Rapid Environmental Impact Assessment (REIA) Study <strong>for</strong> Proposed Integrated Complex <strong>for</strong> Delhi Judicial Academy,<br />

National Law School, and National Institute <strong>for</strong> Mediation & Conciliation at Dwarka, New Delhi<br />

Domestic sewage will be generated during the operation phase of the project which will be<br />

treated in the <strong>proposed</strong> STP in the <strong>complex</strong>. Significant proportion of Municipal Solid Wastes<br />

will be generated from both the academic and residential <strong>complex</strong> and will need to be disposed<br />

off safely. The sludge generated from STP will be reused in horticulture within and outside the<br />

project site.<br />

3.7 Construction Plan and Timetable<br />

The preliminary schedule and timetable of major construction activities is outlined in Table 3.5.<br />

The total construction period <strong>for</strong> the entire <strong>complex</strong> will be about 30 months. This schedule is<br />

dependant on receiving timely environmental approvals from the concerned authorities.<br />

Table 3.5<br />

Proposed Integrated Judicial Complex Construction Schedule<br />

project activity<br />

Earth Excavation<br />

Casting of foundations and basement<br />

Casting of roof slabs<br />

Finishing<br />

Development and other related work<br />

<strong>proposed</strong> duration (FROM<br />

START DATE)<br />

1 month<br />

4 months<br />

18 months<br />

24 months<br />

30 months<br />

3.8 Construction Work<strong>for</strong>ce Requirements<br />

The site works during construction are highly labour intensive and a sizeable work<strong>for</strong>ce is<br />

anticipated. The entire project will be executed in 30 months period. The peak labour <strong>for</strong>ce<br />

requirement <strong>for</strong> the project will be about 1500 workers. It is expected that about 500 workers<br />

will stay in temporary shelters on the site during the construction period.<br />

3.9 Project Cost<br />

The estimated cost of the project including construction and machinery cost is expected to be Rs<br />

125 crores.<br />

3.10 Project Site Layout Plan and Model Photographs<br />