: <strong>SAMPLING</strong> LOCATIONS <strong>AND</strong> METHODS/SOP<br />
REQUIREMENTS TABLE<br />
This worksheet provides a list of all anticipated sample locations and corresponding<br />
analyses and a reference to the applicable collection SOP(s) provided in Appendix A.<br />
Sampling<br />
Location/ID<br />
Number 1<br />
PC-SO-001<br />
through PC-SO-<br />
101<br />
Matrix<br />
Soil<br />
Sampling<br />
Interval<br />
Analytical<br />
Group(s)<br />
Pre-Construction Samples<br />
Pre-Construction<br />
PCB, Lead,<br />
Asbestos<br />
Sampling<br />
Frequency<br />
Anticipated<br />
Number of<br />
Samples<br />
1 102<br />
Sampling<br />
SOP<br />
Reference<br />
Worksheet<br />
14<br />
PC-SD-001<br />
through 004<br />
CO-SO-200<br />
through 250<br />
CO-W-500<br />
through 540<br />
Sediment<br />
Soil<br />
Surface<br />
Wipe<br />
PCB, Lead,<br />
Pre-Construction<br />
Asbestos<br />
Confirmation Soil Samples<br />
PCB, Lead,<br />
Confirmation<br />
Asbestos<br />
Confirmation Wipe Samples<br />
1 4<br />
1 51<br />
Confirmation PCB, Lead 1 41<br />
Import Soil Samples<br />
PCBs,<br />
A-clean-ddmmyy Soil Import soil<br />
Metals,<br />
Asbestos,<br />
pH<br />
NA 2<br />
Treated Water Samples<br />
PCBs,<br />
Chromium, One every<br />
A-TW-ddmmyy Water Treated water Zinc, lead, 120,000 13<br />
asbestos, gallons<br />
and pH<br />
Notes:<br />
1 Please refer to Worksheet 27 <strong>for</strong> a detailed description of the project sample naming scheme<br />
Worksheet<br />
14<br />
Worksheet<br />
14<br />
Worksheet<br />
14<br />
Worksheet<br />
14<br />
Worksheet<br />
14<br />
Final Sampling and Analysis Plan<br />
Installation Restoration Site 29, Hangar 1<br />
Former Naval Air Station, <strong>Moffett</strong> <strong>Field</strong>, <strong>Moffett</strong> <strong>Field</strong>,<br />
Cali<strong>for</strong>nia<br />
DCN: AMEC-8816-0005-0039<br />
April 2010<br />
Page 18-1
This page left intentionally blank.<br />
Final Sampling and Analysis Plan<br />
Installation Restoration Site 29, Hangar 1<br />
Former Naval Air Station, <strong>Moffett</strong> <strong>Field</strong>, <strong>Moffett</strong> <strong>Field</strong>,<br />
Cali<strong>for</strong>nia<br />
DCN: AMEC-8816-0005-0039<br />
April 2010<br />
Page 18-2
WORKSHEET #19: ANALYTICAL SOP REQUIREMENTS TABLE<br />
This worksheet presents the analytical and preparation method/SOP and associated<br />
container specifications, preservation requirements, and maximum holding time <strong>for</strong> each<br />
matrix and analytical group.<br />
Matrix<br />
Wipe<br />
Wipe<br />
Soil<br />
Soil<br />
Soil<br />
Soil<br />
Analytical<br />
Group<br />
PCBs<br />
Lead<br />
PCBs<br />
Lead<br />
SVOCs<br />
PAHs<br />
TPHs<br />
Table 19-1. Analytical SOP Requirements<br />
Preparation and<br />
Analytical Method/<br />
SOP Reference<br />
EPA Method<br />
3550B/8082<br />
BCPREP0002/<br />
BCORG019<br />
EPA Method<br />
3050B/6010B<br />
BCPREP015/<br />
BCMET013<br />
EPA Method<br />
3550B/8082<br />
BCPREP0002/<br />
BCORG019<br />
EPA Method<br />
3050B/6020,6010B<br />
BCPREP015/<br />
BCMET013<br />
EPA Method<br />
3550B/8270C<br />
BCPREP0002/BCO<br />
RG020<br />
EPA Method<br />
3550B/8015B<br />
BCPREP0002/BCO<br />
RG005<br />
Soil Asbestos CARB 435 /TBD<br />
Sediment<br />
Sediment<br />
PCBs<br />
Lead<br />
EPA Method<br />
3550B/8082<br />
BCPREP0002/<br />
BCORG019<br />
EPA Method<br />
3050B/6010B<br />
BCPREP015/<br />
BCMET013<br />
Sediment Asbestos CARB 435 /TBD<br />
Water<br />
PCBs<br />
EPA Method<br />
3520C/8082<br />
BCPREP001/<br />
BCORG019<br />
Containers<br />
8 oz glass<br />
jar<br />
8 oz glass<br />
jar<br />
8 oz glass<br />
jar<br />
4 oz glass<br />
gar<br />
8 oz glass<br />
jar<br />
8 oz glass<br />
jar<br />
4 oz glass<br />
gar<br />
1 L amber<br />
bottle<br />
Minimum<br />
Sample<br />
Volume 2<br />
10 X 10<br />
cm<br />
Preservation<br />
Requirements<br />
Matrix<br />
Water<br />
Water<br />
Analytical<br />
Group<br />
Chromium<br />
,Zinc,<br />
Lead<br />
pH<br />
Preparation and<br />
Analytical Method/<br />
SOP Reference<br />
EPA Method<br />
3010A/ 6010B<br />
BCPREP0006/<br />
BCMET013<br />
EPA Method 150.1<br />
/BCGEN065<br />
Containers<br />
250 ml Poly<br />
bottle<br />
250 ml Poly<br />
bottle<br />
Minimum<br />
Sample<br />
Volume 2<br />
100 ml<br />
Preservation<br />
Requirements<br />
pH < 2 with<br />
HNO 3<br />
WORKSHEET #20: FIELD QUALITY CONTROL SAMPLE SUMMARY<br />
<strong>Field</strong> QC samples serve as a check on the precision and accuracy of analytical methods and instrumentation, and potential<br />
contamination that may occur during laboratory sample preparation and analyses.<br />
Matrix<br />
Analytical<br />
Group<br />
No. of<br />
Sampling<br />
Events<br />
Table 20-1. <strong>Field</strong> Quality Control Sample Summary<br />
No. of <strong>Field</strong><br />
Duplicates<br />
No. of<br />
MS/MSDs<br />
No. of<br />
<strong>Field</strong><br />
Blanks<br />
No. of Equip.<br />
Blanks<br />
No. of VOA<br />
Trip Blanks<br />
No. of PT<br />
Samples<br />
Anticipated<br />
No. of<br />
Samples to<br />
Lab<br />
Soil PCBs 155 1 16 8 0 0 0 0 179<br />
Soil Lead 104 1 11 6 0 0 0 0 121<br />
Soil Asbestos 104 1 11 0 0 0 0 0 121<br />
Soil SVOCs 2 0 1 0 0 0 0 3<br />
Soil PAHs 2 0 1 0 0 0 0 3<br />
Soil TPHs 2 0 1 0 0 0 0 3<br />
Sediment PCBs 8 1 1 0 0 0 0 10<br />
Sediment Lead 8 1 1 0 0 0 0 10<br />
Sediment Asbestos 8 1 0 0 0 0 0 10<br />
Wipe PCBs 41 2 0 0 2 0 0 0 43<br />
Wipe Lead 41 2 0 0 2 0 0 0 43<br />
Notes:<br />
1<br />
Total number of soil sample will increase if excavation is necessary.<br />
2<br />
Additional wipe samples will be collected if decontamination of the Hangar floor is warranted.<br />
Final Sampling and Analysis Plan<br />
Installation Restoration Site 29, Hangar 1<br />
Former Naval Air Station, <strong>Moffett</strong> <strong>Field</strong>, <strong>Moffett</strong> <strong>Field</strong>, Cali<strong>for</strong>nia<br />
DCN: AMEC-8816-0005-0039<br />
April 2010<br />
Page 20-1
This page left intentionally blank.<br />
Final Sampling and Analysis Plan<br />
Installation Restoration Site 29, Hangar 1<br />
Former Naval Air Station, <strong>Moffett</strong> <strong>Field</strong>, <strong>Moffett</strong> <strong>Field</strong>, Cali<strong>for</strong>nia<br />
DCN: AMEC-8816-0005-0039<br />
April 2010<br />
Page 20-2
WORKSHEET #21: PROJECT <strong>SAMPLING</strong> SOP REFERENCES TABLE<br />
This worksheet presents a list of relevant SOPs and sampling methodology. Copies of the<br />
SOPs listed in this worksheet are included in Appendix A of this SAP.<br />
Reference<br />
Number<br />
FP-F-7<br />
Table 21-1. Project Sampling SOP References<br />
Title<br />
Sample Handling,<br />
Storage, and Shipping<br />
Originating<br />
Organization<br />
of Sampling<br />
SOP<br />
Equipment<br />
Type<br />
Modified<br />
<strong>for</strong><br />
Project<br />
Work?<br />
(Y/N)<br />
Comments<br />
AMEC NA No None<br />
Final Sampling and Analysis Plan<br />
Installation Restoration Site 29, Hangar 1<br />
Former Naval Air Station, <strong>Moffett</strong> <strong>Field</strong>, <strong>Moffett</strong> <strong>Field</strong>,<br />
Cali<strong>for</strong>nia<br />
DCN: AMEC-8816-0005-0039<br />
April 2010<br />
Page 21-1
This page left intentionally blank.<br />
Final Sampling and Analysis Plan<br />
Installation Restoration Site 29, Hangar 1<br />
Former Naval Air Station, <strong>Moffett</strong> <strong>Field</strong>, <strong>Moffett</strong> <strong>Field</strong>,<br />
Cali<strong>for</strong>nia<br />
DCN: AMEC-8816-0005-0039<br />
April 2010<br />
Page 21-2
WORKSHEET #22: FIELD EQUIPMENT CALIBRATION, MAINTENANCE,<br />
TESTING, <strong>AND</strong> INSPECTION TABLE<br />
Table 22-1. <strong>Field</strong> Equipment Calibration, Maintenance, Testing, and<br />
Inspection<br />
<strong>Field</strong><br />
Acceptance Corrective Resp.<br />
Activity Frequency<br />
Equipment<br />
Criteria Action Person<br />
All field testing equipments to be used on site is <strong>for</strong> health and safety purposes.<br />
SOP<br />
Reference<br />
Comments<br />
Final Sampling and Analysis Plan<br />
Installation Restoration Site 29, Hangar 1<br />
Former Naval Air Station, <strong>Moffett</strong> <strong>Field</strong>, <strong>Moffett</strong> <strong>Field</strong>,<br />
Cali<strong>for</strong>nia<br />
DCN: AMEC-8816-0005-0039<br />
April 2010<br />
Page 22-1
This page left intentionally blank.<br />
Final Sampling and Analysis Plan<br />
Installation Restoration Site 29, Hangar 1<br />
Former Naval Air Station, <strong>Moffett</strong> <strong>Field</strong>, <strong>Moffett</strong> <strong>Field</strong>,<br />
Cali<strong>for</strong>nia<br />
DCN: AMEC-8816-0005-0039<br />
April 2010<br />
Page 22-2
WORKSHEET #23: ANALYTICAL SOP REFERENCES TABLE<br />
This worksheet identifies all analytical procedures that will be implemented during this<br />
project. This worksheet will be completed upon laboratory procurement. Laboratoryspecific<br />
SOPs will be listed <strong>for</strong> all off-site analyses and copies of the SOPs will be<br />
included in Appendix C of this SAP upon laboratory procurement. The laboratory SOP<br />
reference numbers will be referenced throughout the SAP to refer to a specific SOP.<br />
Lab SOP<br />
Number<br />
BCORG019<br />
Title, Revision<br />
Date, and/or<br />
Number<br />
Gas<br />
Chromatorgraphy<br />
<strong>for</strong> PCBs EPA<br />
8082 Rev.8<br />
BCMET013 Determination of<br />
Metals and Trace<br />
Elements in<br />
Water and Waste<br />
Water by ICP-<br />
AES 200.7/6010<br />
Rev.15<br />
1265 CARB 435 and<br />
EPA Screening<br />
Protocol Modified<br />
(Qualitative and<br />
Semi-<br />
Quantitative)<br />
using PLM, Rev.<br />
0<br />
BCORG019 Gas<br />
Chromatorgraphy<br />
<strong>for</strong> PCBs EPA<br />
8082 Rev.8<br />
Table 23-1. Analytical SOP Reference Table<br />
Definitive<br />
or<br />
Screening<br />
Data<br />
Definitive<br />
Definitive<br />
Definitive<br />
Matrix and<br />
Analytical<br />
Group<br />
Soil/Sediment,<br />
PCBs<br />
Soil/Sediment,<br />
Lead<br />
Soil/Sediment,<br />
Asbestos<br />
Instrument<br />
Organization<br />
Per<strong>for</strong>ming<br />
Analysis<br />
Modified<br />
<strong>for</strong> Project<br />
Work?<br />
(Y/N)<br />
GC BC Labs N<br />
ICP BC Labs N<br />
Microscope EM Lab N<br />
Definitive Wipe, PCBs GC BC Labs N<br />
Final Sampling and Analysis Plan<br />
Installation Restoration Site 29, Hangar 1<br />
Former Naval Air Station, <strong>Moffett</strong> <strong>Field</strong>, <strong>Moffett</strong> <strong>Field</strong>,<br />
Cali<strong>for</strong>nia<br />
DCN: AMEC-8816-0005-0039<br />
April 2010<br />
Page 23-1
Lab SOP<br />
Number<br />
BCMET013<br />
BCGEN065<br />
BCORG020<br />
BCORG005<br />
Title, Revision<br />
Date, and/or<br />
Number<br />
Determination of<br />
Metals and Trace<br />
Elements in<br />
Water and Waste<br />
Water by ICP-<br />
AES 200.7/6010<br />
Rev.15<br />
Electrical<br />
Conductivity, pH,<br />
Alkalinity Rev. 1<br />
GC/MS <strong>for</strong> Semivolatiles,<br />
Rev. 12<br />
TPH (Fuels),<br />
Rev. 10<br />
Table 23-1. Analytical SOP Reference Table<br />
Definitive<br />
or<br />
Screening<br />
Data<br />
Matrix and<br />
Analytical<br />
Group<br />
Instrument<br />
Organization<br />
Per<strong>for</strong>ming<br />
Analysis<br />
Modified<br />
<strong>for</strong> Project<br />
Work?<br />
(Y/N)<br />
Definitive Wipe, Lead ICP BC Labs N<br />
Definitive Soil pH meter BC Labs N<br />
Definitive Soil GC/MS BC Labs N<br />
Definitive Soil GC BC Labs N<br />
Final Sampling and Analysis Plan<br />
Installation Restoration Site 29, Hangar 1<br />
Former Naval Air Station, <strong>Moffett</strong> <strong>Field</strong>, <strong>Moffett</strong> <strong>Field</strong>,<br />
Cali<strong>for</strong>nia<br />
DCN: AMEC-8816-0005-0039<br />
April 2010<br />
Page 23-2
Instrument<br />
WORKSHEET #24: ANALYTICAL INSTRUMENT CALIBRATION TABLE<br />
This worksheet provides a list of analytical instrumentation required to per<strong>for</strong>m the laboratory analyses and the associated<br />
calibration procedures. In addition, documentation of the frequency, acceptance criteria, and corrective action requirements are<br />
also provided. All instruments will be calibrated according to the schedule specified by the method and instrument manual or<br />
applicable SOPs. This worksheet will be completed upon laboratory procurement.<br />
Calibration<br />
Procedure<br />
GC ICAL Initially, prior to sample<br />
analysis<br />
GC Second source<br />
initial calibration<br />
verification (ICV)<br />
GC CCV Daily be<strong>for</strong>e sample<br />
analysis, every 10<br />
samples, and at the end of<br />
the analysis sequence<br />
GC/MS<br />
ICAL<br />
Table 24-1. Analytical Instrument Calibration<br />
Frequency of Calibration Acceptance Criteria Corrective Action<br />
One of the options below:<br />
Option 1: relative standard<br />
deviation (RSD) <strong>for</strong> each<br />
analyte ≤ 20%<br />
Option 2: linear least<br />
squares regression:<br />
r≥0.995<br />
Option 3: non-linear<br />
regression: coefficient of<br />
determination (COD) r 2 ≥<br />
0.99.<br />
After every ICAL All analytes within ± 20%<br />
of expected value from the<br />
ICAL.<br />
Method inception, CCAL<br />
fails<br />
All analytes within ± 20%<br />
of expected value from the<br />
ICAL.<br />
Locate the source of the problem. If<br />
expected RSD is not met, then check<br />
<strong>for</strong> standard degradation or per<strong>for</strong>m<br />
instrument adjustment and/or<br />
maintenance to correct the problem and<br />
repeat ICAL.<br />
Prepare fresh standard and re-analyze<br />
ICV to rule out standard degradation or<br />
inaccurate injection. If problem persists,<br />
then per<strong>for</strong>m instrument adjustment<br />
and/or maintenance to correct the<br />
problem and repeat ICAL.<br />
Prepare fresh standard and re-analyze<br />
CCV to rule out standard degradation<br />
or inaccurate injection. If problem<br />
persists, then per<strong>for</strong>m instrument<br />
adjustment and/or maintenance to<br />
correct the problem and repeat ICAL.<br />
Person<br />
Responsible <strong>for</strong><br />
Corrective Action<br />
Laboratory Analyst<br />
Laboratory Analyst<br />
Laboratory Analyst<br />
SOP<br />
Reference<br />
BCORG019<br />
BCORG005<br />
BCORG019<br />
BCORG005<br />
BCORG019<br />
BCORG005<br />
RRF ≥ 0.05, %RSD
Instrument<br />
Calibration<br />
Procedure<br />
GC/MS<br />
GC/MS DFTPP<br />
Tune<br />
Prior to start of analysis<br />
GC/MS CCAL<br />
and every 12 hours<br />
thereafter<br />
ICP ICAL Daily and prior to sample<br />
analysis<br />
ICP ICV After ICAL, prior to<br />
beginning a sample run<br />
ICP CCV Daily be<strong>for</strong>e sample<br />
analysis, every 10<br />
samples, and at the end of<br />
the analysis sequence<br />
Polarized Light<br />
Microscopy<br />
(PLM)<br />
Blank<br />
Table 24-1. Analytical Instrument Calibration<br />
Frequency of Calibration Acceptance Criteria Corrective Action<br />
Person<br />
Responsible <strong>for</strong><br />
Corrective Action<br />
SOP<br />
Reference<br />
Beginning of 12-hour shift Method-specified Repeat until criteria are met Laboratory Analyst BCORG020<br />
Friable – one blank side<br />
daily or every 50 samples,<br />
whichever is less.<br />
Non-friable – one<br />
asbestos containing<br />
material (ACM) or nonfriable<br />
material every 20<br />
samples.<br />
RRF ≥ 0.05, %D±25%<br />
All analytes within ±10%<br />
of expected value. r ≥<br />
0.995.<br />
All analytes within + 10%<br />
of expected value<br />
RSD of replicate<br />
integrations: < 5%<br />
All analytes within + 10%<br />
of expected value<br />
RSD of replicate<br />
integrations < 5%<br />
Repeat CCAL once; repeat ICAL if<br />
second CCAL fails<br />
Prepare fresh standard and re-analyze<br />
ICV to rule out standard degradation or<br />
inaccurate injection. If problem persists,<br />
then per<strong>for</strong>m instrument adjustment<br />
and/or maintenance to correct the<br />
problem and repeat ICAL.<br />
If RSDs 5%, then per<strong>for</strong>m<br />
instrument maintenance to correct the<br />
problem and repeat ICAL.<br />
If RSDs 5%, then per<strong>for</strong>m<br />
instrument maintenance to correct the<br />
problem. Recalibrate and reanalyze all<br />
samples since last successful CCV.<br />
Laboratory Analyst<br />
Laboratory Analyst<br />
Laboratory Analyst<br />
Laboratory Analyst<br />
Negative Prepare and analyze another blank. Laboratory Analyst 1265<br />
BCORG020<br />
BCMET013<br />
BCMET013<br />
BCMET013<br />
Final Sampling and Analysis Plan<br />
Installation Restoration Site 29, Hangar 1<br />
Former Naval Air Station, <strong>Moffett</strong> <strong>Field</strong>, <strong>Moffett</strong> <strong>Field</strong>, Cali<strong>for</strong>nia<br />
DCN: AMEC-8816-0005-0039<br />
April 2010<br />
Page 24-2
WORKSHEET #25: ANALYTICAL INSTRUMENT <strong>AND</strong> EQUIPMENT MAINTENANCE, TESTING, <strong>AND</strong> INSPECTION<br />
TABLE<br />
This worksheet identifies all analytical instrumentation that requires maintenance, testing, or inspection and provides the laboratory<br />
SOP reference number <strong>for</strong> each. In addition, documentation of the frequency, acceptance criteria, and corrective action requirements<br />
are also provided on this worksheet. This worksheet will be completed upon laboratory procurement.<br />
Instrument/<br />
Equipment<br />
Table 25-1. Analytical Instrument and Equipment Maintenance, Testing, and Inspection<br />
Maintenance<br />
Activity<br />
Testing<br />
Activity<br />
Inspection<br />
Activity<br />
GC Parameter Setup Physical check Physical<br />
check<br />
GC Retention time<br />
(RT) window<br />
width calculated<br />
<strong>for</strong> each analyte<br />
and surrogate<br />
GC RT window<br />
position <strong>for</strong> each<br />
analyte check<br />
Instrument<br />
Per<strong>for</strong>mance<br />
Instrument<br />
Per<strong>for</strong>mance<br />
Instrument<br />
per<strong>for</strong>mance<br />
check<br />
Instrument<br />
per<strong>for</strong>mance<br />
check<br />
Frequency<br />
Initially; prior<br />
to daily<br />
calibration<br />
check<br />
At method setup<br />
and after<br />
major<br />
maintenance<br />
(e.g. column<br />
change)<br />
Once per ICAL<br />
and at the<br />
beginning of<br />
the analytical<br />
shift<br />
Acceptance Criteria<br />
Autosampler must<br />
move to the expected<br />
position when<br />
activated.<br />
Refer to instrument<br />
optimize temperature<br />
program setup.<br />
RT width is ± 3 times<br />
standard deviation <strong>for</strong><br />
each analyte RT from<br />
a 72-hour study.<br />
Position shall be set<br />
using the midpoint<br />
standard of the ICAL<br />
curve when ICAL is<br />
per<strong>for</strong>med. On days<br />
when ICAL is not<br />
per<strong>for</strong>med, the initial<br />
CCV is used.<br />
Corrective<br />
Action<br />
Reset if<br />
incorrect<br />
Locate<br />
source of<br />
the problem.<br />
Repeat if<br />
incorrect.<br />
Locate<br />
source of<br />
the problem.<br />
Repeat if<br />
incorrect.<br />
Responsible<br />
Person<br />
Laboratory<br />
Analyst<br />
Laboratory<br />
Analyst<br />
Laboratory<br />
Analyst<br />
SOP<br />
Reference<br />
BCORG019<br />
BCORG005<br />
BCORG019<br />
BCORG005<br />
BCORG019<br />
BCORG005<br />
Final Sampling and Analysis Plan<br />
Installation Restoration Site 29, Hangar 1<br />
Former Naval Air Station, <strong>Moffett</strong> <strong>Field</strong>, <strong>Moffett</strong> <strong>Field</strong>, Cali<strong>for</strong>nia<br />
DCN: AMEC-8816-0005-0039<br />
April 2010<br />
Page 25-1
Instrument/<br />
Equipment<br />
Mass<br />
Spectrometer<br />
Mass<br />
Spectrometer<br />
Mass<br />
Spectrometer<br />
Mass<br />
Spectrometer<br />
Maintenance<br />
Activity<br />
Pump Oil Level<br />
Detector<br />
Bakeout<br />
Clean source,<br />
replace filament<br />
Detector Precalibration<br />
Testing<br />
Activity<br />
NA<br />
Observation of<br />
deteriorating<br />
chromatograp<br />
hy<br />
Observation of<br />
deteriorating<br />
chromatograp<br />
hy<br />
Resolution<br />
adjustment<br />
Inspection<br />
Activity<br />
Visual<br />
inspection of<br />
oil gauge<br />
and color of<br />
oil<br />
NA<br />
Visual<br />
inspection of<br />
filaments<br />
Observation<br />
of tuning<br />
spectrum<br />
ICP Parameter Setup Physical check Physical<br />
check<br />
Frequency<br />
Check<br />
Monthly;<br />
Change<br />
Annually<br />
As needed<br />
As needed<br />
Every 12<br />
hours<br />
Initially; prior<br />
to DCC<br />
Acceptance Criteria<br />
Adequate oil<br />
level<br />
No interference/<br />
carryover peaks<br />
No interference;<br />
adequate<br />
spectral<br />
resolution<br />
Per method<br />
tuning<br />
requirements<br />
Predetermined<br />
optimum parameter<br />
settings<br />
Corrective<br />
Action<br />
Add oil<br />
Clean<br />
detector<br />
Clean<br />
source;<br />
replace<br />
filament<br />
Adjust<br />
optics<br />
Reset if<br />
incorrect<br />
Responsible<br />
Person<br />
Laboratory<br />
Analyst<br />
Laboratory<br />
Analyst<br />
Laboratory<br />
Analyst<br />
Laboratory<br />
Analyst<br />
Laboratory<br />
Analyst<br />
SOP<br />
Reference<br />
BCORG020<br />
BCORG020<br />
BCORG020<br />
BCORG020<br />
BCMET013<br />
Final Sampling and Analysis Plan<br />
Installation Restoration Site 29, Hangar 1<br />
Former Naval Air Station, <strong>Moffett</strong> <strong>Field</strong>, <strong>Moffett</strong> <strong>Field</strong>, Cali<strong>for</strong>nia<br />
DCN: AMEC-8816-0005-0039<br />
April 2010<br />
Page 25-2
Instrument/<br />
Equipment<br />
ICP<br />
ICP<br />
Maintenance<br />
Activity<br />
Interference<br />
check<br />
solutions/interfer<br />
ence check<br />
solution – A<br />
(ICS/ICS-A)<br />
ICAL<br />
blank/CCAL<br />
blank (ICB/CCB)<br />
Testing<br />
Activity<br />
Instrument<br />
Per<strong>for</strong>mance<br />
Instrument<br />
Per<strong>for</strong>mance<br />
Inspection<br />
Activity<br />
Con<strong>for</strong>manc<br />
e to<br />
interference<br />
check<br />
Instrument<br />
contaminati<br />
on check<br />
Frequency<br />
Prior to<br />
sample<br />
analysis<br />
After every<br />
calibration<br />
verification<br />
Acceptance Criteria<br />
Within + 20% of<br />
expected value<br />
No analytes detected<br />
greater than (>) three<br />
times instrument<br />
detection limit (IDL)<br />
Corrective<br />
Action<br />
Terminate<br />
analysis,<br />
reanalyze<br />
ICS to rule<br />
out standard<br />
degradation<br />
or<br />
inaccurate<br />
injection. If<br />
problem<br />
persist, then<br />
per<strong>for</strong>m<br />
instrument<br />
maintenanc<br />
e, repeat<br />
calibrations,<br />
and<br />
reanalyze all<br />
associated<br />
samples.<br />
Determine<br />
possible<br />
source of<br />
contaminati<br />
on and<br />
apply<br />
appropriate<br />
measure to<br />
correct the<br />
problem.<br />
Reanalyze<br />
calibration<br />
blank and all<br />
associated<br />
samples.<br />
Responsible<br />
Person<br />
Laboratory<br />
Analyst<br />
Laboratory<br />
Analyst<br />
SOP<br />
Reference<br />
BCMET013<br />
BCMET013<br />
Final Sampling and Analysis Plan<br />
Installation Restoration Site 29, Hangar 1<br />
Former Naval Air Station, <strong>Moffett</strong> <strong>Field</strong>, <strong>Moffett</strong> <strong>Field</strong>, Cali<strong>for</strong>nia<br />
DCN: AMEC-8816-0005-0039<br />
April 2010<br />
Page 25-3
Instrument/<br />
Equipment<br />
Maintenance<br />
Activity<br />
Testing<br />
Activity<br />
Inspection<br />
Activity<br />
Frequency<br />
PLM PLM alignment Prior to each<br />
use.<br />
PLM Refractive<br />
Initially and<br />
Index liquid<br />
semiannually,<br />
calibration<br />
or next use<br />
whichever is<br />
less frequent<br />
Acceptance Criteria<br />
Accuracy of 0.004<br />
with temperature<br />
accuracy of 2 o C<br />
Corrective<br />
Action<br />
Repeat<br />
refractive<br />
index liquid<br />
calibration.<br />
If problem<br />
persists,<br />
then<br />
per<strong>for</strong>m<br />
maintenanc<br />
e and repeat<br />
calibration.<br />
Responsible<br />
Person<br />
Laboratory<br />
Analyst 1<br />
Laboratory<br />
Analyst 1<br />
SOP<br />
Reference<br />
EM Lab<br />
EM Lab<br />
Final Sampling and Analysis Plan<br />
Installation Restoration Site 29, Hangar 1<br />
Former Naval Air Station, <strong>Moffett</strong> <strong>Field</strong>, <strong>Moffett</strong> <strong>Field</strong>, Cali<strong>for</strong>nia<br />
DCN: AMEC-8816-0005-0039<br />
April 2010<br />
Page 25-4
WORKSHEET #26: SAMPLE H<strong>AND</strong>LING SYSTEM<br />
This worksheet identifies components of the project-specific sample handling system. Key<br />
personnel (and their organizational affiliations) who are primarily responsible <strong>for</strong> ensuring<br />
proper handling, custody, and storage of field samples are identified in the table below.<br />
The table also identifies the number of days that field samples and their extracts/digestates<br />
will be archived prior to disposal.<br />
SAMPLE COLLECTION, PACKAGING, <strong>AND</strong> SHIPMENT<br />
Sample Collection (Personnel/Organization): AMEC field personnel<br />
Sample Packaging (Personnel/Organization): AMEC field personnel<br />
Coordination of Shipment (Personnel/Organization): AMEC field personnel<br />
Type of Shipment/Carrier: FedEx or equivalent overnight delivery service or contract courier<br />
SAMPLE RECEIPT <strong>AND</strong> <strong>ANALYSIS</strong><br />
Sample Receipt (Personnel/Organization): BC Labs Sample Control personnel<br />
Sample Custody and Storage (Personnel/Organization): BC Labs Sample Control personnel<br />
Sample Preparation (Personnel/Organization): BC Labs Organic Prep and Inorganic Prep personnel<br />
Sample Determinative Analysis (Personnel/Organization): BC Labs Organic and Inorganic analyst<br />
SAMPLE ARCHIVING<br />
<strong>Field</strong> Sample Storage (No. of days from report delivery): 60 days<br />
Sample Extract/Digestate Storage (No. of days from report delivery): 60 days<br />
Biological Sample Storage (No. of days from sample collection): Not Applicable<br />
SAMPLE DISPOSAL<br />
Personnel/Organization: BC Labs Personnel<br />
Number of Days from Report Delivery: 90 days<br />
Final Sampling and Analysis Plan<br />
Installation Restoration Site 29, Hangar 1<br />
Former Naval Air Station, <strong>Moffett</strong> <strong>Field</strong>, <strong>Moffett</strong> <strong>Field</strong>, Cali<strong>for</strong>nia<br />
DCN: AMEC-8816-0005-0039<br />
April 2010<br />
Page 26-1
This page left intentionally blank.<br />
Final Sampling and Analysis Plan<br />
Installation Restoration Site 29, Hangar 1<br />
Former Naval Air Station, <strong>Moffett</strong> <strong>Field</strong>, <strong>Moffett</strong> <strong>Field</strong>, Cali<strong>for</strong>nia<br />
DCN: AMEC-8816-0005-0039<br />
April 2010<br />
Page 26-2
WORKSHEET #27: SAMPLE CUSTODY REQUIREMENTS<br />
The integrity of data obtained <strong>for</strong> samples collected in the field and those created in the lab<br />
<strong>for</strong> the bench test depends on adherence to proper procedures <strong>for</strong> sample management<br />
involving both proper labeling and handling of samples.<br />
27.1 Sample Name Assignment<br />
Sample names will be unique alpha numeric codes assigned by AMEC, with a maximum<br />
length of 40 characters. The following designations will be used <strong>for</strong> samples associated<br />
with this project:<br />
• Event-matrix-XXXX<br />
“Event” refers to either the baseline/pre-construction (PC) or post-construction<br />
confirmation (CO) stage of work; “matrix” refers to the matrix of the sample; and<br />
“XXXX” refers to three-digit sequential integer number assignment <strong>for</strong> this project. For integers<br />
less than ten, the first two characters will be “00”, and <strong>for</strong> less than one hundred, the first<br />
character will be”0”. For example, the first soil sample collected from the pre-construction<br />
event would be assigned the sample name “PC- SO-001.”<br />
All coded sample names, will be recorded in the field on the “Sample Record Form”<br />
(Appendix B).<br />
27.2 <strong>Field</strong> Sample Collection<br />
To limit sample contamination during sample collection and handling, field staff will wear<br />
a clean new pair of disposable nitrile gloves each time a different sample is collected. <strong>Field</strong><br />
staff will not touch the inside of the sample container or lid during sample collection.<br />
27.3 <strong>Field</strong> Sample Container Custody<br />
All sample collection containers will be laboratory-supplied and pre-preserved (if required<br />
by method). The sample jars will be delivered in sealed containers to the AMEC Project<br />
<strong>Field</strong> Office at <strong>Moffett</strong> <strong>Field</strong> by laboratory personnel or by a common carrier (e.g. FedEx).<br />
The laboratory will include a list of the containers shipped and the purpose of each<br />
container.<br />
27.4 <strong>Field</strong> Sample Identification Procedures<br />
Samples will be identified with water-proof labels pre-printed with analytical methods,<br />
project name, and project number. <strong>Field</strong> staff will add the sample name, sample date, and<br />
sample time to the label in ink at the time the sample is collected. All coded sample names<br />
Final Sampling and Analysis Plan<br />
Installation Restoration Site 29, Hangar 1<br />
Former Naval Air Station, <strong>Moffett</strong> <strong>Field</strong>, <strong>Moffett</strong> <strong>Field</strong>, Cali<strong>for</strong>nia<br />
DCN: AMEC-8816-0005-0039<br />
April 2010<br />
Page 27-1
and field quality control sample associations will be recorded in the field on the “Sample<br />
Record Form” (see Appendix B).<br />
27.5 Chain-of-Custody Forms<br />
Samples will be accompanied by a completed chain-of-custody <strong>for</strong>m (see Appendix B)<br />
containing the following in<strong>for</strong>mation: sample name, sample date and time, sample matrix,<br />
total number of bottles <strong>for</strong> each sample and requested analyses, special instructions <strong>for</strong> the<br />
laboratory, as well as the signature of the person collecting the samples.<br />
27.6 <strong>Field</strong> Sample Packaging<br />
<strong>Field</strong> samples will be packaged and shipped in accordance with SOP FP-F-7, Sample<br />
Handling, Storage, and Shipping Procedure provided in Appendix A.<br />
27.7 Laboratory Sample Custody Procedures<br />
The chain-of-custody <strong>for</strong>m will be signed on receipt by the laboratory to complete the<br />
custody chain. The condition of the samples upon receipt by the laboratory will be<br />
documented on a cooler receipt log or sample condition upon receipt <strong>for</strong>m. This <strong>for</strong>m will<br />
note sample integrity, preservation, temperature, custody seal condition, and will note any<br />
discrepancies between in<strong>for</strong>mation on the sample labels and that on the chain-of-custody<br />
<strong>for</strong>m.<br />
Each sample will be logged into the laboratory in<strong>for</strong>mation management system (LIMS)<br />
by assigning it a unique sample number. This number and the field sample ID number will<br />
be recorded on the laboratory report. Samples will be stored and analyzed according to<br />
specified methods. The original chain-of-custody <strong>for</strong>m will be returned to the AMEC Data<br />
Manager <strong>for</strong> permanent storage.<br />
Once the laboratory has logged in the samples, their progress through preparation and<br />
analysis will be tracked and monitored through the LIMS. The analysts will be required to<br />
sign out samples from the sample storage area or refrigerator by entering their initials, date<br />
and time of sample removal. The samples will be taken to the appropriate analytical<br />
section <strong>for</strong> preparation and analysis, where all procedures will be documented in laboratory<br />
notebooks or <strong>for</strong>ms and on run logs. Dates of preparation and analysis will be entered into<br />
the LIMS. Sample results will be entered into the LIMS either through direct download<br />
from the instrument or manually. Unused sample portions and extracts will be returned to<br />
the sample storage area and signed back in. The sample or extract will remain in storage at<br />
the laboratory until the disposal time period is reached. Disposal in<strong>for</strong>mation will be<br />
entered into the laboratory in<strong>for</strong>mation system. Sample disposal will not occur until<br />
AMEC confirms that all data have been fully validated and have provided written approval<br />
to permit sample disposal.<br />
Final Sampling and Analysis Plan<br />
Installation Restoration Site 29, Hangar 1<br />
Former Naval Air Station, <strong>Moffett</strong> <strong>Field</strong>, <strong>Moffett</strong> <strong>Field</strong>, Cali<strong>for</strong>nia<br />
DCN: AMEC-8816-0005-0039<br />
April 2010<br />
Page 27-2
27.8 <strong>Field</strong> Sample Custody, Shipment, and Laboratory Receipt<br />
Samples are considered “in custody” if the following conditions are true:<br />
• The responsible person (either the person collecting the sample or the person<br />
designated on the chain-of-custody <strong>for</strong>m as having custody) maintains possession<br />
of the samples.<br />
• After the samples are collected by or relinquished to a responsible person they must<br />
remain in view of, or in the physical possession of, the responsible person.<br />
• Samples are sealed so that no one can tamper with them.<br />
• Samples are maintained in an area restricted to authorized personnel.<br />
Samples will be maintained in the custody of the sampling personnel during daily sample<br />
activities. As each sample is collected, field personnel will complete a chain-of-custody<br />
<strong>for</strong>m (see Appendix B <strong>for</strong> that sample that includes sample name, sample date and time,<br />
sample matrix, total number of bottles <strong>for</strong> each sample, and requested analyses, as well as<br />
the signature of the person collecting the samples.<br />
Be<strong>for</strong>e leaving the field, sampling personnel will verify that the in<strong>for</strong>mation on the chainof-custody<br />
<strong>for</strong>m matches the in<strong>for</strong>mation on each sample’s scheduled analyses, and will<br />
make sure that each cooler contains the correct bottle count <strong>for</strong> each sample. On transfer of<br />
custody to a new responsible person, the sampling personnel will sign and date the<br />
relinquishment of custody, and the recipient of custody will sign and date<br />
acknowledgement of receipt. If samples are shipped by a common carrier then the<br />
receiving agent will not sign the chain-of-custody <strong>for</strong>m, and instead the signed<br />
relinquishment will be sealed in the cooler.<br />
On receipt by the laboratory the receiving agent (custodian) will document the condition of<br />
the cooler, the integrity of the custody seal, the internal temperature of the cooler and the<br />
condition of the sample containers. After the samples are logged in, the laboratory<br />
custodian will sign and date the chain-of-custody <strong>for</strong>m. The original <strong>for</strong>m will be retained<br />
by the laboratory and a copy of the <strong>for</strong>m will be provided to AMEC to be included in the<br />
project files. In addition, the laboratory will provide AMEC with a copy of the sample<br />
receiving documentation, including the sample receipt date, the number of samples and<br />
containers received, a summary of the analyses to be per<strong>for</strong>med, expected results reporting<br />
date, and a laboratory-issued sample delivery group number.<br />
Final Sampling and Analysis Plan<br />
Installation Restoration Site 29, Hangar 1<br />
Former Naval Air Station, <strong>Moffett</strong> <strong>Field</strong>, <strong>Moffett</strong> <strong>Field</strong>, Cali<strong>for</strong>nia<br />
DCN: AMEC-8816-0005-0039<br />
April 2010<br />
Page 27-3
This page left intentionally blank.<br />
Final Sampling and Analysis Plan<br />
Installation Restoration Site 29, Hangar 1<br />
Former Naval Air Station, <strong>Moffett</strong> <strong>Field</strong>, <strong>Moffett</strong> <strong>Field</strong>, Cali<strong>for</strong>nia<br />
DCN: AMEC-8816-0005-0039<br />
April 2010<br />
Page 27-4
WORKSHEET #28: LABORATORY QC SAMPLES TABLE<br />
This worksheet identifies all laboratory QC samples anticipated to be completed <strong>for</strong> this<br />
investigation. A separate table is provided <strong>for</strong> each analytical method, matrix, and<br />
analytical group. Laboratory QC samples are analyzed as part of standard laboratory<br />
practice. The laboratory monitors the precision and accuracy of the results of its analytical<br />
procedures through analysis of QC samples.<br />
At a minimum, one laboratory QC sample is required per 20 samples (including blanks and<br />
duplicates). If method/SOP QC acceptance limits exceed the measurement per<strong>for</strong>mance<br />
criteria identified in the tables below, the data may be qualified in the data validation<br />
process and be unusable <strong>for</strong> making project decisions if rejected.<br />
Table 28-1. Laboratory Quality Control Samples – Soil/EPA Method 8082<br />
Matrix Soil<br />
Analytical<br />
Group<br />
PCBs<br />
Method/SOP EPA Method<br />
References 3550B/8082<br />
QC Sample<br />
Method<br />
Blank<br />
LCS<br />
Surrogate<br />
MS/MSD<br />
Frequency/<br />
Number 1<br />
1/batch<br />
1/batch<br />
All<br />
environmental<br />
and laboratory<br />
samples<br />
1/batch<br />
Method/SOP<br />
QC<br />
Acceptance<br />
Limits<br />
No detects ≥ ½<br />
QL<br />
PCB-1016:<br />
25-145%<br />
PCB-1260:<br />
30-145%<br />
Corrective<br />
Action<br />
Reanalyze with<br />
all associated<br />
samples<br />
Reanalyze with<br />
all associated<br />
samples<br />
Person(s)<br />
Responsible<br />
<strong>for</strong> Corrective<br />
Action<br />
Analyst<br />
Analyst<br />
Data<br />
Quality<br />
Indicator<br />
(DQI)<br />
Accuracy<br />
Accuracy<br />
Measurement<br />
Per<strong>for</strong>mance<br />
Criteria<br />
No detects ≥ ½<br />
QL<br />
PCB-1016:<br />
25-145%<br />
PCB-1260:<br />
30-145%<br />
Decachlorbiph<br />
enyl: 30-150% Reanalyze once Analyst Accuracy Decachlorbipheny<br />
l: 30-150%<br />
PCB-1016:<br />
25-145%<br />
PCB-1260:<br />
30-145%<br />
RPD < 30%<br />
None<br />
Analyst<br />
Accuracy,<br />
Precision<br />
Notes:<br />
1<br />
Batch is equivalent to 20 or fewer samples prepared and analyzed together with common QC samples.<br />
PCB-1016:<br />
25-145%<br />
PCB-1260:<br />
30-145%<br />
Final Sampling and Analysis Plan<br />
Installation Restoration Site 29, Hangar 1<br />
Former Naval Air Station, <strong>Moffett</strong> <strong>Field</strong>, <strong>Moffett</strong> <strong>Field</strong>, Cali<strong>for</strong>nia<br />
DCN: AMEC-8816-0005-0039<br />
April 2010<br />
Page 28-1
Table 28-2. Laboratory Quality Control Samples – Wipe/EPA Method 8082<br />
Matrix Wipe<br />
Analytical<br />
Group<br />
PCBs<br />
Method/SOP EPA Method<br />
References 3550B/8082<br />
QC Sample<br />
Method<br />
Blank<br />
LCS<br />
Surrogate<br />
Frequency/<br />
Number 1<br />
1/batch<br />
1/batch<br />
All<br />
environmental<br />
and laboratory<br />
samples<br />
Method/SOP QC<br />
Acceptance<br />
Limits<br />
No detects ≥ ½ QL<br />
PCB-1016:<br />
25-145%<br />
PCB-1260:<br />
30-145%<br />
Decachlorbiphenyl<br />
30-150%<br />
Corrective<br />
Action<br />
Reanalyze with<br />
all associated<br />
samples<br />
Reanalyze with<br />
all associated<br />
samples<br />
Reanalyze<br />
once<br />
Person(s)<br />
Responsible<br />
<strong>for</strong> Corrective<br />
Action<br />
Data<br />
Quality<br />
Indicator<br />
(DQI)<br />
Measurement<br />
Per<strong>for</strong>mance<br />
Criteria<br />
Analyst Accuracy No detects ≥ ½ QL<br />
Analyst<br />
Analyst<br />
Accuracy<br />
Accuracy<br />
PCB-1016:<br />
25-145%<br />
PCB-1260:<br />
30-145%<br />
Decachlorbiphenyl<br />
30-150%<br />
MS/MSD NA 2 NA None Analyst NA NA<br />
Notes:<br />
1<br />
Batch is equivalent to 20 or fewer samples prepared and analyzed together with common QC samples.<br />
2<br />
MS/MSD will not be collected <strong>for</strong> wipe sample because it is not practical to collect the number of samples needed.<br />
Final Sampling and Analysis Plan<br />
Installation Restoration Site 29, Hangar 1<br />
Former Naval Air Station, <strong>Moffett</strong> <strong>Field</strong>, <strong>Moffett</strong> <strong>Field</strong>, Cali<strong>for</strong>nia<br />
DCN: AMEC-8816-0005-0039<br />
April 2010<br />
Page 28-2
Table 28-3. Laboratory Quality Control Samples – Water/EPA Method 6010B<br />
Matrix Water<br />
Analytical<br />
Group<br />
Metals<br />
Method/SOP<br />
EPA 6010B<br />
Reference<br />
QC Sample<br />
Method<br />
Blank<br />
Frequency/<br />
Number 1<br />
1/batch<br />
Method/SOP<br />
QC Acceptance<br />
Limits<br />
No detects ≥ ½<br />
QL<br />
LCS 1/batch 80%-120%<br />
Postdigestion<br />
Spike<br />
Serial<br />
Dilution<br />
When dilution<br />
fails<br />
1/batch<br />
75%-125%<br />
≤10% <strong>for</strong><br />
analytes with<br />
concentration<br />
>50x QL<br />
MS/MSD 1/batch 80%-120%<br />
Method of<br />
Standard<br />
Addition<br />
When matrix<br />
interference is<br />
suspected<br />
Corrective<br />
Action<br />
Reanalyze with<br />
all associated<br />
samples<br />
Reprep and<br />
reanalyze the<br />
LCS and all<br />
samples<br />
Analyze<br />
samples by<br />
method of<br />
standard of<br />
addition<br />
Per<strong>for</strong>m post<br />
digestion spike<br />
If the result is<br />
indicative of<br />
matrix<br />
interference,<br />
discuss in the<br />
case narrative.<br />
Otherwise,<br />
check <strong>for</strong> a<br />
possible source<br />
of error, and<br />
extract/reanalyz<br />
e the sample.<br />
Person(s)<br />
Responsible<br />
<strong>for</strong> Corrective<br />
Action<br />
Analyst<br />
Data Quality<br />
Indicator<br />
(DQI)<br />
Accuracy<br />
Measurement<br />
Per<strong>for</strong>mance<br />
Criteria<br />
No detects ≥ ½<br />
QL<br />
Analyst Accuracy 80%-120%<br />
Analyst Accuracy 75%-125%<br />
Analyst<br />
Analyst<br />
Accuracy<br />
Interferences -<br />
Accuracy/Bias<br />
- Precision<br />
≤10% <strong>for</strong><br />
analytes with<br />
concentration<br />
>50x QL<br />
80%-120%<br />
NA NA NA Interferences NA<br />
Notes:<br />
1<br />
Batch is equivalent to 20 or fewer samples prepared and analyzed together with common QC samples.<br />
Final Sampling and Analysis Plan<br />
Installation Restoration Site 29, Hangar 1<br />
Former Naval Air Station, <strong>Moffett</strong> <strong>Field</strong>, <strong>Moffett</strong> <strong>Field</strong>, Cali<strong>for</strong>nia<br />
DCN: AMEC-8816-0005-0039<br />
April 2010<br />
Page 28-3
Matrix<br />
Analytical<br />
Group<br />
Method/SOP<br />
Reference<br />
QC Sample<br />
Method Blank<br />
Table 28-4. Laboratory Quality Control Samples – Wipe/Soil/ EPA Method<br />
6010B<br />
Wipe/Soil<br />
Metals<br />
EPA 6010B<br />
Frequency/<br />
Number 1<br />
1/batch<br />
Method/SOP QC<br />
Acceptance<br />
Limits<br />
No detects ≥ ½<br />
QL<br />
LCS 1/batch 80%-120%<br />
Post-digestion<br />
Spike<br />
Serial Dilution<br />
MS/MSD<br />
(soil only)<br />
Method of<br />
Standard<br />
Addition<br />
When dilution<br />
fails<br />
1/batch<br />
75%-125%<br />
≤10% <strong>for</strong><br />
analytes with<br />
concentration<br />
>50x QL<br />
1/batch 80%-120%<br />
When matrix<br />
interference is<br />
suspected<br />
Corrective Action<br />
Reanalyze with all<br />
associated samples<br />
Reprep and<br />
reanalyze the LCS<br />
and all samples<br />
Analyze samples by<br />
method of standard<br />
of addition<br />
Per<strong>for</strong>m post<br />
digestion spike<br />
If the result is<br />
indicative of matrix<br />
interference, discuss<br />
in the case narrative.<br />
Otherwise, check <strong>for</strong><br />
a possible source of<br />
error, and<br />
extract/reanalyze the<br />
sample.<br />
Person(s)<br />
Responsible<br />
<strong>for</strong> Corrective<br />
Action<br />
Analyst<br />
Data Quality<br />
Indicator<br />
(DQI)<br />
Accuracy<br />
Measurement<br />
Per<strong>for</strong>mance<br />
Criteria<br />
No detects ≥ ½<br />
QL<br />
Analyst Accuracy 80%-120%<br />
Analyst Accuracy 75%-125%<br />
Analyst<br />
Analyst<br />
Accuracy<br />
Interferences -<br />
Accuracy/Bias<br />
- Precision<br />
≤10% <strong>for</strong><br />
analytes with<br />
concentration<br />
>50x QL<br />
80%-120%<br />
NA NA NA Interferences NA<br />
Notes:<br />
1<br />
Batch is equivalent to 20 or fewer samples prepared and analyzed together with common QC samples.<br />
Final Sampling and Analysis Plan<br />
Installation Restoration Site 29, Hangar 1<br />
Former Naval Air Station, <strong>Moffett</strong> <strong>Field</strong>, <strong>Moffett</strong> <strong>Field</strong>, Cali<strong>for</strong>nia<br />
DCN: AMEC-8816-0005-0039<br />
April 2010<br />
Page 28-4
Table 28-5. Laboratory Quality Control Samples – Soil/ EPA Method 8270B<br />
Matrix<br />
Analytical<br />
Group<br />
Method/SOP<br />
Reference<br />
QC Sample<br />
Soil<br />
SVOCs<br />
EPA 8270C<br />
Frequency/<br />
Number 1<br />
Method/SOP<br />
QC<br />
Acceptance<br />
Limits 2<br />
Method Blank 1/batch No detects ≥QL<br />
LCS<br />
1/batch<br />
Laboratory<br />
Limits<br />
(Appendix C)<br />
Lab Duplicate 1/batch ≤20% RPD<br />
Surrogate<br />
Internal<br />
Standard<br />
All<br />
environmental<br />
and laboratory<br />
samples<br />
All<br />
environmental<br />
and laboratory<br />
samples<br />
Laboratory<br />
Limits<br />
(Appendix C)<br />
50%-100%<br />
Corrective Action<br />
Reanalyze with all<br />
associated samples if<br />
there are suspect<br />
instrument per<strong>for</strong>mance<br />
or loading issues.<br />
If instrument is ok then<br />
re-prep and reanalyze<br />
samples.<br />
See note 3<br />
Reanalyze with all<br />
associated samples if<br />
there are suspect<br />
instrument per<strong>for</strong>mance<br />
or loading issues.<br />
If instrument is ok the<br />
re-prep and reanalyze<br />
samples<br />
See note 3<br />
Evaluate in<br />
consideration of other<br />
batch QC parameters<br />
and sample<br />
homogeneity. Re-prep<br />
and reanalyze if no<br />
extenuating<br />
circumstances are<br />
found. High RPD <strong>for</strong><br />
non-detects are not<br />
reanalyzed<br />
Reanalyze once to<br />
confirm matrix<br />
interference<br />
Reanalyze once to<br />
confirm matrix<br />
interference<br />
Person(s)<br />
Responsib<br />
le <strong>for</strong><br />
Corrective<br />
Action<br />
Analyst or<br />
QA<br />
Manager<br />
Analyst or<br />
QA<br />
Manager<br />
Analyst or<br />
QA<br />
Manager<br />
Analyst or<br />
QA<br />
Manager<br />
Analyst or<br />
QA<br />
Manager<br />
Data<br />
Quality<br />
Indicator<br />
(DQI)<br />
Accuracy<br />
Accuracy<br />
Precision<br />
Accuracy<br />
Measurement<br />
Per<strong>for</strong>mance<br />
Criteria<br />
No detects ≥QL<br />
Laboratory Limits<br />
(Appendix C)<br />
≤20% RPD<br />
Laboratory Limits<br />
(Appendix C)<br />
Accuracy 50%-100%<br />
Notes:<br />
1<br />
Batch is equivalent to 20 or fewer samples prepared and analyzed together with common QC samples.<br />
Final Sampling and Analysis Plan<br />
Installation Restoration Site 29, Hangar 1<br />
Former Naval Air Station, <strong>Moffett</strong> <strong>Field</strong>, <strong>Moffett</strong> <strong>Field</strong>, Cali<strong>for</strong>nia<br />
DCN: AMEC-8816-0005-0039<br />
April 2010<br />
Page 28-5
Table 28-6. Laboratory Quality Control Samples – Soil/ EPA Method 8015B<br />
QC Sample<br />
Frequency/<br />
Number 1<br />
Method/SOP<br />
QC<br />
Acceptance<br />
Limits 2<br />
Method Blank 1/batch No detects ≥QL<br />
LCS<br />
Surrogate<br />
1/batch<br />
All<br />
environmental<br />
and laboratory<br />
samples<br />
Diesel: 50-<br />
136%<br />
Tetracosane:<br />
34-136%<br />
MS/MSD 1/batch 40-137%<br />
Corrective<br />
Action<br />
Reanalyze with all<br />
associated<br />
samples if there<br />
are suspect<br />
instrument<br />
per<strong>for</strong>mance or<br />
loading issues.<br />
If instrument is ok<br />
then re-prep and<br />
reanalyze<br />
samples.<br />
Reanalyze with all<br />
associated<br />
samples if there<br />
are suspect<br />
instrument<br />
per<strong>for</strong>mance or<br />
loading issues.<br />
If instrument is ok<br />
the re-prep and<br />
reanalyze<br />
samples<br />
Reanalyze once<br />
to confirm matrix<br />
interference<br />
Evaluate in<br />
consideration of<br />
LCS results. If<br />
LCS is acceptable<br />
then narrate<br />
indication of<br />
matrix effects in<br />
MS/MSD present.<br />
Person(s)<br />
Responsible<br />
<strong>for</strong> Corrective<br />
Action<br />
Analyst or QA<br />
Manager<br />
Analyst or QA<br />
Manager<br />
Analyst or QA<br />
Manager<br />
Analyst or QA<br />
Manager<br />
Data Quality<br />
Indicator<br />
(DQI)<br />
Accuracy<br />
Measurement<br />
Per<strong>for</strong>mance<br />
Criteria<br />
No detects ≥QL<br />
Accuracy Diesel: 50-136%<br />
Accuracy<br />
Accuracy,<br />
Precision<br />
Notes:<br />
1<br />
Batch is equivalent to 20 or fewer samples prepared and analyzed together with common QC samples<br />
Tetracosane: 34-<br />
136<br />
40-137%<br />
Final Sampling and Analysis Plan<br />
Installation Restoration Site 29, Hangar 1<br />
Former Naval Air Station, <strong>Moffett</strong> <strong>Field</strong>, <strong>Moffett</strong> <strong>Field</strong>, Cali<strong>for</strong>nia<br />
DCN: AMEC-8816-0005-0039<br />
April 2010<br />
Page 28-6
WORKSHEET #29: PROJECT DOCUMENTS <strong>AND</strong> RECORDS TABLE<br />
This worksheet identifies the documents and records that will be generated <strong>for</strong> all aspects<br />
of the project including, but not limited to, sample collection and field measurement, offsite<br />
analysis, and data assessment. All project data and in<strong>for</strong>mation will be documented in<br />
a <strong>for</strong>mat that is usable by project personnel. This worksheet also describes how project<br />
data and in<strong>for</strong>mation will be documented, tracked, and managed, from generation in the<br />
field to final use and storage in a manner that ensures data integrity, defensibility and<br />
retrieval. All project documents and records that will be generated <strong>for</strong> every aspect of the<br />
project are identified in the table below. The second column in the table below is used to<br />
note where the project documents will be maintained to facilitate future retrieval of this<br />
in<strong>for</strong>mation. Long-term storage/location is also provided <strong>for</strong> archiving of data after the<br />
project is complete.<br />
Table 29-1. Project <strong>Documents</strong> and Records<br />
Document<br />
Sample Collection and <strong>Field</strong> Measurement<br />
Records<br />
<strong>Field</strong> logbook<br />
Chain-of-custody records<br />
Corrective action reports<br />
Documentation of corrective action results<br />
Documentation of deviation from methods<br />
Documentation of internal QA review<br />
ID of QC samples<br />
Meteorological data from field (e.g. wind,<br />
temperature)<br />
Sample locations (global positioning system<br />
[GPS] or survey coordinates)<br />
Photographs and/or digital videos<br />
Analytical Records (hard copy)<br />
Chain-of-custody records<br />
Sample receipt <strong>for</strong>ms and sample tracking <strong>for</strong>ms<br />
Preparation and analysis <strong>for</strong>ms and/or logbooks<br />
Case narrative<br />
Sample chronology (time of receipt, extraction,<br />
and analysis)<br />
Raw data<br />
ID of QC samples<br />
Communication logs<br />
Corrective action reports<br />
Definitions of laboratory qualifiers<br />
Documentation of corrective action results<br />
Documentation of laboratory method deviations<br />
Instrument calibration reports<br />
Laboratory name<br />
Laboratory sample ID numbers<br />
Reporting <strong>for</strong>ms, completed with actual results<br />
Signatures <strong>for</strong> laboratory sign-off (e.g. lab QA<br />
manager)<br />
EDD (NEDD <strong>for</strong>mat)<br />
Where Maintained<br />
All records generated in the field will be stored in a field<br />
binder and kept in the custody of the field crew. These<br />
records will be periodically delivered to the AMEC Project<br />
Manager. Once in the possession of the project manager,<br />
the records will be stored in the project file in a secured<br />
file cabinet. After project close-out, the project files will be<br />
archived at a commercial document storage facility in San<br />
Diego, CA <strong>for</strong> the contract required period of time.<br />
All analytical records generated by the laboratory will be<br />
delivered to the AMEC Project Chemist within the<br />
specified turn-around time. Once in the possession of the<br />
Project Chemist, the analytical records will be stored in<br />
the project file in a secured file cabinet. Analytical records<br />
will be submitted to the Navy Administrative Record office<br />
after the report is prepared.<br />
Final Sampling and Analysis Plan<br />
Installation Restoration Site 29, Hangar 1<br />
Former Naval Air Station, <strong>Moffett</strong> <strong>Field</strong>, <strong>Moffett</strong> <strong>Field</strong>, Cali<strong>for</strong>nia<br />
DCN: AMEC-8816-0005-0039<br />
April 2010<br />
Page 29-1
Table 29-1. Project <strong>Documents</strong> and Records<br />
Document<br />
Project Data Assessment Records<br />
<strong>Field</strong> sampling audit checklists<br />
Data validation reports<br />
Telephone logs<br />
Corrective action reports<br />
Laboratory QA plans<br />
Laboratory accreditation certificates<br />
Where Maintained<br />
All data assessment records will be compiled and stored<br />
in the project file in a secured file cabinet. After project<br />
close-out, the project files will be archived at a commercial<br />
document storage facility in San Diego, CA <strong>for</strong> the<br />
contract required period of time. Data Validation reports<br />
will be transferred to NAVFAC SW Administrative Record<br />
office.<br />
Final Sampling and Analysis Plan<br />
Installation Restoration Site 29, Hangar 1<br />
Former Naval Air Station, <strong>Moffett</strong> <strong>Field</strong>, <strong>Moffett</strong> <strong>Field</strong>, Cali<strong>for</strong>nia<br />
DCN: AMEC-8816-0005-0039<br />
April 2010<br />
Page 29-2
WORKSHEET #30: ANALYTICAL SERVICES TABLE<br />
This worksheet identifies all laboratories that will provide analytical services <strong>for</strong> the<br />
project grouped by matrix and analytical group. This worksheet will be completed upon<br />
laboratory procurement. Backup laboratories will also be identified in the event that the<br />
primary laboratory cannot be used. The desired data package turnaround time will be<br />
identified in this worksheet.<br />
Matrix<br />
Soil<br />
Soil<br />
Sediment<br />
Sediment<br />
Wipe<br />
Analytical<br />
Group<br />
PCBs, Lead<br />
Asbestos<br />
PCBs, Lead,<br />
Asbestos<br />
PCBs, Lead<br />
Table 30-1. Analytical Services Matrix<br />
Sample<br />
Locations/ID<br />
Number<br />
PC-SO-001 through<br />
101<br />
CO-SO-200<br />
through 250<br />
PC-SO-001 through<br />
101<br />
CO-SO-200<br />
through 250<br />
PC-SD-01 through<br />
PC-SD-04<br />
PC-SD-01 through<br />
PC-SD-04<br />
CO-W-500 through<br />
540<br />
Analytical<br />
Method<br />
EPA<br />
8082,<br />
6020,<br />
CARB 435<br />
EPA<br />
8082,<br />
6020,<br />
CARB 435<br />
EPA<br />
8082,<br />
6020<br />
Data<br />
Package<br />
Turnaround<br />
Time<br />
15 days<br />
15 days<br />
15 days<br />
15 days<br />
15 days<br />
Laboratory/<br />
Organization<br />
(name and<br />
address,<br />
contact<br />
person and<br />
telephone<br />
number)<br />
Tina Green<br />
BC Labs<br />
4100 Atlas<br />
Court<br />
Bakersfield,<br />
CA. 93308<br />
Simone Singh<br />
EM Lab<br />
1150 Bayhill<br />
Drive, Suite<br />
100<br />
San Bruno,<br />
CA 94066<br />
Tina Green<br />
BC Labs<br />
4100 Atlas<br />
Court<br />
Bakersfield,<br />
CA. 93308<br />
Simone Singh<br />
EM Lab<br />
1150 Bayhill<br />
Drive, Suite<br />
100<br />
San Bruno,<br />
CA 94066<br />
Tina Green<br />
BC Labs<br />
4100 Atlas<br />
Court<br />
Bakersfield,<br />
CA. 93308<br />
Backup<br />
Laboratory/<br />
Organization<br />
(name and<br />
address,<br />
contact<br />
person and<br />
telephone<br />
number)<br />
NA<br />
NA<br />
NA<br />
NA<br />
NA<br />
Final Sampling and Analysis Plan<br />
Installation Restoration Site 29, Hangar 1<br />
Former Naval Air Station, <strong>Moffett</strong> <strong>Field</strong>, <strong>Moffett</strong> <strong>Field</strong>, Cali<strong>for</strong>nia<br />
DCN: AMEC-8816-0005-0039<br />
April 2010<br />
Page 30-1
Matrix<br />
Water<br />
Analytical<br />
Group<br />
PCBs,<br />
Chromium,<br />
Zinc, Lead,<br />
pH<br />
Sample<br />
Locations/ID<br />
Number<br />
A-TW-ddmmyy<br />
Analytical<br />
Method<br />
EPA<br />
8082,<br />
6020,<br />
150.1<br />
Data<br />
Package<br />
Turnaround<br />
Time<br />
15 days<br />
Laboratory/<br />
Organization<br />
(name and<br />
address,<br />
contact<br />
person and<br />
telephone<br />
number)<br />
Tina Green<br />
BC Labs<br />
4100 Atlas<br />
Court<br />
Bakersfield,<br />
CA. 93308<br />
Backup<br />
Laboratory/<br />
Organization<br />
(name and<br />
address,<br />
contact<br />
person and<br />
telephone<br />
number)<br />
NA<br />
Final Sampling and Analysis Plan<br />
Installation Restoration Site 29, Hangar 1<br />
Former Naval Air Station, <strong>Moffett</strong> <strong>Field</strong>, <strong>Moffett</strong> <strong>Field</strong>, Cali<strong>for</strong>nia<br />
DCN: AMEC-8816-0005-0039<br />
April 2010<br />
Page 30-2
WORKSHEET #31: <strong>PLAN</strong>NED PROJECT ASSESSMENTS TABLE<br />
This worksheet identifies the different types of assessments <strong>for</strong> evaluating the project activities. The table below identifies the<br />
type, frequency, and responsible parties of planned assessment activities that will be per<strong>for</strong>med <strong>for</strong> the project. Laboratory<br />
assessments are not anticipated <strong>for</strong> this investigation, because only laboratories that have passed the evaluation of Naval<br />
Facilities Engineering Services Center (NFESC) or DoD ELAP will be utilized.<br />
Assessment<br />
Type<br />
Project<br />
Document<br />
Assessment<br />
Frequency<br />
Once <strong>for</strong><br />
each draft<br />
version of all<br />
planning<br />
documents<br />
Internal or<br />
External<br />
Internal<br />
Table 31-1. Planned Project Assessments Matrix<br />
Organization<br />
Per<strong>for</strong>ming<br />
Assessment<br />
AMEC<br />
Person(s)<br />
Responsible <strong>for</strong><br />
Per<strong>for</strong>ming<br />
Assessment<br />
(title and<br />
organizational<br />
affiliation)<br />
Ann Bernhardt<br />
AMEC Program QCM<br />
Person(s)<br />
Responsible <strong>for</strong><br />
Responding to<br />
Assessment<br />
Findings<br />
(title and<br />
organizational<br />
affiliation)<br />
Various report<br />
authors at AMEC<br />
Person(s) Responsible<br />
<strong>for</strong> Identifying and<br />
Implementing<br />
Corrective Actions<br />
(CA)<br />
(title and<br />
organizational<br />
affiliation)<br />
Mary Schneider<br />
AMEC Project QCM<br />
Person(s)<br />
Responsible <strong>for</strong><br />
Monitoring<br />
Effectiveness of CA<br />
(title and<br />
organizational<br />
affiliation)<br />
Ann Bernhardt<br />
AMEC Program QCM<br />
<strong>Field</strong> Sampling<br />
Technical<br />
Systems Audit<br />
Once during<br />
first week of<br />
field ef<strong>for</strong>t<br />
Internal<br />
AMEC<br />
Ann Bernhardt (or<br />
designee)<br />
AMEC Program QCM<br />
Mark Maniaci<br />
AMEC Construction<br />
Manager<br />
Mary Schneider<br />
AMEC Project QCM<br />
Mary Schneider<br />
AMEC Project QCM<br />
Final Sampling and Analysis Plan<br />
Installation Restoration Site 29, Hangar 1<br />
Former Naval Air Station, <strong>Moffett</strong> <strong>Field</strong>, <strong>Moffett</strong> <strong>Field</strong>, Cali<strong>for</strong>nia<br />
DCN: AMEC-8816-0005-0039<br />
April 2010<br />
Page 31-1
This page left intentionally blank.<br />
Final Sampling and Analysis Plan<br />
Installation Restoration Site 29, Hangar 1<br />
Former Naval Air Station, <strong>Moffett</strong> <strong>Field</strong>, <strong>Moffett</strong> <strong>Field</strong>, Cali<strong>for</strong>nia<br />
DCN: AMEC-8816-0005-0039<br />
April 2010<br />
Page 31-2
WORKSHEET #32: ASSESSMENT FINDINGS <strong>AND</strong> CORRECTIVE ACTION RESPONSES<br />
This worksheet describes the activities <strong>for</strong> identifying and correcting any problems encountered during the project that have the<br />
potential to impact data quality (e.g. sampling error).<br />
Assessment<br />
Type<br />
Project<br />
Document<br />
Assessment<br />
<strong>Field</strong><br />
Sampling<br />
Technical<br />
Systems<br />
Audit (TSA)<br />
Nature of<br />
Deficiencies<br />
Documentation<br />
Written<br />
comments (or<br />
embedded track<br />
changes) and<br />
signed peer<br />
review <strong>for</strong>m<br />
Memo or email<br />
Table 32-1. Assessment Findings and Corrective Action Response<br />
Individual(s)<br />
Notified of<br />
Findings (name,<br />
title, organization)<br />
Various report<br />
authors at AMEC<br />
Mark Maniaci<br />
AMEC<br />
Construction<br />
Manager,<br />
Ann Bernhardt<br />
AMEC Program<br />
QCM,<br />
Mike Schulz<br />
AMEC Project<br />
Manager,<br />
Angela Lind<br />
BRAC RPM,<br />
Narciso Ancog<br />
Navy QAO,<br />
Sarah Kloss<br />
EPA RPM,<br />
Elizabeth Wells<br />
Water Board<br />
Project Manager<br />
Timeframe of<br />
Notification<br />
Written comments<br />
(or embedded<br />
track changes)<br />
within 24 hours of<br />
document review<br />
Verbal notification<br />
within 24 hours<br />
and written within<br />
1 week<br />
Nature of<br />
Corrective Action<br />
Response<br />
Documentation<br />
Revised reports<br />
Corrective Action<br />
Report<br />
Notes:<br />
1 Corrective action response(s) <strong>for</strong> any significant event will be <strong>for</strong>warded to the EPA by the RPM<br />
Individual(s) Receiving<br />
Corrective Action<br />
Response 1 (name, title,<br />
organization)<br />
Ann Bernhardt<br />
AMEC Program QCM<br />
Mark Maniaci<br />
AMEC Construction<br />
Manager,<br />
Ann Bernhardt<br />
AMEC Program QCM,<br />
Mike Schulz<br />
AMEC Project Manager,<br />
Angela Lind<br />
BRAC RPM,<br />
Narciso Ancog<br />
Navy QAO,<br />
Sarah Kloss<br />
EPA RPM,<br />
Elizabeth Wells<br />
Water Board Project<br />
Manager<br />
Timeframe <strong>for</strong><br />
Response<br />
As soon as possible,<br />
but not later than 5<br />
working days<br />
following receipt of<br />
comments<br />
As soon as possible,<br />
but not later than 3<br />
working days<br />
following deficiency<br />
notification<br />
Final Sampling and Analysis Plan<br />
Installation Restoration Site 29, Hangar 1<br />
Former Naval Air Station, <strong>Moffett</strong> <strong>Field</strong>, <strong>Moffett</strong> <strong>Field</strong>, Cali<strong>for</strong>nia<br />
DCN: AMEC-8816-0005-0039<br />
April 2010<br />
Page 32-1
This page left intentionally blank.<br />
Final Sampling and Analysis Plan<br />
Installation Restoration Site 29, Hangar 1<br />
Former Naval Air Station, <strong>Moffett</strong> <strong>Field</strong>, <strong>Moffett</strong> <strong>Field</strong>, Cali<strong>for</strong>nia<br />
DCN: AMEC-8816-0005-0039<br />
April 2010<br />
Page 32-2
WORKSHEET #33: QUALITY ASSURANCE MANAGEMENT REPORTS<br />
This worksheet describes the type and frequency of each QA management report that will be<br />
generated <strong>for</strong> the project. The personnel responsible <strong>for</strong> generating the reports and the personnel<br />
receiving the reports are also identified in this worksheet.<br />
Type of Report<br />
Contractor<br />
Quality Control<br />
Report<br />
Contractor<br />
Production<br />
Report<br />
<strong>Field</strong> Sampling<br />
TSA<br />
Corrective Action<br />
Report<br />
Monthly Rework<br />
Items List<br />
Table 33-1. Quality Assurance Management Reports<br />
Frequency<br />
(daily, weekly<br />
monthly, quarterly,<br />
annually, etc.)<br />
Projected<br />
Delivery Date(s)<br />
Person(s)<br />
Responsible <strong>for</strong><br />
Report Preparation<br />
(title and<br />
organizational<br />
affiliation)<br />
Daily Daily Mary Schneider<br />
AMEC Project QCM<br />
Daily Daily Mark Maniaci<br />
AMEC Construction<br />
Manager<br />
Once during first<br />
week of field ef<strong>for</strong>t<br />
Once following any<br />
non-con<strong>for</strong>mance<br />
issue identified<br />
Monthly<br />
Verbal<br />
notification within<br />
24 hours and<br />
written audit<br />
report within 1<br />
week<br />
Verbal<br />
notification within<br />
24 hours and<br />
written report<br />
within 1 week<br />
Last working day<br />
of each month<br />
containing an<br />
open noncon<strong>for</strong>ming<br />
issue<br />
Mary Schneider (or<br />
designee)<br />
AMEC Project QCM<br />
Mary Schneider<br />
AMEC Project QCM<br />
Mary Schneider<br />
AMEC Project QCM<br />
Report Recipient(s)<br />
(title and organizational<br />
affiliation)<br />
ROICC<br />
Angela Lind<br />
ROICC<br />
Angela Lind<br />
Mark Maniaci<br />
AMEC Construction<br />
Manager,<br />
Ann Bernhardt<br />
AMEC Program QCM,<br />
Mike Schulz AMEC<br />
Project Manager,<br />
Angela Lind<br />
BRAC RPM, and<br />
Narciso Ancog<br />
Navy QAO - Navy<br />
Mark Maniaci<br />
AMEC Construction<br />
Manager,<br />
Ann Bernhardt<br />
AMEC Program QCM,<br />
Mike Schulz AMEC<br />
Project Manager,<br />
Angela Lind<br />
BRAC RPM, and<br />
Narciso Ancog<br />
Navy QAO<br />
Mark Maniaci<br />
AMEC Construction<br />
Manager,<br />
Ann Bernhardt<br />
AMEC Program QCM,<br />
Mike Schulz AMEC<br />
Project Manager,<br />
Angela Lind<br />
BRAC RPM, and<br />
Narciso Ancog<br />
Navy QAO<br />
Final Sampling and Analysis Plan<br />
Installation Restoration Site 29, Hangar 1<br />
Former Naval Air Station, <strong>Moffett</strong> <strong>Field</strong>, <strong>Moffett</strong> <strong>Field</strong>, Cali<strong>for</strong>nia<br />
DCN: AMEC-8816-0005-0039<br />
April 2010<br />
Page 33-1
This page left intentionally blank.<br />
Final Sampling and Analysis Plan<br />
Installation Restoration Site 29, Hangar 1<br />
Former Naval Air Station, <strong>Moffett</strong> <strong>Field</strong>, <strong>Moffett</strong> <strong>Field</strong>, Cali<strong>for</strong>nia<br />
DCN: AMEC-8816-0005-0039<br />
April 2010<br />
Page 33-2
WORKSHEET #34: VERIFICATION (STEP 1) PROCESS TABLE<br />
This worksheet describes the processes that will be followed to verify project data quality.<br />
The table below describes how each item will be verified, when the activity will occur,<br />
what documentation is necessary, and who the responsible person is.<br />
Verification<br />
Input<br />
Chain-of-<br />
Custody<br />
Audit<br />
Reports<br />
<strong>Field</strong> Notes<br />
Analytical<br />
Data<br />
Packages<br />
Table 34-1. Verification Process<br />
Description<br />
Chain-of-custody <strong>for</strong>ms will be reviewed by the project team in the<br />
field upon completion and verified against the packed sample<br />
coolers they represent. The shipper’s signature on the chain-ofcustody<br />
will be initialed by the reviewer, a copy of the chain-ofcustody<br />
retained in the project file, and the original and remaining<br />
copies taped inside the cooler <strong>for</strong> shipment.<br />
A copy of all audit reports will be placed in the project file upon<br />
completion. If corrective actions are required, a copy of the<br />
documented corrective action taken will be attached to the<br />
appropriate audit report in the project file. At the beginning of each<br />
week and at the completion of the site work, project file audit reports<br />
will be reviewed internally to ensure that all appropriate corrective<br />
actions have been taken and that corrective action reports have<br />
been attached. If corrective actions have not been taken, the project<br />
manager will be notified to ensure action is taken.<br />
<strong>Field</strong> notes will be reviewed internally and placed in the project file.<br />
A copy of the field notes will be attached to the final report.<br />
All laboratory data packages will be verified internally by the<br />
laboratory per<strong>for</strong>ming the work <strong>for</strong> completeness and technical<br />
accuracy prior to submittal.<br />
All data packages will be verified externally by data validator who is<br />
not associated with the collection and analysis of samples,<br />
interpretation of sample data, or with any decision-making process<br />
within the scope of this investigation. The EWI #1 3EN2.1-specified<br />
data validation strategy <strong>for</strong> this project is 20% Level IV data<br />
validation and 80% Level III data validation <strong>for</strong> all laboratory data. In<br />
Level III data validation, data quality is assessed evaluating<br />
parameters by the appropriate criteria (or limits) specified in<br />
Worksheets 12, 19, and 28 of the project SAP, Contract Laboratory<br />
Program (CLP) requirements, EWI 3EN2.1 requirements, or the<br />
analytical methods. If calculations <strong>for</strong> quantitation are verified, it is<br />
done on a limited basis and may require raw data in addition to the<br />
standard data <strong>for</strong>ms normally present in a data package.<br />
Level IV data validation follows the EPA protocols and CLP criteria<br />
set <strong>for</strong>th in the functional guidelines <strong>for</strong> evaluating organic and<br />
inorganic analyses (EPA 1999, 2004). Level IV data validation<br />
consists of Level III data validation as well as checking calculations<br />
of quantified analytical data, including routine field samples and field<br />
and laboratory QC samples. Additionally, instrument per<strong>for</strong>mance,<br />
calibration, and calibration standard data are evaluated to ensure<br />
that detection limits and data values are appropriate.<br />
Internal/External<br />
Internal<br />
Internal<br />
Internal<br />
Internal and<br />
External<br />
Responsible<br />
<strong>for</strong><br />
Verification<br />
(name,<br />
organization)<br />
<strong>Field</strong><br />
Personnel<br />
Ann<br />
Bernhardt,<br />
AMEC<br />
Program<br />
QCM<br />
<strong>Field</strong><br />
Personnel<br />
Internal:<br />
Tina Green/<br />
BC Labs<br />
External:<br />
Jeanne<br />
Peterson/<br />
AQA<br />
Final Sampling and Analysis Plan<br />
Installation Restoration Site 29, Hangar 1<br />
Former Naval Air Station, <strong>Moffett</strong> <strong>Field</strong>, <strong>Moffett</strong> <strong>Field</strong>, Cali<strong>for</strong>nia<br />
DCN: AMEC-8816-0005-0039<br />
April 2010<br />
Page 34-1
This page left intentionally blank.<br />
Final Sampling and Analysis Plan<br />
Installation Restoration Site 29, Hangar 1<br />
Former Naval Air Station, <strong>Moffett</strong> <strong>Field</strong>, <strong>Moffett</strong> <strong>Field</strong>, Cali<strong>for</strong>nia<br />
DCN: AMEC-8816-0005-0039<br />
April 2010<br />
Page 34-2
WORKSHEET #35: VALIDATION (STEPS IIA <strong>AND</strong> IIB) PROCESS TABLE<br />
This worksheet describes the process <strong>for</strong> documenting and establishing the validation<br />
procedures and criteria <strong>for</strong> the project. Validation procedures and criteria are documented<br />
in the SAP to ensure that data are evaluated properly, completely, and consistently <strong>for</strong> use<br />
in meeting DQOs.<br />
Table 35-1. Validation Process<br />
Step<br />
IIa/IIb 1 Validation Input Description<br />
IIa<br />
IIa<br />
IIa<br />
IIa<br />
IIa<br />
IIa<br />
IIa<br />
IIa<br />
IIa<br />
IIa<br />
IIa<br />
Data Deliverables<br />
and SAP<br />
Analytes<br />
Chain-of-Custody<br />
Holding Times<br />
Sample Handling<br />
Sampling<br />
Methods and<br />
Procedures<br />
<strong>Field</strong><br />
Transcription<br />
Analytical<br />
Methods and<br />
Procedures<br />
Data Qualifiers<br />
Laboratory<br />
Transcription<br />
Standards<br />
Ensure that all required in<strong>for</strong>mation on sampling and<br />
analysis from Step I was provided (including planning<br />
documents).<br />
Ensure that required lists of analytes were reported as<br />
specified in governing documents (i.e. method,<br />
procedure, or contract).<br />
Examine the traceability of the data from time of<br />
sample collection until reporting of data. Examine<br />
chain-of-custody records against contract, method, or<br />
procedural requirements.<br />
Ensure that samples were analyzed within holding<br />
times specified in method, procedure, or contract<br />
requirements (Worksheet #19). If holding times were<br />
not met, confirm that deviations were documented,<br />
that appropriate notifications were made (consistent<br />
with procedural requirements), and that approval to<br />
proceed was received prior to analysis.<br />
Ensure that required sample handling, receipt, and<br />
storage procedures were followed, and that any<br />
deviations were documented. Verify summa canister<br />
vacuum present after sample collection and prior to<br />
analysis.<br />
Establish that required sampling methods were used<br />
and that any deviations were noted. Ensure that the<br />
sampling procedures and field measurements met<br />
per<strong>for</strong>mance criteria and that any deviations were<br />
documented.<br />
Authenticate transcription accuracy of sampling data<br />
(i.e. from field notebook to reports).<br />
Establish that required analytical methods were used<br />
and that any deviations were noted. Ensure that the<br />
QC samples met per<strong>for</strong>mance criteria and that any<br />
deviations were documented.<br />
Determine that the laboratory data qualifiers were<br />
defined and applied as specified in methods,<br />
procedures, or contracts.<br />
Authenticate accuracy of the transcription of analytical<br />
data (i.e. laboratory notebook to reporting <strong>for</strong>m, or<br />
instrument to LIMS).<br />
Determine that standards are traceable and meet<br />
contract, method, or procedural requirements.<br />
Responsible <strong>for</strong><br />
Validation<br />
(name, organization)<br />
Jeanne Peterson/ AQA<br />
Jeanne Peterson/ AQA<br />
Jeanne Peterson/ AQA<br />
Jeanne Peterson/ AQA<br />
Jeanne Peterson/ AQA<br />
Jeanne Peterson/ AQA<br />
Danille<br />
Jorgensen/AMEC<br />
Jeanne Peterson/ AQA<br />
Jeanne Peterson/ AQA<br />
Jeanne Peterson/ AQA<br />
Jeanne Peterson/ AQA<br />
Final Sampling and Analysis Plan<br />
Installation Restoration Site 29, Hangar 1<br />
Former Naval Air Station, <strong>Moffett</strong> <strong>Field</strong>, <strong>Moffett</strong> <strong>Field</strong>, Cali<strong>for</strong>nia<br />
DCN: AMEC-8816-0005-0039<br />
April 2010<br />
Page 35-1
Table 35-1. Validation Process<br />
Step<br />
IIa/IIb 1 Validation Input Description<br />
IIa<br />
IIa<br />
IIa<br />
IIb<br />
IIb<br />
IIb<br />
IIb<br />
IIb<br />
IIb<br />
IIb<br />
IIb<br />
IIb<br />
IIb<br />
Communication<br />
Audits<br />
Step IIa<br />
Validation Report<br />
Data Deliverables<br />
and SAP<br />
Deviations<br />
Sampling Plan<br />
Sampling<br />
Procedures<br />
<strong>Field</strong> Duplicates<br />
Project<br />
Quantitation<br />
Limits<br />
Confirmatory<br />
Analysis<br />
Per<strong>for</strong>mance<br />
Criteria<br />
Data Qualifiers<br />
Step IIb<br />
Validation Report<br />
Establish that required communication procedures<br />
were followed by field or laboratory personnel.<br />
Review laboratory audit reports, accreditation, and<br />
certification records <strong>for</strong> the laboratory’s per<strong>for</strong>mance<br />
on specific methods. Conduct field audit to verify<br />
compliance with planned procedures.<br />
Summarize deviations from methods, procedures, or<br />
contracts. Include qualified data and explanation of all<br />
data qualifiers.<br />
Ensure that the data report from Step IIa was<br />
provided.<br />
Determine the impacts of any deviations from<br />
sampling or analytical methods and SOPs. For<br />
example, confirm that the methods given in the SAP<br />
were used and, if they were not, determine if data still<br />
meet MPCs. Consider the effectiveness and<br />
appropriateness of any corrective action.<br />
Determine whether the sampling plan was executed<br />
as specified (i.e. the number, location, and type of<br />
field samples were collected and analyzed as<br />
specified in the SAP).<br />
Evaluate whether sampling procedures were followed<br />
with respect to equipment and proper sampling<br />
support (e.g. techniques, equipment,<br />
decontamination, volume, temperature, preservatives,<br />
etc.).<br />
Compare results of collocated field duplicates with<br />
criteria established in the SAP.<br />
Determine that quantitation limits were achieved, as<br />
outlined in the SAP, and that the laboratory<br />
successfully analyzed a standard at the QL.<br />
Evaluate agreement of laboratory results.<br />
Evaluate QC data against project-specific<br />
per<strong>for</strong>mance criteria in the SAP (i.e. evaluate quality<br />
parameters beyond those outlined in the methods).<br />
Determine that the data qualifiers applied in step IIa<br />
were those specified in the SAP and that any<br />
deviations from specifications were justified.<br />
Summarize outcome of comparison of data to MPC in<br />
the SAP. Include qualified data and explanation of all<br />
data qualifiers.<br />
Responsible <strong>for</strong><br />
Validation<br />
(name, organization)<br />
Danille<br />
Jorgensen/AMEC<br />
Danille<br />
Jorgensen/AMEC<br />
Mary Schneider/AMEC<br />
Jeanne Peterson/ AQA<br />
Danille<br />
Jorgensen/AMEC<br />
Danille<br />
Jorgensen/AMEC<br />
Danille<br />
Jorgensen/AMEC<br />
Danille<br />
Jorgensen/AMEC<br />
Danille<br />
Jorgensen/AMEC<br />
Danille<br />
Jorgensen/AMEC<br />
Danille<br />
Jorgensen/AMEC<br />
Danille<br />
Jorgensen/AMEC<br />
Danille<br />
Jorgensen/AMEC<br />
Danille<br />
Jorgensen/AMEC<br />
Note:<br />
1<br />
IIa-compliance with methods, procedures, and contracts [see Table 10, page 117, UFP-QAPP manual, V.1, March<br />
2005.]<br />
IIb-comparison with measurement per<strong>for</strong>mance criteria in the SAP [see Table 11, page 118, UFP-QAPP manual, V.1,<br />
March 2005]<br />
Final Sampling and Analysis Plan<br />
Installation Restoration Site 29, Hangar 1<br />
Former Naval Air Station, <strong>Moffett</strong> <strong>Field</strong>, <strong>Moffett</strong> <strong>Field</strong>, Cali<strong>for</strong>nia<br />
DCN: AMEC-8816-0005-0039<br />
April 2010<br />
Page 35-2
WORKSHEET #36: ANALYTICAL DATA VALIDATION (STEPS IIA <strong>AND</strong> IIB)<br />
SUMMARY TABLE<br />
Following data verification, data validation will be per<strong>for</strong>med in accordance with<br />
NAVFAC SW EWI#1 (SWDIV 2001a). Following the NAVFAC SW policy, an<br />
independent party with experience per<strong>for</strong>ming data validation <strong>for</strong> Navy projects will<br />
per<strong>for</strong>m the validation. With the exception of waste characterization samples, data will be<br />
validated at 80% EPA Level III and 20% EPA Level IV. Data validation will be per<strong>for</strong>med<br />
in accordance with the Navy Installation Restoration Chemical Data Quality Manual<br />
(NFESC, 1999), and patterned after the EPA CLP National Functional Guidelines <strong>for</strong><br />
Superfund Organic Methods Data Review and Inorganic Data Review (EPA 2008, 2004),<br />
and QC criteria specified in this document. Validation of data generated from previous<br />
investigations will generally con<strong>for</strong>m to Level III guidelines, except that evaluation of QC<br />
sample results will be limited to the in<strong>for</strong>mation provided in the available laboratory<br />
reports.<br />
For Level III data validation, data quality will be assessed by comparing the QC<br />
parameters to the appropriate criteria (or limits) as specified in this SAP. Verification of<br />
quantitation calculations may be per<strong>for</strong>med on a limited basis and may require raw data in<br />
addition to the standard data <strong>for</strong>ms.<br />
Level IV (full) data validation follows the EPA protocols and CLP criteria as set <strong>for</strong>th in<br />
the functional guidelines <strong>for</strong> evaluating organic (EPA 2008) and inorganic (EPA 2004)<br />
analyses. These guidelines apply to full data packages that include raw data (e.g.<br />
instrument spectra and chromatograms), backup documentation <strong>for</strong> calibration standards,<br />
analysis run logs, dilution factors, and additional in<strong>for</strong>mation necessary to check<br />
calculations <strong>for</strong> quantified analytical data. Calculations are checked <strong>for</strong> QC samples (e.g.<br />
MS/MSD and LCS data) and routine field samples (including field duplicates, field blanks,<br />
equipment blanks, and volatile organic compounds, trip blanks). To assure that detection<br />
limits and data values are appropriate, an instrument per<strong>for</strong>mance, method of calibration,<br />
and calibration standards are evaluated.<br />
Analytical data may be qualified based on data validation reviews. Qualifiers will be<br />
consistent with the applicable EPA national functional guidelines and will be used to<br />
provide data users with an estimate of the level of uncertainty associated with the qualified<br />
result.<br />
Data validation results will be evaluated with respect to the attached qualifiers to determine<br />
data usability issues, if any. The following qualifiers may be assigned during the validation<br />
process.<br />
Final Sampling and Analysis Plan<br />
Installation Restoration Site 29, Hangar 1<br />
Former Naval Air Station, <strong>Moffett</strong> <strong>Field</strong>, <strong>Moffett</strong> <strong>Field</strong>, Cali<strong>for</strong>nia<br />
DCN: AMEC-8816-0005-0039<br />
April 2010<br />
Page 36-1
J - estimated concentration<br />
R - rejected value (unusable)<br />
N - presumed identity<br />
U - not detected (e.g. not present based on blank contamination)<br />
UJ - sample detection limit is estimated.<br />
Data validation will be patterned after CLP NFG. The objectives, evaluations, and actions<br />
employed during the data validation process will follow those outlined in the NFG.<br />
Differences between NFG and project validation procedures will include; review items and<br />
data validation criteria. The laboratory will be permitted to provide CLP-like <strong>for</strong>ms in lieu<br />
of true CLP <strong>for</strong>ms. The data validation criteria will not adhere to NFG but will be based on<br />
method criteria <strong>for</strong> preservation, holding times, instrument tuning, calibration, instrument<br />
per<strong>for</strong>mance checks, internal standard responses, serial dilutions, and target compound ID;<br />
laboratory-specified criteria <strong>for</strong> surrogate, laboratory control samples, laboratory<br />
duplicates, and matrix spikes; and the validator’s professional judgment.<br />
Step<br />
IIa/ IIb<br />
Matrix<br />
IIa/IIb Wipe Lead<br />
IIa/IIb Wipe PCBs<br />
IIa/IIb Soil Lead<br />
IIa/IIb Soil PCBs<br />
Table 36-1. Analytical Data Validation Summary<br />
Analytical<br />
Group<br />
Validation Criteria<br />
EPA Method 6010B; EWI #1,<br />
DoD QSM<br />
EPA Method 8082, EWI #1,<br />
DoD QSM<br />
EPA Method 6010B; EWI #1,<br />
DoD QSM<br />
EPA Method 8082, EWI #1,<br />
DoD QSM<br />
Data Validator<br />
(title and organizational<br />
affiliation)<br />
IIa: Jeanne Peterson/ AQA<br />
IIb: Danille Jorgensen, AMEC<br />
IIa: Jeanne Peterson/ AQA<br />
IIb: Danille Jorgensen, AMEC<br />
IIa: Jeanne Peterson/ AQA<br />
IIb: Danille Jorgensen, AMEC<br />
IIa: Jeanne Peterson/ AQA<br />
IIb: Danille Jorgensen, AMEC<br />
Final Sampling and Analysis Plan<br />
Installation Restoration Site 29, Hangar 1<br />
Former Naval Air Station, <strong>Moffett</strong> <strong>Field</strong>, <strong>Moffett</strong> <strong>Field</strong>, Cali<strong>for</strong>nia<br />
DCN: AMEC-8816-0005-0039<br />
April 2010<br />
Page 36-2
WORKSHEET #37: USABILITY ASSESSMENT<br />
A data usability report will be prepared by AMEC incorporating the findings of the data<br />
validation ef<strong>for</strong>t, evaluation of the data against the DQOs specified in this SAP, and other<br />
supporting in<strong>for</strong>mation. This assessment will evaluate data on a matrix-specific, analytespecific<br />
and location-specific basis. The potential impact of any sampling discrepancies or<br />
data qualifications (rejected, nondetected, estimated) on the removal actions will be<br />
discussed with the remedial program manager (RPM) and QAO. Recommendations <strong>for</strong><br />
further actions will be provided, if necessary and appropriate.<br />
Elements that will be addressed in the usability report include, but are not limited to:<br />
• Compliance of sampling methods with the SAP<br />
• Completeness of sampling ef<strong>for</strong>t<br />
• Potential sampling error<br />
• Compliance of analyses with SAP methods and QC requirements<br />
• Completeness of laboratory analyses<br />
• Potential analytical error<br />
• Corrective actions and resolutions<br />
• Validation findings<br />
• Measurement per<strong>for</strong>mance criteria<br />
• Remedial options<br />
Completeness of sampling will be determined by the number of samples collected divided<br />
by the number of samples to be collected as specified in the SAP, expressed as a<br />
percentage. The requirement of completeness is 95% <strong>for</strong> sampling.<br />
Completeness <strong>for</strong> laboratory analyses will be determined by the number of valid results<br />
(results not qualified with a rejected (R) flag) divided by the number of possible individual<br />
analyte results, expressed as a percentage. The requirement <strong>for</strong> analytical completeness is<br />
95%.<br />
Assessment activities are presented below.<br />
Final Sampling and Analysis Plan<br />
Installation Restoration Site 29, Hangar 1<br />
Former Naval Air Station, <strong>Moffett</strong> <strong>Field</strong>, <strong>Moffett</strong> <strong>Field</strong>, Cali<strong>for</strong>nia<br />
DCN: AMEC-8816-0005-0039<br />
April 2010<br />
Page 37-1
Item<br />
Data<br />
Deliverables<br />
and SAP<br />
Deviations<br />
Sampling<br />
Locations<br />
Chain-of-<br />
Custody<br />
Holding Times<br />
Damaged<br />
Samples<br />
SOPs and<br />
Methods<br />
QC Samples<br />
Matrix<br />
Meteorological<br />
Data and Site<br />
Conditions<br />
Comparability<br />
Completeness<br />
Critical<br />
Samples<br />
Data<br />
Restrictions<br />
Usability<br />
Decision<br />
Usability<br />
Report<br />
Table 37-1. Usability Assessment Activities<br />
Assessment<br />
Activity<br />
Ensure that all necessary in<strong>for</strong>mation was provided, including but not<br />
limited to validation results.<br />
Determine the impact of deviations on the usability of data.<br />
Determine if alterations to sample locations continue to satisfy the project<br />
objectives.<br />
Establish that any problems with documentation or custody procedures do<br />
not prevent the data from being used <strong>for</strong> the intended purpose.<br />
Determine the acceptability of data where holding times were exceeded.<br />
Determine whether the data from damaged samples are usable. If the data<br />
cannot be used, determine whether resampling is necessary.<br />
Evaluate the impact of deviations from SOPs and specified methods on<br />
data quality.<br />
Evaluate the implications of unacceptable QC sample results on the data<br />
usability <strong>for</strong> the associated samples. For example, consider the effects of<br />
observed blank contamination.<br />
Evaluate matrix effects (interference or bias).<br />
Evaluate matrix effects (interference or bias).<br />
Evaluate the possible effects of meteorological (e.g. wind, rain,<br />
temperature) and site conditions on sample results. Review field reports to<br />
identify whether any unusual conditions were present and how the<br />
sampling plan was executed.<br />
Evaluate the impact of missing in<strong>for</strong>mation. Ensure that enough in<strong>for</strong>mation<br />
was obtained <strong>for</strong> the data to be usable (completeness as defined in PQOs<br />
documented in the SAP).<br />
Establish that critical samples and critical target analytes, as defined in the<br />
SAP, were collected and analyzed. Determine if the results meet criteria<br />
specified in the SAP.<br />
Describe the exact process <strong>for</strong> handling data that do not meet PQOs (i.e.<br />
when measurement per<strong>for</strong>mance criteria are not met). Depending on how<br />
those data will be used, specify the restrictions on use of those data <strong>for</strong><br />
environmental decision-making.<br />
Determine if the data can be used to make a specific decision considering<br />
the implications of all deviations and corrective actions.<br />
Discuss and compare overall precision, accuracy/bias, representativeness,<br />
comparability, completeness, and sensitivity <strong>for</strong> each matrix, analytical<br />
group, and concentration level. Describe limitations on the use of project<br />
data if criteria <strong>for</strong> data quality indicators are not met.<br />
Person Responsible <strong>for</strong><br />
Activity<br />
Danille<br />
Jorgensen/AMEC<br />
Danille<br />
Jorgensen/AMEC<br />
Mike Schulz/AMEC<br />
Danille<br />
Jorgensen/AMEC<br />
Danille<br />
Jorgensen/AMEC<br />
Danille<br />
Jorgensen/AMEC<br />
Danille<br />
Jorgensen/AMEC<br />
Danille<br />
Jorgensen/AMEC<br />
Danille<br />
Jorgensen/AMEC<br />
Danille<br />
Jorgensen/AMEC<br />
Danille<br />
Jorgensen/AMEC<br />
Danille<br />
Jorgensen/AMEC<br />
Danille<br />
Jorgensen/AMEC<br />
Danille<br />
Jorgensen/AMEC<br />
Danille<br />
Jorgensen/AMEC<br />
Danille<br />
Jorgensen/AMEC<br />
Final Sampling and Analysis Plan<br />
Installation Restoration Site 29, Hangar 1<br />
Former Naval Air Station, <strong>Moffett</strong> <strong>Field</strong>, <strong>Moffett</strong> <strong>Field</strong>, Cali<strong>for</strong>nia<br />
DCN: AMEC-8816-0005-0039<br />
April 2010<br />
Page 37-2
REFERENCES<br />
Navy, 2001. Draft Proposed Plan <strong>for</strong> Stationwide No Action Sites, <strong>Moffett</strong> Federal Air<br />
<strong>Field</strong>, Cali<strong>for</strong>nia.<br />
Navy (Department of Navy), 2008. Action Memorandum <strong>for</strong> the Non-Time-Critical<br />
Removal Action <strong>for</strong> the PCB Contamination at Installation Restoration Site 29, Hangar<br />
1, Former Naval Air Station <strong>Moffett</strong> <strong>Field</strong>, <strong>Moffett</strong> <strong>Field</strong>, Cali<strong>for</strong>nia. December.<br />
Intergovernmental Data Quality Task Force (IDQTF). 2005a. Uni<strong>for</strong>m Federal Policy <strong>for</strong><br />
Quality Assurance Project Plans – Evaluating, Assessing, and Documenting<br />
Environmental Data Collection and Use Programs, Part 1: UFP-QAPP Manual. Final.<br />
Version 1. March.<br />
IDQTF. 2005b. Workbook <strong>for</strong> Uni<strong>for</strong>m Federal Policy <strong>for</strong> Quality Assurance Project Plans<br />
– Evaluating, Assessing, and Documenting Environmental Data Collection and Use<br />
Programs, Part 2A: UFP-QAPP Workbook, Final, Version 1, March.<br />
Naval Facilities Engineering Command, Southwest Division (SWDIV). 2001a.<br />
Environmental Work Instruction (EWI) #1: Chemical Data Validation. November.<br />
EPA. 2002. USEPA Guidance <strong>for</strong> Quality Assurance Project Plans, EPA QA/G-5, QAMS<br />
EPA. 2004. USEPA Contract Laboratory Program National Functional Guidelines <strong>for</strong><br />
Inorganic Data Review. October.<br />
EPA. 2006. Guidance on Systematic Planning Using the Data Quality Objectives Process,<br />
EPA QA/G-4<br />
EPA. 2007. Test Methods <strong>for</strong> Evaluating Solid Wastes (SW-846). 3 rd Edition. Revision 6.<br />
February.<br />
Final Sampling and Analysis Plan<br />
Installation Restoration Site 29, Hangar 1<br />
Former Naval Air Station, <strong>Moffett</strong> <strong>Field</strong>, <strong>Moffett</strong> <strong>Field</strong>, Cali<strong>for</strong>nia<br />
DCN: AMEC-8816-0005-0039<br />
April 2010<br />
References Page 1
This page left intentionally blank.<br />
Final Sampling and Analysis Plan<br />
Installation Restoration Site 29, Hangar 1<br />
Former Naval Air Station, <strong>Moffett</strong> <strong>Field</strong>, <strong>Moffett</strong> <strong>Field</strong>, Cali<strong>for</strong>nia<br />
DCN: AMEC-8816-0005-0039<br />
April 2010<br />
References Page 2
APPENDIX A<br />
ST<strong>AND</strong>ARD OPERATING PROCEDURES<br />
Final Sampling and Analysis Plan<br />
Installation Restoration Site 29, Hangar 1<br />
Former Naval Air Station, <strong>Moffett</strong> <strong>Field</strong>, <strong>Moffett</strong> <strong>Field</strong>, Cali<strong>for</strong>nia<br />
DCN: AMEC-8816-0005-0039<br />
April 2010
This page left intentionally blank.<br />
Final Sampling and Analysis Plan<br />
Installation Restoration Site 29, Hangar 1<br />
Former Naval Air Station, <strong>Moffett</strong> <strong>Field</strong>, <strong>Moffett</strong> <strong>Field</strong>, Cali<strong>for</strong>nia<br />
DCN: AMEC-8816-0005-0039<br />
April 2010
AMEC<br />
Standard Operating Procedures<br />
Procedure No.:<br />
FP-F-7<br />
Revision No.: 0<br />
Revision Date:<br />
Page: 1 of 1<br />
Approved by:<br />
SAMPLE H<strong>AND</strong>LING, STORAGE,<br />
<strong>AND</strong> SHIPPING<br />
Ann Bernhardt<br />
PERMAC QC Manager<br />
1.0 PURPOSE<br />
The objective of this procedure is to provide standard methods <strong>for</strong> handling, storing, and<br />
transporting of environmental samples following their collection.<br />
2.0 SCOPE<br />
This procedure will be used during the collection of all types of environmental media that<br />
include, but are not limited to, groundwater, surface water, soil, and sediment.<br />
This procedure has been developed to serve as AMEC Earth and Environmental<br />
(AMEC)-approved professional guidance <strong>for</strong> the AMEC Program. As professional<br />
guidance <strong>for</strong> specific activities, this procedure is not intended to obviate the need <strong>for</strong><br />
professional judgment to accommodate un<strong>for</strong>eseen circumstances. Deviation from this<br />
procedure in the execution of planned activities must be documented in the field logbook.<br />
3.0 DEFINITIONS<br />
Temperature Blank – A vial filled with tap water and stored in the cooler during sample<br />
collection and transportation. The temperature of the cooler will be recorded by the<br />
laboratory on the chain-of-custody record immediately upon receipt of the samples.<br />
4.0 RESPONSIBILITIES<br />
The Project Manager or designee will have the responsibility to oversee and ensure that<br />
the handling of samples is in accordance with this standard operating procedure (SOP)<br />
and project specific Sampling and Analysis Plan (SAP).<br />
The field sampling personnel will be responsible <strong>for</strong> the understanding and<br />
implementation of this SOP during all sampling activities, as well as, obtaining the<br />
FP-F-7-1
AMEC<br />
Standard Operating Procedures<br />
Procedure No.:<br />
FP-F-7<br />
Revision No.: 0<br />
Revision Date:<br />
Page: 2 of 2<br />
appropriate field logbooks, <strong>for</strong>ms, and records necessary to complete the sampling<br />
activities.<br />
The Quality Control (QC) Manager is responsible <strong>for</strong> ensuring that sample handling,<br />
storage, and transport activities conducted during all projects are in compliance with this<br />
SOP.<br />
5.0<br />
PROCEDURES<br />
The following method outlines general considerations <strong>for</strong> sample handlings in the field<br />
and maintaining sample custody after collection.<br />
Immediately following collection, all samples will be labeled in accordance with<br />
procedure FP-F-6 Record Keeping, Sample Labeling, and Chain-of-Custody. Sample<br />
labels are required on all sample containers <strong>for</strong> the purpose of sample identification. A<br />
chain-of-custody <strong>for</strong>m must be initiated at the time that the sample containers are filled.<br />
Immediately after sample labeling, custody seals will be affixed to each sample<br />
container.The lids of the containers shall not be sealed with duct tape. For vials, the<br />
custody seal will be placed on the outside of the first resealable bag; then the container<br />
will be placed in a second resealable bag. This will prevent any contact with the<br />
adhesive from the custody seal and the sample. Other sample containers will be placed in<br />
double-resealable plastic bags to protect the sample from moisture, and to prevent<br />
breakage and potential cross-contamination during transportation to the laboratory. All<br />
glass sample containers will be protected with bubble wrap first, if transported by a<br />
commercial carrier. Vials should be wrapped with bubble wrap, then placed in a<br />
resealable bag, a custody seal placed over the bag, and then placed in another resealable<br />
bag. Samples must be placed in an insulated cooler with ice to preserve at 6 o C during<br />
field work.<br />
Samples shall be shipped as soon as possible to allow the laboratory to meet holding<br />
times <strong>for</strong> analysis. Environmental samples, including groundwater samples, are currently<br />
exempt from Hazardous Goods regulation. 40 Code of Federal Regulations 261.40(d)<br />
states, “A sample of solid waste or a sample of water, soil or air which is collected fro the<br />
sole purpose of testing to determine its characteristics or composition is not subject to<br />
this Part or Parts 262 through 267 or Part 124 of this chapter or to notification<br />
requirements of Section 3010 of RCRA.” There<strong>for</strong>e, no special regulations are required<br />
to be followed <strong>for</strong> the shipment of environmental samples from the field. However,<br />
sample containers should be properly packed such that inadvertent spillage does not<br />
occur during shipment (e.g., any discharge spouts should be taped closed).<br />
FP-F-7-2
AMEC<br />
Standard Operating Procedures<br />
Procedure No.:<br />
FP-F-7<br />
Revision No.: 0<br />
Revision Date:<br />
Page: 3 of 3<br />
The sample containers will be placed in an insulated cooler with ice in double-resealable<br />
bags or with pre-frozen “blue ice”. Ice will be placed at the bottom of the<br />
cooler; one<br />
layer of sample containers will be placed on the ice, and more double-bagged ice will be<br />
placed on top of the containers. This will be repeated until the cooler is filled with ice as<br />
the top layer in the cooler. Each cooler will be shipped with a temperature blank.<br />
The field personnel collecting the samples will be responsible <strong>for</strong> the custody of the<br />
samples until transport to the laboratory by either transferring to a laboratory<br />
representative or shipping by common carriers (i.e., Federal Express). If samples are to<br />
be transferred to a laboratory representative, signature of individuals relinquishing and<br />
receiving the samples, and date and time of transfer must be completed on the chain-ofcustody<br />
<strong>for</strong>m. A copy of the chain-of-custody record will be maintained by the field<br />
personnel. Common carriers are not expected to sign the chain-of-custody <strong>for</strong>m.<br />
However, the bill of lading or airbill becomes part of the chain-of-custody record.<br />
If samples are to be shipped by common carriers, the top two copies of the chain-of-<strong>for</strong>m<br />
will be placed in a double-resealable bag and then taped to the inside of the sample cooler<br />
lid. The cooler will be taped shut with strapping tape. Two custody seals will be taped<br />
across the cooler lid: one seal in the front and one seal in the back. Clear tape will be<br />
applied to the custody seals to prevent accidental breakage during shipment. The pouch<br />
<strong>for</strong> the airbill will be placed on the cooler and secured with clear tape. The airbill will be<br />
completed <strong>for</strong> priority overnight delivery and placed in the pouch. If multiple coolers are<br />
being shipped, the original airbill will be placed on the cooler with the chain-of-custody<br />
record, and copies of the airbill will be placed on the other coolers. The number of<br />
packages should be included on each airbill (e.g., 1 of 2, 2 of 2). Saturday deliveries<br />
should be coordinated with the laboratory in advance, and field sampling personnel, or<br />
their designees, must ensure that Saturday delivery stickers are placed on each cooler by<br />
the commercial courier. A letter stating the names and telephone numbers of AMEC and<br />
laboratory personnel at various locations who can be contacted in the event of problems<br />
with the sample shipment should also be taped to the outside of the cooler.<br />
6.0 RECORDS<br />
<strong>Field</strong> personnel are responsible <strong>for</strong> assuring that the original documentation is maintained<br />
in the project file.<br />
FP-F-7-3
AMEC<br />
Standard Operating Procedures<br />
Procedure No.:<br />
FP-F-7<br />
Revision No.: 0<br />
Revision Date:<br />
Page: 4 of 4<br />
7.0 REFERENCES<br />
None.<br />
8.0 ATTACHMENTS<br />
Example chain-of-custody<br />
Example Sample Label<br />
Example custody seal<br />
FP-F-7-4
AMEC<br />
Standard Operating Procedures<br />
Procedure No.:<br />
FP-F-7<br />
Revision No.: 0<br />
Revision Date:<br />
Page: 5 of 5<br />
ATTACHMENT<br />
FP-F-7-5
AMEC<br />
Standard Operating Procedures<br />
Procedure No.:<br />
FP-F-7<br />
Revision No.: 0<br />
Revision Date:<br />
Page: 6 of 6<br />
SAMPLE LABEL (EXAMPLE)<br />
AMEC<br />
7376 SW Durham Road<br />
Portland, Oregon 97224<br />
PH: 503-639-3400<br />
FX: 503-620-7892<br />
Job Name:<br />
Job Number:<br />
Sample I.D.:<br />
Date:<br />
Sampler:<br />
Time:<br />
Comments:<br />
CUSTODY SEAL (EXAMPLE)<br />
CUSTODY SEAL<br />
Person Collecting Sample: ____________________________ Sample No.:______<br />
(Signature)<br />
Date Collected:______________ Time___________<br />
__________________________________________________________<br />
FP-F-7-6
Procedure No.: FP-F-7<br />
AMEC Earth & Environmental<br />
Revision No.: 0<br />
Standard Operating Procedures Revision Date:<br />
Page: 7 of 7<br />
Project Name:<br />
Project Number:<br />
Project Manager:<br />
SHIP TO:<br />
DATE:<br />
AMEC<br />
7376 SW Durham Road<br />
Portland, OR 97224<br />
C HAIN OF CUSTODY COC #:<br />
(503) 639-3400 PAGE:<br />
Project Contact: Bill To: AMEC Disposal Instructions:<br />
Phone Number:<br />
Shipment Method:<br />
Project Phase:<br />
Waybill Number:<br />
OF<br />
LAB<br />
COURIER/FedEx<br />
N/A<br />
Sample In<strong>for</strong>mation Methods <strong>for</strong> Analysis RUSH<br />
No.<br />
1<br />
2<br />
3<br />
4<br />
5<br />
6<br />
7<br />
8<br />
9<br />
10<br />
11<br />
12<br />
Sample ID<br />
Date<br />
Sampled Time Sampled Matrix<br />
Sam pler's Signature: Date:<br />
Tim e:<br />
For Lab Use<br />
For Lab Use<br />
Does COC match samples: Y or N Comments: H=Hold Analysis Request X=Analyze<br />
Relinquished By/Affiliation:<br />
Date :<br />
Time: Broken Container:<br />
COC seal intact:<br />
Y or N<br />
Received By:<br />
Relinquished By/Affiliation:<br />
Date :<br />
Date :<br />
Time: Other problems:<br />
AMEC contacted:<br />
Time: Date contacted:<br />
Y or N<br />
Y or N<br />
Y or N<br />
Received By: Date :<br />
Time: Cooler Temperature at receipt: C<br />
Relinquished By/Affiliation:<br />
Date :<br />
Time:<br />
NUMBER OF COOLERS SENT:<br />
Received By (LAB): Date :<br />
Tim e:<br />
FP-F-7-7
APPENDIX B<br />
FIELD FORMS<br />
Final Sampling and Analysis Plan<br />
Installation Restoration Site 29, Hangar 1<br />
Former Naval Air Station, <strong>Moffett</strong> <strong>Field</strong>, <strong>Moffett</strong> <strong>Field</strong>, Cali<strong>for</strong>nia<br />
DCN: AMEC-8816-0005-0039<br />
April 2010
This page left intentionally blank.<br />
Final Sampling and Analysis Plan<br />
Installation Restoration Site 29, Hangar 1<br />
Former Naval Air Station, <strong>Moffett</strong> <strong>Field</strong>, <strong>Moffett</strong> <strong>Field</strong>, Cali<strong>for</strong>nia<br />
DCN: AMEC-8816-0005-0039<br />
April 2010
This page left intentionally blank.<br />
Final Sampling and Analysis Plan<br />
Installation Restoration Site 29, Hangar 1<br />
Former Naval Air Station, <strong>Moffett</strong> <strong>Field</strong>, <strong>Moffett</strong> <strong>Field</strong>, Cali<strong>for</strong>nia<br />
DCN: AMEC-8816-0005-0039<br />
April 2010
This page left intentionally blank.<br />
Final Sampling and Analysis Plan<br />
Installation Restoration Site 29, Hangar 1<br />
Former Naval Air Station, <strong>Moffett</strong> <strong>Field</strong>, <strong>Moffett</strong> <strong>Field</strong>, Cali<strong>for</strong>nia<br />
DCN: AMEC-8816-0005-0039<br />
April 2010
This page left intentionally blank.<br />
Final Sampling and Analysis Plan<br />
Installation Restoration Site 29, Hangar 1<br />
Former Naval Air Station, <strong>Moffett</strong> <strong>Field</strong>, <strong>Moffett</strong> <strong>Field</strong>, Cali<strong>for</strong>nia<br />
DCN: AMEC-8816-0005-0039<br />
April 2010
Sample Collection Log<br />
Sample name Sample ID Parent Sample<br />
Trip Blank<br />
Association<br />
Equipment/Rinse<br />
Blank Association<br />
<strong>Field</strong> Blank<br />
Association<br />
Source Blank<br />
Sample<br />
Type<br />
Sample er Initials<br />
Spike Collected? (Y?N)<br />
Matrix<br />
Matrix<br />
Sample<br />
Start Depth (feet)<br />
Sample<br />
End Depth (feet)<br />
Sample<br />
Date<br />
Sample<br />
Time<br />
PCBs 8082<br />
Lead 6010<br />
Asbes stos<br />
Notes<br />
C:\<strong>Documents</strong> and Settings\gerrie.gomez\Desktop\Gerrie Gomez\00 PERMAC\moffett <strong>for</strong> size\Appendix B\Sample Collection Log.xls Page 1 8:58 AM4/12/2010
APPENDIX C<br />
RESPONSES TO COMMENTS<br />
Final Sampling and Analysis Plan<br />
Installation Restoration Site 29, Hangar 1<br />
Former Naval Air Station, <strong>Moffett</strong> <strong>Field</strong>, <strong>Moffett</strong> <strong>Field</strong>, Cali<strong>for</strong>nia<br />
DCN: AMEC-8816-0005-0039<br />
April 2010
This page left intentionally blank.<br />
Final Sampling and Analysis Plan<br />
Installation Restoration Site 29, Hangar 1<br />
Former Naval Air Station, <strong>Moffett</strong> <strong>Field</strong>, <strong>Moffett</strong> <strong>Field</strong>, Cali<strong>for</strong>nia<br />
DCN: AMEC-8816-0005-0039<br />
April 2010
RESPONSE TO COMMENTS ON<br />
Draft Sampling and Analysis Plan <strong>for</strong> Non-Time Critical Removal Action<br />
<strong>for</strong> Polychlorinated Biphenyl Contamination at Installation Restoration Site<br />
29 Hangar 1<br />
Former Naval Air Station <strong>Moffett</strong> <strong>Field</strong><br />
<strong>Moffett</strong> <strong>Field</strong>, Cali<strong>for</strong>nia<br />
Comments by:<br />
Sarah Kloss<br />
Remedial Project Manager<br />
US EPA Region 9<br />
DCN: AMEC‐ 8816‐0005‐0040<br />
Responses by:<br />
AMEC Earth & Environmental, Inc.<br />
Line Number<br />
Section/Figure/<br />
Table/Appendix<br />
Comments<br />
1 Worksheet 10 Scope of Soil Sampling: Worksheet<br />
#10 of the Draft Sampling and<br />
Analysis Plan (SAP) states that one<br />
of the objectives of the soil<br />
sampling is to "verify that the<br />
removal is executed without the<br />
release of PCBs into the<br />
environment as a result of the<br />
removal action." However, it is not<br />
clear how the area of potential<br />
impact due to the removal action<br />
was determined. The soil sampling<br />
design proposed assumes that<br />
possible PCB releases during the<br />
removal action will deposit on the<br />
soil within 35 ft of the Hangar<br />
footprint. Please revise the report to<br />
include justification why the 35 ft<br />
radius is considered appropriate or<br />
Responses (Contractor)<br />
The soil sampling strategy will be<br />
revised. A grid approach will be<br />
utilized to collect soil samples<br />
from soil areas on the east side of<br />
the Hangar. The grid will cover the<br />
entire soil area. Language<br />
regarding a lateral step-out<br />
approach will be eliminated.<br />
Response to Comments on Draft Sampling and Analysis Plan<br />
<strong>Moffett</strong> <strong>Field</strong>, Cali<strong>for</strong>nia<br />
DCN: AMEC-8816-0005-0040<br />
April 2010<br />
Page 1 of 10
expand the radius as necessary.<br />
2 SAP Ecological Receptors: Please<br />
include justification <strong>for</strong> why the soil<br />
areas adjacent to Hangar 1 are not<br />
considered ecologically important.<br />
Likewise, if the radius of potential<br />
impact expands in the next revision<br />
of this SAP, the Navy should<br />
evaluate potential ecological<br />
impacts in other nearby unpaved<br />
areas that may be considered<br />
habitat. An alternative to expanding<br />
the baseline soil sampling radius<br />
due to ecological concerns would be<br />
to expand air monitoring to include<br />
potential habitat areas that could be<br />
impacted by the removal action.<br />
3 Worksheets 11, 14, 15, 17 The rationale <strong>for</strong> the where the<br />
samples are located and the number<br />
of samples <strong>for</strong> each area (concrete<br />
pad, soil, etc.) is not provided. Also,<br />
the soil areas should be fully<br />
characterized. Due to the large<br />
height of Hangar 1, PCBs could be<br />
found at 35 ft from the edge of the<br />
pavement even if they are not found<br />
at 20 ft; thus, the Navy should<br />
sample at 35 ft from the pavement<br />
edge regardless of the 20 ft results.<br />
Revise the SAP to provide the<br />
rationale <strong>for</strong> the selected sampling<br />
locations, indicate if the sample<br />
The Pre-Final Draft will provide<br />
references to substantiate that the<br />
soil areas adjacent to the hangar<br />
are not ecologically sensitive.<br />
Additional site description<br />
in<strong>for</strong>mation will be provided that<br />
defines the distance of other<br />
potential nearby habitats from the<br />
hangar.<br />
See response to general comment<br />
1.<br />
Response to Comments on Draft Sampling and Analysis Plan<br />
<strong>Moffett</strong> <strong>Field</strong>, Cali<strong>for</strong>nia<br />
DCN: AMEC-8816-0005-0040<br />
April 2010<br />
Page 2 of 10
Worksheets 11, 14, 15, 17<br />
Worksheets 11, 14, 15, 17<br />
locations were selected randomly<br />
and edit the sampling approach to<br />
include analyzing all samples at<br />
once instead of a step-out approach.<br />
The soil decision units is (are) not<br />
clearly defined. Step 5 of Table 11-<br />
1 states that the contaminated soil at<br />
the area where exceedance was<br />
detected will be removed. However,<br />
the boundaries of the area that<br />
would be removed are not indicated<br />
in the SAP. Revise the SAP to<br />
define the decision units <strong>for</strong> the<br />
potential soil excavation areas.<br />
Please eliminate the references to<br />
the 95% confidence levels <strong>for</strong><br />
confirming the removal action has<br />
not impacted soil. The comparison<br />
between baseline and post- removal<br />
levels should be conducted on a<br />
point by point basis with regulatory<br />
consultation. The 95% confidence<br />
interval approach may average over<br />
too large of an area to be able to<br />
The Pre-Final Draft will define the<br />
soil decision units and boundaries<br />
of excavation areas. A grid<br />
approach will be adopted <strong>for</strong><br />
baseline and confirmation<br />
sampling. In general, if an<br />
exceedance occurs at any sample<br />
location, the soil will be excavated<br />
half way to the next clean location,<br />
in each direction. Confirmation<br />
samples will then be collected<br />
from the bottom of the excavation,<br />
at the center and on all four sides<br />
of the excavation. Sample results<br />
will be provided to both EPA and<br />
Water Board <strong>for</strong> consultation on<br />
the specific soil removal approach.<br />
Text references to the 95% will be<br />
removed. The comparison between<br />
baseline and post- removal levels<br />
will be conducted on a point by<br />
point basis in consultation with<br />
EPA and the Water Board.<br />
Response to Comments on Draft Sampling and Analysis Plan<br />
<strong>Moffett</strong> <strong>Field</strong>, Cali<strong>for</strong>nia<br />
DCN: AMEC-8816-0005-0040<br />
April 2010<br />
Page 3 of 10
Worksheets 11, 14, 15, 17<br />
spot smaller impacted areas.<br />
The timing and depth of the<br />
excavation described in Worksheet<br />
#17 is unclear. Worksheet #17<br />
states that if the PCB results <strong>for</strong><br />
baseline/pre-construction samples<br />
are greater than 1,000 micrograms<br />
per kilogram (ug/kg), the 12-inch<br />
depth samples "may" be analyzed to<br />
determine vertical extent and the<br />
soil down to 6 inches will be<br />
removed. The plan should clearly<br />
state that the Navy will analyze the<br />
12-inch samples if the 6-inch<br />
samples show PCBs are above the<br />
action level. Also, please specify if<br />
the 12-inch samples will be<br />
analyzed be<strong>for</strong>e or after excavation<br />
of the top six inches of soil (if any<br />
excavation is needed). Finally, it is<br />
unclear if additional action would<br />
be per<strong>for</strong>med as a part of this<br />
removal action should the 12-inch<br />
samples exceed the action limits.<br />
Revise the SAP to clarify the<br />
decision criteria and timing of each<br />
step.<br />
The Pre-Final Draft plan will state<br />
that the Navy will analyze the 12-<br />
inch samples if the 6-inch samples<br />
show PCBs are above the action<br />
level. The 12-inch samples will be<br />
analyzed be<strong>for</strong>e excavation of the<br />
top 6 inches. If the 12 inch<br />
samples exceed the action limit,<br />
then additional excavation will<br />
occur until the action levels are<br />
met. The SAP will be revised to<br />
clarify the decision criteria and<br />
timing of each step.<br />
Response to Comments on Draft Sampling and Analysis Plan<br />
<strong>Moffett</strong> <strong>Field</strong>, Cali<strong>for</strong>nia<br />
DCN: AMEC-8816-0005-0040<br />
April 2010<br />
Page 4 of 10
Worksheets 11, 14, 15, 17<br />
The description of the procedure <strong>for</strong><br />
collecting the excavation<br />
confirmation samples presented in<br />
Worksheet #14 is insufficiently<br />
detailed. For example, it is not clear<br />
what depth will be targeted <strong>for</strong><br />
these samples and why the top two<br />
inches of top soil will be removed<br />
prior to collection of the<br />
confirmation samples. Revise<br />
Worksheet # 14 to provide<br />
additional details and justification<br />
<strong>for</strong> how excavation confirmation<br />
samples will be collected.<br />
Revise the in<strong>for</strong>mation presented in<br />
Worksheets #11, #14, #15, and #17<br />
to be consistent and clearly describe<br />
the timing and decision criteria <strong>for</strong><br />
all steps of the removal action. It<br />
may be useful to include a decision<br />
tree <strong>for</strong> this purpose.<br />
The sampling procedure <strong>for</strong><br />
confirmation samples will be<br />
revised to provide the requested<br />
detail. Confirmation samples will<br />
be collected from the bottom of<br />
the excavation, at the center and<br />
on all four sides.<br />
The in<strong>for</strong>mation in Worksheets 11,<br />
14, 15, and 17 will be revised to<br />
describe the new sampling<br />
approach (see response to<br />
comment 1 above). A new figure<br />
(decision tree) will be added in<br />
Worksheet 17 to illustrate the<br />
sequence and timing of data<br />
collection steps, decision points,<br />
and removal actions.<br />
4 Laboratory In<strong>for</strong>mation. The SAP<br />
does not provide the laboratoryspecific<br />
standard operating<br />
procedures (SOPs). Further, please<br />
specify if the quantitation limits<br />
(QLs) and method detection limits<br />
(MDLs) presented in Worksheet<br />
#15 are laboratory-specific limits or<br />
Laboratory-specific SOPs are not<br />
provided in the SAP because they<br />
are proprietary documents. They<br />
will be available <strong>for</strong> review, if<br />
requested.<br />
Per the NAVFAC SAP template<br />
requirements, MDLs and QLs<br />
Response to Comments on Draft Sampling and Analysis Plan<br />
<strong>Moffett</strong> <strong>Field</strong>, Cali<strong>for</strong>nia<br />
DCN: AMEC-8816-0005-0040<br />
April 2010<br />
Page 5 of 10
limits established by the analytical<br />
method or some other document.<br />
Also, discuss why the Project<br />
Quantitation Limit Goal <strong>for</strong> arsenic<br />
is less than the QL. Revise the SAP<br />
to include all relevant laboratoryspecific<br />
SOPs as discussed the<br />
Uni<strong>for</strong>m Federal Policy <strong>for</strong> Quality<br />
Assurance Project Plans Manual<br />
dated March 2005 (UFP QAPP<br />
Manual) or provide a summary of<br />
all laboratory procedures in the<br />
SAP. Also, revise the SAP to<br />
reference a source <strong>for</strong> the QLs and<br />
MDLs presented in Worksheet #15.<br />
Finally, assess the QL <strong>for</strong> arsenic to<br />
ensure that it meets the PAL.<br />
5 <strong>Field</strong> Duplicates. This SAP states<br />
that field duplicate samples will not<br />
be collected due to the nonhomogenous<br />
nature of soils and<br />
sediments; however, it is unclear<br />
how reliable decisions can be made<br />
if sample heterogeneity is a<br />
concern. Collection of duplicates is<br />
recommended and procedures<br />
should be included to assess sample<br />
heterogeneity. Revise the SAP to<br />
include field duplicates <strong>for</strong> soil and<br />
sediment samples. Additionally,<br />
indicate what measures will be<br />
taken to reduce sample<br />
heterogeneity.<br />
listed are specific to BC Labs as<br />
identified in Worksheet 30.<br />
The Project Quantitation Limit<br />
Goal <strong>for</strong> arsenic will be changed to<br />
0.5 mg/kg.<br />
<strong>Field</strong> duplicate samples <strong>for</strong> soil<br />
and sediment will be collected at<br />
10% frequency.<br />
The sampling procedure will be<br />
revised to include homogenization<br />
process.<br />
Response to Comments on Draft Sampling and Analysis Plan<br />
<strong>Moffett</strong> <strong>Field</strong>, Cali<strong>for</strong>nia<br />
DCN: AMEC-8816-0005-0040<br />
April 2010<br />
Page 6 of 10
6 Worksheets #6 and #32 Notification to EPA of Corrective<br />
Action. The corrective action<br />
presented in the SAP is<br />
insufficiently detailed. For example,<br />
the SAP does not indicate that EPA<br />
will be notified of any significant<br />
changes to the SAP by corrective<br />
action. Revise worksheets #6 and<br />
#32 to indicate that EPA will be<br />
notified of any significant<br />
corrective action and the time frame<br />
of notification.<br />
7 Data Validation. The SAP states<br />
that 20% of the data will be<br />
validated at Level IV and 80% will<br />
be validated at Level III. However,<br />
it is unclear how data will be<br />
selected <strong>for</strong> each level (e.g.,<br />
randomly). Revise the SAP to<br />
clarify this issue.<br />
8 Reporting Requirements. The SAP<br />
does not discuss manual<br />
integrations <strong>for</strong> chromatographic<br />
analyses or second column<br />
confirmation <strong>for</strong> PCB identification.<br />
Revise the SAP to indicate that if<br />
manual integration is required,<br />
supporting in<strong>for</strong>mation <strong>for</strong> manual<br />
integrations (i.e., chromatograms<br />
be<strong>for</strong>e and after manual integration<br />
as well as a brief explanation <strong>for</strong> the<br />
manual integration) will be included<br />
SAP will be revised accordingly.<br />
Samples <strong>for</strong> Level IV validation<br />
will be selected randomly.<br />
Reporting requirements <strong>for</strong> manual<br />
integrations and second column<br />
confirmation will be included in<br />
Section 14.7.5.<br />
Response to Comments on Draft Sampling and Analysis Plan<br />
<strong>Moffett</strong> <strong>Field</strong>, Cali<strong>for</strong>nia<br />
DCN: AMEC-8816-0005-0040<br />
April 2010<br />
Page 7 of 10
in the data package deliverables and<br />
evaluated during data validation.<br />
Further, revise the SAP to ensure<br />
that second column confirmation<br />
in<strong>for</strong>mation is provided <strong>for</strong> PCB<br />
analysis.<br />
9 Checklists The SAP does not contain data<br />
verification and quality control<br />
(QC) checklists. Revise the SAP to<br />
provide all data verifications and<br />
QC checklists as discussed in<br />
Section 5 of the UFP QAPP Manual<br />
(Data Review Elements).<br />
Specific Comments<br />
1 Page 10-2 Worksheet 10 Problem<br />
Definition<br />
2 Page 11-1 Worksheet #11 - Table 11-1,<br />
Data Quality Objectives<br />
Summary Pre-Construction and<br />
Confirmation Sampling<br />
3 Page 12-1 through 12-2 Worksheet #12 -<br />
Measurement Per<strong>for</strong>mance<br />
Criteria Table<br />
In the first sentence of the fourth<br />
paragraph please change<br />
"eliminate" to "address" or some<br />
other word that indicates that the<br />
risk will be greatly reduced, but not<br />
completely eliminated. Also, in the<br />
fifth paragraph please clarify that<br />
there have been no impacts to<br />
groundwater from PCBs, lead, or<br />
asbestos. There is evidence to<br />
suggest that the regional plume<br />
extends under the footprint of the<br />
Hangar.<br />
Please change "eliminate" to<br />
"address" or similar language <strong>for</strong><br />
Step 1 as noted in Specific<br />
Comment 1.<br />
This worksheet does not include<br />
any QC samples <strong>for</strong> asbestos.<br />
Revise the table to include QC<br />
samples <strong>for</strong> the asbestos analysis<br />
(e.g., confirmation of the<br />
Data verification in<strong>for</strong>mation as<br />
described in Section 5 of the UFP-<br />
QAPP manual is presented in<br />
Worksheet 34.<br />
Comment noted. The word<br />
“eliminate” will be replaced with<br />
“address” in the first sentence of<br />
the fourth paragraph.<br />
The first sentence of the fifth<br />
paragraph will be revised as “It<br />
should be noted … there have been<br />
no impacts on groundwater from<br />
PCBs, lead, or asbestos; …”.<br />
Comment noted. The word<br />
“eliminate” will be replaced with<br />
“address”.<br />
Comment noted. Worksheet 12<br />
will be revised.<br />
Response to Comments on Draft Sampling and Analysis Plan<br />
<strong>Moffett</strong> <strong>Field</strong>, Cali<strong>for</strong>nia<br />
DCN: AMEC-8816-0005-0040<br />
April 2010<br />
Page 8 of 10
4 Worksheet #15 - Reference<br />
Limits and Evaluation Table,<br />
Tables 15-1 and 15-4, Pages<br />
15-1 and 15-4<br />
5 Worksheet #15 - Reference<br />
Limits and Evaluation Table,<br />
Table 15-4, Page 15-4<br />
6 Worksheet #15 - Reference<br />
Limits and Evaluation Table,<br />
Table 15-7, Page 15-6<br />
7 Worksheet #15 - Reference<br />
Limits and Evaluation Table,<br />
Pages 15-1 through 15-3<br />
quantitation result by a second<br />
analysis of 10% of the analyzed<br />
samples).<br />
It is unclear if the PALs, QLs, and<br />
MDLs presented on this table are<br />
given on a dry weight or wet weight<br />
basis. Revise the SAP to clarify this<br />
in<strong>for</strong>mation.<br />
The acronym RSL stands <strong>for</strong><br />
"Regional" Screening Level.<br />
It is unclear if total Aroclors will be<br />
determined by adding individual<br />
Aroclor concentrations or if the area<br />
under the entire chromatogram will<br />
be quantified. If total Aroclor<br />
concentrations will be determined<br />
additively, it is unclear if and how<br />
non-detected results will be<br />
incorporated into the calculation<br />
(e.g., non-detects will be set at zero,<br />
the QL, or one half the QL, etc.).<br />
Revise this worksheet to describe<br />
how total Aroclor concentrations<br />
will be determined and how nondetected<br />
results will be<br />
incorporated.<br />
The project action limit listed <strong>for</strong><br />
asbestos, 1 %, is not considered<br />
health protective. In the event that<br />
fill will be imported, the Navy will<br />
have to work with the EPA to<br />
develop a more health protective<br />
process <strong>for</strong> screening asbestos in<br />
fill.<br />
Soil and sediment samples <strong>for</strong> this<br />
project will be reported on a dry<br />
weight basis. A footnote will be<br />
added to Table 15-1 and 15-4 to<br />
clarify this in<strong>for</strong>mation.<br />
Comment noted. The acronym will<br />
be revised.<br />
Total Aroclors will be determined<br />
by adding individual Aroclor<br />
concentrations. For this project,<br />
the laboratory will report detected<br />
concentration between method<br />
detection limit (MDL) and<br />
quantitation limit (QL) as<br />
estimated. If an Aroclor is not<br />
detected, the MDL value will be<br />
used to determine total Aroclor<br />
concentration.<br />
The project action limit <strong>for</strong><br />
asbestos will be revised to 0.25<br />
percent, as recommended by EPA.<br />
Response to Comments on Draft Sampling and Analysis Plan<br />
<strong>Moffett</strong> <strong>Field</strong>, Cali<strong>for</strong>nia<br />
DCN: AMEC-8816-0005-0040<br />
April 2010<br />
Page 9 of 10
8 Worksheet #19 - Analytical<br />
SOP Requirements Table,<br />
Page 19-1<br />
9 Worksheet #19 - Analytical<br />
SOP Requirements Table,<br />
Page 19-1<br />
10 Worksheet #28 - Laboratory<br />
QC Samples Table,<br />
Page 28-3 through 28-4<br />
11 Worksheet #30 - Analytical<br />
Services Table, Page 30-1<br />
The extraction methods listed <strong>for</strong><br />
the water and wipe matrices are not<br />
the methods recommended by EPA<br />
methods. For example, the SAP<br />
lists EPA Method 3050 and 3550B<br />
<strong>for</strong> extraction of water samples, but<br />
these methods are intended <strong>for</strong> solid<br />
matrices, not water. The PCB<br />
extraction method listed <strong>for</strong> the<br />
wipe samples (EPA Method 3580)<br />
is applicable to waste dilutions, not<br />
wipe samples. Revise this<br />
worksheet to present applicable<br />
methods <strong>for</strong> each analyte group and<br />
matrix.<br />
The Navy should discuss further<br />
with the EPA modifications to the<br />
CARB 435 method that may be<br />
needed to increase sensitivity once<br />
laboratory services <strong>for</strong> asbestos are<br />
procured.<br />
The table <strong>for</strong> Method 6010B states<br />
that post-digest spikes are analyzed<br />
when the dilution fails. However,<br />
post digest spikes should be<br />
analyzed when the matrix<br />
spike/matrix spike duplicate fails.<br />
Further, the QC limits <strong>for</strong> the post<br />
digest spike should reflect the limits<br />
established in the most recent<br />
version of EPA Method 6010C (i.e.,<br />
80-120%). Revise the table to<br />
correct<br />
these discrepancies.<br />
The table does not list a laboratory<br />
<strong>for</strong> asbestos analysis. Revise the<br />
table to include this in<strong>for</strong>mation.<br />
EPA method 3580 is not the<br />
extraction method of wipe<br />
matrices. Worksheet 19 will be<br />
revised with the appropriate<br />
extraction method <strong>for</strong> wipe<br />
samples.<br />
Comment noted. EPA will be<br />
contacted to discuss CARB 435<br />
method modifications if the<br />
subcontract laboratory is not able<br />
to meet reporting limit of 0.25<br />
percent.<br />
Laboratory per<strong>for</strong>ming samples <strong>for</strong><br />
DoD Installation Restoration<br />
project must meet DoD Quality<br />
System Manual (QSM)<br />
requirements. The acceptance<br />
limits and frequency of postdigestion<br />
spike presented in the<br />
SAP are in accordance with the<br />
QSM.<br />
The asbestos laboratory name will<br />
be included in the Pre-Final<br />
Sampling and Analysis Plan.<br />
Response to Comments on Draft Sampling and Analysis Plan<br />
<strong>Moffett</strong> <strong>Field</strong>, Cali<strong>for</strong>nia<br />
DCN: AMEC-8816-0005-0040<br />
April 2010<br />
Page 10 of 10
RESPONSE TO COMMENTS ON<br />
Draft Sampling and Analysis Plan <strong>for</strong> Non‐Time Critical Removal Action <strong>for</strong><br />
Polychlorinated Biphenyl Contamination at Installation Restoration Site 29 Hangar 1<br />
Former Naval Air Station <strong>Moffett</strong> <strong>Field</strong><br />
<strong>Moffett</strong> <strong>Field</strong>, Cali<strong>for</strong>nia<br />
Comments by:<br />
Alec Naugle<br />
Sr. Engineering Geologist<br />
Cali<strong>for</strong>nia Regional Water Quality Control Board,<br />
San Francisco Bay Region<br />
DCN: AMEC‐8816‐0005‐0041<br />
Responses by:<br />
AMEC Earth & Environmental, Inc.<br />
Line Number<br />
Section/Figure/<br />
Table/Appendix<br />
Comments<br />
1 SAP The acronym “RWQCB” <strong>for</strong> the San<br />
Francisco Regional Water Quality<br />
Control Board should be changed to<br />
“Water Board” throughout the document.<br />
2 SAP Import soil samples should be tested <strong>for</strong><br />
other chemicals, including petroleum<br />
hydrocarbons, semivolatile organic<br />
compounds, and polynuclear aromatic<br />
hydrocarbons, in addition to the<br />
chemicals of concern (PCBs, lead, and<br />
asbestos) to document that it is “clean”<br />
fill. The Navy should document that<br />
import soil is clean and contains neither<br />
the chemicals of concern nor other<br />
chemicals that could pose a risk to<br />
human health and the environment.<br />
Responses (Contractor)<br />
Comment noted. “RWQCB” will be<br />
replaced with “Water Board”<br />
throughout the document.<br />
Comment noted. Soil samples <strong>for</strong><br />
import soil will also be tested <strong>for</strong> total<br />
petroleum hydrocarbon, semi-volatile<br />
organic compounds, and polynuclear<br />
aromatic hydrocarbons.<br />
Response to Comments on Draft Sampling and Analysis Plan<br />
<strong>Moffett</strong> <strong>Field</strong>, Cali<strong>for</strong>nia<br />
DCN: AMEC-8816-0005-0041<br />
April 2010<br />
Page 1 of 4
3 SAP The areas of soil in question are small<br />
and disconnected. Water Board staff<br />
suggest soil data from each sampling<br />
location and be compared the project<br />
action limit sample by sample to<br />
determine what action is required, if any.<br />
4 Worksheets #3, #7, and #9 Correct Elizabeth Wells’ title to be<br />
“Water Board PM.”<br />
5 Page 10-2 Worksheet #10 Revise the text to read “…1) potential<br />
releases to groundwater, because data<br />
previously collected indicates there have<br />
been no PCB-impacts on groundwater<br />
…” The statement as presented is<br />
incorrect; groundwater beneath Hangar 1<br />
is impacted by volatile organic<br />
compounds.<br />
6 Worksheet #11, Section Revise the schedule to show the correct<br />
11.1<br />
7 Worksheet #14, Section<br />
14.2.1<br />
date(s) <strong>for</strong> distribution of the Work Plan.<br />
Clarify if gloves will be worn <strong>for</strong> soil<br />
sampling activities. Sampling without<br />
gloves is a health and safety concern, and<br />
could result in cross contamination of<br />
soil samples. The text states that gloves<br />
will be worn <strong>for</strong> all other sampling<br />
activities.<br />
The soil sampling strategy will be<br />
revised. A grid approach will be<br />
utilized to collect soil samples from<br />
soil areas on the east side of the<br />
Hangar. The grid will cover the entire<br />
soil area. Sample results will be<br />
provided to both EPA and Water<br />
Board <strong>for</strong> consultation on the specific<br />
soil removal approach.<br />
Comment noted. Elizabeth Wells’<br />
title will be changed to “Water Board<br />
PM”.<br />
The first sentence of the fifth<br />
paragraph will be revised as “It<br />
should be noted … there have been no<br />
impacts on groundwater from PCBs,<br />
lead, or asbestos; …”.<br />
Comment noted. Project schedule will<br />
be updated.<br />
Section 14.2.1 will be revised to<br />
include wearing a new pair of gloves<br />
<strong>for</strong> each sample collection.<br />
Response to Comments on Draft Sampling and Analysis Plan<br />
<strong>Moffett</strong> <strong>Field</strong>, Cali<strong>for</strong>nia<br />
DCN: AMEC-8816-0005-0041<br />
April 2010<br />
Page 2 of 4
8 Worksheet #15, Table 15-4 Change the project action limit <strong>for</strong> lead<br />
to the September 2009 Cali<strong>for</strong>nia Human<br />
Health Screening Level (CHHSL). The<br />
Cali<strong>for</strong>nia Office of Environmental<br />
Health Hazard Assessment recalculated<br />
the cleanup number based on a level of<br />
lead in soil that could result in up to a 1<br />
microgram per deciliter (µg/dL) increase<br />
in blood lead level.. The re-calculation<br />
reduced the CHHSL <strong>for</strong> lead to 320<br />
milligrams per kilogram <strong>for</strong><br />
commercial/industrial exposure. If the<br />
Navy elects not to make this<br />
recommended change, provide<br />
justification <strong>for</strong> the decision.<br />
9 Worksheet #16 Revise the schedule to show the correct<br />
date(s) <strong>for</strong> distribution of the Work Plan.<br />
10 Worksheet #17 Describe the steps that will be taken if<br />
the soil samples from 12 inches below<br />
ground surface contain chemicals of<br />
concern at concentrations greater than the<br />
screening criteria. The Navy has not<br />
included a sampling contingency <strong>for</strong> this<br />
scenario.<br />
11 Worksheet #17 Revise the soil sampling locations to<br />
collect representative soil samples from<br />
each soil area. Soil contamination, if<br />
present, likely is the result of deposition<br />
of contaminated particles that slough off<br />
the hangar. Because these particles could<br />
be transported via wind prior to<br />
deposition on the soil surface, there is no<br />
basis <strong>for</strong> sampling solely at the locations<br />
closest to the hangar.<br />
The project action limit <strong>for</strong> lead <strong>for</strong><br />
import soil will be changed to 320<br />
milligrams per kilogram.<br />
Comment noted. Project schedule will<br />
be updated.<br />
If the 12 inch samples exceed the<br />
action limit, then additional<br />
excavation will occur until the action<br />
levels are met. The Pre-Final Draft of<br />
the SAP will be revised accordingly.<br />
The soil sampling strategy will be<br />
revised. A grid approach will be<br />
utilized to collect soil samples from<br />
soil areas on the east side of the<br />
Hangar. The grid will cover the entire<br />
soil area. Sample results will be<br />
provided to both EPA and Water<br />
Board <strong>for</strong> consultation on the specific<br />
soil removal approach.<br />
Response to Comments on Draft Sampling and Analysis Plan<br />
<strong>Moffett</strong> <strong>Field</strong>, Cali<strong>for</strong>nia<br />
DCN: AMEC-8816-0005-0041<br />
April 2010<br />
Page 3 of 4
12 Worksheet #17 Provide the basis <strong>for</strong> the sampling<br />
frequency of one sample per 120,000<br />
gallons of treated water.<br />
13 Worksheet #17 Describe how wastewater will be treated<br />
and how any by-product (such as<br />
sediment from settling tanks), if<br />
generated, will be tested and disposed.<br />
The City of Sunnyvale Incidental<br />
Sewer Discharge (ISD) Permit<br />
requires demonstrating compliance<br />
with the permit discharge limits,<br />
however the sampling frequency is<br />
not specified. An initial sample of the<br />
treated wastewater will be collected<br />
as part of the ISD permit application.<br />
AMEC anticipates that 500,000<br />
gallons of waste water will be<br />
discharged during the project. Since<br />
the wastewater will be generated by a<br />
consistent pressure washing<br />
operation, the effluent concentrations<br />
are not expected to change. There<strong>for</strong>e<br />
one sample per 120,000 gallons is<br />
considered appropriate.<br />
Detailed in<strong>for</strong>mation on the<br />
wastewater treatment system design<br />
and process is contained in the Work<br />
Plan <strong>for</strong> this removal action. Waste<br />
characterization and disposal<br />
requirements <strong>for</strong> tank sediment are<br />
also discussed in the Work Plan. A<br />
summary of the pertinent in<strong>for</strong>mation<br />
will be added to the SAP<br />
Response to Comments on Draft Sampling and Analysis Plan<br />
<strong>Moffett</strong> <strong>Field</strong>, Cali<strong>for</strong>nia<br />
DCN: AMEC-8816-0005-0041<br />
April 2010<br />
Page 4 of 4